Other: ML15327A213, ML16133A459, ML16133A499, ML16312A270, ML17207A165, ML17250A244, ML17256A286, ML18212A032, ML18212A181, ML18212A185, ML18212A188, ML18212A190, ML18212A194, ML18212A195, ML18213A104, ML18213A114, NL-16-138, Amendment 18 to License Renewal Application, NL-17-005, Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components, NL-17-019, Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms, NL-17-020, License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan, NL-17-157, Amendment 19 to License Renewal Application (LRA)
|
MONTHYEARML15344A4362015-12-10010 December 2015 Lr Hearing - (External_Sender) Draft Audit Plan Edits Project stage: Request ML15327A2132015-12-21021 December 2015 Plan for the Regulatory Audit of the Service Water Integrity and Fire Water System Aging Management Programs Pertaining to the Indian Point Nuclear Generating Unit Nos. 2 and 3 LRA Project stage: Other ML15351A2032015-12-30030 December 2015 Summary of Conference Call Held on December 9, 2015, Between the NRC and Entergy Nuclear Operations, Inc. Concerning the Draft Audit Plan for the Service Water Integrity and Fire Water System Aging Management Programs Project stage: Draft Other 05000247/LER-2016-004, Re Unanalyzed Condition Due to Degraded Reactor Baffle-Former Bolts2016-05-31031 May 2016 Re Unanalyzed Condition Due to Degraded Reactor Baffle-Former Bolts Project stage: Request ML16133A4592016-06-15015 June 2016 Service Water and Fire Water Systems Aging Management Programs Audit Report for the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application Project stage: Other ML16133A4992016-06-21021 June 2016 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Safety Review Project stage: Other ML16138A1942016-07-25025 July 2016 Request for Additional Information for the Review of License Renewal Application, Set 2016-01 Project stage: RAI ML16208A2772016-07-26026 July 2016 Lr Hearing - RAI Set 2016-01 Project stage: Request ML16312A2702016-11-0909 November 2016 Project Manager Change for the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 Project stage: Other NL-16-122, Reply to Request for Additional Information for the Review of License Renewal Application, Set 2016-012016-12-0202 December 2016 Reply to Request for Additional Information for the Review of License Renewal Application, Set 2016-01 Project stage: Response to RAI NL-16-138, Amendment 18 to License Renewal Application2016-12-15015 December 2016 Amendment 18 to License Renewal Application Project stage: Other ML16350A4852016-12-15015 December 2016 Letter Enclosing Sipos Notice of Withdrawal Project stage: Request NL-17-005, Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components2017-01-17017 January 2017 Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components Project stage: Other NL-17-020, License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan2017-02-0606 February 2017 License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan Project stage: Other NL-17-019, Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms2017-02-0808 February 2017 Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms Project stage: Other ML17046A2312017-03-0808 March 2017 Request for Additional Information for the Review of the Indian Point License Renewal - Set 2017-01 Project stage: RAI ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 Project stage: RAI ML17088A3272017-04-19019 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 Project stage: RAI ML17088A4052017-04-20020 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-3 Project stage: RAI ML17101A6972017-04-25025 April 2017 License Renewal Clarification Call on Baffle Bolt RAIs Project stage: Approval NL-17-052, Reply to Request for Additional Information for the Review of the License Renewal Application, Set 2017-012017-05-0808 May 2017 Reply to Request for Additional Information for the Review of the License Renewal Application, Set 2017-01 Project stage: Response to RAI NL-17-053, Reply to Request for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-032017-05-18018 May 2017 Reply to Request for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-03 Project stage: Response to RAI NL-17-060, Reply to Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-022017-05-19019 May 2017 Reply to Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 Project stage: Response to RAI ML17128A3352017-05-23023 May 2017 Summary of Telephone Conference Call Between the NRC and Entergy Concerning RAIs Pertaining to IP2 and IP3 Project stage: RAI NL-17-061, Reply to Requests for Additional Information for the Review of the License Renewal Application RAI Set 2017-042017-05-24024 May 2017 Reply to Requests for Additional Information for the Review of the License Renewal Application RAI Set 2017-04 Project stage: Response to RAI NL-17-069, Reply to Requests for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application