ML20217N131
ML20217N131 | |
Person / Time | |
---|---|
Site: | Hatch |
Issue date: | 04/21/1998 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
To: | |
Shared Package | |
ML20217N092 | List: |
References | |
50-321-98-01, 50-321-98-1, 50-366-98-01, 50-366-98-1, NUDOCS 9805050232 | |
Download: ML20217N131 (39) | |
See also: IR 05000321/1998001
Text
. _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
U.S. NUCLEAR REGULATORY COMMISSION
REGION II
Docket Nos: 50-321. 50-366
Report No: 50-321/98-01. 50-366/98-01
Licensee: Southern Nuclear Operating Company. Inc. (SNC)
Facility: E. I. Hatch Units 1 & 2
Location: P. O. Box 2010
Baxley Georgia 31515
Dates: February 8 - March 21, 1998
Inspectors: B. Holbrook. Senior Resident Inspector
J. Canady. Resident Inspector
W. Kleinsorge. Reactor Inspector. Sections M1.3.
M1.4. and M2.1
G. Wiseman. Reactor Inspector. Sections F1.1.
F2.1, and F5.1
G. Kuzo. Senior Radiation Specialist. Sections
R1.2 and R2.1
Accompanying Inspector: T. Fredette. Resident Inspector
Approved by: P. Skinner Chief. Projects Branch 2
Division of Reactor Projects
Enclosure 2
9805050232 980421
PDR ADOCK 05000321 ;
G PDR b
. . .
.
. . .
_ _ _ _ _ _ _ _ _ _ _ _ _ _ .
.
. .
EXECUTIVE SUMMARY
Plant Hatch. Units 1 and 2
NRC Inspection Report 50-321/98-01, 50-366/98-01
1his 6-week integrated inspection included aspects of licensee
operations, engineering, maintenance, and plant support. The report is
a compilation of observations and findings by the resident inspection
staff and region-based specialist inspection staff. ,
!
Doerations i
1
e Operator use of three-part communications and the phonetic
alphabets during the power reduction for the sequence exchange on
Unit I was good (Section 02.1).
)
Maintenance
e Site management was kept informed of the number of outstanding and
backlogged work items. A documentation review indicated that work
items were being identified and corrected within a reasonable time
(Section M1.2).
e The licensee's plans for performing periodic evaluations and
assessments met the requirements of the Maintenance Rule.
However, several weaknesses were identified in the periodic
assessment procedure (Section M1.3).
- For Maintenance Rule (a)(2) systems, structures and components
(SSCs). performance criteria had been established, suitable
trending had been performed and corrective actions were taken ,
when SSCs failed to meet performance criteria or experienced i
failures. Industry wide operating experience had been considered
(Section M1.4).
e Personnel performance during surveillance activities was
excellent. Procedures were used: communications were generally
three-part; and supervisory oversight was evident. All test
results reviewed met the procedure and Technical Specification
acceptance criteria (Section M3.1).
e Violation 50-366/98-01-02. Failure to Follow Maintenance
Procedures, was identified. Maintenance work was performed that
was not specified on the maintenance work order and was outside
the approved clearance boundary. (Section M4.1).
!
Enclosure 2
i
l
l
}
l-
.
, .
,
2
Enaineerino
e Apparent Violation EEI 50-321. 366/98-01-08. Plant Operation
Outside of the Design Basis for an Engineered Safeguard System,
was identified, associated with design issues that resulted in the
Main Control Room Environmental Control System being unable to
perform a design safety function. The corrective actions were
effective in returning the system to its design condition
(Section E2.1).
e Violation 50-366/98-01-03. Failure to Follow Engineering Test
Procedures. was identified. This violation was for the failure to
follow procedures for review, approval, and signature authority of
the responsible engineer for a pressure test (Section E3.1).
Plant Sucoort
e Excluding the Unit 1 Condensate Pump Turbine Building 112-foot
elevation high radiation area, radiological controls for normal
operations and for radwaste and radioactive material storage areas
were implemented properly and maintained in accordance with
procedural Technical Specification (TS), and 10 CFR Part 20
requirements (Section R1.2)
e Radiological surveys were inadequate and established controls were
not implemented properly for routine Unit 1 Condensate Pump
vibration analysis measurements conducted in the Turbine Building
-112-foot elevation high radiation area (Section R1.2).
e Violation 50-321/98-01-04 was identified for failure to follow
3rocedures in accordance with TS 5.4.1 for Entry into a High
Radiation Area (Section R1.2)
e Violation 50-321/98-01-06 was identified for Failure to Conduct
Adequate surveys to Evaluate the Extent of Radiation Levels and
Potential Hazards to Workers Conducting Condensate Pump Vibration
Analysis Measurements within a High Radiation Area on the Unit 1
Turbine Building 112-foot elevation (Section R1,2).
o Numerous examples of poor facility housekeeping and cleanliness,
and poor contamination control practices were identified (Section
R1.2).
e The. material condition of the Main Control Room Environmental
. Control ventilation ductwork insulation was degraded (Section
R2.1).
Enclosure 2
t .
. .
.
3
e 'A lack of supervisory' oversight of chemistry activities and
chemistry interface with the operations department resulted in a
violation of a failure to follow surveillance procedures (Section
R4.1).
e Chemistry technicians used proper equipment and sampling .
technigues while' obtaining fuel oil samples of the Security Diesel
g fuel oil (Section R4.2).
e The installation and repair procedures ~ for penetration seals
provided adequate guidance to ensure materials were installed per
design requirements (Section F1.1).
' e The licensee's fire barrier penetration report evaluations-
conducted for penetration seals that were inaccessible for visual
inspections were adequate (Section F1.1).
e Brand Industrial Services Company silicone foam penetration seal
designs were not supported by available vendor qualification test
reports. The licensee did not perform engineering evaluations that
satisfied the guidance of NRC GL 86-10 for deviations from fire
barrier configurations qualified by tests. These were considered
fire protection engineering program weaknesses (Section F1.1).
'
e The fire brigade leader demonstrated good leadership' abilities
during the performance of the unannounced fire drill conducted on-
March 3. The overall performance and effectiveness of the fire
brigade was satisfactory (Section F4.1).
e The fire barrier penetration seal installers were appropriately
trained to accomplish fire barrier penetration seal installation
work and Quality Control inspectors were qualified to perform the
appro)riate verification for installation and repairs made to the
fire Jarrier penetration seals (Section F6.1).
Enclosure 2
.
. .
Report Details
Summary of Plant Status
Unit 1 began the report period at 100% rated thermal power (RTP).
Reactor 30wer was reduced to about 60% RTP on February 21 to
troubles 1oot and repair the control valves on the ~B" reactor feedwater
pump turbine (RFPT). Reactor power was returro ' to rated the following
day. The unit remained at 100% RTP for the rem " r of the reporting
period except during routine testing activities.
Unit 2 operated at 100% RTP for the report period, except during routine
testing activities.
I. Operations
01 Conduct of Operations
01.1 General Comments (71707)
Using inspection procedure 71707. the inspectors conducted
frecuent reviews of ongoing plant operations. In general, the
concuct of operations was professional and safety-conscious;
specific events and observation are detailed in the section below.
02 Operational Status of Facilities and Equipment
02.1 Power Reduction for Unit 1 Control Rod Seauence Exchance and
Balance of Plant Reoairs
a. Insoection Scopo d'O ll
The inspectors observed a Unit 1 power reduction for the
performance of a control rod sequence exchange, repair of the
control valve linkage for the IB RFPT. and the repair of leakage
in the condenser bay.
b. Observations and Findinas
On February 21 reactor power was reduced to approximately 75% RTP
for a scheduled control rod sequence exchange. The inspectors
observed control room operators reducing power in accordance with
general operating procedure 34G0-0PS-005-15. " Power Changes."
Revision (Rev.) 21. Another operator was present at the control
board to verify rod movement in accordance with the procedure.
Power was later reduced to approximately 60% RTP for the removal
of the 1B RFPT from service for repairs and the repair of leaks in
the condenser bay.
Enclosure 2
1
\
i
2
Maintenance personnel found that the 1B RFPT control valve linkage
was binding. Speed on the 1B RFPT could be increased, but
intermittent problems were encountered when trying to reduce
speed. Maintenance personnel completed repairs on February 21.
c. Conclusions
Operator use of three-part communications and the ahonetic
alphabet was good during the power reduction for t1e sequence
exchange on Unit 1. Supervisory oversight and Shift Technical
Advisor support were evident.
08 Miscellaneous Operations Issues (92901)(92700)
08.1 (Closed) Violation (VIO) 50-321. 366/97-06-01. Failure to Prevent
Recurrence of Imorocer Eauioment Storace in Control Room.
The licensee responded to this violation in documentation dated
August 8. 1997. The inspectors questioned several operators
during a routine tour of the control room about storage of
material in the control room. All operators questioned were aware
of the seismic requirements for the storage of material in the
control room. The inspectors also performed a general tour of the
control room, including the back panel areas, and did not identify
any improperly stored material. Based upon the inspector's review
of the licensee's action, this violation is closed.
08.2 (Closed) LER 50-366/97-02. Grounded Jumoer Causes Blown Fuse _and
ESF actuation.
This problem is discussed in Section 4.1 of IR 50-321, 366/97-02.
No new information was presented. Based upon the inspectors
review of licensee actions, this LER is closed.
08.3 Safety Related Overtime (OT) Review (71707) (92901)
The inspectors reviewed the Unit 1 and Unit 2 OT records for the
months of September to November 1997. Included in the review was
OT worked during the 1997 Fall Refueling Outage on Unit 1.
The inspectors concluded that site management maintained good 1
control of overtime for the 1997 Refueling Outage on Unit 1. I
Technical Specification and procedural requirements were met.
I
Enclosure 2
1
1
.
. .
