MONTHYEARML24303A3142024-10-25025 October 2024 Notification of Shearon Harris Nuclear Power Plant FEI and Information Request ML24227A9572024-08-14014 August 2024 LRA - Requests for Additional Information - Set 1 (Email to Applicant) ML24187A0262024-07-0303 July 2024 NRR E-mail Capture - Change in Review Schedule - Harris Risk-Informed Process for Evaluations Exemption (L-2024-LLE-0004) ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24113A2522024-04-22022 April 2024 NRR E-mail Capture - Audit Plan - Shearon Harris Nuclear Power Plant, Unit 1 - RIPE Exemption 10 CFR 50.55a(h)(2) (L-2024-LLE-0004) ML24101A0542024-04-10010 April 2024 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-23-0244 - Extend CT for Accumulators - CLIIP (L-2024-LLA-0032) ML24101A0522024-04-10010 April 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - ITS Alignments LAR (L-2023-LLA-0078) ML24145A1732024-02-26026 February 2024 002 Radiation Safety Baseline Inspection Information Request ML24025A1592024-01-25025 January 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) ML23177A1992023-06-26026 June 2023 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-23-0005 - LAR to Align Certain TSs with ISTS (L-2023-LLA-0078) ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23082A0432023-03-23023 March 2023 002 Radiation Safety Baseline Inspection Information Request Final ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23065A0942023-03-0606 March 2023 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-22-0081 - LAR to Address Administrative Changes to the Operating License and Technical Specifications (L-2023-LLA-0020) ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22108A0182022-04-15015 April 2022 NRR E-mail Capture - Accepted for Review - Duke Energy Relief Request for Harris Nuclear Plant Inservice Testing Program Plan - Fourth Ten-Year Interval to Extend Type C Test to 75 Months ML22083A0702022-03-24024 March 2022 NRR E-mail Capture - Catawba Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, and McGuire Nuclear Station, Units 1 and 2 - Acceptance Review for TSTF-569 LAR ML22083A0282022-03-23023 March 2022 Email Snsb Safety Evaluation for Harris LAR to Revise Reactor Protection System TS ML22038A1572022-02-0707 February 2022 NRR E-mail Capture - Duke Energy Fleet - Acceptance of License Amendment Request Regarding Adoption of TSTF-541, Revision 2 ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21361A0122021-12-23023 December 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Relocate Emergency Operations Facility ML21354A8612021-12-15015 December 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) ML21321A3782021-11-16016 November 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSEL Unit 1 - Acceptance of License Amendment Request Adoption of TSTF-554 EPID-L-2021-LLA-0193 ML21288A0802021-10-15015 October 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-21-0213 - Remove Limitations to Perform Certain SRs During Shutdown (L-2021-LLA-0167) ML21295A0372021-10-0505 October 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Adopt TSTF-577 Revised Frequencies for Steam Generator Tube Inspections ML21252A0112021-08-30030 August 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1- RA-21-0191 - Revised TS Related to Reactor Trip System Instrumentation (L-2021-LLA-0149) ML21189A0282021-07-0101 July 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-21-0112 - Revise TS to Reflect Development of TRM (L-2021-LLA-0108) ML21172A2432021-06-21021 June 2021 NRR E-mail Capture - Request for Additional Information - Harris RA-20-0252 - LAR to Remove Extraneous Requirements from OL and TS (L-2021-LLA-0027) ML21106A0112021-04-15015 April 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-21-0052 - Revise Containment Spray Nozzle Surveillance Frequency (L-2021-LLA-0058) ML21084A2492021-03-24024 March 2021 Notification of Inspection and Request for Information ML21084A2512021-03-22022 March 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-20-0252 - LAR to Remove Extraneous Content and Requirements from the OL and TS (L-2021-LLA-0027) ML21039A6382021-02-0808 February 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1-RA-20-0311 - 10 CFR 50.69 Categorization Process to Reflect an Alternative Seismic Approach (L-2021-LLA-0003) ML21036A1142021-02-0505 February 2021 NRR E-mail Capture - Request for Additional Information - Harris - Relief Request RA-20-0312 - SW Pinhole Leak (L-2020-LLR-0143) ML21049A2632021-02-0404 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan ML21033B1062021-02-0202 February 2021 NRR E-mail Capture - (External_Sender) (External) State Notification of Amendments to Shearon Harris Nuclear Power Plant, Unit 1 - Revision Minimum RCS Flow Rate and Update COLR References ML21033A8452021-02-0202 February 2021 NRR E-mail Capture - State Notification of Amendments to Shearon Harris Nuclear Power Plant, Unit 1 - Revision Minimum RCS Flow Rate and Update COLR References ML21032A0492021-02-0101 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet RA-20-0263 - Use of Later ASME B&Pv, XI for Repair - Replacement (L-2020-LLR-0124) ML21025A2922021-01-25025 