{{#Wiki_filter:December 03, 2009 LICENSEE: Florida Power Corporation | {{#Wiki_filter:December 03, 2009 LICENSEE: Florida Power Corporation FACILITY: Crystal River Unit 3 Nuclear Generating Plant | ||
FACILITY: Crystal River Unit 3 Nuclear Generating Plant | |||
==SUBJECT:== | ==SUBJECT:== | ||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING LICENSEE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Florida Power Corporation (FPC) held a telephone conference call on October 28, 2009, to discuss the | OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING LICENSEE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Florida Power Corporation (FPC) held a telephone conference call on October 28, 2009, to discuss the applicants response to a request for additional information concerning the Crystal River Unit 3 Nuclear Generating Plant (CR-3) license renewal application. The telephone conference call was useful in clarifying the applicants response to requests for information (RAIs) related to neutron absorption materials in the spent fuel pools at CR-3. | ||
By letter dated October 2, 2009, FPC provided responses to RAIs B.2.37-1 and RAI 3.3.2.2.6-1. | |||
By letter dated October 2, 2009, FPC provided responses to RAIs B.2.37-1 and RAI 3.3.2.2.6-1. RAI B.2.37-1 requested information related to the Carborundum Monitoring Program and RAI 3.3.2.2.6-1 requested information on how the applicant planned to manage the aging effects of Boral in the spent fuel pool. The staff sought clarification on the use of weight loss to determine the acceptability of the Carborundum spent fuel pool material. The staff also sought clarification on the | RAI B.2.37-1 requested information related to the Carborundum Monitoring Program and RAI 3.3.2.2.6-1 requested information on how the applicant planned to manage the aging effects of Boral in the spent fuel pool. The staff sought clarification on the use of weight loss to determine the acceptability of the Carborundum spent fuel pool material. The staff also sought clarification on the licensees plan for monitoring both Carborundum and Boral in the spent fuel pool for the period of extended operation including: determining a baseline as a reference point for determining the trend of neutron absorption material loss, the frequency of inspection, and the | ||
Florida Power Corporation type of inspection that will be implemented. The staff may consider issuing additional RAIs related to the applicants plans for managing the aging effects of the spent fuel pool neutron absorbing materials. | |||
The enclosure provides a listing of the participants. | The enclosure provides a listing of the participants. | ||
The applicant had an opportunity to comment on this summary. | The applicant had an opportunity to comment on this summary. | ||
/RA/ | |||
Robert Kuntz, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302 | |||
Docket No. 50-302 | |||
==Enclosure:== | ==Enclosure:== | ||
cc w/encl: | List of Participants cc w/encl: See next page | ||
ML093290034 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME SFigueroa RKuntz DWrona RKuntz DATE 11/ 25/09 11/30/09 12/1/09 12/3/09 | ML093290034 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME SFigueroa RKuntz DWrona RKuntz DATE 11/ 25/09 11/30/09 12/1/09 12/3/09 | ||
PARTICIPANTS | TELEPHONE CONFERENCE CALL CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS OCTOBER 28, 2009 PARTICIPANTS AFFILIATIONS Robert Kuntz U.S. Nuclear Regulatory Commission (NRC) | ||
Matthew Yoder NRC Emma Wong NRC Aloysius Obodoako NRC Kent Wood NRC Allen Hiser NRC Mike Heath Florida Power Corporation Bob Reynolds Florida Power Corporation Mike Fletcher Florida Power Corporation Mike Culver Florida Power Corporation ENCLOSURE | |||
Letter to Florida Power Corporation from R. Kuntz, dated December 03, 2009 DISTRIBUTION: | Letter to Florida Power Corporation from R. Kuntz, dated December 03, 2009 DISTRIBUTION: | ||