.
3
i
i
II. Maintenance
l M1 Conduct of Maintenance
M1.1 General Comments (62707)
I
'
The inspectors observed or reviewed all or portions cf the
following work activities:
!
. MWO 1-98-0217: Repair Reactor Feedwater Pump Turbine
(RFPT) IB control valve linkage
)
e MWO 1-98-0233: Repair oil leak on IB RFPT main oil pump
'
- MWO 2-98-0128: Core Spray preventive maintenance
- MWO 2-97-2053: Remove old valve 2C41-F033B and install a
new valve
\
! lhe inspectors four.2 that the work was performed with the work
l packages present and being actively used. Maintenance activities
! were generally completed thoroughly and professionally. No
deficiencies were identified by the inspectors.
M1.2 Review of Maintenance Backloa
a. Insoection Scooe (62707)
l The inspectors reviewed licensee documentation for maintenance
items completed and the existing maintenance backlog including a
Unit I refueling outage for a 5-month time period.
.
b. Observations and Findinas
!
I
The inspectors observed that Outage and Planning personnel tracked
work items and routinely submitted a Backlog Report to management
personnel.
The inspectors observed during a control room walkdown that the
l number.of work items placed on equipment that might affect the
operators' ability to use equipment was low. At the time of the
control room walkdown, there were no instruments out of service.
l The reviewed documents indicated there were no overdue preventive
maintenance (PM) items and the specific PM items the inspectors
'
reviewed were not overdue,
c. Conclusions
The inspectors concluded that management personnel were kept.
informed of the number of outstanding and backlogged work items.
A documentation review indicated that work items were being 4
identified and corrected within a reasonable time. l
Enclosure 2
!
!
o
- .
.
4
M1.3 Maintenance Rule - Periodic Evaluation
a. Insoection Scooe (62706)
Paragraph (a)(3) of 10 CFR 50.65, the Maintenance Rule, required
that performance and condition monitoring activities and
associated goals and preventive maintenance activities be
evaluated taking into account, where practical, industry-wide
operating experience. This evaluation was required to be
performed at least one time during each refueling cycle not to
exceed 24 months between evaluations. The inspectors reviewed the
licensee's periodic evaluation process.
b. Observations and Findinos
At the time of this inspection, the licensee was not required to
have completed the first periodic evaluation.
Periodic maintenance assessment was addressed in licensee
procedure 40AC-ENG-020-05. " Maintenance Rule (10 CFR 50.65)
Implementation." Rev. 3. The procedure guidance did not
adequately address the NUMARC 93-01 topics of sections 12.2.1.
" Review of Goals (a)(1)." 12.2.2. " Review of S.C. Performance
(a)(2)." 12.2.3 ~i<eview of Effectiveness of Corrective Actions."
and 12.2.4. " Optimizing Availability and Reliability for SSCs."
The licensee indicated that Procedure 40AC-ENG-020-05 was in the
process of revision, and the new revision will completely address
the topics of section 12 of NUMARC 93-01. l
The licensee planned to complete a periodic maintenance assessment
for both units by June 1, 1998. This assessment was planned to
cover at least that portion of the Unit 1 Fuel Cycle 17 after the
implementation of the Rule (July 10. 1996. to October 11. 1997),
and that portion of the Unit 2 Fuel Cycle 13 after the
implementation of the Rule (July 10. 1996, to March 14. 1997).
Inspector Followu) Item (IFI) 50-321, 366/98-01-01. Review of
Maintenance Rule )eriodic Assessment Procedure, was opened to
review the revisions to procedure 40AC-ENG-020-0S.
4
c. Conclusions
The inspectors concluded that the licensee's plans for performing
periodic evaluations and assessments met the requirements of the
Maintenance Rule. However, the inspectors identified several
weaknesses in the periodic assessment procedure, which the
licensee planned to correct in a subsequent procedure revision.
Enclosure 2
.
. .
,
5
M1.4 Maintenance Rule - Preventive Maintenance and Trendina for
Paraaraoh (a)(2)
a. Insoection Scooe (62706)(62002)
Paragraph (a)(2) of the 10 CFR 50.65 states that monitoring as
required in paragra)h (a)(1) is not required where it has been
demonstrated that tie performance or condition of a system
structure or component (SSC) is being effectively controlled
through the performance of appropriate preventive maintenance,
such that the SSC remains capable of performing its intended
function. The licensee utilizes conditioning monitoring for
structures within the scope of the Maintenance Rule.-
The inspectors examined the below-listed structures to verify that
a)propriate preventive maintenance was being performed, such that
t1e structures remained capable of performing their intended
function. The inspectors verified that industry-wide operating
experience was considered, where practical, that appropriate
trending was being performed, that safety was considered when
performance criteria were established, and that corrective action
was taken when structures failed to meet performance criteria.
The inspectors reviewed program documents and records for the
structures that the licensee had placed in the (a)(2) category in
order to evaluate this area. The inspectors also discussed the
program with licensee management, the Maintenance Rule
coordinator, engineering and maintenance personnel, and other
licensee personnel
b. Observations and Findinas
, The licensee had completed the last section of its " Structural
Monitoring Baseline Inspection" in May 1997.
'
The inspectors
reviewed the " Structural Monitoring Program for the Maintenance
l Rule." Rev. 3. dated December 1997. (SMP) to assess the adequacy
L
of the acceptance criteria and performance criteria for the
evaluation of the concrete and structural steel. The licensee
uses the SMP at all three of their licensed sites. The inspectors
noted that the SMP did not address roof system ponding and only
addressed concrete cracks in terms of width. As a result of the
January 1998 inspection in the area of 10 CFR 50.65, at the
licensee's Vogtle site. NRC Inspection Report 50-424. 425/98-01.
the licensee had initiated Vogtle Plant Action Item C00037982 to
evaluate this issue and initiate appropriate corrective actions.
As the SMP is a company-wide program, the Vogtle action item will
address this issue at Hatch. ,
!
Enclosure 2
l
l l
l.
r .
1 . .
<
6
The inspectors conducted a walkdown inspection of several
structures and noted the following discrepant condition: hich had
not been documented in the structural baseline database.
- Concrete cracking at all cooling tower riser pipe thrust
blocks.
- Long diagonal cracking on the diesel generator and
recombiner building walls.
- Extensive corrosion at the interface of the precast panels
and the 228'-0" floor, around the perimeter of refueling
deck floor.
. Missing large diameter connection nut at TA/T13 Turbine
Building Elevation 164'-0"
. Severely corroded bolt in large X-bracing connection between
Columns T22/TI and T21/TI of the Turbine Building.
. Significant wastage reducing the diameter of some Unit 2
condensate storage tank hold down bolts.
The inspectors discussed the above with licensee personnel,
indicating that without detailed baseline information, trending of
minor discrepant conditions was not possible. The licensee i
personnel concurred and indicated that they would amend the f
" Structural Monitoring Baseline Inspection" to include the above !
and similar items.
The inspectors concluded that the surface cracking in the concrete
structures and the corrosion discussed above was minor in nature
and that the structures appeared to be sound. No unacceptable
conditions were noted During the walkdown inspection, the
inspectors were accompanied by civil engineers who were
knowledgeable and qualified to perform structural evaluations.
c. Conclusions
1
For Jaragraph (a)(2) SSCs. performance criteria had been
esta)lished, suitable trending had been performed and corrective
actions were taken when SSCs failed to meet performance criteria
or experienced failures. Industry-wide operating experience had
been considered. Procedure weaknesses (lack of detail) were
identified in the areas of structural monitoring.
.
Enclosure 2
!
.
-
,
.
7
M2 Maintenance and Material Condition of Facilities and Equipment
M2.1 Material Condition Walkdowns
a. Insoection Scooe (62706)
The inspectors performed walkdowns of selected portions of the
following structures and plant areas, and observed the material
condition of SSCs: intake structure; diesel generator building:
offgas recombiner building: Units 1 and 2 turbine buildings:
control building: Units 1 and 2 condensate storage tanks: Units 1
and 2 reactor buildings: and the cooling towers.
b. Observations and Findinas
Housekeeping in the general areas around equipment was good.
Piping and components were painted, and few indications of
corrosion, oil leaks, or water leaks were evident. During the
walkdown inspection of structures, the inspectors noted several
material condition deficiencies:
. Caulk associated with the interior rubber seal on the
vertical seismic gap on the east wall of the reactor
building above the refueling deck was significantly degraded ;
and could. but had not affected, secondary containment. i
!
. Metallic material was degraded at the precast panel to slab
interface adjacent to HPCI roof (exterior).
. The large diameter blowdown pipe at the Unit 1 flume has
corrosion rosettes at the saddle interface of the pipe to
the concrete thrust block E1.164'-0.
.' Wastage of anchor bolts and stringers was located on the
stairs associated with Unit 1 condensate storage tank.
. Several of base plates and anchor bolt / nuts exhibiting
flaking expansive rust.
These conditions were identified to the licensee personnel for j
appropriate corrective actions. '
c. Conclusions
In general. plant material condition and housekeeping observed
- during walkdowns were good. Preservation of equipment by painting
! was considered to be good.
Enclosure 2
!
'. .
.
4
8
M3 Maintenance Procedures and Documentation
M3.1 Surveillance Observations (61726)
The inspectors observed all or portions of six Unit 1 and Unit 2
surveillances which included the following surveillance
activities:
. 34SV-SUV-008-2S: Primary Containment Isolation Valve
Operability Test
. 34SV-R43-004-15: Diesel Generator 1A Semi-Annual Test
The inspectors observed that personnel performance during the
surveillance activities was excellent. Procedures were used:
communications were generally three-part: and supervisory
oversight was evident. All test results reviewed met the
procedure and TS acceptance criteria.