January 2021 NRR E-mail Capture - (External_Sender) State Notification of Amendment to Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS 3/4.4.9, Pressure/Temperature Limits - Reactor Coolant System ML21007A3722021-01-0707 January 2021 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-19-0352 - Proposed Alternative for Reactor Vessel Close Stud Examinations (L-2020-LLR-0156) ML21006A4042021-01-0606 January 2021 NRR E-mail Capture - State Notification of Amendment to Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS 3/4.4.9, Pressure/Temperature Limits - Reactor Coolant System ML21006A4302021-01-0606 January 2021 Acceptance Review - Duke Fleet RA-20-0207 Request to Revise the Technical Specification for Engineered Safety Feature Actuation System (ESFAS) Instrumentation ML20345A3052020-12-10010 December 2020 NRR E-mail Capture - (External_Sender) (External) State Notification of Amendments to Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS 3.3.3.6 and TS 3.9.2 ML20344A4192020-12-0909 December 2020 NRR E-mail Capture - State Notification of Amendments to Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS 3.3.3.6 and TS 3.9.2 2024-08-14
[Table view] Category:Inspection Plan
MONTHYEARML24303A3142024-10-25025 October 2024 Notification of Shearon Harris Nuclear Power Plant FEI and Information Request IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24145A1732024-02-26026 February 2024 002 Radiation Safety Baseline Inspection Information Request IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter ML23107A2052023-04-17017 April 2023 Initial Information Request 05000400/2023002 IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) ML22075A3592022-03-17017 March 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21258A3652021-09-15015 September 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) IR 05000400/20210052021-08-26026 August 2021 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2021005) IR 05000400/20200062021-03-0303 March 2021 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2020006 ML20309A2012020-11-0404 November 2020 Radiation Safety Baseline Inspection Information Request IR 05000400/20200052020-08-24024 August 2020 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, NRC Inspection Report 05000400/2020005 ML20223A3702020-08-10010 August 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML19255H2282019-09-12012 September 2019 RFI Unit 1 ISI & Sgisi 2019004 IR 05000400/20190052019-08-27027 August 2019 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2019005 ML19129A2572019-05-0909 May 2019 Heat Sink RFI ML19123A0392019-05-0303 May 2019 Heat Sink RFI 2019002 IR 05000400/20180062019-03-0404 March 2019 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2018006 IR 05000400/20180052018-08-23023 August 2018 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2018005 ML18059A0882018-02-28028 February 2018 EOC Assessment Letter ML18058B2242018-02-26026 February 2018 Emailed Radiation Safety RFI ML18046A3312018-02-0909 February 2018 RFI 2018002 ADAMS Package IR 05000400/20170052017-08-28028 August 2017 Updated Inspection Plan - NRC Inspection Report 05000400/2017005 ML17156A3932017-06-0505 June 2017 PI&R Notification Letter 2017 ML17145A5232017-05-25025 May 2017 Requalification Program Inspection for Shearon Harris Nuclear Plant ML17142A2182017-05-19019 May 2017 Notification of Inspection and Request for Information Dated: May 19, 2017 IR 05000400/20160062017-03-0101 March 2017 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016006 ML16258A2332016-09-13013 September 2016 Notification of Inspection and Request for Information IR 05000400/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016005 ML16113A0062016-04-20020 April 2016 Notification of Inspection and Request for Information IR 05000400/20150062016-03-0202 March 2016 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015006 IR 05000400/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015005 ML15218A0042015-08-0404 August 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20140012015-03-0404 March 2015 Annual Assessment Letter for Shearon Harris Nuclear Power Plant NRC Inspection Report 05000400/2014001 ML14245A1652014-09-0202 September 2014 Mid-Cycle Ltr 2014 ML14066A4732014-03-0707 March 2014 Notification of Shearon Harris Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000400-14-007 ML14063A1492014-03-0404 March 2014 2013 Annual Assessment Letter for Shearon Harris Nuclear Plant ML14023A7972014-01-23023 January 2014 Tfpi 2014008 Notification Letter - Copy ML13246A0662013-09-0303 September 2013 Mid Cycle Assessment Letter ML13120A5892013-04-29029 April 2013 Notification of Inspection and Request for Information IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) IR 05000400/20120012013-03-0404 March 2013 Annual Assessment Letter Shearon Harris, 05000400/2012001 ML12248A0912012-09-0404 September 2012 Mid Cycle Assessment Letter Harris 2012 2024-08-26
[Table view] |
Text
From: Jonathan Rivera (He/Him/His)
To: McDaniel, Sarah A Cc: Binoy Desai; Darrell Neal; Bob Kellner; Jose Diaz Bcc: Jonathan Rivera (He/Him/His)
Subject:
Harris RP inspection document request.
