June 19, 2014 & July 16, 2014 Summary of Conference Calls Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Regarding Entergy Response to a Request for Additional Information
ML14206B128
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/01/2014
From: Kimberly Green
License Renewal Projects Branch 1
To:
Green K, 415-1627
References
Download: ML14206B128 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 1, 2014 LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Indian Point Nuclear Generating Unit Nos. 2 and 3

SUBJECT:

SUMMARY

OF CONFERENCE CALLS HELD ON JUNE 19 AND JULY 16, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., REGARDING ENTERGYS RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION ON APPLICANT/LICENSEE ACTION ITEM 7 FROM MRP-227-A Representatives of the U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc., (Entergy or the applicant) held conference calls on June 19 and July 16, 2014, to obtain clarification on Entergys June 9, 2014 response regarding applicant/licensee action item 7. A list of the participants is enclosed.

By letter dated June 9, 2014, Entergy responded to request for additional information (RAI) 11-C, which requested that Entergy modify its Reactor Vessel Internals Inspection Plan to provide a link to a primary component that is an appropriate predictor of irradiation embrittlement and irradiation-assisted stress corrosion cracking (IASCC). In its response, Entergy stated that it has selected the lower core plate as a leading indicator of degradation for the column caps with regard to the embrittlement and IASCC mechanisms. Entergy will inspect the lower core plate using the VT-3 inspection method.

During the call on June 19, 2014, the staff stated that it needed clarification on the inspection method proposed and how it is capable of detecting cracking (small indications). The staff believes that an enhanced visual inspection (i.e., EVT-1) is the appropriate technique for detecting small indications.

Entergy requested time to consider the staffs statements and a second phone call.

During the phone call on July 16, 2014, Entergy stated that it plans to change the primary component from the lower core plate to the control rod guide tube lower flange welds and the core barrel cylinder girth welds. Entergy plans to submit a revised response in the near future.

The staff requested that, in its revised response, Entergy provide sufficient justification for the selection of the primary component as a leading indicator for the lower support column bodies, the expansion criteria, and the timing of any required expansion inspections.

The applicant had an opportunity to comment on this summary.

/RA/

Kimberly J. Green, Sr. Mechanical Engineer Aging Management of Plant Systems Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286

Enclosure:

List of Participants cc w/encl: Listserv

ML14206B128 *concurrence via e-mail OFFICE LA: DLR/RPB2* PM: DLR/RAPB BC: RPB1:DLR PM: DLR/RAPB NAME IKing KGreen YDiaz KGreen DATE 7/31/14 8/1/14 8/1/14 8/1/14

SUBJECT:

SUMMARY

OF CONFERENCE CALLS HELD ON JUNE 19 AND JULY 16, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., REGARDING ENTERGYS RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION ON APPLICANT/LICENSEE ACTION ITEM 7 FROM MRP-227-A DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDeEvib Resource RidsRgn1MailCenter RidsNrrPMIndianPoint RidsOgcMailCenter Resource YDiaz MGray, RI KGreen ABurritt, RI JPoehler DonaldJackson, RI SRosenberg MModes, RI AHiser NSheehan, RI OPA AustinYoung DScrenci, RI OPA GCheruvenki DTifft, RI STurk, OGC NMcNamara, RI BMizuno, OGC GNewman, RI DRoth, OGC JSStewart, RI BHarris, OGC AmiPatel, RI SBurnell, OPA DMcIntyre, OPA EDacus, OCA

TELEPHONE CONFERENCE CALLS INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JUNE 19 AND JULY 16, 2014 PARTICIPANTS: AFFILIATION:

Kim Green U.S. Nuclear Regulatory Commission (NRC)

Allen Hiser NRC Stacey Rosenberg NRC Jeff Poehler NRC Austin Young NRC Ganesh Cheruvenki** NRC Roger Waters Entergy Nuclear Operations, Inc. (Entergy)

Robert Dolansky Entergy Nelson Azevedo Entergy Charlie Caputo Entergy John Curry Entergy Ted Ivy** Entergy Randy Lott Westinghouse Cheryl Boggess Westinghouse Bradford Grimmel Westinghouse Dave Radonovich* Westinghouse

  • June 19, 2014 call only
    • July 16, 2014 call only ENCLOSURE