M3.2 Unit 2 Reactor Core Isolation Coolino (RCIC) System Post
Maintenance Testina
a. Insoection Scooe (62707)(71707)
The inspectors observed personnel perform sections of the RCIC
surveillance test procedures.
b. Observations and Findinas
The inspectors attended the pre-test briefings conducted prior. to
the RCIC surveillances. The briefings were conducted by
o)erations personnel with representatives from maintenance, health
p1ysics, and operations management.in attendance.
The inspectors observed that the maintenance personnel conducted
their activities in a deliberate. professional' manner using the '
respective procedure and noted that the activities were well
planned and controlled. ,
,
c. Conclusions j
For the RCIC surveillance activities observed, all data met the
required acceptance criteria and the equipment performance was
satisfactory. The performance of the personnel conducting the
surveillance test procedures was good.
Enclosure 2
_ _ _ _ - _
'
. .
g
9
M4 Maintenance Staff Knowledge and Performance
l
l M4.1' Maintenance Work Renders Both Trains of the Unit 2 Standby Liouid
Control (SBLC) System Inocerable.
l a. Insoection Scoce (62707)
l
On March 5. a maintenance error. rendered both trains of the Unit 2
SBLC system inoperable. The. inspectors reviewed the maintenance
work package. applicable procedures, and circumstances surrounding
l the error. Procedures reviewed included the following:
- * 30AC-0PS-001-05. " Control of Equipment Clearances and Tags."
l
Rev. 16
. 50AC-MNT-001-05. " Maintenance Program." Rev. 26
- 34SV-C41-002-2S. "SBLC Pump Operability." Rev. 17
b. Observations and Findinas
On March 5. operations personnel placed the "B" train of SBLC
under clearance to support the 18-month PM activities and to
repair check valve 2C41-F033B. The inspectors reviewed the
clearance used to isolate the SBLC train and determined that it
satisfactorily established the isolation boundaries during the
maintenance activities.
However, when maintenance personnel cut the pump discharge line to
remove 2C41-F033B the cut was made outside the clearance boundary
rendering both trains of the SBLC system inoperable. Maintenance
3ersonnel recognized the error and contacted operations personnel.
Jnit 2 control room supervision declared both trains of the SBLC
system inoperable and entered the TS required action statement
- (RAS). TS section 3.1.7 requires that at least one of the SBLC
systems be restored to operable status within eight hours or the
unit placed in Mode 3 within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
Maintenance 3ersonnel repaired the incorrect system breach. The
inspectors o) served that the weld for the incorrect cut was
completed and inspected and operations personnel completed the-"A"
l train post-maintenance operability surveillance test in about five
hours. Maintenance completed the check valve replacement and
l operations com)leted the post-maintenance operability surveillance
l test for the "3" train about 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the system was
initially removed from service. The inspectors reviewed procedure
34SV-C41-002-2S and concluded that all TS surveillance
requirements were met for both trains of SBLC.
Enclosure 2
i
'.
.
i
10
l
'
During the review, the inspectors observed that step 4.2.5 of
procedure 50AC-MNT-001-0S identified that personnel were
! responsible to ensure that plant maintenance is performed and
controlled within the clearance boundaries. Additionally. step
,
6.2.3 stated, in part, that personnel performing work shall not
l exceed the scope of work as authorized in the work instructions
and work requested in the MWO. Also, procedure step 8.5.11.3
'
required personnel performing the work to verify clearance
boundaries. In this case, work was performed that was not
saecified in the MWO work package and a system breach occurred
tlat was outside the established and approved clearance boundary.
The inspectors reviewed the licensee's performance of the ]rior
two years and noted an instance where work was performed tlat was
not specified on a MWO. This resulted in a violation that was
documented in IR 50-321. 366/97-02. The inspectors identified the
!
most recent problem for maintenance work performed that was not
specified on work instructions and performed outside the
established clearance boundary as a repeat VIO 50-366/98-01-02:
Failure to Follow Maintenance Procedures.
The inspectors review of engineering performance and procedures
associated with this issue is discussed in Section E3.1 of this
,
Inspection Report.
l
c. Conclusions
VIO 50-366/98-01-02. for a failure to follow maintenance
procedures, was identified. Maintenance work was performed that
was not specified on the maintenance work order and was outside
the approved clearance boundary.
M8 Miscellaneous Maintenance Issues (92902)
M8.1 (Closed) Violation 50-321. 366/96-12-01: Failure to Include All
Structures. Systems, and Components in the Scope of the
Maintenance Rule as required by 10 CFR 50.65. By letter dated
March 5.1997. the licensee identified its corrective actiont . As
a result, the licensee included the communications, non-Appendix R
emergency lighting. Appendix R emergency lighting, and cooling
tower systems in the Maintenance Rule program. The inspectors
determined that the licensee had conducted an appropriate survey
and determined the extent of the noncompliance, and took
appropriate actions to correct the condition and prevent its
recurrence. This issue is closed.
M8.2 (Closed) Violation 50-321. 366/96-12-02: Failure to Establish
Adequate Performance Criteria for SSC Risk-significant Functions.
By letter dated December 19. 1996. and March 5. 1997, the licensee
provided their corrective actions. As a result, the licensee
Enclosure 2
l
I
,
I .
- = l
l
I
11
)
established appropriate additional performance criteria for the
following systems: AC and DC electrical and analog transmitter
trip, primary containent and primary containment isolation. <
feedwater and condensate. circulating water, electro-hydraulic l
control, and 3rimary containment chilled water. The inspectors j
determined tlat the licensee had conducted an appropriate survey
and determined the extent of the noncompliance, and took l
appropriate actions to correct the condition and prevent its
recurrence. This issue is closed.
M8.3 (Closed) IFI 50-321. 366/96-12-04: Failure to Provide Adequate
Procedure for Implementation of Maintenance Rule Requirements.
The licensee opened Action Item Tracking (AIT) No 96-261 with a
due date of January 5. 1998. Regulatory Guide (RG) 1.160. l
" Monitoring the Effectiveness of Maintenance at Nuclear Plants."
Rev. 2. issued March 1997. paragraph 1.2. provided specific {
guidance in the area in question, that of the role of ,
organizations, other than the Maintenance department, as it
relates to Maintenance Preventable Functional Failures (MPFF)s.
The licensee has revised Administrative Control Procedure ACP i
'
40AC-ENG-020-05. Rev. 2. " Maintenance Rule (10 CFR 50.65)
Implementation." Procedure ACP 40AC-ENG-020-0S Rev. 3. dated
October 10. 1997, incorporated the definition of maintenance as
stated in RG 1.160. Rev. 2. paragraph 1.2. verbatim. This issue I
is closed. l
,
M8.4 (Closed) IFI 50-321.366/96-12-05: Followup on Licensee Actions to
Provide Performance Criteria for Structures After Industry
Resolution of this Issue. The licensee opened AIT No 96-262 with l
a due date of January 7. 1998. RG 1.160. Rev. 2. issued March {
1997, paragraph 1.5. provides specific guidance in the area in
question. that of monitoring structures. The licensee issued the
SMP and has completed their " Structural Monitoring Baseline
Inspection" as discussed in paragraph M1.2 above. This issue is -
closed.
III. Enaineerina
E2 Engineering Support of Facilities and Equipment
E2.1 Unit 1 and Unit 2 Main Control Room Environmental Control (MCREC)
Systems Outside Their Desian Basis
a. Insoection Scooe (37551) (92903)
On February 16. the licensee identified that two temperature
,
switches, one switch on each of the MCREC subsystems, were not
l installed. This allowed system bypass flow into the main control
i room that would not be fully filtered or treated. The inspectors l
l
reviewed the impact of the missing switches on the MCREC system
Enclosure 2
l
'. .
I~
12
operability. The inspectors also discussed the problem with
licensee personnel
b. Observations and Findinos
.
'
On February 16, during charcoal filter testing and )lanned
calibration of temperature switch associated with t1e charcoal of i
.the "B" MCREC filter subsystem, engineering personnel discovered
the temperature switch to be missing. The missing temperature
switch left an approximately one-half inch diameter hole in the i
MCREC filter train that was opened to a conduit containing the
wiring for the missing temperature switch. The wiring from the
conduit at the location of the missing temperature switch was
connected with a wire nut thereby providing circuit continuity and l
! allowing the carbon drying heater to function. The hole left by
- the missing temperature switch allowed bypass flow to enter the
control room without filtration by the charcoal in the affected
MCREC filter train. .The two MCREC filter trains are shared by the J
main control room for each unit. The purpose of the charcoal in
l the filter train is to remove a very high percentage of the iodine
that is postulated to be present following various design basis
,
accidents (DBA). This removal of iodine ensures that the
,
requirements of 10 CFR 50, Appendix A. Criterion 19 are met.
l
l
Within about two hours of the first identified problem on the "B" l
- subsystem, an investig6 tion of the "A" subsystem revealed that its
l associated temperature switch was also missing. Both MCREC filter
'
trains were declared inoperable and the Required Action Statements
i (RAS) of TS 3.0.3 were entered for each unit.
L Two rubber plugs (a plug within a plug) were installed in place of
i the temperature switch for the "A" MCREC subsystem. The system
!
was declared operable at about 4:30 p.m. on February 16 and
TS 3.0.3 was exited. The inspectors reviewed the 10 CFR 50.59
evaluation and Temporary Modification to complete this work
I
activity. The inspectors concluded that the 10 CFR 50.59
evaluation was satisfactory.
A temperature switch was installed ulibrated, and tested for the
"B" MCREC subsystem. Following p. 'intenance testing. the
system was declared operable on Feto wry 17. On February 18, the
temporary rubber plugs were removed from the "A" MCREC subsystem
and a new temperature switch was installed. The subsystem was
tested and returned to service on February 20.
