MONTHYEARML24303A3142024-10-25025 October 2024 Notification of Shearon Harris Nuclear Power Plant FEI and Information Request IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24145A1732024-02-26026 February 2024 002 Radiation Safety Baseline Inspection Information Request IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter ML23107A2052023-04-17017 April 2023 Initial Information Request 05000400/2023002 IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) ML22075A3592022-03-17017 March 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21258A3652021-09-15015 September 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) IR 05000400/20210052021-08-26026 August 2021 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2021005) IR 05000400/20200062021-03-0303 March 2021 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2020006 ML20309A2012020-11-0404 November 2020 Radiation Safety Baseline Inspection Information Request IR 05000400/20200052020-08-24024 August 2020 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, NRC Inspection Report 05000400/2020005 ML20223A3702020-08-10010 August 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML19255H2282019-09-12012 September 2019 RFI Unit 1 ISI & Sgisi 2019004 IR 05000400/20190052019-08-27027 August 2019 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2019005 ML19129A2572019-05-0909 May 2019 Heat Sink RFI ML19123A0392019-05-0303 May 2019 Heat Sink RFI 2019002 IR 05000400/20180062019-03-0404 March 2019 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2018006 IR 05000400/20180052018-08-23023 August 2018 Updated Inspection Plan for Shearon Harris Nuclear Power Plant - NRC Report 05000400/2018005 ML18059A0882018-02-28028 February 2018 EOC Assessment Letter ML18058B2242018-02-26026 February 2018 Emailed Radiation Safety RFI ML18046A3312018-02-0909 February 2018 RFI 2018002 ADAMS Package IR 05000400/20170052017-08-28028 August 2017 Updated Inspection Plan - NRC Inspection Report 05000400/2017005 ML17156A3932017-06-0505 June 2017 PI&R Notification Letter 2017 ML17145A5232017-05-25025 May 2017 Requalification Program Inspection for Shearon Harris Nuclear Plant ML17142A2182017-05-19019 May 2017 Notification of Inspection and Request for Information Dated: May 19, 2017 IR 05000400/20160062017-03-0101 March 2017 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016006 ML16258A2332016-09-13013 September 2016 Notification of Inspection and Request for Information IR 05000400/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2016005 ML16113A0062016-04-20020 April 2016 Notification of Inspection and Request for Information IR 05000400/20150062016-03-0202 March 2016 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015006 IR 05000400/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2015005 ML15218A0042015-08-0404 August 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20140012015-03-0404 March 2015 Annual Assessment Letter for Shearon Harris Nuclear Power Plant NRC Inspection Report 05000400/2014001 ML14245A1652014-09-0202 September 2014 Mid-Cycle Ltr 2014 ML14066A4732014-03-0707 March 2014 Notification of Shearon Harris Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000400-14-007 ML14063A1492014-03-0404 March 2014 2013 Annual Assessment Letter for Shearon Harris Nuclear Plant ML14023A7972014-01-23023 January 2014 Tfpi 2014008 Notification Letter - Copy ML13246A0662013-09-0303 September 2013 Mid Cycle Assessment Letter ML13120A5892013-04-29029 April 2013 Notification of Inspection and Request for Information IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) IR 05000400/20120012013-03-0404 March 2013 Annual Assessment Letter Shearon Harris, 05000400/2012001 ML12248A0912012-09-0404 September 2012 Mid Cycle Assessment Letter Harris 2012 2024-08-26
[Table view] Category:Letter
MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter 05000400/LER-2022-006-02, Auxiliary Feedwater Pump Inoperability2023-07-11011 July 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20243012023-05-15015 May 2023 – Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility 05000400/LER-1922-006-01, Auxiliary Feedwater Pump Inoperability2023-03-10010 March 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 05000400/LER-2022-007-01, Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus2023-01-26026 January 2023 Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) 05000400/LER-2022-006, Auxiliary Feedwater Pump Inoperability2022-12-20020 December 2022 Auxiliary Feedwater Pump Inoperability 2024-09-10
[Table view] |
See also: IR 05000400/2014007
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
March 7, 2014
Mr. Ernie Kapopoulos
Vice President
Shearon Harris Nuclear Power Plant
Carolina Power and Light Company
P.O. Box 165, Mail Code: Zone 1
New Hill, NC 27562-0165
SUBJECT: NOTIFICATION OF SHEARON HARRIS NUCLEAR PLANT - COMPONENT
DESIGN BASES INSPECTION - NRC INSPECTION REPORT
05000400/2014007
Dear Mr. Kapopulous:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a component design bases inspection (CDBI) at your Harris Nuclear
Plant during the weeks of June 23 - 27, July 7 - 11, and July 21 - 25, 2014. Jason Eargle, a
Senior Reactor Inspector from the NRCs Region II Office, will lead the inspection team. This
inspection will be conducted in accordance with Inspection Procedure 71111.21, Component
Design Bases Inspection, issued August 14, 2012.
The inspection will evaluate the capability of risk-significant /low-margin components to function
as designed and to support proper system operation. The inspection will also include a review
of selected operator actions, operating experience, and modifications.