Line 49: | Line 46: | ||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING LICENSEE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter | OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING LICENSEE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION HARD COPY: | ||
DLR RF E-MAIL: | |||
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter | |||
________ | |||
RKuntz EKeegan AJones, OGC LLake, RII MSykes, RII TMorrissey, RII RReyes, RI | RKuntz EKeegan AJones, OGC LLake, RII MSykes, RII TMorrissey, RII RReyes, RI | ||
Crystal River Nuclear Generating | Crystal River Nuclear Generating Plant Unit 3 cc: | ||
Mr. R. Alexander Glenn Mr. Jon A. Franke, Vice President Associate General Counsel (MAC-BT15A) Crystal River Nuclear Plant (NA1B) | |||
Florida Power Corporation ATTN: Supervisor, Licensing & Regulator P.O. Box 14042 Programs St. Petersburg, FL 33733-4042 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. James W. Holt Plant General Manager Senior Resident Inspector Crystal River Nuclear Plant (NA2C) Crystal River Unit 3 15760 W. Power Line Street U.S. Nuclear Regulatory Commission Crystal River, FL 34428-6708 6745 N. Tallahassee Road Crystal River, FL 34428 Mr. William A. Passetti, Chief Department of Health Ms. Phyllis Dixon Bureau of Radiation Control Manager, Nuclear Assessment 2020 Capital Circle, SE, Bin #C21 Crystal River Nuclear Plant (NA2C) | |||
Tallahassee, FL 32399-1741 15760 W. Power Line Street Crystal River, FL 34428-6708 Attorney General Department of Legal Affairs Mr. David T. Conley The Capitol Associate General Counsel II - Legal Dept. | |||
Tallahassee, FL 32304 Progress Energy Service Company, LLC Post Office Box 1551 Mr. Ruben D. Almaluer, Director Raleigh, NC 27602-1551 Division of Emergency Preparedness Department of Community Affairs Mr. Daniel L. Roderick 2740 Centerview Drive Vice President, Nuclear Projects & | |||
Tallahassee, FL 32399-2100 Construction Crystal River Nuclear Plant (SA2C) | |||
Chairman 15760 W. Power Line Street Board of County Commissioners Crystal River, FL 34428-6708 Citrus County 110 North Apopka Avenue Mr. Mark Rigsby Inverness, FL 34450-4245 Manager, Support Services - Nuclear Crystal River Nuclear Plant (SA2C) | |||
Mr. Stephen J. Cahill 15760 W. Power Line Street Engineering Manager Crystal River, FL 34428-6708 Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Mr. Robert J. Duncan II Crystal River, FL 34428-6708 Vice President, Nuclear Operations Progress Energy Mr. Daniel R. Westcott Post Office Box 1551 Supervisor, Licensing & Regulatory Raleigh, NC 27602-1551 Programs Crystal River Nuclear Plant Mr. Brian C. McCabe 15760 W. Power Line Street Manager, Nuclear Regulatory Affairs Crystal River, FL 34428-6708 Progress Energy Post Office Box 1551 Raleigh, NC 27602-1551}} | |||
Ms. Phyllis Dixon Manager, Nuclear Assessment Crystal River Nuclear Plant (NA2C) | |||
Mr. David T. Conley Associate General Counsel II - Legal Dept. Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, NC |
Latest revision as of 00:04, 14 November 2019
ML093290034 | |
Person / Time | |
---|---|
Site: | Crystal River |
Issue date: | 12/03/2009 |
From: | Robert Kuntz License Renewal Projects Branch 2 |
To: | Florida Power Corp |
KUNTZ R, NRR/DLR, 415-2989 | |
References | |
Download: ML093290034 (6) | |
Text
December 03, 2009 LICENSEE: Florida Power Corporation FACILITY: Crystal River Unit 3 Nuclear Generating Plant
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING LICENSEE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Florida Power Corporation (FPC) held a telephone conference call on October 28, 2009, to discuss the applicants response to a request for additional information concerning the Crystal River Unit 3 Nuclear Generating Plant (CR-3) license renewal application. The telephone conference call was useful in clarifying the applicants response to requests for information (RAIs) related to neutron absorption materials in the spent fuel pools at CR-3.
By letter dated October 2, 2009, FPC provided responses to RAIs B.2.37-1 and RAI 3.3.2.2.6-1.