The licensee considered the failure to install or the removal of
the temperature switches an isolated event and that plant
process-es and procedures in place were adequate to maintain proper
plant configuration. As part of the licensee's immediate
corrective actions, the Standby Gas Treatment Systems for both
Enclosure 2
,
. .
.
i
! 13
units, which have a simila' configuration as the MCREC systems,
were verified to have no missing temperature switches. i
TS 5.5.7 requires that the MCREC be tested in accordance with
.
Regulatory Guide 1.52. Revision'2. Section 5d, and ASME N510-1989,
!~
Section 11. The ins)ectors reviewed procedure 42SV-Z41-002-0S,
" Testing of. Control Room Habitability Filter Trains." Rev. 7, and -
- determined that the previous test acceptance criteria for the
MCREC system were acceptable.
On February 17, the licensee performed an initial review of
calculations for the thyroid doso nf iodine'to control room
< operators following a DBA. The licensee concluded that the
l
Jotential existed that the holes in the MCREC filter trains would
lave allowed sufficient contaminated air to bypass the carbon
filters allowing the control room personnel to exceed the NRC
,
iodine limit to the thyroid of 30 rem. This wn outside of the
design basis for an engineered safeguard systern (MCREC). This is
an apparent vf olation of 10 CFR 50, Appendix B. Criterion III.
Design Controls, which requires that measures be established to
verify adequacy of design.
The licensee requested the architecture / engineering company for
the plant to perform additional quantitative calculations for the
thyroid iodine exposure to control room personnel during and
following a DBA. The analysis were performed using actual main
steam isolation valve and containment leakage rates as inputs, to
determine the projected dose. The results of these calculation
identified that a thyroid dose of 30 rem would have been exceeded
using conservative, deterministic assumptions. ,
The licensee completed Licensee Event Report (LER)
50-321/1998-001. Inoperable MCREC System Filter Trains Result in
Entry Into LCO 3.0.3, dated March 18. The licensee was not able
to determine the cause for the missing temperature switches from j
this review. *
I
,
TS 5.5.7 requires that the MCREC be tested in accordance with
Regulatory Guide 1.52. Revision 2. Section 5d and ASME N510-1989.
Section 11. The inspectors reviewed the above documents and
arocedure 42SV-Z41-002-05, " Testing of Control Room Habitability
ilter Trains." Rev. 7. and determined that the previous test
acceptance criteria for the MCREC system for the past two years
was acceptable.
f' A review by the inspectors of UFSAR Table 6.4-2 (sheet 1 of 2)
indicated that a failed electric carbon drying heating coil
control (missing temperature switch) resulted in constant coil
operation which was not sufficient to cause damage and heater coil
Enclosure 2
l
'. .
.
i-
14
operation was not essential to the operation of the filter during
a LOCA.
The inspectors were informed by engineering personnel that a
request for calibration of the temperature switches was initiated
in 1993. A review by the licensee of FSAR Table 6.4-2 (sheet 1 of
2) indicated that a failed electric carbon drying heating coil
control (missing temperature switch) resulted in constant coil
operation which was not sufficient to cause damage and heater coil
operation was not essential to the operation of the filter during
a LOCA. 'As a result.-little emphasis was placed on calibrating '
the temperature switches. The MWO that was initiated in 1993 was
not performed and was replaced with another MWO in 1996. The
inspectors reviewed the applicable MW0s to verify the. information
provided by engineering personnel. The missing temperature
switches would have been discovered sooner had the MW0s been
worked earlier.
c. Conclusions
An Apparent Violation (EEI) 50-321. 366/98-01-08. Plant Operation
Outside of the Design Basis for an Engineered Safeguard System,
was identified, associated with design issues that resulted in the
Main Control Room Environmental Control System being unable to
- perform a design safety function. The corrective actions were
! effective in returning the system to its design condition.
E3 Engineering Procedures and Documentation
,
E3.1 Review of Enaineerina Activities Associated with Unit 2 Standby
Liauid Control (SBLC) System
l
a. .Insoection Scooe (37551) (92903)
' On March 5. a maintenance error rendered both trains of the Unit 2
SBLC system inoperable. The inspectors reviewed applicable
l procedures and reviewed engineering performance associated with
L the activities.
The inspectors * review of maintenance activities is discussed in
Section M4.1 of this inspection Report.
b. Observations and Findinas
The maintenance work scope included routine preventive maintenance ;
activities and repair of a SBLC pump check valve. The inspectors '
were informed that the initial work plan was to cut pipe supports
and remove the check valve. Workers reviewed the physical piping ,
layout and. identified a method of repair that did not require !
Enclosure 2
f.
. .
F
15
cutting the pipe supports. The responsible engineering personnel
who revised the weld isometrics.to accommodate the new repair plan
did not recognize that the revised work plan called for pipe cuts
outside the clearance boundary and authorized the pipe cut. This
oversight contributed.to both trains of the Unit 2 SBLC system
'
i
l being. rendered inoperable. The maintenance work plan changes were
!
not reviewed and discussed with maintenance or operations
i supervision.
!
l
The inspectors reviewed procedure 42IT-TET-004-0S, " Operating
Pressure Testing of Piping and Components " Rev. 5 used to test
the SBLC welds following the maintenance activities. The
inspectors observed that procedure step 7 2.4 stated, in part.
l that the resaonsible engineer will indicate if test results are
l acceptable. 3ased on no evidence of leakage from welds pipes, or
j components bodies. A note preceding the procedure step stated. in
l
'
part, that the VT-2 inspector may sign for the responsible
,
engineer when verbal concurrence is given by the responsible
, engineer for pressure tests which contain neither valve
!
manipulations nor leakage. The inspectors noted that a VT-2
inspector had signed the test acceptance sheets for the . i
responsible engineer for the three weld inspections completed i
during the maintenance repair activities. When questioned by the-
, inspectors, the responsible engineer stated that he had not
!
reviewed the test nor given verbal approval for the VT-2 inspector
to sign for his responsibility. The VT-2 inspector presented a
computer E-Mail dated January 20. from the ISI engineer stating. l
in part. that "This memo may be used to satisfy procedural
requirements when the ISI pressure test engineer is unavailable.
When an ISI pressure test is performed by the VT-2 inspector and
no leakage or valve manipulation is required. the VT-2 inspector
may sign.for the responsible engineer (ISI pressure testing
engineer or designated personnel). This memo serves as verbal
"
concurrence.
- The inspectors discussed this issue with Nuclear Safety and
Compliance and engineering management. The inspectors' concern
was that the E-mail gave blanket approval for test review. j
Additionally, the E-mail gave approval to not follow procedures in ;
that the intent of the procedure step was not being met and the j
procedure had not been revised. The following day, the inspectors !
l were informed that engineering management had rescinded the E-mail '
memo and informed all involved personnel that verbal approval was
required for each test. The inspectors identified this failure to
follow procedure as VIO 50-366/98-01-03: Failure to Follow
j. Engineering Test Procedures.
i
I
Enclosure 2
,
. .
.
16
c. Conclusions
A violation for a failure to follow engineering test procedures,
was identified. This violation was for the failure to follow
procedure for. review.- approval, and signature authority of the
responsible engineer for pressure testing.
E8 Miscellaneous Engineering Issues
l
E8.1- (Closed) LER 50-321.98-01. Inocerable MCREC System Filter Trains
Result in Entry Into LCO 3.0.1.
This issue is' discussed in Section E2.1 of this Inspection Report.
- This LER is closed.
!
IV Plant SuDoort
R1 Radiological Protection and Chemistry (RP&C) Controls
R1.1 Observation of Routine Radiolooical Controls (71750)
l General Health Physics (HP) activities were observed during the
report period including: locked high radiation area doors, proper
'
radiological posting, and personnel frisking upon exiting the
radiologically-controlled area (RCA). The inspectors made
frequent tours of the RCA and discussed radiological controls with
, HP technicians and HP management. Minor deficiencies identified {
were discussed with HP management. I
R1.2 Conduct of Radiological Prot'ection Controls
a. Insoection Scooe (83750) (84750)
Radiological controls associated with on-going routine Unit 1 (U1)
and Unit 2 (U2) operations were reviewed and evaluated by the
inspectors. Reviewed program activities included area postings
and radioactive waste (radwaste) and material container labels,
high and locked high radiation area controls, and procedural and
radiation work permit (RWP) implementation.
The observed radiation protection activities were compared against
anlicable sections of the Updated Final Safety Analysis Report
-
(FSAR) and against approved procedures Technical Specifications
(TSs) and 10 CFR Part 20 requirements.
l b. Observations and Findinas
All high radiation area postings and container labels were
determined to be adequate for the associated radiological
conditions. Calibrations for "in use" direct radiation and air
l Enclosure 2
i
l b
!
- . .
l*
,
17
sampler instrumentation were current. Excluding worker and HP
- actions required for surveillances conducted on the U1 Condensate
Pump equipment on the Turbine Building 112-foot (') elevation.
radiation controls for high and locked high radiation areas were
adequate and implemented appropriately.
