Other: ML071900365, ML11090A078, ML11109A067, ML12199A025, ML13043A527, ML13067A315, ML13077A284, ML13134A367, ML13155A504, ML13270A248, ML14217A206, ML15007A430, ML15055A004, ML15055A014, ML15268A128, NL-07-078, Station Blackout (SBO) / Appendix R Diesel Generator Commitment, Response to NRC Review Status of License Renewal Application, NL-10-054, Correction to License Renewal Application, NL-12-037, License Renewal Application - Revised Reactor Vessel Internals Program and Inspection Plan Compliant with MRP-227-A, NL-14-013, Additional Information Regarding the License Renewal Application - Action Item 7 from MRP-227-A
|
MONTHYEARNL-07-056, Supplement to License Renewal Application2007-05-0303 May 2007 Supplement to License Renewal Application Project stage: Supplement ML0729601252007-06-21021 June 2007 E-mail from K. Mcmullin of Entergy to Various, Regarding IPEC Status Report for June 21 2007 Project stage: Request NL-07-078, Station Blackout (SBO) / Appendix R Diesel Generator Commitment, Response to NRC Review Status of License Renewal Application2007-06-21021 June 2007 Station Blackout (SBO) / Appendix R Diesel Generator Commitment, Response to NRC Review Status of License Renewal Application Project stage: Other ML0719003652007-07-25025 July 2007 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from ENO, Inc. for Renewal of the Operating License for the Indian Point Nuclear Generating Unit Project stage: Other ML0727804392007-10-16016 October 2007 Summary of Telephone Conference Call with Entergy Nuclear Operations, Inc., Requests for Additional Information Project stage: RAI NL-10-054, Correction to License Renewal Application2010-05-27027 May 2010 Correction to License Renewal Application Project stage: Other ML11090A0782011-04-19019 April 2011 Safety Project Manager Change for the License Renewal Project for Indian Point Nuclear Generating Unit Numbers 2 and 3 Project stage: Other ML11109A0672011-04-19019 April 2011 Lr Hearing - FW: OAR - Safety PM Change for the License Renewal Project for Indian Point...(Tac Nos. MD5407 & MD5408) Project stage: Other CNRO-2011-00006, Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications2011-12-13013 December 2011 Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications Project stage: Request ML12048B4082012-02-17017 February 2012 State of New Yorks Answer to Entergys Motion in Limine to Exclude Portions of Pre-Filed Testimony and Exhibits for Contention NYS-37 (Entergy Alternatives) Project stage: Request NL-12-037, License Renewal Application - Revised Reactor Vessel Internals Program and Inspection Plan Compliant with MRP-227-A2012-02-17017 February 2012 License Renewal Application - Revised Reactor Vessel Internals Program and Inspection Plan Compliant with MRP-227-A Project stage: Other CNRO-2012-00004, Request for Additional Information Regarding Changes to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Plant Technical Specifications Regarding Staff Qualifications2012-05-21021 May 2012 Request for Additional Information Regarding Changes to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Plant Technical Specifications Regarding Staff Qualifications Project stage: Request ML12184A0372012-06-14014 June 2012 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI ML12199A0252012-07-30030 July 2012 Project Manager Change for the License Renewal of Indian Point, Units 2 & 3 Project stage: Other ML12223A3882012-09-10010 September 2012 RAI for the Review of the Indian Pont Nuclear Generating Unit Nos. 2 and 3, LRA Set 2012-02 Project stage: RAI ML12223A3672012-09-12012 September 2012 Summary of Telephone Conference Call Held Between NRC and Entergy Nuclear Operations, Inc., Concerning RAI Set 2012-02, Reactor Vessel Internals Program Pertaining to the Indian Point, Units 2 & 3, License Renewal Application Project stage: RAI ML12270A3842012-09-26026 September 2012 Lr Hearing - Meeting Summary Project stage: Request ML12278A0772012-10-16016 October 2012 Request for Additional Information for the Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application, Set 2012-03 Project stage: RAI NL-12-140, Reply to Request for Additional Information Regarding the License Renewal Application2012-10-17017 October 2012 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI NL-12-166, Reply to Request for Additional Information Regarding the License Renewal Application2012-11-20020 November 2012 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI CNRO-2012-00009, Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications2012-11-20020 November 2012 Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications Project stage: Response to RAI ML13015A1752013-02-0606 February 