MONTHYEARML23192A0552023-07-11011 July 2023 Relief Request Later Edition of ASME Code for ISI ML23087A2492023-03-27027 March 2023 50.69 Acceptance Email ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML22291A4602022-10-17017 October 2022 Relief Request Impractical RPV and Rx Coolant Sys. Welds ML21006A4302021-01-0606 January 2021 Acceptance Review - Duke Fleet RA-20-0207 Request to Revise the Technical Specification for Engineered Safety Feature Actuation System (ESFAS) Instrumentation ML20157A1062020-06-24024 June 2020 Review of the Fall 2019 Steam Generator Tube Inspections During Refueling Outage No. 22 ML20133K0722020-05-12012 May 2020 Acceptance of Requested Licensing Action Technical Specifications Related to Reducing the Minimum Required Reactor Coolant System Flow Rate and Update the List of Analytical Methods Used in the Determination of Core Operating Limits ML19311C3412019-11-0707 November 2019 Acceptance Review: Shearon Harris License Amendment Request for TSTF-505 ML18270A1292018-10-0404 October 2018 Acceptance of Requested Licensing Action ML17319A5012017-11-21021 November 2017 Acceptance Review Letter, License Amendment Request to Revise Updated Final Safety Analysis Report to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis ML17261A7272017-09-20020 September 2017 Shearon Harris Nuclear Power Plant, Unit 1 - Acceptance of Requested Licensing Action Regarding Spent Fuel Storage Pool Criticality Analyses (CAC No. MF9996) ML17167A3172017-06-30030 June 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action LAR Proposing Changes to TS3.8.1, AC Source-Operating (CAC Nos. MF9667 Through MF9674) ML16308A3702016-11-0707 November 2016 Results of Acceptance Review of Requested Licensing Action Application to Revise Technical Specifications to Adopt TSTF-522, Revision 0 (CAC Nos. MF8422-MF8429) ML16225A6542016-08-11011 August 2016 Email - McGuire Unit No. 1: Acceptance REVIEW- Relief Request 16-MN-003 Alternative to Defect Removal Prior to Performing Temporary Repair Activities on Three-Inch-Diameter Nuclear Service Water System Piping. ML16215A0972016-08-0101 August 2016 Email - McGuire Units 1 and 2: Acceptance REVIEW- LAR for TS 3.6.14, Divider Barrier Integrity - Hatch to Be Open for Up to 48 Hours ML16152A5962016-06-0303 June 2016 NRC Acceptance of Requested Licensing Action Amendment Request ML16113A3012016-05-0303 May 2016 Acceptance Review of License Amendment Request Alternative Verification of Ice Condenser Lower Inlet Door Position ML16085A0992016-03-31031 March 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request for Control Room Chilled Water System Technical Specifications ML16055A3332016-03-0101 March 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action LAR for Control Room Chilled Water System TS ML16050A0692016-02-19019 February 2016 E-mail from J. Whited to L. Rudy-Acceptance of Catawba LAR Containment Leakage Rate Testing Program ML15309A7282015-12-0101 December 2015 Acceptance of Requested Licensing Action Regarding Duke Energy Progress, Inc. Application to Revise Technical Specifications to Adopt Methodology Report ML15294A5402015-10-28028 October 2015 Acceptance for Technical Review: Exemption from Title 10 of the Code of Federal Regulations Part 74.19(c) ML15266A3692015-10-0505 October 2015 Acceptance for Technical Review: Exemption from Title 10 of the Code of Federal Regulations (10 Cfr), Part 74.19(c) ML14324A9642014-12-0909 December 2014 Acceptance Review of Proposed Changes to Quality Assurance Topical Report ML14246A4552014-09-0808 September 2014 Acceptance Review of License Amendment Request Measurement Uncertainty Recapture Power Uprate ML14157A0552014-06-13013 June 2014 Acceptance of Requested Relief Request I3R-14-Deferral of Reactor Vessel Inspections Inservice Inspection Program-Third 10-Year Interval ML14010A4612014-01-15015 January 2014 Acceptance of Requested Licensing Action License Amendment Request to Adopt National Fire Protection Association (NFPA) 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants ML14014A2792014-01-15015 January 2014 Acceptance of Requested Licensing Action License Amendment Request to Adopt National Fire Protection Association (NFPA) 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating ML13354B8792013-12-31031 December 2013 Acceptance Review Results License Amendment Request to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants ML13329A4572013-11-25025 November 2013 Accepted for Review Shearon Harris--Acceptance Review for Relief Request I3R-13 Reactor Vessel Closure Head Nozzle 37 ML13324B0812013-11-20020 November 2013 E-mail Re. Acceptance Review for Relief Request I3R-12 Repair of Accumulator Fill Valve Piping Weld ML13277A6762013-10-17017 October 2013 Acceptance of Requested Licensing Action Relief Request 13-MN-002 Risk Informed Inservice Inspection Program, Fourth Inservice Inspection Interval ML13150A0322013-05-29029 