PNO-I-89-034, on 890426,Unit 2 Initiated Startup After Receiving Approval to Operate at Power Levels Not Exceeding 35% Full Power.Licensee Will Be Performing Control Rod Manipulations.Addl NRC Inspectors on Site to Monitor Plant

From kanterella
Jump to navigation Jump to search
PNO-I-89-034:on 890426,Unit 2 Initiated Startup After Receiving Approval to Operate at Power Levels Not Exceeding 35% Full Power.Licensee Will Be Performing Control Rod Manipulations.Addl NRC Inspectors on Site to Monitor Plant
ML20245G561
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/27/1989
From: Linville J, Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
References
PNO-I-89-034, PNO-I-89-34, NUDOCS 8905030177
Download: ML20245G561 (2)


r DCS No: 50277/278990427 Date: April 27, 1989 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE--PNO -

This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region I 1 staff on this date.

Facility: Licensee Emergency Classification:

Philadelphia Electric Cc. Notification of Unusual Event Peach Bottom Atomic Power Station Alert Philadelphia, Pennsylvania Site Area Emergency DNs 50-277/278 General Emergency X Not Applicable

Subject:

PEACH BOTTOM UNIT 2 RESTART 1

Peach Bottom Unit 2 initiated startup on April 26, 1989 after receiving approvt' from the Regional Administrator to operate unit 2 at power levels not exceeding 35 -

t of full power. The partial release from the Order shutting down the facility came after the utility announced they had completed all work and all systems were ready to support restart operations.

Criticality was achieved at 0544 on April 27, 1989. The licensee will be performing control rod manipulations for the next two days to give operating crews, particularly cold licensed operators, an opportunity to take the plant critical.

NRC inspectors have verified the readiness of the unit for operations. Mr. Russell, the Regional Administrator, signed the letter modifying the Order. The NRC has additional inspectors on site to monitor around the clock the startup and initial phase of the power testing program which is scheduled for about fourteen weeks.

The Commonwealth of Pennsylvania and State of Maryland have been informed and I representatives are on site to observe startup activities.

1 CONTACT: J. Linville E. Wenzinger 346-5122 346-5225 DISTRIBUTION:

OWFN MNBB H-St. NL Mail: ADM:DMB Chairman Zech AEOD ACRS RES DOT:Trans only Comm. Roberts ARM PDR Comm. Carr OGC NRC Ops Ctr Comm. Rogers Comm. Curtiss INPO----

SECY NMSS NSAC----

CA NRR OGC OIA Regional Offices GPA 01 RI Resident Office PA SLITP E00 OE Licensee:

(Reactor Licensees)

Region I Form 83 (Rev. April 1988) 0 {

8905030177 890427 PDR I&E h

DISTRIBUTION:

INRC1718 Chyirman Zech j

~

Comm Roberts i Comm Carr  !

Comm Rogers Comm Curtiss ACRS SECY CA PDR OGC-H GPA OIA INRCO2/ORDAZ (Please make PA internal distribution)

INRC1718/ DAY (Pleae make internal Distribution)

INRC1112/NRRPN (Please make NRR internal distribution) k l!

1NRC0304, HILL (SLITP, please deliver to C. Kammerer)

INRC0708, SUMMERS (OE, please deliver to J. Lieberman)

NRCRES,RESPN (Please make internal distribution)

NRCIE, LEAD 0P (Please make internal distribution)

NRCRII,RIIPN (Please make Internal RII distribution)

NRCRIII,RIIIPN (Please make Internal RIII distribution) i NRCRIV,Leadop (Please make Internal RIV distribution) i NRCRV,Leadop (Please make Internal RV distribution) l Region I WPS Resident OTTice (Site PC) (If secretary is off FAX)

RI Office Services Section (Mail to ADM:0MB & DOT (transportation only)

FAX to INP0 NSAC 1