RAI Set 2017-052017-06-0808 June 2017 Reply to Requests for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application RAI Set 2017-05 Project stage: Response to RAI ML17170A2862017-06-27027 June 2017 RAI Set 2017-06 Project stage: RAI NL-17-074, Supplemental Information Regarding Reply to Request for Additional Information Set 2017-01 for the Review of the License Renewal Application (LRA)2017-06-27027 June 2017 Supplemental Information Regarding Reply to Request for Additional Information Set 2017-01 for the Review of the License Renewal Application (LRA) Project stage: Supplement ML17160A1652017-06-27027 June 2017 Summary of Telephone Conference Call Held on May 31,2017, Between the NRC and Entergy Nuclear Operations Inc. Concerning Requests for Additional Information Pertaining to the Indian Point, License Renewal Application (TAC Nos. MD5407/MD5408 Project stage: RAI NL-17-092, Amended Response to Request for Additional Information Question RAI 3.3.2-17-IP3-1 Re License Renewal Application RAI Set 2017-052017-07-27027 July 2017 Amended Response to Request for Additional Information Question RAI 3.3.2-17-IP3-1 Re License Renewal Application RAI Set 2017-05 Project stage: Response to RAI NL-17-084, Reply to Requests for Additional Information for the Review of the License Renewal Application. Re RAI Set 2017-062017-07-27027 July 2017 Reply to Requests for Additional Information for the Review of the License Renewal Application. Re RAI Set 2017-06 Project stage: Response to RAI ML17243A3152017-08-31031 August 2017 NMFS to NRC, Endangered Species Act Section 7 Conference Report for Proposed Indian Point Relicensing Project stage: Request ML17207A1652017-09-0101 September 2017 License Renewal Audit Plan Regarding the Service Water Integrity Program Project stage: Other ML17250A2442017-09-20020 September 2017 Audit Report for IP Swi - Aug 2017 Project stage: Other ML17191A4562017-09-20020 September 2017 Telecon Summary Related to Indian Point License Renewal RAIs Associated with ISG-2016-01 Project stage: RAI ML17180A5032017-09-21021 September 2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application Project stage: RAI ML17256A2862017-09-25025 September 2017 Summary of Telephone Call on 09/06/17, Between NRC and Entergy Concerning Next Steps from the Site Audit on 08/1-3/17 Project stage: Other NL-17-127, Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA)2017-11-0808 November 2017 Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) Project stage: Supplement ML17298A5442017-11-13013 November 2017 Summary of Meeting with the National Marine Fisheries Service Related to Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Project stage: Meeting NL-17-155, Re-Submittal of Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA)2017-12-14014 December 2017 Re-Submittal of Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) Project stage: Supplement NL-17-157, Amendment 19 to License Renewal Application (LRA)2017-12-14014 December 2017 Amendment 19 to License Renewal Application (LRA) Project stage: Other NL-17-161, Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application (LRA)2017-12-21021 December 2017 Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application (LRA) Project stage: Supplement NL-18-010, Supplemental Information Regarding the Review of the License Renewal Application2018-02-26026 February 2018 Supplemental Information Regarding the Review of the License Renewal Application Project stage: Supplement ML18107A7592018-04-30030 April 2018 NUREG-1437, Suppl. 38, Vol. 5, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 38 Regarding Indian Port Nuclear Generating Unit Nos. 2 and 3 Final. Project stage: Acceptance Review NL-18-030, Supplemental Information Associated with Amendment 19 to the License Renewal Application (LRA)2018-05-0808 May 2018 Supplemental Information Associated with Amendment 19 to the License Renewal Application (LRA) Project stage: Supplement NL-18-044, Supplemental Information Regarding the Review of the License Renewal Application2018-06-25025 June 2018 Supplemental Information Regarding the Review of the License Renewal Application Project stage: Supplement ML18200A3332018-08-0101 August 2018 NUREG-1930, Supp 3, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Plant, Units 2 and 3. Project stage: Approval ML18213A1142018-09-17017 September 2018 Renewed Facility Operating License Project stage: Other ML18211A5962018-09-17017 September 2018 Transmittal Letter - Issuance of Renewed Facility Operating License Nos. DPR-26 and DPR-64 for Indian Point Nuclear Generating Unit Nos. 2 and 3 Project stage: Approval ML18211A5782018-09-17017 September 2018 Federal Register Notice - Announcing the Issuance of the Indian Point Renewed Licenses Project stage: Approval 2017-04-19
[Table View] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-247 and 50-286; NRC-2008-0672]
Entergy Nuclear Operations, Inc.