Date: Monday, February 26, 2024 1:48:00 PM Attachments: Harris 2024-002 RP RFI.pdf
Hello Sarah,
Please find attached the document request for our upcoming RP inspection at Harris. Feel free to reach out to me with any questions.
- Thanks, Jonathan
Jonathan Rivera Health Physicist Engineering Branch 3 Division of Reactor Safety U.S. NRC - Region II Office: 404-997-4646 Email: jonathan.rivera@nrc.gov Document Request List Occupational and Public Radiation Safety Cornerstones
Licensee: Harris Nuclear Plant License 50-400
Licensing
Contact:
Sarah McDaniel Regulatory Affairs Office: (984) 229-2002 sarah.mcdaniel@duke-energy.com
Inspection Dates: April 1 - 5 and April 22 - 26, 2024
Documents Due to Region II by: March 27, 2024
Inspection Procedures: IP 71124.01 Radiological Hazard Assessment and Exposure Controls IP 71124.03 In-plant Airborne Radioactivity Control and Mitigation IP 71124.04 Occupational Dose Assessment IP 71124.05 Radiation Monitoring Instrumentation IP 71151 Performance Indicator Verification
Lead Inspector Contact Information:
Jonathan Rivera U.S. Nuclear Regulatory Commission Health Physicist Region II US NRC Region II ATTN: Jonathan Rivera (404) 997-4646 245 Peachtree Center Ave., N.E Jonathan.Rivera@nrc.gov Suite 1200 Atlanta, GA 30303
Note: Current version of these documents is expected unless specified otherwise. Secure file server access (Certrec, SharePoint, etc.), or electronic media (CD/DVD), is preferred. To the extent possible, please organize the information as it is arranged below. Experience has shown that poorly organized files can lead to a less efficient inspection and places additional burden on licensee staff. During the inspection, the inspectors may request additional documents. To the extent possible, please organize the information as it is arranged below. Pay attention to the date ranges for the items requested as they may change from item to item. Please redact all PII in any records submitted. If there are questions regarding the documents requested, or if the documents cannot be provided by the due date, please do not hesitate to contact the lead inspector.
We would prefer as much of the information as possible in electronic form. An index of the files is also helpful. For those items requesting a list of documents/areas, the inspector will select documents/areas from the list for on-site review.
Page 2 of 6 Miscellaneous
- 1. Plant Management, Radiation Protection, and Chemistry organizational charts.
- 2. List of primary contacts for each inspection area with contact information.
- 3. Corrective Action Program (CAP) procedure(s).
- 4. List of radiation protection procedures, including title and number.
- 5. Most recent 10 CFR 61 analysis for the DAW waste stream.
- 6. Most recent copy of the Offsite Dose Calculation Manual (ODCM).
- 7. H1R25 outage schedule, including work activities to be conducted during the weeks of the inspection (e.g., Gantt chart or similar list).
- 8. Procedures associated with the Surveillance Frequency Control Program.
71124.01 - Radiological Hazard Assessment and Exposure Controls (Last inspected June 2023)
- 1. Site and corporate procedures related to RP controls (e.g., postings, labeling, surveys, survey frequency, Radiation Work Permits [RWPs], contamination control, HRA/LHRA/VHRA controls, key control, control of divers, special controls during fuel offload, hot spots, etc.).
- 2. Procedures related to the release of personnel and materials (e.g., release surveys, decontamination, guidance for alarm follow-up, etc.).
- 3. List of planned outage & active online RWPs, including dose and dose rate limits.
- 4. List of locations, or plant maps indicating the location, of LHRAs and VHRAs. Include areas with the potential to become a LHRA during routine operations or outages.
- 5. List of all non-fuel items stored in spent fuel pool (e.g., used filters, irradiated hardware, etc.).
