MONTHYEARML24303A3142024-10-25025 October 2024 Notification of Shearon Harris Nuclear Power Plant FEI and Information Request IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24145A1732024-02-26026 February 2024 002 Radiation Safety Baseline Inspection Information Request IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter ML23107A2052023-04-17017 April 2023 Initial Information Request 05000400/2023002 IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) ML22075A3592022-03-17017 March 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21258A3652021-09-15015 September 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) IR 05000400/20210052021-08-26026 August 2021 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2021005) IR 05000400/20200062021-03-0303 March 2021 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2020006 ML20309A2012020-11-0404 November 2020 Radiation Safety Baseline Inspection Information Request IR 05000400/20200052020-08-24024 August 2020 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, NRC Inspection Report 05000400/2020005 ML20223A3702020-08-10010 August 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML19255H2282019-09-12012 September 2019 RFI Unit 1 ISI & Sgisi 2019004 IR 05000400/20190052019-08-27027 August 2019 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2019005 ML19129A2572019-05-0909 May 2019 Heat Sink RFI ML19123A0392019-05-0303 May 2019 Heat Sink RFI 2019002 IR 05000400/20180062019-03-0404 March 2019 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2018006 IR 05000400/20180052018-08-23023 August 2018 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2018005 ML18059A0882018-02-28028 February 2018 EOC Assessment Letter ML18058B2242018-02-26026 February 2018 Emailed Radiation Safety RFI ML18046A3312018-02-0909 February 2018 RFI 2018002 ADAMS Package IR 05000400/20170052017-08-28028 August 2017 Updated Inspection Plan - NRC Inspection Report 05000400/2017005 ML17156A3932017-06-0505 June 2017 PI&R Notification Letter 2017 ML17145A5232017-05-25025 May 2017 Requalification Program Inspection for Shearon Harris Nuclear Plant ML17142A2182017-05-19019 May 2017 Notification of Inspection and Request for Information Dated: May 19, 2017 IR 05000400/20160062017-03-0101 March 2017 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016006 ML16258A2332016-09-13013 September 2016 Notification of Inspection and Request for Information IR 05000400/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016005 ML16113A0062016-04-20020 April 2016 Notification of Inspection and Request for Information IR 05000400/20150062016-03-0202 March 2016 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015006 IR 05000400/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015005 ML15218A0042015-08-0404 August 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20140012015-03-0404 March 2015 Annual Assessment Letter for Shearon Harris Nuclear Power Plant NRC Inspection Report 05000400/2014001 ML14245A1652014-09-0202 September 2014 Mid-Cycle Ltr 2014 ML14066A4732014-03-0707 March 2014 Notification of Shearon Harris Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000400-14-007 ML14063A1492014-03-0404 March 2014 2013 Annual Assessment Letter for Shearon Harris Nuclear Plant ML14023A7972014-01-23023 January 2014 Tfpi 2014008 Notification Letter - Copy ML13246A0662013-09-0303 September 2013 Mid Cycle Assessment Letter ML13120A5892013-04-29029 April 2013 Notification of Inspection and Request for Information IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) IR 05000400/20120012013-03-0404 March 2013 Annual Assessment Letter Shearon Harris, 05000400/2012001 ML12248A0912012-09-0404 September 2012 Mid Cycle Assessment Letter Harris 2012 2024-08-26
[Table view] Category:Letter
MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter 05000400/LER-2022-006-02, Auxiliary Feedwater Pump Inoperability2023-07-11011 July 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20243012023-05-15015 May 2023 – Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility 05000400/LER-1922-006-01, Auxiliary Feedwater Pump Inoperability2023-03-10010 March 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 05000400/LER-2022-007-01, Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus2023-01-26026 January 2023 Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) 05000400/LER-2022-006, Auxiliary Feedwater Pump Inoperability2022-12-20020 December 2022 Auxiliary Feedwater Pump Inoperability 2024-09-10
[Table view] |
Text
ML19129A257 Harris Nuclear Station - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION Mr. Charles Yarley:
From June 17 - June 21 2019, the Nuclear Regulatory Commission (NRC) will perform the triennial portion of the baseline heat sink inspection at the Harris Nuclear Station in accordance with NRC inspection procedure IP 71111.07, Heat Sink Performance.
Experience has shown that this inspection is resource intensive for both the NRC inspectors and your staff. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we are requesting in advance documents needed for this activity.
Section A of the enclosure identifies information to be provided prior to the inspection to ensure adequate sample selection and preparation. The NRC requests that these documents be provided to the lead inspector no later than June 7, 2019. Section B of the enclosure identifies additional information the inspectors will need upon arrival at the site to complete the review of inspection samples. The inspection staff will appreciate if all the documents requested are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
Please note that our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection, changes to the schedule of activities, or the material requested, please contact the lead inspector, Al Butcavage, at (404) 997-4640 or Alexander.Butcavage@nrc.gov or the Engineering Branch 3 Chief, Brian Bonser at (404) 997-4653.
