IR 05000400/2018006
Jump to navigation
Jump to search
| ML19063C921 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 03/04/2019 |
| From: | Lundy Pressley Division Reactor Projects II |
| To: | Hamilton T Progress Energy Carolinas |
| Geanette D | |
| References | |
| IR 2018006 | |
| Download: ML19063C921 (6) | |
Text
T. Hamilton
SUBJECT:
ANNUAL ASSESSMENT LEITER FOR SHEARON HARRIS NUCLEAR POWER PLANT - NRC INSPECTION REPORT 05000400/2018006 March 4, 2019 DISTRIBUTION:
M. Kowal, RII OE MAIL RIDSNRRDIRS PUBLIC RidsNrrPMShearonHarris Resource ROPassessment Resource ROPreports Resource Institute of Nuclear Power Operations (INPO)
ADAMS Accession No. ML19063C921 OFFICE Rll:DRP Rll:DRP Rll:DRP NAME DJackson JDodson PNiebaum DATE 2/ 26 /2019 2/ 26 /2019 2/ 26 /2019 Rll:DRP LPressley 2/ 26 /2019 OFFICIAL AGENCY RECORD