DCS No:  50277/278881021 Date: October 4 , 1988
                                                                                                        \'
PRELIMINARY *' NOTIFICATION OF EVENT OR UNUSUAL' OCCURRENCE--PNO-1-88-110 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region I staff on this date.
      . Facility:                                    Licensee Emergency Classification:
Philadelphia Electric Co.                          Notificat. ton of Unusual Event
      ' Peach Bottom Atomic Po'wer Station                Alert DNs 50-277/278                                      Site Area Emergency Philadelphia, Pennsylvania                    ..
General Emergency X Not Applicable
 
==Subject:==
PEACH BOTTOM ATOMIC POWER STATION RESTART SCHEDULE Philadelphia Electric Company announced today that there would De a delay in the rostart of Units 2 and 3 to allow further upgrade in areas such as operator training, managerial and supervisory effectiveness and plant security. These actions will delay restart readiness of Unit 2 until the second quarter of 1989 and of Unit 3 until the third quarter of 1989.
The Commonwealth of Pennsylvania and State of Maryland have been informed.
CONTACT: J. Linville              E. Wenzinger (215) 337-5122            (215) 337-5225 346-5122                  346-5225 DISTRIBUTION:
OWFN                    MNBB            H-St.              NL        Mail: ADM:DMB thairman Zech          Afb 0          FCll3 C              RES                00T:Tra ,only Com. Roberts            ARM            POR Com. Carr              OGC                                          NRC Ops Ctr Com. Rogers INPO----
SECY      NMSS                                            NSAC----
CA        NRR OGC        OIA          Regional Offices                                              '
GPA        O!                                              RI Resident Office PA        SLITP E00      OE                                              Licensee:
(Reactor Licensees)
Region I Form 83 (Rsv. April 1988) l
!                                                                                                    3h g e r -le:1 FN0-I-G8-110        FDC g@
                                                                                              -    .-}}


{{PNO-Nav|region=I}}
{{PNO-Nav|region=I}}

Latest revision as of 13:38, 29 December 2020

PNO-I-88-110:on 881021,delay in Restart of Units 2 & 3 Until Second & Third Quarter 1989,respectively,to Allow Further Upgrade in Operator Training,Managerial & Supervisory Effectiveness & Plant Security
ML20205H853
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/21/1988
From: Linville J, Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
References
PNO-I-88-110, NUDOCS 8810310188
Download: ML20205H853 (1)


  • ~

DCS No: 50277/278881021 Date: October 4 , 1988

\'

PRELIMINARY *' NOTIFICATION OF EVENT OR UNUSUAL' OCCURRENCE--PNO-1-88-110 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region I staff on this date.

. Facility: Licensee Emergency Classification:

Philadelphia Electric Co. Notificat. ton of Unusual Event

' Peach Bottom Atomic Po'wer Station Alert DNs 50-277/278 Site Area Emergency Philadelphia, Pennsylvania ..

General Emergency X Not Applicable

Subject:

PEACH BOTTOM ATOMIC POWER STATION RESTART SCHEDULE Philadelphia Electric Company announced today that there would De a delay in the rostart of Units 2 and 3 to allow further upgrade in areas such as operator training, managerial and supervisory effectiveness and plant security. These actions will delay restart readiness of Unit 2 until the second quarter of 1989 and of Unit 3 until the third quarter of 1989.

The Commonwealth of Pennsylvania and State of Maryland have been informed.

CONTACT: J. Linville E. Wenzinger (215) 337-5122 (215) 337-5225 346-5122 346-5225 DISTRIBUTION:

OWFN MNBB H-St. NL Mail: ADM:DMB thairman Zech Afb 0 FCll3 C RES 00T:Tra ,only Com. Roberts ARM POR Com. Carr OGC NRC Ops Ctr Com. Rogers INPO----

SECY NMSS NSAC----

CA NRR OGC OIA Regional Offices '

GPA O! RI Resident Office PA SLITP E00 OE Licensee:

(Reactor Licensees)

Region I Form 83 (Rsv. April 1988) l

! 3h g e r -le:1 FN0-I-G8-110 FDC g@

- .-