May 2013 Acceptance Review for TS Sections 3.3.2, 3.5.4, and 3.6.6 ML12122B0262012-04-25025 April 2012 NRR E-mail Capture - Acceptance for Review for License Amendment Request Dated March 5, 2012 ML11181A0162011-07-0101 July 2011 Acceptance for Review of Measurement Uncertainty Recapture Power Uprate License Amendment Request ML1105300792011-02-18018 February 2011 E-mail, Acceptance Review of ME5410, Application for Exemption for M5 Cladding: 1/19/11 ML1018707202010-07-0909 July 2010 Acceptance Review Regarding a Relief Request for Approval of an Alternative Inservice Inspection Method for Six Pressure Retaining Dissimilar Metal Welds in the Reactor Pressure Vessel Nozzles ML0935801382009-12-30030 December 2009 Acceptance Review Regarding Request for Exemption from the Requirements of 10 CFR Part 73, Section 73.55 ML0912705692009-05-15015 May 2009 Acceptance Review Re Amendment to Adopt Tech Spec Task Force (TSTF) Standard Tech Spec Change Traveler, TSTF-447, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors ML0903603132009-02-0606 February 2009 Acceptance Review Regarding Amendment to Remove Credit for Boraflex in Boiling Water Reactor Spent Fuel Pool Storage Racks ML0903000302009-01-30030 January 2009 Acceptance Review Regarding Amendment to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition ML0902100672009-01-29029 January 2009 Acceptance Review Regarding Relief Request to Defer an ASME Code Repair of an Emergency Service Water System Weld Until the Next Refueling Outage ML0902100112009-01-27027 January 2009 Acceptance Review Regarding Amendment to Remove Credit for Boraflex in BWR Spent Fuel Pool Storage Racks ML0827011582008-09-26026 September 2008 Acceptance Review Regarding the License Amendment Request to Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants. 2023-07-11
[Table view] Category:E-Mail
MONTHYEARML24025A1592024-01-25025 January 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) ML24029A1132024-01-16016 January 2024 Notification of Inspection and Request for Information (Email) ML23271A1792023-09-28028 September 2023 Request for Confirmation License Amendment Application to Revise Control Room Cooling TS 3.7.11 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23192A0552023-07-11011 July 2023 Relief Request Later Edition of ASME Code for ISI ML23188A0732023-07-0707 July 2023 Acceptance of Requested Licensing Action License Amendment Application to Revise Control Room Cooling Technical Specifications ML23177A1992023-06-26026 June 2023 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-23-0005 - LAR to Align Certain TSs with ISTS (L-2023-LLA-0078) ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23087A2492023-03-27027 March 2023 50.69 Acceptance Email ML23087A0282023-03-27027 March 2023 Acceptance of Requested Licensing Action Amendment TSTF-505 ML23082A0432023-03-23023 March 2023 002 Radiation Safety Baseline Inspection Information Request Final ML23080A1892023-03-20020 March 2023 RP Inspection Document Request ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23065A0942023-03-0606 March 2023 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-22-0081 - LAR to Address Administrative Changes to the Operating License and Technical Specifications (L-2023-LLA-0020) ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML23030B9032023-01-30030 January 2023 Formal Release of RAIs for McGuire Unit 1, Relief Request Impractical RPV Rx Coolant System Welds, Due March 1, 2023 (Email) ML23017A2232023-01-13013 January 2023 Request for Additional Information (RAI) Issuance for McGuire Unit 1 Steam Generator Tube Inspection Report (Email) ML22336A0692022-11-28028 November 2022 Final 2023 Catawba Nuclear Station (CNS) Commercial Grade Dedication (CGD) Inspection Information Request ML22303A0052022-10-24024 October 2022 EN 56178 - Tioga Final. LTR-TP-22-29 2021 10CFR Part 21 Improper Notification of NRC ML22291A4602022-10-17017 October 2022 Relief Request Impractical RPV and Rx Coolant Sys. Welds NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22242A1602022-08-30030 August 2022 Hardship Relief Request Pilot-Operated Relief Valve Acceptance Review Results ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request ML22213A0472022-08-0101 August 2022 Document Request for Catawba Nuclear Station - Radiation Protection Inspection - Inspection Report 2022-03 NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22154A1312022-06-0303 June 2022 NRR E-mail Capture - Catawba Nuclear Station, Units 1 and 2 - Request for Additional Information Environmentally-Assisted Fatigue License Renewal Commitment ML22174A0802022-06-0101 June 2022 Transmittal External Distribution Notification TR-NUC-CN-014344 - SLC Manual Revision to Loes and SLC 16.7-5 ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22108A0182022-04-15015 April 2022 NRR E-mail Capture - Accepted for Review - Duke Energy Relief Request