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, LRA, Set 2013-01 Project stage: RAI ML15335A2722013-02-0606 February 2013 Official Exhibit - NRC000187-00-BD01 - Letter from John Daily, NRC, to Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-01 (TAC Nos. MD5407 and Project stage: RAI ML15334A2562013-02-0606 February 2013 Official Exhibit - ENT000660-00-BD01 - Letter from J. Daly, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3 LRA, Set 2013-01 (TAC Nos. MD5407 and Project stage: Request ML15223A2632013-02-0606 February 2013 NRC000187 - Letter from John Daily, NRC, to Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-01 (TAC Nos. MD5407 and MD5408) Feb. 6, Project stage: RAI ML15222A8962013-02-0606 February 2013 ENT000660 - Letter from J. Daly, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application, Set 2013-01 (TAC Nos. MD54 Project stage: Request ML13043A5272013-02-26026 February 2013 PM Change Letter - February 2013 Project stage: Other ML13077A2842013-03-0808 March 2013 Correction PM Letter Indian Point Project stage: Other ML13067A3152013-03-0808 March 2013 Correction to Project Manager Change for the License Renewal of Indian Point, Units 2 and 3 (TAC Nos. MD5407 & MD5408) Project stage: Other ML13127A3762013-05-0707 May 2013 Errata to NRC Staff'S Proposed and Reply Findings of Fact and Conclusions of Law on Contention NYS-5 (Buried Piping and Tanks) Project stage: Request NL-13-052, Reply to Request for Additional Information Regarding the License Renewal Application2013-05-0707 May 2013 Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI ML13155A5042013-06-11011 June 2013 IP2-32-390 Request to Withhold-NL-12-166 Project stage: Other ML13162A6062013-06-12012 June 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-02 Project stage: RAI ML13186A1692013-07-17017 July 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013 03 Project stage: RAI ML13134A3672013-07-19019 July 2013 PM Change Letter Project stage: Other ML13205A0222013-07-24024 July 2013 Lr Hearing - Telecon Summary for 7-19-13 Call on Drais for Rvi Program and Inspection Plan Project stage: Request ML15222A8982013-07-26026 July 2013 ENT000661 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application, Set 2013-04 (TAC Nos. MD5 Project stage: Request ML15334A2572013-07-26026 July 2013 Official Exhibit - ENT000661-00-BD01 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3 Lr Application, Set 2013-04 (TAC Nos Project stage: Request ML13204A1992013-07-26026 July 2013 RAI for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2013-04 Project stage: RAI ML13240A0762013-09-0303 September 2013 RAI Set 2013-5 follow-up RAI on CP Project stage: RAI ML13270A2482013-09-27027 September 2013 Lr Hearing - IPEC License Renewal - Response to Set 2013-04 RAIs Project stage: Other ML13318A4502013-11-19019 November 2013 Request for Additional Information for the Review of the Indian Point Nuclear Generating, Units 2 and 3, License Renewal Application, Set 2013-06 Project stage: RAI NL-14-010, Units, 2 & 3 - Reply to Request for Additional Information Regarding the License Renewal Application2014-01-16016 January 2014 Units, 2 & 3 - Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI ML14027A4152014-01-16016 January 2014 Enclosure 2 to NL-14-010, Attachment 2, Final Response to U.S. NRC RAI 6-A Items 1 and 2 on the Rvi Program and Rvi Inspection Plan Project stage: Request NL-14-013, Additional Information Regarding the License Renewal Application - Action Item 7 from MRP-227-A2014-01-28028 January 2014 Additional Information Regarding the License Renewal Application - Action Item 7 from MRP-227-A Project stage: Other ML15160A2002014-01-28028 January 2014 NYS000503 - Dacimo, Fred, Entergy, Letter to Document Control Desk, USNRC, Reply to Request for Additional Information Regarding the License Renewal Application, NL-14-013 (January 28, 2014) (ML14038A150) Project stage: Response to RAI ML14084A3872014-04-0101 April 2014 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2014-01 Project stage: RAI ML15334A2582014-04-0909 April 2014 Official Exhibit - ENT000662-00-BD01 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the IP Nuclear Generating Unit Nos. 2 and 3 LRA, Set 2014-02 (TAC Nos. MD5407 and Project stage: Request ML15222A9012014-04-0909 April 2014 ENT000662 - Letter from K. Green, NRC, to Vice President, Operations, Entergy, Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application, Set 2014-02 (TAC Nos. MD5 Project stage: Request ML14094A1732014-04-0909 April 2014 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2014-02 Project stage: RAI 2012-09-26
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 22, 2015 LICENSEE:
Entergy Nuclear Operations, Inc.