Several concerns regarding radiological controls were identified
during direct observations on March 10, 1998, and from subsequent
followup, of established practices for engineer / maintenance
workers conducting vibration analysis measurements on the U1
Condensate Pump cquipment located in the posted high radiation
area on the 112' elevation of the Turbine Building. The concerns
involved the adequacy of radiological surveys and implementation
of 3rocedural controls based on discussions with the involved
worcer cognizant HP staff and engineering managers and
verification of applicable RWP and associated )rocedural
requirements. From review and discussion of t1e current and the
three previous U1 Condensate Pump vibration analysis measurements
made on October 7. 1997. January 13, 1998, and February 10. 1998,
the inspectors noted that detailed radiation surveys to identify
the specific radiation levels and the potential hazards to workers
performing the measurements were not conducted. Licensee
representatives stated that general radiation surveys of the work
area conducted on May 15. 1997. December 15. 1997, and
December 31, 1997, within the U1 Condensate Pump ecuipment high
radiation area, were used in lieu of performing adcitional surveys ,
for each of the four vibration analysis measurements conducted
between October 7, 1997 and March 10, 1998. However, the
inspectors noted that these surveys failed to identify the maximum
contact and general area dose rates associated with specific
locations where the vibration analysis measurements were conducted
and the documented dose rates varied significantly. For example,
the March 10. 1998, radiation survey indicated maximum contact and
general area dose rates of 300 and 260 millirem per hour
(mrem /hr), respectively: whereas, the May 15, 1997, survey
documented a maximum general area dose rate of 700 mrem /hr but no
contact values. The inspectors identified the failure to conduct
adecuate radiation surveys in accordance with 10 CFR 20.1501 for
concen. sate pump vibration analysis tests as violation (VIO)
50-321/98-01-06. Failure to Conduct Adequate Surveys to Evaluate
the Radiation Levels and Potential Hazards to Workers Conducting
U1 Condensate Pump Vibration Analysis Measurements. j
i
In addition. procedural adherence concerns were identified for the ;
, March 10, 1998, entry into the high radiation area. The
inspectors noted that procedure 60AC-HPX-004-0S. Radiation and
i
Contamination Control. Rev. 15. required, in part, plant personnel
to comply with all radiation protection postings, rules,
regulations and 3rocedures: to notify Health Physics (HP) prior to
the start of worc authorized in any RWP: and to read and to comply
.
Enclosure 2 l
'. .
.
!
'
- with the requirements of the RWP whenever their duties require
l such authorization. For jobs within a high radiation area. HP is
!
D
required to perform pre-job surveys or enter the area with the
workcrew to perform surveys while the job is worked to document
- the survey-data. and to adjust RWP requirements. if necessary.
Radiation Work Permit.98-0003. Rev. 0.-starting January 1. 1998.
required. in part, workers to notify HP of work scope prior to the
l
'
start of the job and HP personnel to determine or verify radiation
conditions for each specific work location. The inspectors noted ~
-that the worker failed to notify HP personnel of the work scope
prior to the start of the job nor were surveys conducted
,
immediately preceding, or during conduct of-the testing in the
area. The inspectors identified the failure to follow procedures
in accordance with TS 5.4.1 as VIO 50-321. 366/98-01-04 Failure
to Follow Procedures for Entry into a High Radiation Area.
General facility housekeeping and cleanliness concerns were also
noted during the week of March 9. 1997. Numerous examples of used
protective clothes, including cloth and paper coveralls. cloth
liners and rubber gloves discarded outside of established
collection receptacles and examples of potentially contaminated
PCs overflowing collection receptacles were observed. Numerous
examples of discarded paper trash were noted throughout the
- facility. Also.- abandoned tools identified as having fixed
contamination and several instances of tools and equipment
'
extending across established contamination boundaries were
observed.
c. Conclusions
Excluding the U1 Condensate Pump Turbine Building 112' elevation
high radiation area. radiological controls for normal operations
and for radwaste and radioactive material storage areas were
implemented )roperly and maintained in accordance with procedural.
TS and 10 CFR Part 20 requirements.
A violation of 10 CFR 20.1501 requirements was identified for
failure to conduct adequate surveys to evaluate the extent of
radiation levels and potential hazards to workers conducting
condensate pump vibration analysis measurements within a high
radiation area.
A violation was identified for failure to follow procedures in
accordance with TS 5.4.1 for entry into a High Radiation Area.
l- A negative observation of numerous examples of poor facility
housekeeping and cleanliness, and poor contamination control
practices was identified.
l
Enclosure 2
. .
\'
l
19
R2.1 Status of RP&C Engineered Safety Feature (ESF) Ventilation Systems
(84750)
a. Insoection Scoce
Operability of the Main Control Room Environmental Control (MCREC)
Engineered Safety Feature (ESF) ventilation system was reviewed.
The review included system walk-downs. verification and analysis
of results from selected surveillances, and evaluation of
resultant data for the previous two refueling cycles.
Results of this review were compared against recuirements
specified in TS Section 3.7.4 and TS Program anc Manual.
Section 5.5. Ventilation Filter Testing Program.
b. Observations and Findinas
All MCREC ESF ventilation system surveillances were conducted at
the required frequencies and the results met established
acceatance criteria. However, the inspectors questioned whether
the MCREC chiller units would meet the established acceptance
criteria during periods of elevated service water temperatures.
For the most recent chiller capacity tests, conducted in November
1996 when service inlet water temperature was relatively low,
approximately 60 degrees Fahrenheit. the documented cooling
capacities for two of the three chiller units were only slightly l
above the control room cooling load acceptance criteria of 311.011
'
British Thermal Units. Licensee representatives stated that
modifications made to the chiller piping after completion of the
November 1996 surveillance test were expected to improve the
cocling capacity results. Licensee representatives stated that
'
the next MCREC cooling capacity test was scheduled for
approximately May-June 1998.
Concerns were also noted for the material condition of the MCREC
ductwork and ventilation equipment. Specifically, the inspectors
noted insulation missing from sections of the ventilation
ductwork. Licensee representatives acknowledged the degraded
condition of the insulation but noted that a decision was made to
delay repairing the insulation until completion of a potential
modification to the system. However, no dates had been scheduled
for actual modification work on the system nor dates when the
insulation would be repaired if the modification was not
implemented.
As a result of questions regarding the MCREC chiller capacity test
results and ductwork insulation, the inspectors opened Inspector
Followup Item (IFI) 50-321, 366/98-01-07 Review of May-June 1998
Main Control Room Ventilation Cooling Capacity Test Results and
Evaluate Material Condition of System Components.
f
j Enclosure 2
'. .
p-
,
l
20
,
c. Conclusions
l
l Main control room environmental control (MCREC) Engineered Safety
( Feature (ESF) subsystem surveillance tests were conducted in
accordance with TS requirements and results met established
acceptance criteria to establish operability.
'
Results for the
l MCREC chiller cooling tests showed marginal cooling capacity.
l
l A negative observation of the material condition of the
l ventilation ductwork insulation was identified.
1
R4 Staff Knowledge and Performance
,-
'
R4.1 Failure to Analyze Unit 1 Drywell (DW) Containment Atmosohere Grab
Samole
!
a. Insoection Scone (71750) (92904)
The inspectors reviewed procedure 64CI-0CB-005-0S " Fission i
Product Monitors." Rev. 2. ED 1. TS 4.4.5, RCS Leakage Detection i
Instrumentation. and chemistry personnel performance for DW
containment sampling activities.
b. Observations and Findinas
, On February 8, 1998, operations personnel declared both the
! gaseous and the particulate channels of Unit 1 Fission Product
Monitor (FPM) system inoperable to implement corrective
j maintenance. With both channels inoperable. TS 4.4.5 requires
that personnel analyze grab samples of primary containment
atmosphere once per every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. Grab samples of the primary
containment atmosphere must be taken and analyzed to provide
periodic leakage information. Procedure 64CI-0CB-005-05.
Subsection 7.20. Inoperable Monitoring System (s), provided the
required actions to complete the sampling and analysis for
particulate, iodine, and noble gas. - Chemistry personnel were
responsible for implementing the requirements of the surveillance
procedure.
0)erations personnel had declared the FPM system inoperable at
a)out 1:25 a.m. The grab sample was taken at about 8:00 a.m..
however, the sam)le was not analyzed within the required 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
A subsequent gra) sample and analysis, completed at about 6:30
p.m.. did not indicate any leakage and met the procedure
acceptance criteria. The technician obtained the first grab sample
but analyzed for oxygen concentration only. This did not meet the
requirements of the surveillance 3rocedure. A TS violation did
not occur due to a subsequent gra) sample being analyzed within
the required time.
Enclosure 2
( ,
. .
,
V.
l
L 21
l
The inspectors identified other factors that are associated with
l
the failure to follow a surveillance test procedure. For example,
o)erations personnel generally inform the chemistry department
w1en surveillance procedures or TS-required actions are to be
completed. -However, operations personnel do not routinely discuss
,
or review chemistry surveillance procedure results.
Additionally operations approval for the beginning or completion
of chemistry surveillance test procedures was not required. In
this case, chemistry personnel reported the oxygen concentration
of the grab sample to the control room. However, control room ,
t o)erations personnel did not ask for or cuestion the results of
t1e analysis for particulate. iodine, anc noble gas, which were
required by the procedure and TS. The chemistry procedure did not )
provide specific guidance for chemistry personnel to inform '
operations of the grab sample results.
Procedure 64CI-0CB-005-05. Subsection 7.20. required the chemistry
technician to complete the grab sam)le, document the results on
y procedure attachments and present t1e attachments. to the
l chemistry foreman for review and approval. In this case the
technician did not. complete the attachments because an oxygen
concentration was the only analysis obtained. The Health Physics
(HP)/ Chemistry foreman on duty did not question why the technician
did not.present the attachments for review and ap)roval. HP
supervision informed the inspectors that the HP/Clemistry foreman
on duty during the shift had expertise in HP activities and relied
i- upon the knowledge and abilities of the chemistry technicians to
correctly perform their required duties.
c. Conclusions l
Failure to completely analyze the grab sample as required by I
procedure 64CI-0CB-005-0S subsection 7.20 is identified as VIO
50-321.-366/98-01-09. Failure to Analyze Grab Samples. The
inspectors-concluded that poor supervisory oversight of chemistry
activities and chemistry department interface with operations-
personnel contributed to a failure to follow procedure.
R4 2 Fuel Oil Samolina Technioues
i a. Insoection Scooe (71750)
The inspectors reviewed procedure 64CH-SAM-002-0S. " Diesel Fuel
Oil. Sampling and Analysis." Rev. 5. and observed chemistry
personnel obtain samples of the Security Diesel fuel oil.