- 6. Technical basis documents (white paper, engineering calculation, etc.) related to the facility beta-gamma and alpha radiation characterization.
- 7. Outage ALARA report from the previous refueling outage.
- 8. ALARA planning packages for the 3 highest dose jobs for the upcoming H1R25 refueling outage.
- 9. All self-assessments or audits covering radiological hazard assessment and exposure controls and HP controls since June 1, 2023.
- 10. List of Corrective Action Program (CAP) documents (CR, NRC, AR, etc.) related to RP controls (e.g., radworker error, HP technician error, posting issues, Nationally Tracked Sources issues, HRA/LHRA/VHRA issues, survey problems, ALARA, etc.) generated since June 1, 2023. This should be a list of corrective action documents containing a CAP document number and a brief description, not complete documents.
71124.03 - In-Plant Airborne Radioactivity Control and Mitigation (Last inspected October 2022)
- 1. Procedures related to airborne monitoring and control (e.g., use of purge systems, use of portable HEPA/charcoal units, temporary ventilation enclosures, use of CAMs, air sampling guidance, Alpha air sampling, etc.), as applicable.
- 2. Procedures related to the use of respiratory protection devices, (e.g., SCBA, TEDE-ALARA guidance, PAPRs, storage, maintenance, training, QA, fit-testing, etc.).
- 3. The two most recent HEPA filter DOP and charcoal test results for the Main Control Room ventilation system.
- 4. Copy of the last 2 grade D air testing certificates for each supplied air system and
Page 3 of 6 SCBA filling station.
- 5. Documentation of the last 2 surveillances performed on SCBAs and negative pressure respirators available for emergency use, and negative pressure respirators designated as in storage but available for use.
- 6. Most recent audit or self-assessment covering airborne controls and respiratory protection.
- 7. List of CRs related to airborne monitoring and respiratory protection since October 1, 2022.
This should be a list of corrective action documents containing a CAP document number and a brief description, not complete documents.
- 8. Available for onsite review during inspection:
a) Inventory, inspection, and maintenance records for respiratory protection devices and SCBA equipment.
b) Training records, including fit tests, for SCBA qualified individuals.
c) List of all licensed operators qualified to wear an SCBA.
d) List of site ERO personnel qualified to wear an SCBA.
e) List of all RP personnel qualified to wear an SCBA.
f) Training/qualification certificates for all onsite and/or vendor personnel qualified to repair SCBAs that performed maintenance or repairs from October 1, 2022 to present.
71124.04 - Occupational Dose Assessment (Last inspected October 2022)
- 1. Procedures related to occupational dose assessment (e.g., dosimetry issuance and use, unusual dosimetry occurrences, multi-badging/extremity dosimetry/badge relocation, Effective Dose Equivalent, personnel contamination events, storage/care of personal dosimeters, in-vivo and in-vitro internal dose assessment, skin dose assessment, QC for whole body counter, use of passive monitoring if applicable, declared pregnant workers).
- 2. NVLAP accreditation documentation for CY 2022, CY 2023, and the current year for worker dosimetry used by the site.
- 3. List of all positive whole-body counts, in vitro, or air sampling analyses which resulted in a CEDE equal to or exceeding 10 millirem since October 1, 2022. [Note: only a listing should be provided for use by the inspectors to select a sample of issues for review during the onsite inspection].
- 4. List of all Level III personnel contamination events identified since October 1, 2022. [Note:
only a listing should be provided for use by the inspectors to select a sample of issues for review during the onsite inspection.]
- 5. Most recent neutron characterization (including the ISFSI area).
- 6. Most recent alpha characterization.
- 7. Last 18 months of area TLD results for general plant areas (not REMP TLDs).
- 8. Copies of current WBC libraries (e.g., routine, medical, investigative, etc.).
- 9. Most recent audit or self-assessment of the dosimetry program and/or the most recent audit of the lab that processes site dosimetry.
- 10. List of CRs generated since October 1, 2022 for internal or external dosimetry issues/events. This should be a list of corrective action documents containing a CAP document number and a brief description, not complete documents.
71124.05 - Radiation Monitoring Instrumentation (Last inspected October 2022)
- 1. Radiation Protection and Maintenance procedures/guidance documents, as applicable, for the following:
a) Calibration and functional test/source checks of portable radiation detection instruments.