In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
PAPERWORK REDUCTION ACT STATEMENT This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.
PUBLIC PROTECTION NOTIFICATION The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
HEAT SINK PERFORMANCE DOCUMENT REQUEST Inspection Dates: June 17 - June 21, 2019 Inspection Procedures: IP 71111.07, Heat Sink Performance dated 12/08/16 Inspector: Al Butcavage A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (preferred), in care of Al Butcavage by June 7, 2019, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (Section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector, and the provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.
Heat Exchangers and Service Water Equipment
- 1. List of heat exchangers (HXs) or equipment cooled by service water (SW) directly or indirectly.
- 2. Include the risk ranking from the site specific risk assessment for each listed HX.
- 3. Detail whether any cleaning or inspection activities are planned during the proposed onsite inspection period for any of the listed HXs.
- 4. For HXs directly cooled by SW, provide the testing, inspection, maintenance, and monitoring of biotic fouling and macro-fouling program documents.
- 5. Detail the HX performance inspection methods for HXs that are inspected/cleaned.
- 6. Response to Generic Letter 89-13 including any regulatory commitments made.
- 7. Design Basis documents associated with the SW system.
- 8. Design Basis documents associated with the Ultimate Heat Sink (UHS).
- 9. SW system flow diagrams.
- 10. Recent Health Reports associated with the SW System and systems that are cooled by SW.
- 11. List of SW system related corrective action documents (with a brief description) which have received a Root Cause Analysis or an elevated severity level in the last
three years.
- 12. Recent Operating Experience Events (last three years).
- 13. List of applicable Codes and Industry Guidelines.
- 14. List of findings and violations in the heat sink/heat exchanger performance area for the last three years.
- 15. List of redundant or infrequently used HXs.
- 16. Chemistry Program for safety-related HXs.
- 17. Detail whether the UHS is above ground encapsulated by embankments, weirs or excavated side slopes; underwater weir or excavation; or forced draft cooling tower or spray pond.
- 18. Provide a list of buried or inaccessible piping and the piping test program, inspection or monitoring program.
- 19. List of safety-related and non-safety related valve interfaces.
- 20. Most recent self-assessment reports performed on the UHS and SW systems.
B. Information to be provided on-site to the inspector at the entrance meeting June 17, 2019:
Heat Exchangers and Service Water Equipment The inspector will select two to four heat exchangers and/or heat sink samples as required by the inspection procedure during in-office preparation. The following items will be requested when the selections are made:
- 1. Updated list of System Engineers.
- 2. List of any through-wall leaks including completed or planned corrective actions and structural evaluations.
- 3. Provide a copy of the corrective actions and supporting documentation.
- 4. For the HXs that have Visual and/or Eddy Current Testing performed, provide a copy of the written procedures used, examination records, examiner qualification records, and associated corrective action documents.
- 5. Heat transfer calculations.
- 6. Evaluations for the potential of water hammer.
- 7. Documentation for controls and operational limits for excessive flow induced vibrations.
- 8. Periodic flow test results at/or near maximum design flow.
- 9. For an UHS that is encapsulated by embankments, weirs, or excavated side slopes, provide third party dam inspection results, and documentation showing that there is sufficient reservoir capacity.
- 10. For an UHS that is an underwater weir or excavation, provide documentation demonstrating:
- Periodic monitoring and trending of sediment build-up
- Sufficient reservoir capacity
- Considerations for adjacent non-seismic and/or non-safety related structures of possible degradation or blocking of safety-related flow paths due to severe weather or seismic events
- Performance monitoring of heat transfer capabilities
- Performance monitoring of UHS structural integrity
- SW flow balance test results Inspector Contact Information:
Al Butcavage Reactor Inspector 404-997-4640 Alexander.Butcavage@nrc.gov Mailing Address:
US NRC Region 2 Attn: Alexander Butcavage Marquis One Tower 245 Peachtree Center Avenue, NE Suite 1200 Atlanta, GA 30303
From: Butcavage, Alexander To: Charles.Yarley@duke-energy.com Cc: Bonser, Brian; Egelstad, Donna
Subject:
Heat Sink Inspection RFI Date: Wednesday, May 01, 2019 5:25:29 PM Attachments: Harris Heat Sink 2019002 .pdf Mr. Charles Yarley, Please find attached the NRC request for information for use during the upcoming Harris Nuclear Plant Tri-Annual Heat Sink Inspection in accordance with IP 71111.07, Heat Sink Performance, Scheduled for 17 - 21 June, 2019.
Please confirm receipt of this request by return E-mail.
Thank You in advance for your help in compiling the requested information.
Al Butcavage USNRC R-II Alexander.Butcavage@nrc.gov x404-997-4640