Enclosure 2
r-
'
<
. .
4
22
l
b. Observations and Findinas
The inspectors observed that chemistry technicians had the
,
procedure and all equipment recommended by the procedure in their
. possession. The equipment used and the sampling techniques
'
observed met the requirements of the procedure.
c. Conclusions
The inspectors concluded that chemistry technicians used proper
equipment and sampling techniques while obtaining fuel oil
samples.
R8 Miscellaneous RP&C Issues (83750, 84750)
'
R8.1 (Closed) VIO 50-321. 366/97-10-05: Failure to Meet 10 CFR 20.1904
Labelina Reauirements for Containers of Radioactive Materials
Temocrarily Stored in the Unit 1 Torus Pool .
The inspectors reviewed and verified that training guidance was
modified to better define and provide examples of the term
" container" as used within the context of 10 CFR 20.1904. Based
on revisions to training modules. review of this issue during
completion of continuing training by the "in-house" technicians,
and provisions to provide the enhanced guidance to contractor HP
technicians, this item is closed.
R8.2 (Closed) VIO 50-321. 366/97-11-06: Failure to Follow Procedures
for Radiation and Contamination Control and Personnel
Decontamination Activities.
The inspectors reviewed and discussed the identified root causes
l' and verified corrective actions documented in Significant
L Occurrence Report Number (No.) C09705936. dated January 5. 1998.
Corrective actions were incor) orated into lesson plan details
'
l provided to "in-house" HP tec1nicians during continuing training
and contractor HP technicians. Training was completed for the
in-house" staff by the end of the inspection period. Based on
licensee actions. this item is closed.
L
'
R8.3 (Closed) VIO: 50-321. 366/97-11-07: Failure to Foll.ow Procedures
for RWP Imolementation
Licensee initial corrective actions included continuation of
numerous quality checks during the outage and notification to
appropriate departments to address access control issues. Also,
for subsequent refueling outages, several outage RWPs were
initiated before contractors began in-processing. In addition,
the licensee reinstalled access control printers and required
Enclosure 2
-
. .
9
23
L check-in at HP control points to detect improper RWP usage. Based
l on licensee action, this item is closed.
P8 Miscellaneous Emergency Preparedness Issues (92904)
l P8.1 (Closed) Insoector Followuo Item (IFI) 50-321. 366/96-10-07. Lack
I
of Guidance for Inocerable Instrumentation Used for Offsite Dose
Calculations.
The inspectors reviewed the licensee's actions to perform timely
offsite dose calculations in the event that radiological-
l instrumentation was not functional. Section 7 2 of
! 73EP-ElP-015-05. Offsite Dose Assessment. Rev. 4. and Sections 7.3
and 7.4 of 73EP-EIP-018-0S. Prompt Offsite Dose Assessment. Rev.5,
were revised to include guidance in performing offsite assessments
,
in the event that normal range effluent radiation monitors are
l offscale and accident range monitors are unavailable.
Based upon the inspectors' review of the licensee's actions in
response to this item, it is closed.
l
l S2 Status of Security Facilities and Equipment (71750)
!
The inspectors. toured the protected area and observed that the
l perimeter fence was intact and not compromised by erosion or
!- disrepair. The fence fabric was secured and barbed wire was
- angled as required by the licensee's Plant Security Program (PSP).
l Isolation zones were maintained on both sides of the barrier and
were free of objects which could shield or conceal an individual'.
l The inspectors observed that personnel and packages entering the
protected area were searched either by special purpose detectors
'
or by a physical patdown for firearms, explosives, and contraband.
Badge issuance was observed, as was the processing and escorting
of visitors. Vehicles were searched, escorted, and secured as-
l
described in applicable procedures.
The inspectors concluded that the areas of security inspected met
the applicable requirewnts.
F1 Control of Fire Protection Activities
F1.1 Desian Basis of Fire Barrier Penetration Seals
! a. Insoection Scooe (64704)
The inspectors reviewed the fire barrier penetration seal designs
and testing for compliance with the facility's licensing
requirements identified in the Updated Final Safety Analysis ,
Report-(UFSAR) Section 9.5.1 " Fire Protection Systems." and i
Enclosure 2
<
i
l !
_ _ - _ _ - _ _-____ _ _ - _ _ _
. .
.
24
Sections 9.4 and 9.9 of the Hatch Fire Hazards Analysis, and Fire
Protection Program.
The inspectors compared selected as-built fire barrier 3enetration
seals to fire 2ndurance test configurations to verify tlat those
seals were qualified by appropriate fire endurance tests and
representative of the design and construction of the fire
endurance test specimens-. During plant walkdowns, the inspectors
observed the installation configurations of selected accessible
fire barrier penetration seals to confirm that the licensee had
established an acceptable design basis for those fire barriers
used to separate safe shutdown functions for a fire event,
b. Observations and Findinas
Laboratory testing of fire barrier materials is done only on a
limited range of test assemblies. In-plant installations can vary
from the tested configurations. Under the provisions of Generic
Letter (GL) 86-10. " Implementation of Fire Protection
Requirements." licensees were permitted to develop engineering
evaluations justifying such deviations.
The inspectors reviewed the fire barrier penetration seal design
records. Hatch Nuclear Plant Management Information System
computer database design records, cuality assurance and quality i
control (0A/0C) installation recorcs penetration seal typical l
detail drawings and testing records.
For the review, the inspectors used UFSAR Section 9.5.1. " Fire
,
Protection Systems *" the Hatch " Fire Hazards Analysis and Fire
l' Protection Program." Rev. 12B, Section 3.4. " Establishment of Fire
I
Area / Zones." Section 4.3 " Fire Barriers." Section 9.4.
" Appendix A Compliance Matrix." and Section 9.9. " Fire Barrier
Penetration Report:" Hatch Fire Protection Procedure No.
42FP-FPX-014-0S. " Installation and Repair of Silicone Foam Seals."
Rev. 1: Hatch Fire Protection Procedure No. 42FP-FPX-003-05.
" Installation of Nelson Electric Fire Stops." Rev. 3: Hatch
nuclear safety reviews concerning NRC Information Notices
(ins) 88-04. IN 88-56. and IN 94-28: selected penetration seal as-
built location drawings. B-19631 series: selected Fire Rated
Penetration Seal Qualification Data. S-52429. Brand Industrial
Services Company (BISCO) silicone foam products. S-52480/52483.
Chemtrol Corporation silicone foam products, and S-52439/52482.
Nelson Electric Firestop Products: and recognized industry fire 1
penetration seal testing guidance of American Society for Testing
and Material (ASTM) Standard E814-1988. " Standard Test Method for
Fire Tests of Through-Penetration Fire Stops." and Institute of
Electrical and Electronics Engineers (IEEE) Standard 634-1978.
"IEEE Standard Cable Penetration Fire Stop Qualification Test."
Enclosure 2
_ - _ _ _____ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
25
Using the UFSAR Fire Hazards Analysis (FHA) and the composite fire
wall delineation drawings H-15907 through H-15911 to determine the
location and description of the plant fire areas, the inspectors
conducted walkdowns and inspected penetration seal installations.
The inspectors' review focused on verifying that the following
design and installation Jarameters for the as-built configurations
were adequately bounded ]y tests or ju.stified by licensee's
engineering evaluations:
e penetration type and opening size:
e seal material type and depth:
e damming material type and orientation:
e types and thermal mass of penetrating items;
e clearances of penetrating items; and
e fire test results for unexposed surface temperatures
The following penetration seals were visually inspected and the
OA/0C engineering and construction penetration procedure data
package records for these seals were reviewed to determine that
the as-built plant seal configurations were representative of
those utilized in fire seal qualification tests:
_
PENETRAT1001 SEAL SUtst4ARY SEAL DAMGENG
GAATEIRAL BAATENAL
EMNTRCATIOtil LOCATIOtt i SIZE DESIGN DEPTH I TYPE 1YPE / ORIENTATION FIRE TEST REPORTS /
NuttBEll DNCHES) DETAAL QUALIFICATIOtt
COVERED UNIT 2 CONTROL CT 7 11" - CT 18 CT-23 CHEMTROL S 52483
ELECTRICAL CABLE BUILDING / FLOOR CHEMTROL DAMMING ~ BOTTOM CTP 0303
TRAY BETWEEN FIRE SILICONE FOAM SIDE 3 HOURS
PENETRATION ZONES 0024A AND
2243H014F 2104 / 72 X36
OPEN ELECTRICAL UNIT 2 CONTROL CT-7 11* CT 18 CT 23 CHEMTROL S-52480
CABLE TRAY AND BUILDING / FLOOR CHEMTROL DAMMING -BOTTOM FC-225
CONDUIT BETWEEN FIRE SILICONE FOAM SIDE 3 HOURS
PENETRATION ZONES 0024A AND
2243H016F 2104 / 42 X18
COVERED UNIT 2 CONTROL CT 7 11" - CT 18 CT-23 CHEMTROL S 52483
ELECTRICAL CABLE BUILDING / FLOOR CHEMTROL D AMMING -BOTTOM CTP 0303
TRAY AND BETWEEN FIRE SILICONE FOAM SIDE 3 HOURS
CONDUIT ZONES 0024A AND
PENETRATION 0040 179 X68
2Z43H033F
ELECTRICAL UNIT 2 CONTROL P-7 12". SF 20 NONE TEST REPORT
CONDUli INTERNAL BUILDING / FLOOR BISCO
l
NOT AVAILABLE i
PENETRATION BETWEEN FIRE SILICONE FOAM j
2243H091F ZONES 0028 AND i
2023 / 4
MECHANICAL PIPE UNIT 2 CONTROL XP-3 NOT AVAILABLE NOT AVAILABLE FIRE BARRIER
PENETRATION BUILDING / WALL PENETRATION REPORT
WITH TWO PIPE BETWEEN FIRE EVALUATION 0-13
PENETRANTS ZONES 0001 AND
2243H111C 2003 / 8
Enclosure 2
.
.
- _ _ _ _ _ _ _
. .
26
PenETnAima BEAL BuMMAny BEAT -
MATE 8EAL IBATEfuAL
WBNTW4CA110Ie/ LOCA1MMI / SIZE - DEFFH I TYPE TYPE / OIENTAftoel FWE TEST REPORTS /
IRNM WIC0ESI DETAE. nuas agCAygong
MECHAMCAL PIPE UNIT 2 CONTROL P7 12"- SF.20 NONE TEST REPORT
PENETRAYlON BUILDING / WALL B!SCO SILICONE NOT AVAILABLE
2243rt092D BETWEEN FIRE FOAM
ZONES 2023 AND
0014L / 4
ELECTRICAL UNIT 1 CONTROL E7 11* CT-1B CT 23 CHEMTROL S-62480
CONDUIT BUILDING FLOOR / CHEMTROL DAMMING -BOTTOM FC-225
PENETRATION BETWEEN FIRE SILICONE FOAM SIDE 3 HOURS
1243 HOB 3J ZONES 0024A AND
00240 /87 X 2 6
SPARE BLOCKOUT UNIT 2 CONTROL XSP-1 NOT AVAILABLE NOT AVAILABLE FIRE BARRIER
PENETRATION BUILDING / WALL PENETRATION REPORT
2243H073C BETWEEN FIRE EVALUATION 1-13
ZONES 2003 AND
2101 A /28 X 24
MECHANICAL FIRE UNIT 2 CONTROL XH-7 NOT AVAILABLE NOT AVAILABLE FIRE BARRIER
DAMPER BUILDING / WALL PENETRATION REPORT
PENETRATION SETWCEN FIRE EVALUATION l-15
2243HO92C ZONES 2003 AND
2101A /18 X 18
1
ELECTRICAL UNIT 2 CONTROL E3 0.5". NELSON 2.0"- NELSON S-62439
CONDuli BUILDihiG / WALL ELECTRIC ELECTRIC RSW SWR-86-2-10
PENETRATION BETWEEN FIRE FIRESTOP CAULK FIRESTOP DAMMING 3 HOURS
I 2243H0103F ZONES 0028 AND
>
2023 1 4
!
! MECHANICAL PIPE UNIT 1 CONTROL P-7 9"- SF-20 NONE TEST REPOflT
[ PENETRATION BUILDING / WALL BISCO SILICONE NOT AVAILABLE
1
,
1243H029C BETWEEN FIRE FOAM
'
ZONES 0001 AND
1004iB l
!
l- MECHANICAL PIPE DIESEL GENERATOR P-7 12*- 3F-20 NONE TEST REPORT
I PENETRATION BUILDING / WALL BISCO SILICONE NOT AVAILABLE
! 1Y43H077D BETWEEN FIRE FOAM
ZONES 1409 AND
1411 /8
MECHANICAL PIPE REACTOR AUXILIARY P5 0.6". NELSON NONE S-52482
PENETRATION BUILDING / WALL ELECTRIC ULC SP 68-
1T43H623J BETWEEN FIRE FIRESTOP 3 HOURS
2ONES 1203K AND SPEEDPLUG
1205 / 20 PILLOWS
The inspectors' visual inspections did not identify any missing seals
and verified that the installed fire barrier penetration seals were
continuous with no gaas, cracks, or holes in the barrier material that
would indicate that tie seals were inoperable. The installation and
repair procedures for penetration seals provided adequate guidance to
ensure materials were installed per design requirements. The fire
barrier penetration report evaluations conducted for penetration seals
that were inaccessible for visual inspections were adequate.
1
l
Enclosure 2 i
,
l
.
!
27
The inspectors conducted a review of the Brand Industrial Services
Company and Chemtrol Company silicone foam mechanical prototype design
detail P-7 and electrical prototype design detail CT-7. The inspectors
found that penetration seal as-built field verification documentation
was maintained by the licensee. However, the vendor penetration seal
l
qualification test report documentation and the vendor data for the
tested prototype silicone foam configurations for the Brand Industrial
Services Company silicone foam prototype fire barrier configurations
were not readily available for review. Also, the as-built documentation
did not identify important design parameters with respect to cable tray
fill the maximum or minimum clearances of penetrating items and their
thermal mass and the maximum free area of unsupported penetration seal
material installed within the silicone foam penetration. Because the
test report documents were not available for all silicone foam
penetration seal configurations. the licensee had not compared the
design and installation details with tested configurations nor performed
GL 86-10 engineering evaluations to determine the adequacy of any
deviations from tested fire barrier configurations. This did not
satisfy the guidance of GL 86-10 and was considered to be a program
weakness.
Licensee personnel stated that industry and vendor qualification test
report documentation was available to support these silicone foam
penetration seal installations at Hatch and was being procured under
requisition No. HPBH-980695. The licensee initiated Request for
Engineering Assistance (REA) No. HT-98617 to expand the as-built
penetration seal database to incorporate a higher level of detail
concerning penetration seal design parameters and to document
a)propriate engineering evaluations. Licensee Jersonnel stated that
t1is work was scheduled for completion by Decem)er 1998. The silicone
foam penetration seal qualification testing documentation, penetration
seal design parameters, and evaluations of deviations from tested fire
barrier configurations will be reviewed during a subsequent NRC
inspection. This item is identified as Inspector Follow-up Item (IFI)
50-321, 366/98-01-05. Review of Licensee Records and Engineering
Evaluations to Establish the Fire Resistant Capabilities of Fire Rated
Silicone Foam Penetration Seals.
c. Conclusions
The inspectors concluded that the installation and repair procedures for
penetration seals provided adequate guidance to ensure that materials
were installed per design requirements. The fire barrier penetration
report evaluations conducted for penetration seals that were
inaccessible for visual inspections were adequate. However, the Brand
Industrial Services Com)any silicone foam penetration seal designs were
l
not supported by availa)le vendor qualification test reports.
Engineering evaluations to satisfy the guidance of GL 86-10 for
deviations from the silicone foam fire barrier seal configurations
Enclosure 2
1
1
'
. .
i
28
qualified by tests had not been performed and was considered to be a i
program weaknesses.
I
F2 ' Status of Fire Protection Facilities and Equipment "
F2.1 Surveillance of Fire Protection Features and Equipment
a. Insoection Scooe (64704)
The inspectors reviewed procedures 42SV-FPX-019-1S/25. " Penetration Seal
Surveillance." Revision 2. and the penetration seal surveillance results
records for the surveillance procedures which were completed April 15.
1997. These were reviewed for compliance with the requirements of FSAR
Section 9.5.1 and Fire Hazards Analysis, Ap)endix B. Section 2.1.1.c.
.
" Fire Equipment Operating and Surveillance Requirements."
b. Observations and Findinas I
Surveillance procedures 42SV-FPX-019-1S/2S required a visual inspection
i
each 18 months of a random sample of ten percent of each type of fire
barrier penetration seal. The sample inspections were required to
' include fire barrier seals that had not been inspected within the past
15 years. Each seal was inspected for any apparent change in
l
'
appearance, noticeable damage, signs of abnormal degradation, and
pulling away from wall or penetrating item.. If any abnormality was
found, an additional ten percent of seals was required to be inspected.
,
'
.The inspection and selection process was to continue until an acceptable
sample was found.
The inspectors reviewed Procedure 42SV-FPX-019-1S/2S and concluded that
the procedure met the frequency requirements of Fire Hazards Analysis,
Appendix B. Section 2.1.1.c. " Fire Equipment Operating and Surveillance
Requirements," and met the commitments made to the NRC.
The results of penetration seal surveillance inspections completed
April 15,1997, were reviewed by the inspectors. No discrepancies were
noted.
c. Conclusion
The surveillance inspection procedures for the fire barrier penetration
seals were adequate and the 18-month surveillance requirements were
established appropriately to verify operability. The April 1997
penetration . seal inspections had been satisfactorily implemented.
Enclosure 2
i
.
. .
,.
'
29
F4 Fire-Protection Staff Knowledge and Performance
F4.1 Unannounced Fire Drill and Triennial Audit
a. Insoection Scoce (71750)
In March the inspectors reviewed procedure 42FP-FPX-005-05. " Drill
Planning. Critiques and Drill Documentation " Rev.1. drill objectives,
and audit observations. They also observed fire brigade performance
during an unannounced fire drill.
b. Insoection Findinas
On March 3. the ins)ectors observed an unannounced fire drill for a
simulated fire in t1e Unit 1 reactor building. The inspectors observed
that the procedure requirements for the drill planning and critique were
completed satisfactorily. Drill objectives were clearly defined prior
to the drill. All drill objectives except one were met. That drill
objective was for all fire brigade members responding to the fire to be
fully qualified. Two persons that responded were not fully qualified,
i however neither of the individuals was part of the required five-person
fire brigade.' The inspectors observed that seven licensee evaluators
'
observed and evaluated the fire brigade performance. Some of the
'
evaluators, who performed the triennial audit function, were from
another site and outside of the Hatch organization.
The inspectors also observed that the fire brigade leader set up a
command post, used pre-fire plans, and demonstrated good leadership
abilities during the drill. The overall performance and effectiveness
of the fire brigade was satisfactory.
L c. Conclusions
! The ins)ectors concluded that the fire brigade leader demonstrated good
i leaders 11p abilities during the unannounced fire drill conducted on
!
March 3. The overall performance and effectiveness of the fire brigade
was satisfactory.
F5 Fire Protection Staff Training and Qualification
l
l F5.1 Fire Barrier Penetration Seal Installers and OC Inspectors
a. Insoection Scooe (64704)
The inspectors reviewed training records for three contractor employees
designated to install and repair fire barrier penetration seals and the
'
. OC inspectors designated to inspect the penetration seals for compliance
with the requirements of UFSAR Section 9.5.1.
Enclosure 2
--_ __ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
'
, .
.
30
b. Observations and Findinas
The inspectors reviewed training records for the contractor employees
and the OC inspectors designated on three maintenance work orders
-(MW0s), MWO-1-94-5079, MWO-1-95-4304 and MWO-0-6901. The contractor
employees had received initial classroom training and practical
application in the installation of the types of fire barrier penetration
seals used at the Hatch facility. This training was conducted by the
vendor who supplied the . seal material for the various fire barrier
penetration seals installed at the facility. The inspectors verified l
that the contractor and OC employees had received appropriate outage
retraining and recertification to maintain up-to-date knowledge and
installation techniques for these seals prior to performance of field l
work,
c. Conclusion
The fire barrier penetration seal installers were appropriately trained l
to accomplish fire barrier penetration seal installation work and the OC i
inspectors were qualified to perform the a)propriate verification for l
installation and repairs made to the fire Jarrier per 2 ration seals. i
i
'
.F8 Miscellaneous Fire Protection Issues (92904)
F8.1 (Closed) IFI 50-366/97-02-06. Review of Qualifications and Trainina for
Fire Watch Personnel. '
The licensee reviewed its GET training material for revision to ensure
that fire watch issues (types and expectations) would be more clearly
communicated to all of its em)loyees. The inspectors reviewed the
revised General Employee Hand)ook and noted that it included a section <
on Fire Watch Duty, which addressed the issues. Based upon the
inspectors' review, this item is closed.
V. Manaoement Meetinas
X.2 Review of UFSAR Commitments
A recent discovery of a licensee operating its facility in a manner
contrary to the Updated Final Safety Analysis Report (UFSAR) description
highlighted the need for a special focused review that compares plant
practices. procedures, and/or parameters to the UFSAR descri) tion.
While performing the inspections discussed in this report tie
inspectors reviewed the applicable portions of the UFSAR that related to
, the areas inspected. The inspectors verified that the UFSAR wording was
consistent with the observed plant practices, procedures, and/or
parameters.
Enclosure 2
_ _ _ - _ _ _ - _ _ _ _ _ _ _
'
. ..
.
31
X.3: Exit Meeting Summary
The inspectors presented the inspection results to members of the
licensee management at the conclusion of the inspection on March 27,
1998. The license acknowledged the findings presented. Interim exits
were conducted on February 27 and March 13, 1998.
The inspectors asked the licensee whether any materials examined during
the inspection should be considered proprietary. No proprietary
information was identified.
PARTIAL LIST OF PERSONS CONTACTED
Licensee
Anderson J. , Unit Superintendent
Betsill. J., Assistant General Manager - Operations
Breitenbach. C. . Engineering Support Manager - Acting i
Curtis S. Unit Superintendent
Davis. D., Plant Administration Manager
Ellgass. L., Maintenance Rule Coordinator
Fornel P., Performance Team Manager
Fraser. 0.. Safety Audit and Engineering Review Supervisor.
Hammonds, J. , Operations Support Superintendent
Kirkley. W., Health Physics and Chemistry Manager
Lewis, J., Training and Emergency Preparedness Manager
Madison. D., Operations Manager
Moore C.. Assistant General Manager - Plant Support
Reddick. R., Site Emergency Preparedness Coordinator
Roberts. P., Outages and Planning Manager
,
Thompson. J. , Nuclear Security Manager
Tipps. S. Nuclear Safety and Compliance Manager
Wells. P., General Manager - Nuclear Plant
INSPECTION PROCEDURES USED
IP 37551: Onsite Engineering
IP 61726: Surveillance Observations
IP 62002: Inspection of Structures, Passive Components. and
Civil' Engineering Features at Nuclear Power Plants
IP 62706: Maintenance Rule
IP 62707: Maintenance Observations
IP 64704: . Fire Protection Program
IP 71707: Plant Operations
IP 71750: Plant Support Activities
IP 83750: Occupational Radiation Exposure
IP 84750: Radioactive Waste Treatment, and Effluent and
Environmental Monitoring
IP 92700: Onsite Followup of Written Reports of Non-routine i
Events at Power Reactor Facilities l
Enclosure 2
-
. .
e
32
IP 92901: Followup - Operations
IP 92902: Followup - Maintenance / Surveillance
IP 92903: Followup - Engineering
IP 92904: Followup - Plant Support
ITEMS OPENED. CLOSED, AND DISCUSSED
Ooened
50-321, 366/98-01-01 IFI Review of Maintenance Rule Periodic
Assessment Procedure (Section M1.3)
50-366/98-01-02 VIO Failure to Follow Maintenance
Procedures (Section M4.1).
50-366/98-01-03 VIO Failure to Follow Engineering Test
Procedures (Section E3.1).
50-321/98-01-04 VIO Failure to Follow Procedure for
Entry into a High Radiation Area
(Section R1.2).
50-321, 366/98-01-05 IFI Review of Licensee Records and
Engineering Evaluations to Establish
the Fire Resistant Capabilities of
Fire Rated Silicone Foam Penetration
Seals. (Section F1.1).
50-321/98-01-06 VIO Failure to Conduct Adequate Surveys
to Evaluate the Radiation Levels and
Potential Hazards for Workers
Conducting Unit 1 Condensate Pump
Vibration Analysis Measurements
(Section R1.2).
50-321, 366/98-01-07 IFI Review of May-June 1998 Main Control
Room Vent 11ation Cooling Capacity
Test Re ults and Evaluate Material
Condit wn of System Components i
(Section R2.1)
50-321, 366/98-01-08 EEI Plant 0)eration Outside of the
Design 3 asis for an Engineered
Safeguard System (Section E2.1).
- 50-321/98-01-09 VIO Failure to Follow Procedure for
Analysis of a Grab Sample (Section
R4.1).
Enclosure 2
L
'. .
.
32
IP 92901: Followup - Operations
IP 92902: Followup - Maintenance / Surveillance
IP 92903: Followup - Engineering
IP 92904: Followup - Plant Support
ITEMS OPENED. CLOSED. AND DISCUSSED
Ooened
50-321, 366/98-01-01 IFI Maintenance Rule Periodic Assessment
l (Section M1.3)
50-366/98-01 02 VIO failure to Follow Maintenance '
Procedures (Section M4.1).
50-366/98-01-03 VIO Failure to Follow Engineering Test
Procedures (Section E3.1).
! 50-321/98-01-04 VIO Failure to Follow Procedure for
Entry into a High Radiation Area j
,
(Section R1.2).
l
50-321. 366/98-01-05 IFI Review of Licensee Records and
Engineering Evaluations to Establish
the Fire Resistant Capabilities of
l Fire Rated Silicone Foam Penetration
! Seals. (Section F1.1).
l
50-321/98-01-06 VIO Failure to Conduct Adequate Surveys
l to Evaluate the Radiation Levels and
l Potential Hazards for Workers 1
l Conducting Unit 1 Condensate Pump
Vibration Analysis Measurements
(Section R1.2).
l
I
50-321. 366/98-01-07 IFI Review of May-June 1998 Main Control
l
'
Room Ventilation Cooling Capacity
Test Results and Evaluate Material
- Condition of System Components
l (Section R2.1)
i
i
'
50-321. 366/98-01-08 EEI Plant 0)eration Outside of the
Design Basis for an Engineered
Safeguard System (Section E2.1). 1
50-321. 366/98-01-09 VIO Failure to Follow Procedure for
Analysis of a Grab Sample (Section 1
R4.1).
l
Enclosure 2 1
i
p !
t
n
. .
l
l. 1
33
i
Closed
i
50-321, 366/97 O'6-01 VIO Failure to P'revent Recurrence of
L Improper Equipment Storage in
Control Room (Section 08.1).
50-366/97-02 LER Grounded Jumper Causes Blown Fuse
and ESF actuation (Section 08.2)
50-321, 366/96-12-01 VIO Failure to Include All Structures.
'
Systems, and Components in the Scope
of the Maintenance Rule as Required
by 10 CFR 50.65 (Section M8.t).
50-321, 366/96-12-02 VIO Failure to Establish Adequate
, Performance Criteria for S.C. Risk-
l-
'
Significant Functions (Section
M8.2).
,
50-321, 366/96-12-04 IFI Failure to Provide Adequate
Procedcre for Implementation of
'
Maintenance Rule Requirements
(Section M8.3). i
! 50-321. 366/96-12-05 IFI Followup on Licensee Actions to
Provide Performance Criteria for
Structures After Industry Resolution
of this Issue (Section M8.4).
50-321/98-01 LER Inoperable MCREC System Filter
Trains Result in Entry Into LCO
l 3.0.3 (Section E8.1). 4
l ]
, 50-321. 366/96-10-07 IFI Lack of Guidance for Inoperable
l
Instrumentation Used for Offsite
i Dose Calculations (Section P8.1).
50-366/97-02-06 IFI Review of Qualifications and
Training for Fire Watch Personnel
(Section F8.1).
50-321, 366/97-10-05 VIO Failure to Meet 10 CFR 20.1904
, Labeling Requirements for Containers
i of Radioactive Materials Temporarily
Stored in the Unit 1 Torus Pool
(Section R8.1).
i
Enclosure 2 l
1
i
-
, .
'
(
t'
'
34
50-321, 366/97-11-06 VIO Failure to Follow Procedures for
Radiation and Contamination Control
and Personnel Decontamination
, Activities (Section R8.2).
!
l 50-321, 366/97-11-07 VIO Failure to Follow Procedures for RWP
l
Implementation (Section R8.3).
l
!
I
i
1.
[
Enclosure 2
.