Indian Point Nuclear Generating Unit Nos. 2 and 3 AGENCY: Nuclear Regulatory Commission.
ACTION: License renewal and record of decision; issuance.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) has issued renewed Facility Operating License Nos. DPR-26 and DPR-64 to Entergy Nuclear Operations, Inc. (Entergy or licensee), for Indian Point Nuclear Generating Unit Nos. 2 (IP2) and 3 (IP3). Renewed Facility Operating License Nos. DPR-26 and DPR-64 authorize Entergy to operate IP2 and IP3 at reactor core power levels not in excess of 3,216 megawatts thermal for each unit, in accordance with the provisions of the IP2 and IP3 renewed licenses and technical specifications. In addition, the NRC has prepared a Record of Decision (ROD) that supports the NRCs decision to issue renewed Facility Operating License Nos. DPR-26 and DPR-64.
DATES: The NRC issued the Renewed Facility Operating License Nos. DPR-26 and DPR-64 on September 17, 2018.
ADDRESSES: Please refer to Docket ID NRC-2008-0672 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0672. Address questions about Docket IDs in Regulations.gov to Jennifer Borges; telephone: 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For
2 technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. For the convenience of the reader, instructions about obtaining materials referenced in this document are provided in the Availability of Documents section.
NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, MD 20852.
FOR FURTHER INFORMATION CONTACT: William Burton, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-6332, e-mail: William.Burton@nrc.gov.
SUPPLEMENTARY INFORMATION:
I.
Introduction Notice is hereby given that the NRC has issued Renewed Facility Operating License Nos. DPR-26 and DPR-64 to Entergy Nuclear Operations, Inc. (Entergy or licensee), for the Indian Point Nuclear Generating Unit Nos. 2 (IP2) and 3 (IP3). IP2 and IP3 are pressurized-water reactors located in Buchanan, NY (24 miles north of New York City, NY). Renewed Facility Operating License Nos. DPR-26 and DPR-64 authorize the licensee to operate IP2 and IP3 at reactor core power levels not in excess of 3,216 megawatts thermal for each unit, in accordance with the provisions of the IP2 and IP3
3 renewed licenses and technical specifications. The renewed licenses authorize operation of IP2 and IP3 until April 30, 2024 and April 30, 2025, respectively. The NRCs record of decision (ROD) that supports the NRCs decision to issue Renewed Facility Operating License Nos. DPR-26 and DPR-64 is available in ADAMS under Accession No. ML18212A032.
The NRC has concluded that the application for the renewed licenses, Indian Point Energy Center License Renewal Application, dated April 23, 2007 (ADAMS Accession No. ML071210512), as amended, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the NRCs regulations. As required by the Act and the NRCs regulations set forth in title 10 of the Code of Federal Regulations (10 CFR), the NRC has made appropriate findings, which are set forth in the renewed licenses. No adjudicatory matters are pending before the Commission or the Atomic Safety and Licensing Board regarding the IP2 and IP3 license renewal application.
The NRC staff published its final supplemental environmental impact statement (FSEIS) in five volumes of NUREG-1437, Supplement 38, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 (NUREG-1437, Supplement 38) Final Report. For Volumes 1 through 3, dated December 3, 2010, see ADAMS Package Accession No. ML103270072; for Volume 4, dated June 30, 2013 (FSEIS Supplement 1), see ADAMS Accession No. ML13162A616; and for Volume 5, dated April 30, 2018 (FSEIS Supplement 2), see ADAMS Accession No. ML18107A759. As discussed in the ROD, FSEIS, and FSEIS supplements, the NRC has considered the reasonably foreseeable impacts of IP2 and IP3 license renewal as well as a range of reasonable alternatives to license renewal that included natural gas combined-cycle (NGCC); purchased electric
4 power; conservation; combination alternative 1 (license renewal of either IP2 or IP3 along with wind power, hydropower, biomass fuels, landfill-gas fuels, and conservation);
combination alternative 2 (fossil-fired power (combined-cycle) with wind power, biomass fuels, hydropower, landfill-gas fuels, and conservation); the no-action alternative; and operation of IP2 and IP3 using cooling towers. The FSEIS and FSEIS supplements document the environmental review, including the determination that the adverse environmental impacts of license renewal for IP2 and IP3 are not so great that preserving the option of license renewal for energy planning decisionmakers would be unreasonable.
