U-603624, June 2003 Monthly Operating Report for Clinton Power Station

From kanterella
(Redirected from U-603624)
Jump to navigation Jump to search
June 2003 Monthly Operating Report for Clinton Power Station
ML031980465
Person / Time
Site: Clinton Constellation icon.png
Issue date: 07/07/2003
From: Lliff W
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
U-603624
Download: ML031980465 (5)


Text

AmerGen An Exelon/British Energy Company Clinton Power Station R.R. 3 Box 228 Clinton, IL61727-9351 10CFR50.36 U-603624 July 7, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Clinton Power Station Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

June 2003 Monthly Operating Report Please find in Attachment 1 the Monthly Operating Report for Clinton Power Station, Unit 1, for the period ending June 30, 2003.

Respectfully, W.S.lliff Regulatory Assurance Manager Clinton Power Station MJS/blf Attachments cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Clinton Power Station Office of Nuclear Facility Safety - Illinois Department of Nuclear Safety jQ~A

ATTACHMENT 1 CHALLENGES TO MAIN STEAM SAFETY/RELIEF VALVES Month June 2003 None

j -: v ATTACHMENT 2 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-461 UNIT Clinton 1 DATE 06/30/03 COMPLETED BY M. J. Sloan TELEPHONE (217)937-3280 v _. . __. ___ _

MONTH June 2003 1 _ 1042 17 1040 2 _ 1041 18 1040 3 _ 1042 19 1042 4 _ 1041 20 1042 5 _ 1040 21 1041 6 _ 1041 22 1041 7 1042 23 1040 8 1041 24 1040 9 1040 .

25 1040 10 1041 26 1041 11 1041 27 1042 12 - 1040 28 1042 13 - 1040 29 1041 14 - 1041 30 1042 15 - 1041 16 1040

ATTACHMENT 3 OPERATING DATA REPORT DOCKET NO. 50-461 UNIT Clinton 1 DATE 06/30/03 COMPLETED BY M. J. Sloan TELEPHONE (217)937-3280 OPERATING STATUS

1. REPORTING PERIOD: June 2003 GROSS HOURS IN REPORT PERIOD: 720
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3473 MAX. DEPEND. CAPACITY (MDC) (MWe-Net): 1022 DESIGN ELECTRICAL RATING (MWe-Gross): 1062
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4299.0 93.035.8
6. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
7. HOURS GENERATOR ON LINE 720.0 4286.4 90.875.9
8. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 4.0
9. GROSS THERMAL ENERGY GENERATED (MWH) 2.249.211 13.485.174.0 253.114.919.6
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 779.265.0 4.543.854.0 83.965.567
11. NET ELECTRICAL ENERGY GENERATED (MWH) 7490390 4.379.436.4 80.204.333
12. REACTOR SERVICE FACTOR 100.0% 99.0% 68.0%
13. REACTOR AVAILABILITY FACTOR 100.0% 99.00/0 68.0%
14. UNIT SERVICE FACTOR 1 00.0 % 98.7% 66.5%
15. UNIT AVAILABILITY FACTOR 100.0% 98.7% 66.5%
16. UNIT CAPACITY FACTOR (Using MDC) 111.9% 108.4% 63.1%
17. UNIT CAPACITY FACTOR (Using Design MWe) 102.3% 99.2% 57.7%
18. UNIT FORCED OUTAGE RATE 0.0% 0.00/0 6.5%
19. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, DURATION OF EACH):

TYPE DATE DURATION N/A

20. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

N/A

ATTACHMENT 4 UNIT SHUTDOWNS DOCKET NO. 50-461 UNIT Clinton 1 DATE 06/30/03 COMPLETED BY M. J. Sloan REPORT MONTH June 2003 METHOD OF TYPE SHUTTING DOWN FORCED DURATION THE REACTOR OR CORRECTIVE NO. DATE F: SCHEDULED (HOURS) REASON (1) REDUCING POWER ACTIONS/COMMENTS (2)

NONE (1) Reason A - Equipment Failure (explain), B - Maintenance or Test, C - Refueling, D - Regulatory Restriction E - Operator training & License Examination, F - Administrative, G - Operational Error (explain)

(2) Method 1 - Manual, 2 - Manual Scram, 3 - Automatic Scram, 4 - Other (explain)