RAI B.2.37-1 requested information related to the Carborundum Monitoring Program and RAI 3.3.2.2.6-1 requested information on how the applicant planned to manage the aging effects of Boral in the spent fuel pool. The staff sought clarification on the use of weight loss to determine the acceptability of the Carborundum spent fuel pool material. The staff also sought clarification on the licensees plan for monitoring both Carborundum and Boral in the spent fuel pool for the period of extended operation including: determining a baseline as a reference point for determining the trend of neutron absorption material loss, the frequency of inspection, and the
Florida Power Corporation type of inspection that will be implemented. The staff may consider issuing additional RAIs related to the applicants plans for managing the aging effects of the spent fuel pool neutron absorbing materials.
The enclosure provides a listing of the participants.
The applicant had an opportunity to comment on this summary.
/RA/
Robert Kuntz, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
List of Participants cc w/encl: See next page
ML093290034 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME SFigueroa RKuntz DWrona RKuntz DATE 11/ 25/09 11/30/09 12/1/09 12/3/09
TELEPHONE CONFERENCE CALL CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS OCTOBER 28, 2009 PARTICIPANTS AFFILIATIONS Robert Kuntz U.S. Nuclear Regulatory Commission (NRC)
Matthew Yoder NRC Emma Wong NRC Aloysius Obodoako NRC Kent Wood NRC Allen Hiser NRC Mike Heath Florida Power Corporation Bob Reynolds Florida Power Corporation Mike Fletcher Florida Power Corporation Mike Culver Florida Power Corporation ENCLOSURE
Letter to Florida Power Corporation from R. Kuntz, dated December 03, 2009 DISTRIBUTION:
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING LICENSEE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter
________
RKuntz EKeegan AJones, OGC LLake, RII MSykes, RII TMorrissey, RII RReyes, RI
Crystal River Nuclear Generating Plant Unit 3 cc:
Mr. R. Alexander Glenn Mr. Jon A. Franke, Vice President Associate General Counsel (MAC-BT15A) Crystal River Nuclear Plant (NA1B)
Florida Power Corporation ATTN: Supervisor, Licensing & Regulator P.O. Box 14042 Programs St. Petersburg, FL 33733-4042 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. James W. Holt Plant General Manager Senior Resident Inspector Crystal River Nuclear Plant (NA2C) Crystal River Unit 3 15760 W. Power Line Street U.S. Nuclear Regulatory Commission Crystal River, FL 34428-6708 6745 N. Tallahassee Road Crystal River, FL 34428 Mr. William A. Passetti, Chief Department of Health Ms. Phyllis Dixon Bureau of Radiation Control Manager, Nuclear Assessment 2020 Capital Circle, SE, Bin #C21 Crystal River Nuclear Plant (NA2C)
Tallahassee, FL 32399-1741 15760 W. Power Line Street Crystal River, FL 34428-6708 Attorney General Department of Legal Affairs Mr. David T. Conley The Capitol Associate General Counsel II - Legal Dept.
Tallahassee, FL 32304 Progress Energy Service Company, LLC Post Office Box 1551 Mr. Ruben D. Almaluer, Director Raleigh, NC 27602-1551 Division of Emergency Preparedness Department of Community Affairs Mr. Daniel L. Roderick 2740 Centerview Drive Vice President, Nuclear Projects &
Tallahassee, FL 32399-2100 Construction Crystal River Nuclear Plant (SA2C)
Chairman 15760 W. Power Line Street Board of County Commissioners Crystal River, FL 34428-6708 Citrus County 110 North Apopka Avenue Mr. Mark Rigsby Inverness, FL 34450-4245 Manager, Support Services - Nuclear Crystal River Nuclear Plant (SA2C)
Mr. Stephen J. Cahill 15760 W. Power Line Street Engineering Manager Crystal River, FL 34428-6708 Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Mr. Robert J. Duncan II Crystal River, FL 34428-6708 Vice President, Nuclear Operations Progress Energy Mr. Daniel R. Westcott Post Office Box 1551 Supervisor, Licensing & Regulatory Raleigh, NC 27602-1551 Programs Crystal River Nuclear Plant Mr. Brian C. McCabe 15760 W. Power Line Street Manager, Nuclear Regulatory Affairs Crystal River, FL 34428-6708 Progress Energy Post Office Box 1551 Raleigh, NC 27602-1551