FACILITY:
Indian Point Nuclear Generating Unit Nos. 2 and 3
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC. CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION, SET 2015-02 (TAC NOS. MD5407 AND MD5408)
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Operations, Inc. (Entergy), held a telephone conference call on July 1, 2015, to discuss and clarify the NRC staffs request for additional information (RAI) concerning the Indian Point Nuclear Generating Unit Nos. 2 and 3 license renewal application safety review.
provides a listing of the participants and Enclosure 2 contains a listing of the RAIs discussed with Entergy, including a brief description of the status.
Entergy had an opportunity to comment on this summary.
/RA/
Michael Wentzel, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosure:
As stated cc w/encl: Listserv
ML15190A291
- concurrence via e-mail OFFICE LA:DLR PM:RPB2:DLR BC:RPB1:DLR PM:RPB2:DLR NAME IBetts MWentzel YDiaz MWentzel DATE 7/14/15 7/22/15 7/22/15 7/22/15
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC. CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION, SET 2015-02 (TAC NOS. MD5407 AND MD5408)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsOgcMailCenter Resource MWentzel JWeil, OCA BFu MGray, RI WHolsten ABurritt, RI YDiaz DonaldJackson, RI DMorey MModes, RI DPickett NSheehan, RI OPA STurk, OGC DScrenci, RI OPA BMizuno, OGC DTifft, RI DRoth, OGC NMcNamara, RI BHarris, OGC GNewman, RI SBurnell, OPA JSStewart, RI DMcIntyre, OPA BPinson, RI
ENCLOSURE 1 TELEPHONE CONFERENCE CALL INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JULY 1, 2015 PARTICIPANTS:
AFFILIATIONS:
Bart Fu U.S. Nuclear Regulatory Commission (NRC)
William Holsten NRC Michael Wentzel NRC Stephen Eric Clair Entergy Nuclear Operations, Inc. (Entergy)
Dave Lach Entergy Rich Louie Entergy Andy Taylor Entergy Dave Wootten Entergy
ENCLOSURE 2 TELEPHONE CONFERENCE CALL CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 2015-02 RELATED TO INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION DOCKET NOS. 50-247 AND 50-286 REGARDING LR-ISG-2013-01 JULY 1, 2015 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Operations, Inc. (Entergy), held a telephone conference call on July 1, 2015, to discuss and clarify the following requests for additional information (RAIs) concerning the license renewal application safety review.
RAI 3.0.3-16
=
Background===
As amended by letter dated March 10, 2015, LRA Table 3.3.2-19-43-IP3, Pressurizer System, states that loss of coating integrity is managed for metal components with internal coating in a treated borated water > 140°F environment by the Coating Integrity Program.
Issue Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42, Aging Management of Loss of Coating or Lining Integrity for Internal Coatings/Linings on In-Scope Piping, Piping Components, Heat Exchangers, and Tanks. The changes to the LRA do not state the specific coating material used in systems with temperatures exceeding 140°F. Therefore, the staff lacks sufficient information to conclude that the recommendations in AMP XI.M42 (e.g., inspection intervals, acceptance criteria) are sufficient for the materials exposed to temperatures greater than 140°F.
Request State the coating materials exposed to temperatures greater than 140°F. Provide the basis for concluding that loss of coating integrity is adequately managed in the subject environment.
Discussion: Entergy requested clarification as to what information the staff was requesting.