for Harris Nuclear Plant Inservice Testing Program Plan - Fourth Ten-Year Interval to Extend Type C Test to 75 Months ML22083A0702022-03-24024 March 2022 NRR E-mail Capture - Catawba Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, and McGuire Nuclear Station, Units 1 and 2 - Acceptance Review for TSTF-569 LAR ML22083A0282022-03-23023 March 2022 Email Snsb Safety Evaluation for Harris LAR to Revise Reactor Protection System TS ML22049B0152022-02-17017 February 2022 NRC RP Inspection Document Request Letter ML22041A5312022-02-10010 February 2022 NRR E-mail Capture - Catawba Nuclear Station Unit 2 - Acceptance of Requested Licensing Action Use of Alternative Requirements of ASME Code for Embedded Flaw Repair Method on Reactor Vessel Closure Head Penetration 74 EPID L-2022-LLR-0010 ML22038A1572022-02-0707 February 2022 NRR E-mail Capture - Duke Energy Fleet - Acceptance of License Amendment Request Regarding Adoption of TSTF-541, Revision 2 ML22024A3952022-01-24024 January 2022 Acceptance of Requested Licensing Action Amendment McGuire RCS PT Limits Change TS 3.4.3 and EFPY Changes ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22024A1112022-01-0707 January 2022 E-mail Capture- Catawba POV Inspection Information Request (1) ML21361A0122021-12-23023 December 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Relocate Emergency Operations Facility ML21354A8612021-12-15015 December 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) ML21335A2252021-12-0101 December 2021 NRR E-mail Capture - Catawba Nuclear Station, Unit 2 - Request for Additional Information Spring 2021 Steam Generator Tube Inspection Report (L-2021-LRO-0043) ML21286A7812021-11-22022 November 2021 Acceptance of Requested Licensing Action Revision to the End of Cycle Moderator Temperature Coefficient Measurement Methodology ML21321A3782021-11-16016 November 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSEL Unit 1 - Acceptance of License Amendment Request Adoption of TSTF-554 EPID-L-2021-LLA-0193 ML21288A0802021-10-15015 October 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-21-0213 - Remove Limitations to Perform Certain SRs During Shutdown (L-2021-LLA-0167) ML21295A0372021-10-0505 October 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Adopt TSTF-577 Revised Frequencies for Steam Generator Tube Inspections 2024-01-25
[Table view] |
Text
From: Hood, Tanya To: Steve.Snider@duke-energy.com Cc: Zaremba, Arthur H.
Subject:
Acceptance Review - Duke Fleet - RA-20-0207 - Request to revise the Technical Specification for Engineered Safety Feature Actuation System (ESFAS) Instrumentation (EPID L-2020-LLA-0262)
Date: Wednesday, January 06, 2021 11:01:00 AM
SUBJECT:
CATAWBA NUCLEAR STATION, UNITS 1 AND 2; MCGUIRE NUCLEAR STATION, UNITS 1 AND 2; AND SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: APPLICATION TO REVISE THE TECHNICAL SPECIFICATION FOR ENGINEERED SAFETY FEATURE ACTUATION SYSTEM (ESFAS)
INSTRUMENTATION (EPID L-2020-LLA-0262)
Dear Mr. Snider:
By letter dated December 3, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20338A264), Duke Energy Progress, LLC (the licensee) submitted a license amendment request (LAR) for Catawba Nuclear Station (Catawba), Units 1 and 2; McGuire Nuclear Station (McGuire), Units 1 and 2; and Shearon Harris Nuclear Power Plant (Harris), Unit 1. The licensee is proposing changes to the Engineered Safety Feature Actuation System (ESFAS) Instrumentation Technical Specifications (TSs) for Catawba, McGuire, and Harris to prevent unnecessary trips of the main turbine during turbine warm up that adversely impacts startup and shutdown evolutions. The proposed amendment would modify TSs requirements to Table 3.3.2-1, Function 8.a. of TS 3.3.2, Engineered Safety Feature Actuation System (ESFAS)
Instrumentation for Catawba and Harris. For Harris, the proposed change would revise Table 3.3-3, Functional Unit 10.c. of TS 3/4.3.2, Engineered Safety Features Actuation System Instrumentation. For Catawba only, the licensee is proposing the removal of the steam dump function of the P-4 interlock in MODES 1, 2, and 3. The licensee is also proposing to add a footnote to the applicable modes portion of the P-4 interlock Function to identify the enabled functions and the applicable MODES for each enabled function. In doing so, the licensee is proposing the removal of the turbine trip function of the P-4 interlock in MODE 3 from the existing specifications.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 605 hours0.007 days <br />0.168 hours <br />0.001 weeks <br />2.302025e-4 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is January 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine
interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.
If you have any questions, please contact me.
Tanya E. Hood Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, Maryland 20852-2738 301-415-1387 Tanya.Hood@nrc.gov