Page 4 of 6 b) Calibration and functional tests of small article monitor, personnel contamination monitor, portal monitor, counting room equipment, electronic alarming dosimeters, whole body counting equipment, and continuous air monitors.
c) Collection and analysis of high-range, post-accident effluent samples.
d) Determination of set-points for area radiation monitor, CAM, PCM, PM, and SAM equipment used for area and personnel monitoring equipment.
e) QA program (inter-laboratory comparison program) for count room instruments.
- 2. The last 2 calibration records for each of the following instruments:
a) Plant Vent Stack Monitor (RM-21AV-3509) b) Waste Monitor Tanks Discharge Monitor (21WL-3541) c) Containment High-Range Radiation Monitors (RM-1-3589SA and RM 3590SB) d) Sample Room Area Radiation Monitors (RM-1-3605A and 3605B) e) Fuel Handling Building Normal and Emergency Exhaust Radiation Monitors (1FL-3506, 3507, 3508A, & 3508B) f) Whole Body Counter
- 3. Documentation showing traceability to NIST and/or the primary calibration for the radioactive sources used to calibrate the instruments in item 2 above.
- 4. Chart or procedure listing EALs associated with radiation monitors.
- 5. Emergency plan documents identifying which radiation monitors are used to determine emergency action levels (EALs).
- 6. Provide a current list of in service (available for use) SAMs, PCMs, PMs, air samplers, continuous air monitors (CAMs), portable radiation detection instruments, counting room (RP and Chemistry), and Whole-Body Counters. [Note: The list will be used to select monitors for evaluation during the onsite inspection.]
- 7. Most recent test record of the instrument calibrator (e.g., Shepherd validation testing/dose rate curves).
- 8. Design documents and/or calculations showing how the alarm setpoints for the following instruments are determined:
a) PCMs and PMs at the RCA and Protected Area exit points.
b) CAMs.
- 9. Results of the counting room and whole-body counter Inter-Laboratory Comparison Program since October 1, 2022.
- 10. Two most recent surveillances that verify the flow rates for the following ventilation systems:
a) Reactor Auxiliary Building Ventilation System b) Waste Processing Building Ventilation
- 11. Most recent Radiation Monitoring System engineering performance review/evaluation or system health report, if applicable.
- 12. Most recent audit or self-assessment covering RP instruments (portables, RCA exit point, WBC, count room). Include any reviews conducted of vendor facilities, as applicable.
- 13. List of CAP documents (CR, NRC, AR, etc.) related to portable instruments, area monitors, CAMs, RCA release point monitors, WBCs, and count room instruments generated since October 1, 2022. This should be a list of corrective action documents containing a CAP document number and a brief description, not complete documents.
71151 - Performance Indicator Verification (Occupational and Public Cornerstones)
(Last inspected June 2023 - Occupational and July 2023 - Public)
- 1. Site, Corporate, and radiation protection specific procedure(s) for identifying, reporting, tracking, and correcting performance indicator (PI) occurrences.
- 2. Monthly PI reports since March 1, 2023, and copies of associated condition reports for any
Page 5 of 6 Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual (RETS/ODCM) Radiological Effluent occurrences.
- 3. List of all CAP documents related to effluent dose/ODCM issues using search keywords such as RETS/ODCM, abnormal or unmonitored release, offsite dose, and effluent release, etc. since March 1, 2023. This should be a list of corrective action documents containing a CR number and brief description, not full CRs.
- 4. Most recent gaseous and liquid effluent evaluation of dose to the public (year-to-date doses).
- 5. List of all CAP documents related to occupational radiological controls using search keywords such as HRA, LHRA, VHRA, unintended dose, unlocked door, ALARA, since May 1, 2023. This should be a list of corrective action documents containing a CAP document number and a brief description, not complete documents.
- 6. List of electronic dosimeter alarms since May 1, 2023 (dose and dose rate).
Assistance Requested During On-Site Inspection
x Identification of radiological work activities available during the inspection week for observation, including notification of pre-job briefings, notification of risk significant work activities, and location of audio/visual surveillance for remote job coverage.
x Health physics assistance in coordinating observation of radiological job coverage activities and performing plant walk-downs.
x Identification of any installed radiation monitoring calibration activities planned that may be available for inspector observation during the inspection.
Lead Inspector Contact Information: Mailing Address:
Jonathan Rivera U.S. Nuclear Regulatory Commission Health Physicist US NRC Region II (404) 997-4646 ATTN: Jonathan Rivera Jonathan.Rivera@nrc.gov 245 Peachtree Center Ave., N.E Suite 1200 Atlanta, GA 30303