{{#Wiki_filter:TVA November 15, 2011
 
Mr. Michael D. Skaggs Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
 
==SUBJECT:==
MEETING
 
==SUMMARY==
FOR PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY ON WATTS BAR NUCLEAR PLANT UNIT 2 CONSTRUCTION PROJECT 
 
==Dear Mr. Skaggs:==
 
This refers to the meeting conducted at our request at the Comfort Inn Hotel in Athens, TN on November 8 , 2011 at 1:00 p.m.
The meeting's purpose was to give Tennessee Valley Authority (TVA) the opportunity to present their updated status of the Watts Bar Unit 2 construction project to the NRC.
On November 8, 2011, the NRC's Director of Construction Projects held a Category 1 meeting in which TVA provided a presentation about the current progress and scheduling plans for the Watts Bar Nuclear (WBN) Unit 2 construction project. The NRC staff presented information on the current status of the NRC's construction inspection program for WBN Unit 2. Additional topics related to the WBN Unit 2 construction project were discussed between the NRC and TVA. Following these presentations and discussions, members of the public had an opportunity to provide comments and ask questions. The agenda (Enclosure 1), the list of attendees (Enclosure 2), the TVA presentation material used for discussions (Enclosure 3), and the NRC presentation material used for discussions (Enclosure 4) are attached to this letter.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and the enclosures will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA  30303-1257
 
TVA 2  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning this meeting, please contact Robert Haag at 404-997-4446
. Sincerely, 
      /RA/  Robert C. Haag, Chief Construction Projects Branch 2 Division of Construction Projects
 
==Enclosures:==
: 1. Agenda  2. List of Attendees
: 3. Presentation - TVA Slides 4. Presentation - NRC Slides
 
ML 11319A186____
O  SUNSI REVIEW COMPLETE TVA 3  cc w/encl:
Mr. Gordon P. Arent WBN Unit 2 Licensing Watts Bar Nuclear Plant P.O. Box 2000 Spring City, Tennessee 37381 Mr. David Stinson Vice President WBN Unit Two WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381
 
Ms. Donna Guinn, Manager Licensing and Industry Affairs WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 Mr. Preston D. Swafford Chief Nuclear Officer  and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Place Chattanooga, Tennessee 37402-2801 County Executive 375 Church Street Suite 215 Dayton, Tennessee 37321 Mr. Gregory A. Boerschig Plant Manager, WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 Mr. T. J. Neissen General Manager Quality Assurance Nuclear Generation and Development and Construction 1101 Market Street Blue Ridge 3A Chattanooga, Tennessee 37402-2801 Mr. Joseph Shea Acting Vice President, Nuclear Licensing  Tennessee Valley Authority LP 4B 1101 Market Street Chattanooga, Tennessee 37402-2801
 
Mr. E. J. Vigluicci Assistant General Counsel Tennessee Valley Authority 6A West Tower 400 West Summit Hill Drive Knoxville, Tennessee 37402 Mr. Lawrence E. Nanney, Director Tennessee Department of Environmental Health & Conservation Division of Radiological Health 3rd Floor, L&C Annex 401 Church Street Nashville, TN 37243-1532 Mr. D. E. Grissette Site Vice President WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 County Mayor P.O. Box 156 Decatur, Tennessee 37322 Ms. Ann P. Harris 341 Swing Loop Rockwood, TN 37854 TVA 4  cc email distribution w/encl:
Greg Scott Tennessee Valley Authority Electronic Mail Distribution
 
Watts Bar 2 Licensing Tennessee Valley Authority Electronic Mail Distribution
 
Letter to Michael D. Skaggs from Robert C. Haag dated November 15, 2011. 
 
==SUBJECT:==
MEETING
 
==SUMMARY==
FOR PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY ON WATTS BAR NUCLEAR PLANT UNIT 2 CONSTRUCTION PROJECT  Distribution w/encl
: L. Raghavan, NRR S. Campbell, NRR P. Milano, NRR C. Evans, RII  L. Douglas, RII EICS S. Shaeffer, RII DRP R. Monk, RII WBN Unit 1 SRI OE Mail (email address if applicable) PUBLIC NRO_cROP Resource}}

Revision as of 13:38, 2 August 2018

11/08/2011 Meeting Summary with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant Unit 2 Construction Project
ML11319A231
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 11/15/2011
From: Haag R C
NRC/RGN-II/DCP/CPB2
To: Skaggs M D
Tennessee Valley Authority
Haag R C
References
Download: ML11319A231 (6)


Text

TVA November 15, 2011

Mr. Michael D. Skaggs Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801

SUBJECT:

MEETING

SUMMARY

FOR PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY ON WATTS BAR NUCLEAR PLANT UNIT 2 CONSTRUCTION PROJECT

Dear Mr. Skaggs:

This refers to the meeting conducted at our request at the Comfort Inn Hotel in Athens, TN on November 8 , 2011 at 1:00 p.m.

The meeting's purpose was to give Tennessee Valley Authority (TVA) the opportunity to present their updated status of the Watts Bar Unit 2 construction project to the NRC.

On November 8, 2011, the NRC's Director of Construction Projects held a Category 1 meeting in which TVA provided a presentation about the current progress and scheduling plans for the Watts Bar Nuclear (WBN) Unit 2 construction project. The NRC staff presented information on the current status of the NRC's construction inspection program for WBN Unit 2. Additional topics related to the WBN Unit 2 construction project were discussed between the NRC and TVA. Following these presentations and discussions, members of the public had an opportunity to provide comments and ask questions. The agenda (Enclosure 1), the list of attendees (Enclosure 2), the TVA presentation material used for discussions (Enclosure 3), and the NRC presentation material used for discussions (Enclosure 4) are attached to this letter.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and the enclosures will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257

TVA 2 ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning this meeting, please contact Robert Haag at 404-997-4446

. Sincerely,

/RA/ Robert C. Haag, Chief Construction Projects Branch 2 Division of Construction Projects

Enclosures:

1. Agenda 2. List of Attendees
3. Presentation - TVA Slides 4. Presentation - NRC Slides

ML 11319A186____

O SUNSI REVIEW COMPLETE TVA 3 cc w/encl:

Mr. Gordon P. Arent WBN Unit 2 Licensing Watts Bar Nuclear Plant P.O. Box 2000 Spring City, Tennessee 37381 Mr. David Stinson Vice President WBN Unit Two WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381

Ms. Donna Guinn, Manager Licensing and Industry Affairs WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 Mr. Preston D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Place Chattanooga, Tennessee 37402-2801 County Executive 375 Church Street Suite 215 Dayton, Tennessee 37321 Mr. Gregory A. Boerschig Plant Manager, WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 Mr. T. J. Neissen General Manager Quality Assurance Nuclear Generation and Development and Construction 1101 Market Street Blue Ridge 3A Chattanooga, Tennessee 37402-2801 Mr. Joseph Shea Acting Vice President, Nuclear Licensing Tennessee Valley Authority LP 4B 1101 Market Street Chattanooga, Tennessee 37402-2801

Mr. E. J. Vigluicci Assistant General Counsel Tennessee Valley Authority 6A West Tower 400 West Summit Hill Drive Knoxville, Tennessee 37402 Mr. Lawrence E. Nanney, Director Tennessee Department of Environmental Health & Conservation Division of Radiological Health 3rd Floor, L&C Annex 401 Church Street Nashville, TN 37243-1532 Mr. D. E. Grissette Site Vice President WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 County Mayor P.O. Box 156 Decatur, Tennessee 37322 Ms. Ann P. Harris 341 Swing Loop Rockwood, TN 37854 TVA 4 cc email distribution w/encl:

Greg Scott Tennessee Valley Authority Electronic Mail Distribution

Watts Bar 2 Licensing Tennessee Valley Authority Electronic Mail Distribution

Letter to Michael D. Skaggs from Robert C. Haag dated November 15, 2011.

SUBJECT:

MEETING

SUMMARY

FOR PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY ON WATTS BAR NUCLEAR PLANT UNIT 2 CONSTRUCTION PROJECT Distribution w/encl

L. Raghavan, NRR S. Campbell, NRR P. Milano, NRR C. Evans, RII L. Douglas, RII EICS S. Shaeffer, RII DRP R. Monk, RII WBN Unit 1 SRI OE Mail (email address if applicable) PUBLIC NRO_cROP Resource