MONTHYEARML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24228A2652024-08-20020 August 2024 Summary of Public Pre-Submittal Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant and Watts Bar Nuclear Plant LAR Related to TS 3.5.2. ECCS - Operating ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24173A2122024-06-27027 June 2024 Summary of Public Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding Adoption of TSTF-276-A, Revision 2 to Clarify Requirements for Diesel Generator Testing ML24158A3002024-06-11011 June 2024 Summary of May 6, 2024, Public Meeting with Tennessee Valley Authority to Discuss the Potential for a License Amendment Request Regarding the Control Room Envelope and Selective Use of an Alternative Source Term ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24057A0582024-02-27027 February 2024 Summary of February 15, 2024, Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21253A0872021-09-15015 September 2021 Summary of August 19, 2021, Partially Closed Meeting with Tennessee Valley Authority to Discuss Mid-Cycle Outage Contingencies for Watts Bar Nuclear Plant, Unit 2 ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21120A2192021-05-0404 May 2021 April 28,2021, Summary of Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, to Remove from Technical Specifications Redundant Units of Measurement for Control ML21099A2072021-04-13013 April 2021 Summary of April 7, 2021, Meeting with Tennessee Valley Authority Related to a Planned Relief Request from ASME Code Testing Requirements ML21060B0532021-03-0303 March 2021 Summary of February 11, 2021, Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2, to Apply a Temperature Adjusted Steam Generator Tube Flaw Growth Rate Methodology ML21033A5952021-02-23023 February 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar Nuclear Plant, Unit 2 Steam Generator Replacement ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20351A4212021-01-19019 January 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar, Unit 2, Steam Generator Replacement ML20351A2192021-01-11011 January 2021 Summary of Conference Calls Regarding the Fall 2020 Steam Generator Tube Inspections ML20337A0402020-12-15015 December 2020 Summary of November 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification 5.9.9, Steam Generator Tube Inspection Report ML20323A0662020-11-27027 November 2020 Summary of October 28, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification Surveillance Requirement 3.6.15.4, Shield Building ML20244A1892020-09-11011 September 2020 Summary of Teleconference Call with Tennessee Valley Authority Regarding a Proposed Change to the Containment Leakage Rate Testing Program ML20213C7112020-08-25025 August 2020 Summary of July 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned Alternative Request for Watts Bar Nuclear Plant, Unit 1 ML20233A8352020-08-25025 August 2020 Summary of August 11, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20211L8222020-08-10010 August 2020 Summary of Teleconference Call with the Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20150A4162020-06-24024 June 2020 Summary of May 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20153A3622020-06-22022 June 2020 Summary of May 27, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20135H2702020-05-28028 May 2020 Summary of May 5, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20143A1692020-05-28028 May 2020 Summary of May 14, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2 ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20034F5232020-02-12012 February 2020 Summary of Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML19347D1592020-01-0707 January 2020 Summary of December 12, 2019, Meeting with Northern States Power Co., Doing Business as Xcel Energy, and Tennessee Valley Authority Planned License Amendment Requests for Prairie Island, Units 2 and 2, and Watts Bar, Units 1 and 2 2024-09-23
[Table view] |
Text
September 15, 2021 LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF AUGUST 19, 2021, TELECONFERENCE WITH TENNESSEE VALLEY AUTHORITY REGARDING PLANNED LICENSE AMENDMENT REQUEST RELATED TO THE WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 (EPID L-2021-LRM-0074)
On August 19, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff conducted an observation (i.e., public) teleconference with representatives of Tennessee Valley Authority (TVA). The purpose of the teleconference was for TVA to discuss a proposed license amendment requests (LAR) for Watts Bar Nuclear Plant (Watts Bar), Units 1 and 2 to permanently extend the completion time in Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System, to support cleaning of the 6.9 kilovolt (kV) shutdown board (SDBD) and associate 480 volt boards and motor control centers when a Watts Bar unit is in an outage and defueled. The current completion time to restore an inoperable train of ERCW to operable status is 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. TVA will propose to extend the completion time to 7 days.
Additionally, TVA stated that it is planning to propose to increase the ultimate heat sink temperature during the maintenance from 71 to 78 degrees Fahrenheit (°F).
The meeting notice and agenda, dated July 27, 2021, are available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML21217A184. TVAs presentation slides for the meeting are available at ADAMS Accession No. ML21231A097. A list of participants is enclosed.
TVA reviewed the background of the proposed request and referred to Amendment 35 to the Watts Bar, Unit 2, license for which it received a one-time extension to the completion time from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days. The revised TS was contingent on four conditions (ADAMS Accession No. ML20024F835), two of which limited the activities to spring 2020 outage for Unit 1 and the ultimate heat sink (UHS) temperature to less than or equal to 71 °F.
TVA described the ERCW system which is a common two-train system and consists of four 50 percent capacity pumps per train. Two ERCW pumps per 6.9kV SDBD are required to be operable per train, with two trains required for each unit. Each train of ERCW has sufficient capacity to provide essential cooling loads for both units under any credible plant condition. The system configuration is illustrated on slides 6 and 7.
