NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-20-0252 - LAR to Remove Extraneous Content and Requirements from the OL and TS (L-2021-LLA-0027)
ML21084A251
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/22/2021
From: Michael Mahoney
NRC/NRR/DORL/LPL2-2
To: Earp D
Duke Energy Progress
References
L-2021-LLA-0027
Download: ML21084A251 (3)


Text

From: Mahoney, Michael Sent: Monday, March 22, 2021 6:25 PM To: Dennis Earp (dennis.Earp@duke-energy.com)

Cc: Art Zaremba

Subject:

Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1- RA-20-0252

- LAR to Remove Extraneous Content and Requirements from the OL and TS (L-2021-LLA-0027)

Dennis, By letter RA-20-0252, dated February 24, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21055A819), Duke Energy Carolinas, LLC and Duke Energy Progress, LLC (Duke Energy, the licensee) submitted a submitted a license amendment request (LAR) to revise the Shearon Harris Nuclear Power Plant, Unit 1 (HNP) facility operating license (FOL) and Technical Specifications. The proposed amendment would remove License Condition 2.G, Reporting to the Commission, which requires the licensee to report any violations of Operating License Section 2.C within twenty-four hours to the NRC Operations Center via the Emergency Notification System with a written follow-up within 30 days. Additionally, the proposed change would delete HNP TS 3/4.4.10, Structural Integrity, revise Administrative Control TS 6.1.2 to eliminate the annual management directive requirement, and revise TS Table 4.3-2, Engineered Safety Features Actuation System Instrumentation Surveillance Requirements, to remove an overly restrictive requirement that impedes the full application of the Surveillance Frequency Control Program for a specific subset of relays. Lastly, the proposed amendment would also revise HNP TS to remove the Index and place it under licensee control.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 300 hours0.00347 days <br />0.0833 hours <br />4.960317e-4 weeks <br />1.1415e-4 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is March 25, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

If you have any questions, please contact me.

Thanks Mike Mahoney Project Manager, LPL2-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Desk: (301)-415-3867 Mobile: (301)-250-0450 Email: Michael.Mahoney@nrc.gov

Hearing Identifier: NRR_DRMA Email Number: 1083 Mail Envelope Properties (BLAPR09MB6017EDE69399BA576DBA7630E5659)

Subject:

Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1- RA-20-0252 -

LAR to Remove Extraneous Content and Requirements from the OL and TS (L-2021-LLA-0027)

Sent Date: 3/22/2021 6:24:39 PM Received Date: 3/22/2021 6:24:43 PM From: Mahoney, Michael Created By: Michael.Mahoney@nrc.gov Recipients:

"Art Zaremba" <Arthur.Zaremba@duke-energy.com>

Tracking Status: None "Dennis Earp (dennis.Earp@duke-energy.com)" <dennis.Earp@duke-energy.com>

Tracking Status: None Post Office: BLAPR09MB6017.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 4302 3/22/2021 6:24:43 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: