MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter 05000400/LER-2022-006-02, Auxiliary Feedwater Pump Inoperability2023-07-11011 July 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20243012023-05-15015 May 2023 – Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility 05000400/LER-1922-006-01, Auxiliary Feedwater Pump Inoperability2023-03-10010 March 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 05000400/LER-2022-007-01, Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus2023-01-26026 January 2023 Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) 05000400/LER-2022-006, Auxiliary Feedwater Pump Inoperability2022-12-20020 December 2022 Auxiliary Feedwater Pump Inoperability 2024-09-10
[Table view] Category:Inspection Plan
MONTHYEARML24303A3142024-10-25025 October 2024 Notification of Shearon Harris Nuclear Power Plant FEI and Information Request IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24145A1732024-02-26026 February 2024 002 Radiation Safety Baseline Inspection Information Request IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter ML23107A2052023-04-17017 April 2023 Initial Information Request 05000400/2023002 IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) ML22075A3592022-03-17017 March 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21258A3652021-09-15015 September 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) IR 05000400/20210052021-08-26026 August 2021 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2021005) IR 05000400/20200062021-03-0303 March 2021 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2020006 ML20309A2012020-11-0404 November 2020 Radiation Safety Baseline Inspection Information Request IR 05000400/20200052020-08-24024 August 2020 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, NRC Inspection Report 05000400/2020005 ML20223A3702020-08-10010 August 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML19255H2282019-09-12012 September 2019 RFI Unit 1 ISI & Sgisi 2019004 IR 05000400/20190052019-08-27027 August 2019 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2019005 ML19129A2572019-05-0909 May 2019 Heat Sink RFI ML19123A0392019-05-0303 May 2019 Heat Sink RFI 2019002 IR 05000400/20180062019-03-0404 March 2019 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2018006 IR 05000400/20180052018-08-23023 August 2018 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2018005 ML18059A0882018-02-28028 February 2018 EOC Assessment Letter ML18058B2242018-02-26026 February 2018 Emailed Radiation Safety RFI ML18046A3312018-02-0909 February 2018 RFI 2018002 ADAMS Package IR 05000400/20170052017-08-28028 August 2017 Updated Inspection Plan - NRC Inspection Report 05000400/2017005 ML17156A3932017-06-0505 June 2017 PI&R Notification Letter 2017 ML17145A5232017-05-25025 May 2017 Requalification Program Inspection for Shearon Harris Nuclear Plant ML17142A2182017-05-19019 May 2017 Notification of Inspection and Request for Information Dated: May 19, 2017 IR 05000400/20160062017-03-0101 March 2017 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016006 ML16258A2332016-09-13013 September 2016 Notification of Inspection and Request for Information IR 05000400/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016005 ML16113A0062016-04-20020 April 2016 Notification of Inspection and Request for Information IR 05000400/20150062016-03-0202 March 2016 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015006 IR 05000400/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015005 ML15218A0042015-08-0404 August 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20140012015-03-0404 March 2015 Annual Assessment Letter for Shearon Harris Nuclear Power Plant NRC Inspection Report 05000400/2014001 ML14245A1652014-09-0202 September 2014 Mid-Cycle Ltr 2014 ML14066A4732014-03-0707 March 2014 Notification of Shearon Harris Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000400-14-007 ML14063A1492014-03-0404 March 2014 2013 Annual Assessment Letter for Shearon Harris Nuclear Plant ML14023A7972014-01-23023 January 2014 Tfpi 2014008 Notification Letter - Copy ML13246A0662013-09-0303 September 2013 Mid Cycle Assessment Letter ML13120A5892013-04-29029 April 2013 Notification of Inspection and Request for Information IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) IR 05000400/20120012013-03-0404 March 2013 Annual Assessment Letter Shearon Harris, 05000400/2012001 ML12248A0912012-09-0404 September 2012 Mid Cycle Assessment Letter Harris 2012 2024-08-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 29, 2013 Mr. George T. Hamrick Vice President Shearon Harris Nuclear Power Plant Carolina Power and Light Company P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165
SUBJECT:
HARRIS NUCLEAR PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Hamrick:
During the week of June 17-21, 2013, the Nuclear Regulatory Commission (NRC) will perform a baseline Radiation Safety Inspection at the Harris Nuclear Plant (NRC Inspection Procedures 71124.06, 71124.07, and Radiation Safety Sections of 71151). In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this activity. The NRC requests that these documents be provided to the inspectors no later than June 3, 2013.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Michael Wallace of your organization. If there are any questions about this inspection, or the material requested, please contact the lead inspector, Adam Nielsen, at (404) 997-4660, or the Branch Chief of Plant Support Branch, Brian Bonser, at (404) 997-4653.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget under control numbers 3150-0008, 3150-0011, 3150-0014, 3150-0044, and 3150-0135. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its Enclosure will be available electronically for public inspection in the NRC Public Document
G. Hamrick 2 Room or from the Publicly Available Records component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
Brian Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket No.: 50-400 License No.: NPF-63
Enclosure:
Pre- Inspection Document Request List
_________________________ G SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII: DRS RII: DRS SIGNATURE RA RA NAME ANielsen BBonser DATE 4/29/2013 4/29/2013 5/ /2013 5/ /2013 5/ /2013 5/ /2013 5/ /2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO G. Hamrick 3 cc:
Brian Bernard David H. Corlett Manager, Nuclear Services and EP Supervisor Nuclear Protective Services Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution Electronic Mail Distribution Brian C. McCabe David T. Conley Manager, Nuclear Oversight Senior Counsel Shearon Harris Nuclear Power Plant Legal Department Progress Energy Progress Energy Electronic Mail Distribution Electronic Mail Distribution George T. Hamrick Donna B. Alexander Vice President Manager, Nuclear Regulatory Affairs Carolina Power and Light Company (interim)
Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution Electronic Mail Distribution Lara S. Nichols John H. O'Neill, Jr.
Deputy General Counsel Shaw, Pittman, Potts & Trowbridge Duke Energy Corporation 2300 N. Street, NW Electronic Mail Distribution Washington, DC 20037-1128 M. Christopher Nolan Joseph W. Donahue Director - Regulatory Affairs Vice President General Office Nuclear Oversight Duke Energy Corporation Progress Energy Electronic Mail Distribution Electronic Mail Distribution Robert J. Duncan II W. Lee Cox, III Senior Vice President Section Chief Progress Energy Radiation Protection Section Electronic Mail Distribution N.C. Department of Environmental Commerce & Natural Resources Sean T. O'Connor Electronic Mail Distribution Manager, Support Services Shearon Harris Nuclear Power Plant Public Service Commission Electronic Mail Distribution State of South Carolina P.O. Box 11649 Donald L. Griffith Columbia, SC 29211 Training Manager Shearon Harris Nuclear Power Plant Chairman Progress Energy North Carolina Utilities Commission Electronic Mail Distribution Electronic Mail Distribution R. Keith Holbrook Manager, Support Services cc continued: (See page 4)
Shearon Harris Nuclear Power Plant Electronic Mail Distribution
G. Hamrick 4 cc: (continued) Ernest J. Kapopoulos Jr.
Terrence E. Slake Plant General Manager Manager Carolina Power and Light Company Nuclear Plant Security Shearon Harris Nuclear Power Plant Shearon Harris Nuclear Power Plant Electronic Mail Distribution Electronic Mail Distribution Chair Robert P. Gruber Board of County Commissioners of Executive Director Chatham County Public Staff - NCUC P.O. Box 1809 4326 Mail Service Center Pittsboro, NC 27312 Raleigh, NC 27699-4326 Senior Resident Inspector Chair U.S. Nuclear Regulatory Commission Board of County Commissioners of Wake Shearon Harris Nuclear Power Plant County U.S. NRC P.O. Box 550 5421 Shearon Harris Rd Raleigh, NC 27602 New Hill, NC 27562-9998
Pre- Inspection Document Request List Inspection Dates: June 17-21, 2013 Documents Due to Region II by: June 3, 2013 Inspection Procedures: IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment IP 71124.07 Radiological Environmental Monitoring Program IP 71151 Performance Indicator Verification Lead Inspector: Adam Nielsen Sr. Health Physicist US NRC Region II (404) 997-4660 Adam.Nielsen@nrc.gov Note: The current version of these documents is expected unless specified otherwise.
Electronic media is preferred if readily available. Note that the inspectors cannot accept data provided on USB or flash drives due to NRC IT security policies. Please organize the information as it is arranged below to the extent possible. Experience has shown that a poorly organized CD leads to a less efficient inspection and places additional burden on licensee staff.
Pay particular attention to the date ranges for the items requested as they may change from item to item. If there are questions regarding the documents requested, please do not hesitate to contact the lead inspector.
Miscellaneous
- 1. List of primary contacts for each inspection area w/phone numbers
- 2. Corrective action program procedure
- 3. Most recent 10 CFR 61 results for the DAW waste stream
- 4. Procedure for gathering and reporting NRC PI data 71124.06 - Radioactive Gaseous and Liquid Effluent Treatment
- 1. Offsite Dose Calculation Manual (ODCM) and a list of changes made in the last revision
- 2. List of permitted effluent release points, including any release points from onsite surface water bodies (as applicable)
- 3. Procedures for:
a) collection, analysis, release and dose evaluations for gaseous and liquid effluents b) groundwater monitoring program
- 4. List of changes made to radioactive effluent processing/discharge systems since August 2011
- 5. List of any non-radioactive systems that have become contaminated since August 2011
- 6. List of any unmonitored, unplanned, or otherwise abnormal gaseous or liquid releases since August 2011. Include copies of any reports to the NRC (via 10CFR50.72 or other reporting requirements) regarding abnormal onsite spills/leaks of radioactive material
- 7. List of 10 CFR 50.75(g) entries made since August 2011 Enclosure
2
- 8. List of liquid and gaseous effluent monitors listed as out-of-service (OOS) for > 1 day since August 2011, including any special reports submitted to the NRC as a result of effluent monitor operability
- 9. Inter-laboratory comparison program results (for onsite count lab) since August 2011
- 10. Results of the last 2 surveillance tests performed on the HEPA/Charcoal filter train components of the Containment Building Airborne Radioactivity Removal System.
- 11. The last 2 gaseous effluent release permits and the last 2 liquid effluent release permits
- 12. 2013 year-to-date results of the groundwater monitoring program
- 13. All audits, self-assessments, and/or reviews of the radioactive effluent monitoring program since August 2011.
- 14. List of NCRs generated since August 2011, as a result of gaseous and liquid effluent processing and/or ODCM related activities. Include all NCRs related to voluntary reporting of onsite spills/leaks of radioactive material. This should be a list of corrective action documents containing an AR number and brief description, not full NCRs 71124.07 - Radiological Environmental Monitoring Program (REMP)
- 1. Collection schedule for REMP samples during the week of inspection and contact numbers for collection staff.
- 2. Procedures for:
a) collection and analysis of environmental samples b) calibration and maintenance of REMP air and/or water samplers c) calibration of meteorological monitoring instruments (wind speed & direction, air temperature, etc.)
d) periodic meteorological instrumentation surveillance requirements
- 3. Calibration records for REMP air and water sampling equipment (as applicable) since August 2011
- 4. Last 2 calibration records for each meteorological monitoring instrument on the primary tower (wind speed, wind direction, and air temperature)
- 5. Inter-laboratory comparison program results (environmental lab) since August 2011
- 6. List of systems, structures, or components (SSCs), identified as credible mechanisms for the potential release of licensed material to the groundwater
- 7. List of changes to the REMP (sample locations, sample frequency, type of samples, etc.)
since August 2011
- 8. All audits, self-assessments, and/or reviews of REMP activities since August 2011. The data should include any reviews conducted of vendor activities and their facilities (e.g.
environmental lab)
- 9. List of NCRs generated as a result of REMP activities since August 2011. This should be a list of corrective action documents containing an AR number and brief description, not full NCRs