During a telephone conversation on March 4, 2014, the staff confirmed with Mr. David Corlett of
your staff, arrangements for an information-gathering site visit and the three-week onsite
inspection. The schedule is as follows:
- Information-gathering visit: Week of May 19 - 23, 2014
- Onsite weeks: June 23 - 27, July 7 - 11, and July 21 - 25, 2014
The purpose of the information-gathering visit is to meet with members of your staff to identify
risk-significant components and operator actions. Information and documentation needed to
support the inspection will also be identified. Mr. Robert Patterson, a Reactor Inspector will be
conducting all preparation activities associated with the inspection. In addition, Mr. George
McDonald, a Region II Senior Reactor Analyst, will support Mr. Patterson during the
information-gathering visit to review probabilistic risk assessment data and identify risk-
significant components, which will be examined during the inspection.
The Enclosure lists documents that will be needed prior to the information-gathering visit.
Please provide the referenced information to the Region II Office by May 5, 2014.
E. Kapopoulos 2
Additional documents may be requested during the information-gathering visit. The inspectors
will try to minimize your administrative burden by specifically identifying only those documents
required for inspection preparation. The additional information will need to be available to the
team in the Region II office prior to the inspection teams preparation week of June 16, 2014.
During the information-gathering trip, Mr. Patterson will also discuss the following inspection
support administrative details: (1) availability of knowledgeable plant engineering and licensing
personnel to serve as points of contact during the inspection, (2) method of tracking inspector
requests during the inspection, (3) licensee computer access, (4) working space,
(5) arrangements for site access, and (6) other applicable information.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
Enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's Agencywide
Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC
website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions, regarding the
information requested or the inspection, please contact Mr. Patterson at 404-997-4667 or
contact me at 404-997-4530.
Sincerely,
RA
Rebecca L. Nease, Chief
Engineering Branch 1
Division of Reactor Safety
Docket No.: 50-400
License No.: NPF-63
Enclosure:
Information Request for Shearon Harris Nuclear
Plant, Component Design Bases Inspection
cc: Distribution via Listserv
___________x SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS RII:DRS RII DRS
SIGNATURE RA RA
NAME R. Patterson R. Nease
DATE 3/07/2014 3/07/2014 3/ /2014 3/ /2014 3/ /2014 3/ /2014 3/ /2014
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
INFORMATION REQUEST FOR SHEARON HARRIS NUCLEAR PLANT
COMPONENT DESIGN BASES INSPECTION
Please provide the information electronically in .pdf files, Excel, or other searchable format on
CDROM (or FTP site, Sharepoint, etc.). The CDROM (or website) should be indexed and
hyperlinked to facilitate ease of use.
1. From your most recent probabilistic safety analysis (PSA) excluding external events and
fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by Risk
Achievement Worth (RAW), and the other sorted by Birnbaum Importance
b. A list of the top 500 cutsets
2. From your most recent PSA including external events and fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by RAW,
and the other sorted by Birnbaum Importance
b. A list of the top 500 cutsets
3. Risk ranking of operator actions from your site-specific PSA sorted by RAW. Provide
human reliability worksheets for these items.
4. List of time-critical operator actions with a brief description of each action.
5. List of Emergency and Abnormal Operating Procedures revised (significant) since May 1,
2011, with a brief description of each revision.
6. List of components with low-design margins (i.e., pumps closest to the design limit for flow
or pressure, diesel generator close to design-required output, heat exchangers close to
rated design heat removal, and motor-operated valve risk-margin rankings, etc.), and
associated evaluations or calculations.
7. List of station-operating experience evaluations/reviews performed, and documented in the
stations corrective action program, for industry events and safety-related equipment
failures/vulnerabilities (as communicated by NRC Generic Communications, Industry
Communications, 10 CFR Part 21 Notifications, etc.) since May 1, 2011.
8. List and brief description of safety-related structures, systems, or components (SSCs)
design modifications implemented since May 1, 2011.
9. List and brief description of common-cause component failures that have occurred
since May 1, 2011.
10. List and brief description of operability evaluations completed since May 1, 2011.
Enclosure
2
11. List of equipment on the sites Station Equipment Reliability Issues List, including a
description of the reason(s) why each component is on that list, and summaries (if
available) of your plans to address the issue(s).
12. List and brief description of equipment currently in degraded or nonconforming status as
described in Regulatory Issue Summary 05-020.
13. List and reason for equipment classified in maintenance rule (a)(1) status from
May 1, 2011, to present.
14. Copies of system descriptions (or the design basis documents) for safety-related systems.
15. Copy of Updated Final Safety Analysis Report.
16. Copy of Technical Specification(s).
17. Copy of Technical Specifications Bases.
18. Copy of Technical Requirements Manual(s).
19. List and brief description of Root Cause Evaluations performed since May 1, 2011.
20. In-service Testing Program Procedure(s).
21. Corrective Action Program Procedure(s).
22. One-line diagram of electrical plant. (Electronic and full size - hard copy week
of May 19-23, 2014)
23. Index and legend for electrical plant one-line diagrams.
24. Primary AC calculation(s) for safety-related buses.
25. Primary DC calculation(s) for safety-related buses.
26. Piping and instrumentation diagrams (P&IDs) for safety-related systems. (Electronic
and 1/2 size - hard copy week of May 19 - 23, 2014)
27. Index and Legend for P&IDs.
28. Copy of Operability Determination procedure(s).
30. Copies of corrective action documents (i.e. PIPs) associated with findings from previous
CDBI. (If applicable)
31. Index (procedure number, title, and current revision) of station Emergency Operating
Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures.
32. Copy of any self-assessments performed in preparation for this inspection.
3
33. List of any condition reports generated in preparation for this inspection.
34. Copies of condition reports generated from previous CDBI (2011).
35. Contact information for a person to discuss PSA information prior to the information-
gathering trip. (Name, title, phone number, and e-mail address)