The NRC staff documented the results of its safety review in its Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3, issued August 11, 2009 (ADAMS Accession No. ML092240268). On November 30, 2009, the NRC staff published its final report in two volumes as NUREG-1930, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (for Volume 1, see ADAMS Accession No. ML093170451 and for Volume 2 see ADAMS Accession No. ML093170671). On August 31, 2011, the NRC staff issued Supplement 1 to NUREG-1930 (ADAMS Accession No. ML11242A215). Supplement 1 documents the NRC staffs review of supplemental information provided by the applicant since the issuance of NUREG-1930, including annual updates required by 10 CFR 54.21(b), and updated information and commitments in response to NRC staff requests for additional information. On July 31, 2015, the NRC staff issued Supplement 2 to NUREG-1930 (ADAMS Accession No. ML15188A383). Supplement 2 documents the NRC staff's review of supplemental information provided by the applicant since the issuance of Supplement 1, including information committed to by Entergy as documented in
5 Commitment No. 30 (pertaining to reactor vessel internals), annual updates required by 10 CFR 54.21(b), updated information and commitments, as well as information provided in response to NRC staff requests for additional information. On August 1, 2018, the NRC staff issued Supplement 3 to NUREG-1930 (ADAMS Accession No. ML18200A333). Supplement 3 documents the NRC staff's review of supplemental information provided by the applicant since the issuance of Supplement 2, including annual updates required by 10 CFR 54.21(b), updated information to address new or updated interim staff guidance, and recent operating experience.
II.
Conclusion The NRC has determined that the application for the Indian Point Nuclear Generating Unit Nos. 2 and 3 renewed licenses, Indian Point Energy Center License Renewal Application, dated April 23, 2007, as amended, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the NRCs regulations. As required by the Act and the NRCs regulations in 10 CFR, the NRC has made appropriate findings, which are set forth in the renewed licenses and the ROD. No adjudicatory matters are pending before the Commission or the Atomic Safety and Licensing Board regarding the IP2 and IP3 license renewal application.
Accordingly, the NRC has issued Renewed Facility Operating License Nos. DPR-26 and DPR-64, authorizing operation of IP2 and IP3 until April 30, 2024 and April 30, 2025, respectively.
III.
Availability of Documents The documents identified in the following table are available to interested persons as indicated.
6 DOCUMENT ADAMS ACCESSION NO.
Indian Point Energy Center License Renewal Application, dated April 23, 2007 ML071210512 NUREG-1437, Supplement 38, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 (NUREG-1437, Supplement 38) Final Report. (Volumes 1-3, December 3, 2010)
ML103270072 NUREG-1437, Supplement 38, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 (NUREG-1437, Supplement 38) Final Report. (Volume 4, June 30, 2013)
ML13162A616 NUREG-1437, Supplement 38, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3 (NUREG-1437, Supplement 38) Final Report. (Volume 5, April 30, 2018)
ML18107A759 Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (August 11, 2009)
ML092240268 NUREG-1930, Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (Volume 1 November 30, 2009)
ML093170451 NUREG-1930 Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (Volume 2 November 30, 2009)
ML093170671 NUREG-1930 Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (August 31, 2011)
ML11242A215 NUREG-1930 Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (July 31, 2015)
ML15188A383 NUREG-1930 Safety Evaluation Report (SER) Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3 (August 1, 2018)
ML18200A333 Record of Decision for License Renewal Application For Indian Point Nuclear Generating (September 17, 2018)
ML18212A032
7 Dated at Rockville, MD, this 17th day of September 2018.
For the Nuclear Regulatory Commission.
/RA Sign Electronically /
George A. Wilson, Jr., Director, Division of Materials and License Renewal, Office of Nuclear Reactor Regulation.