TVA enumerated the maintenance activities performed on a 6.9 kV SDBD during an outage, which includes breaker compartment inspections, circuit breaker interface inspections and adjustments, and bus inspections and tests. The NRC staff asked if TVA inspects the fuses.
TVA replied that it looks at the condition of the fuses and replaces them, if needed.
According to TVA, it takes approximately 105 hours0.00122 days <br />0.0292 hours <br />1.736111e-4 weeks <br />3.99525e-5 months <br /> to perform the various maintenance and inspection on the SDBDs. The request would be to extend the completion time to 7 days (i.e.,
168 hours0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br />). TVA stated that the remaining time being requested would allow for a contingency should the need arise for an unexpected repair revealed by the maintenance activities.
TVA described the proposed changes to Watts Bar TS 3.7.8. Because Unit 2s TS was previously revised on a one-time basis, the proposed revisions are slightly different than the proposed changes for Unit 1, but will result in the same requirements for each unit. Each units TS 3.7.8 is proposed to be revised as follows:
TS 3.7.8 Condition A will be revised to increase the completion time for an inoperable ERCW Train from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days with the following Notes:
- 1. Only applicable when WBN (1 or 2) unit is defueled.
- 2. Only applicable during planned maintenance of a Unit (1 or 2) 6.9kV SDBD and the associated 480V boards and MCC.
Both Notes are required to be met in order to use Condition A.
The UHS temperature in the Completion Time for Required Action A.1 and for Required Action A.2 will be revised from 71 °F to 78 °F Conditions A, B, and C will be modified so that they are consistent between Units 1 and 2 The Watts Bar Dual-Unit Updated Final Safety Analysis Report, Section 9.2.1.3, will be revised to reflect the new ERCW system alignments needed to support SDBD maintenance.
TVA stated that it employs a graded approach to defense in depth (DID) as well as protected equipment strategies when equipment is removed from service. These are governed by TVA procedures NPG-SPP-07.0, Work Management, NPG-SPP-07.1, On Line Work Management, and NPG-SPP-07.3.4, Protected Equipment. The NRC staff suggested that inclusion of how the DID applies to the ERCW in its submittal would be helpful to the staff.
TVA also performed engineering analyses with a single ERCW pump powered from the 6.9 kV SDBD under various circumstances. Based on the analyses, TVA concluded that a single ERCW powered from the available 6.9kV SDBD can supply sufficient heat removal while maintaining the outlet piping thermal stress temperature limits. The analyses used Proto-Flo for the hydraulic modeling as modified to reflect the one ERCW pump configuration. TVA described the conservatisms assumed in the analyses as well as proposed hardware change to support the analyses, which is planned to be installed during the Unit 1 Fall 2021 outage. The NRC staff inquired if TVA plans to use risk insights to support the planned LAR. TVA responded that the submittal will not be risk based, but will include a qualitative risk discussion.
To support the change to the UHS temperature, TVA performed a review of the past 6 years of plant intake temperatures for the spring and fall when the Watts Bar outages occur. The results showed that for the typical dates of the outages, the UHS temperatures have historically been below the proposed temperature of 78 °F.
The NRC staff asked if TVA performs the SDBD maintenance activities every outage. TVA stated that the maintenance activities are not performed every outage. The staff also asked if there are other situations for which the plant might enter TS 3.7.8, Condition A. TVA responded that Watts Bar only enters the condition for planned maintenance.
TVA plans to submit the LAR by the end of September 2021 and request approval within 12 months.
No comments or public meeting feedback were received. No regulatory decisions were made at this meeting.
Please direct any inquiries to me at 301-415-1627 or by e-mail to Kimberly.Green@nrc.gov.
/RA/
Kimberly J. Green, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-390 50-391
Enclosure:
List of Participants cc: Listserv
LIST OF PARTICIPANTS AUGUST 19, 2021, TELECONFERENCE WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 PLANNED LICENSE AMENDMENT REQUEST RELATED TO THE COMPLETION TIME FOR TECHNICAL SPECFICATION 3.7.8, ESSENTIAL RAW COOLING WATER (ERCW) SYSTEM Name Organization Kim Green U.S. Nuclear Regulatory Commission (NRC)
Luke Haeg NRC Chang Li NRC Hari Kodali NRC Vijay Goel NRC Josh Wilson NRC Ed Miller NRC Russ Wells Tennessee Valley Authority (TVA)
Kim Hulvey TVA Chuck Broesche TVA John Grant TVA Chris Kerlin TVA Ron Cox TVA Yassine Aboulfalda TVA Tony Langley TVA William Eberly Sargent & Lundy David Gennardo Sargent & Lundy Enclosure
ML21245A425 *via e-mail OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA* DORL/LPL2-2/BC* DORL/LPL2-2/PM NAME KGreen RButler DWrona KGreen DATE 9/2/2021 9/13/2021 9/14/2021 9/15/2021