November 2004 Monthly Operating Report Clinton Power Station Unit 1
ML043560181
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/14/2004
From: Lliff W
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
U-603706
Download: ML043560181 (2)


Text

%-u.

-- ~

AmerG(en An Exelon Company Clinton Power Station R. R.3, Box 228 Clinton, IL 61727 1 OCFR50.36 U-603706 December 14, 2004 U. S. Nuclear Regulatory Commission ATTN:- Do-cinie`it C6ifrol Dek Washington, D.C. 20555-0001 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

November 2004 Monthly Operating Report Please find in the Attachment the Monthly Operating Report for Clinton Power Station, Unit 1, for the period ending November 30, 2004.

Respectfully, A/.S. a W. S. lliff Regulatory Assurance Manager Clinton Power Station

_JLP/blf Attachment cc:

Regional Administrator - NRC Region IlIl NRC Senior Resident Inspector-Clinton Power Station Illinois Emergency Management Agency - Division of Nuclear Safety

.....................4

s 1OPERATING DATA REPORT Attachment to U-603706 DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIO 50-461 Clinton 1 December 10, 2004 P. K. Ryan 217-937-2201 November 2004

1.

Design Electrical Rating

2. Maximum Dependable Capacity (MWe-Net) 1,062.00 1,022.00 This Month Yr-to-Date Cumulative
3.

Number of Hours the Reactor was Critical 720.00 7,391.65 104,810.20

4.

Number of Hours Generator On-line 720.00 7,168.61 102,393.34

5.

Reserve Shutdown Hours 0.00 0.00 4.00

~-

6:Net'Elfbtrcil 'Eery GGnierattd'(MWHri)_

758,516.00 7,217.959.78 91,741,846.48 UNIT SHUTDOWNS

SUMMARY

The were no planned or forced losses in the month of November.

1 2

Reason:

A Equipment Failure (Explain)

B Maintenance or Test C

Refueling D

Regulatory Restriction E

Operator Training & License Examination F

Administration G

Operational Error (Explain)

H Other (Explain)

Method:

1 Manual 2

Manual Trip/Scram 3

Automatic Trip/Scram 4

Continuation 5

Other (Explain)

Challenges to Main Steam Safety Relief Valves: None 1

Page 1 of 1