June 2004 Monthly Operating Report,For Clinton Power Station
ML042020338
Person / Time
Site: Clinton Constellation icon.png
Issue date: 07/12/2004
From: Lliff W
AmerGen Energy Co, Exelon Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
U-603681
Download: ML042020338 (2)


Text

/

Amer~ens.

An Exelon Company Clinton Power Station R. R. 3, Box 228 Clinton, IL 61727 1 OCFR50.36 U-603681 July 12, 2004 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Clinton Power Station Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

June 2004 Monthly Operating Report Please find in the Attachment the Monthly Operating Report for Clinton Power Station, Unit 1, for the period ending June 30, 2004.

Respectfully, h/s X

W. S. Iliff Regulatory Assurance Manager Clinton Power Station JLP/bIf Attachment cc:

Regional Administrator - NRC Region ill NRC Senior Resident Inspector - Clinton Power Station Office of Nuclear Facility Safety - Illinois Emergency Management Agency

OPERATING DATA REPORT Attachment to U-603681 DOCKET NO.

50 UNIT NAME Cli DATE Jul COMPLETED BY P.

TELEPHONE (21 REPORTING PERIOD:

-461 inton 1 ly 07, 2004 K. Ryan

17) 937-2201 June 2004
1. Design Electrical Rating
2.

Maximum Dependable Capacity (MWe-Net) 1,062.00 1,022.00 This Month Yr-to-Date Cumulative

3.

Number of Hours the Reactor was Critical 720.00 3,820.20 101,238.75

4.

Number of Hours Generator On-line 720.00 3,623.19 98,847.92

-5., Reserve Shutdown Hours.,

0.00 -

0.00

__ 4.00

6.

Net Electrical Energy Generated (MWHrs) 756,957.00 3,504,145.60 88,028,032.30 UNIT SHUTDOWNS Type Method of F: Forced Duration l Shutting Cause & Corrective Action No.

Date S: Scheduled (Hours)

Reason 1 Down 2 Comments

SUMMARY

There were no planned or forced losses in June.

1 Reason:

A Equipment Failure (Explain)

B Maintenance or Test C

Refueling D

Regulatory Restriction E

Operator Training & License Examination F

Administration G

Operational Error (Explain)

H Other (Explain) 2 Method:

1 Manual 2

Manual Trip/Scram 3

Automatic Trip/Scram 4

Continuation 5

Other (Explain)

I Challenges to Main Steam Safety Relief Valves: None I

Page 1 of 1