U-603542, January 2002 Monthly Operating Report for Clinton Power Station, Unit 1

From kanterella
Jump to navigation Jump to search
January 2002 Monthly Operating Report for Clinton Power Station, Unit 1
ML020640368
Person / Time
Site: Clinton Constellation icon.png
Issue date: 02/14/2002
From: Iliff W
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
U-603542
Download: ML020640368 (5)


Text

AmerGen An Exelon/British Energy Company Clinton Power Station R.R. 3 Box 228 Clinton, IL 61727-9351 Phone: 217 935-8881 10CFR50.36 U-603542 8E.100c February 14, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Clinton Power Station Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

January 2002 Monthly Operating Report Please find in Attachment 1 the Monthly Operating Report for Clinton Power Station, Unit 1, for the period ending January 31, 2002.

Respectfully, W. S. Iliff

  • A Regulatory Assurance Manager Clinton Power Station MJS/blf Attachments cc: Regional Administrator- NRC Region III NRC Senior Resident Inspector - Clinton Power Station Office of Nuclear Facility Safety - Illinois Department of Nuclear Safety

ATTACHMENT 1 CHALLENGES TO MAIN STEAM SAFETY/RELIEF VALVES Month January 2002 None

ATTACHMENT 2 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-461 UNIT Clinton 1 DATE 01/31/02 COMPLETED BY M. J. Sloan TELEPHONE (217)937-3280 MONTH January 2002 1 929 17 928 2 927 18 927 3 927 19 929 4 927 20 772 5 931 21 923 6 927 22 928 7 928 23 924 8 927 24 924 9 928 25 929 10 928 26 928 11 927 27 930 12 929 28 927 13 930 29 927 14 929 30 928 15 928 31 927 16 928

ATTACHMENT 3 OPERATING DATA REPORT DOCKET NO. 50-461 UNIT Clinton 1 DATE 01131/02 COMPLETED BY M. J. Sloan TELEPHONE (217)937-3280 OPERATING STATUS

1. REPORTING PERIOD: January 2002 GROSS HOURS IN REPORT PERIOD: 744
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2894 MAX. DEPEND. CAPACITY (MDC) (MWe-Net): 930 DESIGN ELECTRICAL RATING (MWe-NET): 933
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE 744.0 744.0 81,555.3
5. NUMBER OF HOURS REACTOR WAS CRITICAL 0.0 0.0 0.0
6. REACTOR RESERVE SHUTDOWN HOURS 744.0 744.0 79,527.7
7. HOURS GENERATOR ON LINE 0.0 0.0 4.0
8. UNIT RESERVE SHUTDOWN HOURS 2,143,316 2,143,316 217,660,655.6
9. GROSS THERMAL ENERGY GENERATED (MWH) 713,898.5 713,898.5 72,159,529
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 686,395 68,853,833
11. NET ELECTRICAL ENERGY GENERATED (MWH) 686,395 100% 65.6%
12. REACTOR SERVICE FACTOR 100%

100% 65.6%

13. REACTOR AVAILABILITY FACTOR 100%

100% 63.9%

14. UNIT SERVICE FACTOR 100%

100% 100% 63.9%

15. UNIT AVAILABILITY FACTOR 99.2% 99.2% 59.5%
16. UNIT CAPACITY FACTOR (Using MDC) 98.9% 98.9% 59.3%
17. UNIT CAPACITY FACTOR (Using Design MWe) 0.0% 0.0% 7.2%
18. UNIT FORCED OUTAGE RATE
19. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, DURATION OF EACH):

TYPE DATE DURATION REFUELING OUTAGE APRIL 2, 2002 34 DAYS No. 8 (Cl R08)

20. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

N/A

ATTACHMENT 4 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-46 1 UNIT Clinton 1 DATE 01/31/02 COMPLETED BY M. J. Sloan REPORT MONTH January 2002 METHOD OF TYPE SHUTTING DOWN FORCED DURATION THE REACTOR OR CORRECTIVE (HOURS) REASON (1) REDUCING POWER ACTIONS/COMMENTS NO. DATE F: SCHEDULED (2) 1 01/20/02 SCHEDULED 3.8 B 1 SURVEILLANCE TESTING, PATTERN ADJUSTMENT (1) Reason A - Equipment Failure (explain), B - Maintenance or Test, C - Refueling, D - Regulatory Restriction E - Operator training & License Examination, F - Administrative, G - Operational Error (explain)

(2) Method 1 - Manual, 2 - Manual Scram, 3 - Automatic Scram, 4 - Other (explain)