TXX-6317, Interim Deficiency Rept CP-85-19 Re Use of Nonrepresentative Sample in Determining Generic Values for Typical Conduit Span Calculations.Initially Reported on 861021.Engineering Evaluations Continuing.Next Rept Expected by 870430

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept CP-85-19 Re Use of Nonrepresentative Sample in Determining Generic Values for Typical Conduit Span Calculations.Initially Reported on 861021.Engineering Evaluations Continuing.Next Rept Expected by 870430
ML20207Q882
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/06/1987
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CP-85-19, TXX-6317, NUDOCS 8703100141
Download: ML20207Q882 (1)


Text

.

E Log # TXX-6317 File # 10110

_ _- C 903.11 r = Ref. # 10CFR50.55(e) tilELECTRIC March 6, 1987 wuu. c.cooma Decuthe ikr />esklent U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 CONOUIT SUPPORT SPANS SDAR: CP-85-19 (INTERIM REPORT)

Gentlemen:

On October 21, 1986, we notified you by our letter logged TXX-6017 of a deficiency regarding the use of a nonrepresentative sample in determining generic values for typical conduit span calculations which we deemed reportable under the provisions of 10CFR50.55(e). This is an interim report to status corrective action implemented to date.

The engineering evaluations and subsequent formulations of corrective actions are continuing. These activities are scheduled for completion by March 30, 1987, for Units 1 and 2.

We anticipate submitting our next report on this issue no later than April 30, 1987.

Very truly yours, W. G. Counsil DAR:lw c - Mr. E. H. Johnson, Region IV Mr. D. L. Kelley, RI - Region IV Mr. H. S. Phillips, RI - Region IV SEU emane S

400 North Oloc Street I H. 81 Dallas, lexas 75201