Mid Cycle Assessment Letter
ML13246A066
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 09/03/2013
From: Croteau R
Division Reactor Projects II
To: Kapopoulos E
Carolina Power & Light Co
References
IR-13-006
Download: ML13246A066 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 3, 2013 Mr. Ernie Kapopoulos, Vice President Carolina Power and Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165

SUBJECT:

MID CYCLE ASSESSMENT LETTER FOR SHEARON HARRIS NUCLEAR POWER PLANT (NRC INSPECTION REPORT 05000400/2013006)

Dear Mr. Kapopoulos:

On August 14, 2013, the NRC staff completed its mid-cycle performance review of the Shearon Harris Nuclear Power Plant, Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2012, through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Shearon Harris Nuclear Power Plant, Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

Plant performance for the first three quarters of the assessment period was within the Regulatory Response column of the NRCs ROP Action Matrix based on one inspection finding being classified as having low-to-moderate safety significance (i.e., White) and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). The White finding involved the failure to adequately maintain the ventilation system equipment of the Emergency Operations Facility for protracted periods of time. This White finding was closed on March 22, 2013, as documented in our letter to you dated April 23, 2013 [ML13114A069]. Unit 1 returned to the Licensee Response Column of the ROP Action Matrix in the second quarter of 2013.

The enclosed inspection plan lists the inspections scheduled through December 31, 2014.

Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end of cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

E. Kapopoulos 2 We also plan on conducting: two non ROP baseline inspections; Initial Operator Licensing Examinations; and 2515/TI-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping, Phase 2.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact George Hopper at 404-997-4645 with any questions you may have regarding this letter.

Sincerely,

/William Jones RA for/

Richard P. Croteau, Director Division of Reactor Projects Docket No.: 50-400 License No.: NPF-63

Enclosure:

Harris Inspection/Activity Plan (09/01/2013 - 12/31/2014) cc: Distribution via Listserv

_________________________ X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JSD /RA/ GTH /RA/ WJB /RA for/

NAME JDodson GHopper RCroteau DATE 08/23/2013 09/03/2013 09/03/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO E. Kapopoulos 3 Letter to Ernie Kapopoulos from Richard P. Croteau dated September 3, 2013

SUBJECT:

MID CYCLE ASSESSMENT LETTER FOR SHEARON HARRIS NUCLEAR POWER PLANT (NRC INSPECTION REPORT 05000400/2013006)

DISTRIBUTION:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMShearonHarris Resource Institute of Nuclear Power Operations (INPO)

ROP Reports

Page 1 of 1 Harris 09/03/2013 08:02:28 Inspection / Activity Plan Report 22 09/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site TI-182 - TI-182 BURIED PIPING/TANK - PHASE 2 1 1 09/09/2013 09/11/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping OL EXAM - INITIAL EXAM WEEK 1 3 1 09/09/2013 09/13/2013 V23403 HARRIS/SEPTEMBER 2013 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM WEEK 2 3 1 09/16/2013 09/20/2013 V23403 HARRIS/SEPTEMBER 2013 INITIAL EXAM AT POWER FACILITIES RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1 11/18/2013 11/22/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 11/18/2013 11/22/2013 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1 11/18/2013 11/22/2013 IP 71151 Performance Indicator Verification TFPI - TRIENNIAL FIRE PROTECTION INSP 4 1 04/21/2014 04/25/2014 IP 7111105x Fire Protection - NFPA 805 (Triennial) 1 05/05/2014 05/09/2014 IP 7111105x Fire Protection - NFPA 805 (Triennial)

EP - EP PROGRAM INSPECTION 1 1 04/21/2014 04/25/2014 IP 7111402 Alert and Notification System Testing 1 04/21/2014 04/25/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 04/21/2014 04/25/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 04/21/2014 04/25/2014 IP 71151 Performance Indicator Verification CDBI - COMPONENT DESIGN BASES INSPECTION 6 1 06/02/2014 06/06/2014 IP 7111121 Component Design Bases Inspection 1 06/23/2014 06/27/2014 IP 7111121 Component Design Bases Inspection 1 07/07/2014 07/11/2014 IP 7111121 Component Design Bases Inspection 1 07/21/2014 07/25/2014 IP 7111121 Component Design Bases Inspection RP - RP PUBLIC RADIATION SAFETY BASELINE 4 1 08/18/2014 08/22/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 08/18/2014 08/22/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 08/18/2014 08/22/2014 IP 71124.07 Radiological Environmental Monitoring Program 1 08/18/2014 08/22/2014 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1 08/18/2014 08/22/2014 IP 71151 Performance Indicator Verification Comments:

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure