U-603624, June 2003 Monthly Operating Report for Clinton Power Station

From kanterella
Jump to navigation Jump to search
June 2003 Monthly Operating Report for Clinton Power Station
ML031980465
Person / Time
Site: Clinton Constellation icon.png
Issue date: 07/07/2003
From: Lliff W
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
U-603624
Download: ML031980465 (5)


Text

AmerGen An Exelon/British Energy Company Clinton Power Station R.R. 3 Box 228 Clinton, IL 61727-9351 1 OCFR50.36 U-603624 July 7, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Clinton Power Station Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

June 2003 Monthly Operating Report Please find in Attachment 1 the Monthly Operating Report for Clinton Power Station, Unit 1, for the period ending June 30, 2003.

Respectfully, W.S.lliff Regulatory Assurance Manager Clinton Power Station MJS/blf Attachments cc:

Regional Administrator - NRC Region III NRC Senior Resident Inspector - Clinton Power Station Office of Nuclear Facility Safety - Illinois Department of Nuclear Safety jQ~A

ATTACHMENT 1 CHALLENGES TO MAIN STEAM SAFETY/RELIEF VALVES Month June 2003 None

j

-: v ATTACHMENT 2 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-461 Clinton 1 06/30/03 M. J. Sloan (217)937-3280 v _.. _ _. _ _ _ _

MONTH 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 June 2003 1042 1041 1042 1041 1040 1041 1042 1041 1040 1041 1041 1040 1040 1041 1041 1040 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1040 1040 1042 1042 1041 1041 1040 1040 1040 1041 1042 1042 1041 1042

ATTACHMENT 3 OPERATING DATA REPORT DOCKET NO.

50-461 UNIT Clinton 1 DATE 06/30/03 COMPLETED BY TELEPHONE M. J. Sloan (217)937-3280 OPERATING STATUS

1.

REPORTING PERIOD:

June 2003 GROSS HOURS IN REPORT PERIOD: 720

2.

CURRENTLY AUTHORIZED POWER LEVEL (MWt):

3473 MAX. DEPEND. CAPACITY (MDC) (MWe-Net):

1022 DESIGN ELECTRICAL RATING (MWe-Gross):

1062

3.

POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net):

None

4.

REASONS FOR RESTRICTION (IF ANY):

N/A 5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

NUMBER OF HOURS REACTOR WAS CRITICAL REACTOR RESERVE SHUTDOWN HOURS HOURS GENERATOR ON LINE UNIT RESERVE SHUTDOWN HOURS GROSS THERMAL ENERGY GENERATED (MWH)

GROSS ELECTRICAL ENERGY GENERATED (MWH)

NET ELECTRICAL ENERGY GENERATED (MWH)

REACTOR SERVICE FACTOR REACTOR AVAILABILITY FACTOR UNIT SERVICE FACTOR UNIT AVAILABILITY FACTOR UNIT CAPACITY FACTOR (Using MDC)

UNIT CAPACITY FACTOR (Using Design MWe)

UNIT FORCED OUTAGE RATE THIS MONTH 720.0 0.0 720.0 0.0 2.249.211 779.265.0 7490390 100.0%

100.0%

1 00.0 %

100.0%

111.9%

102.3%

0.0%

YR TO DATE 4299.0 0.0 4286.4 0.0 13.485.174.0 4.543.854.0 4.379.436.4 99.0%

99.00/0 98.7%

98.7%

108.4%

99.2%

0.00/0 CUMULATIVE 93.035.8 0.0 90.875.9 4.0 253.114.919.6 83.965.567 80.204.333 68.0%

68.0%

66.5%

66.5%

63.1%

57.7%

6.5%

19.

SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, DURATION OF EACH):

TYPE DATE DURATION N/A

20.

IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

N/A

ATTACHMENT 4 UNIT SHUTDOWNS DOCKET NO.

UNIT DATE 50-461 Clinton 1 06/30/03 COMPLETED BY M. J. Sloan REPORT MONTH June 2003 TYPE FORCED NO.

DATE F:

SCHEDULED METHOD OF SHUTTING DOWN THE REACTOR OR REDUCING POWER DURATION (HOURS)

CORRECTIVE ACTIONS/COMMENTS REASON (1)

(2)

NONE (1)

Reason A - Equipment Failure (explain), B - Maintenance or Test, C - Refueling, D - Regulatory Restriction E - Operator training & License Examination, F - Administrative, G - Operational Error (explain)

(2)

Method 1 - Manual, 2 - Manual Scram, 3 - Automatic Scram, 4 - Other (explain)