The staff stated that AMP XI.M42 does not include any elevated temperature environments. As such, the staff needs to know the coating type to ensure that the condition monitoring recommendations of AMP XI.M42 are appropriate. Subsequent to the telephone conference call, Entergy requested that the NRC specify which statement in LR-ISG-2013-01 indicates that Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42 as stated in RAI 3.0.3-16. The NRC staff clairified that there is no explicit statement in the ISG that states that high-temperature environments are not evaluated to be bounding. However, the scope of AMP XI.M42 states:
Scope of Program: The scope of the program is internal coatings/linings for in-scope piping, piping components, heat exchangers, and tanks exposed to closed-cycle cooling water, raw water, treated water, treated borated water, waste water, fuel oil, and lubricating oil where loss of coating or lining integrity could prevent satisfactory accomplishment of any of the components or downstream components CLB intended functions identified under 10 CFR 54.4(a)(1), (a)(2), or (a)(3).
Further, if high-temperature environments had been included, the scope of the program would have listed environments such as Treated water >60°C (>140°F) or Closed-cycle cooling water
>60°C (>140°F) from Generic Aging Lessons-Learned Report Section IX.D and the Generic Aging Lessons-Learned Report aging-management program line item tables.
No changes were made to the RAI as a result of these discussions.
RAI 3.0.3-17
=
Background===
As amended by letter dated March 10, 2015, LRA Sections A.2.1.42, A.3.1.42, and B.1.43, Coating Integrity, state that the Coating Integrity Program will be implemented by December 31, 2024. In addition, Commitment 8, as revised, states that LRA Sections A.2.1.13, A.3.1.13 and B.1.14, Fire Water System, will be implemented by December 31, 2019.
Issue The implementation schedule for LRA Section B.1.43 ranges up to nine years, from 2015 to 2024. In addition, implementation of Commitment 8, as revised, ranges from 2015 to 2019.
SRP-LR Table 3.0-1 for AMP XI.M42 states that the first inspections of internal coatings should be completed no later than the last refueling outage prior to the period of extended operation.
The staff recognizes that Indian Point Unit 2 has entered timely renewal and Indian Point Unit 3 may shortly enter timely renewal. As such, it does not appear that the inspection section schedule recommended in Table 3.0-1 will be met. Further, it is not clear to the staff how loss of coating integrity will be managed in the time frame prior to the programs being implemented.
Request State how loss of coating integrity will be managed between now and the proposed implementation dates and the basis for concluding that coating integrity will be adequately managed in this time period.
Discussion: Entergy stated that they understood what information the NRC staff was requesting.
RAI 3.0.3-18
=
Background===
As amended by letter dated March 10, 2015, LRA Section B.1.14, Fire Water System, provides an enhancement to the corrective actions program element associated with returning degraded coatings (i.e., peeling, delaminated, or blistered) coatings to service without repair, replacement or removal. No exceptions related to conducting adhesion testing are stated in LRA Section B.1.43, Coating Integrity.
Issue GALL Report AMP XI.M42, element 7, corrective actions, recommends that the coatings/linings for in-scope components that do not meet acceptance criteria are repaired, replaced, or removed. GALL Report AMP XI.M42 allows an alternative, which recommends, among other things, that adhesion testing be performed before returning degraded (i.e., peeling, delaminated, or blistered) coatings to service. For the alternative for returning a coating exhibiting peeling and delamination to service without repair, the Fire Water System program does not include adhesion testing as part of the alternative. In addition, the enhancement states that for coatings exhibiting blistering, light tapping of the coating will be performed to determine the extent of blistering. AMP XI.M42 only recommends the use of light tapping when it is physically impossible to perform adhesion testing.
LRA Section B.1.14 did not state an exception to adhesion testing even though the proposed changes to the Fire Water System program were not consistent with GALL Report AMP XI.M42.
LRA Section B.1.43 does not state an exception to adhesion testing. It is not clear to the staff whether adhesion testing will be conducted prior to returning degraded coatings/linings within the scope of the Coating Integrity Program to service.
Request
- 1. State whether the Coating Integrity Program will include adhesion testing prior to returning degraded coatings/linings to service.
- 2. If the Coating Integrity Program does not include adhesion testing for returning degraded coatings/linings to service, explain why adhesion testing is not needed as part of the alternative for returning degraded coatings to service for in-scope fire water system components.
Discussion: Entergy stated that it intends to perform adhesion testing as recommended in AMP XI.M42. As such, no exceptions were stated related to adhesion testing. As such, the staff agreed to delete this RAI and would document the use of adhesion testing, as stated by the applicant, as appropriate.