Letter Sequence RAI |
---|
|
|
MONTHYEARML20216G8911998-04-0808 April 1998 Forwards RAI Re Util 950817 & 1117 Responses to GL 92-01,rev 1,Suppl 1, Reactor Vessel Structural Integrity. Response Requested within 90 Days of Receipt of Ltr Project stage: RAI ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response Project stage: RAI 1998-04-08
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective ML20207G2611999-06-0707 June 1999 Informs That NRR Has Reorganized,Effective 990328.Forwards Organizational Chart IR 05000412/19980091999-05-26026 May 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-412/98-09 ML20195C4461999-05-21021 May 1999 Forwards Insp Repts 50-334/99-02 & 50-412/99-02 on 990321-0501.No Violations Were Identified.Licensee Conduct of Activities at Beaver Valley Power Station Characterized by Safe Conduct of Activities During Refueling Outage ML20206P1241999-05-14014 May 1999 Refers to Proposed Changes Submitted by Dl on 990316 to BVPS QA Program Described in BVPS-2 Ufsar,Chapter 17.2.Forwards RAI Re Proposed QA Program Changes ML20206N3161999-05-0606 May 1999 Responds to Ltr to NRC on Continued Events Re Transfer of Generation Assets Between Dl & Firstenergy.Info Will Be Considered as NRC Monitor Pending License Transfer Application of Bvps,Units 1 & 2 & Pnpp ML20206H7931999-04-30030 April 1999 Ack Receipt of 990426 Request for Enforcement Discretion & 990427 Withdrawal of Request for Enforcement Discretion. Resolution Documented.Enforcement Discretion Not Necessary ML20206B2751999-04-22022 April 1999 Forwards Insp Repts 50-334/99-01 & 50-412/99-01 on 990207- 0320.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206A8381999-04-20020 April 1999 Forwards Reactor Operator Initial Exam Rept 50-412/99-301 on 990322-25.All Three Reactor Operator Applicants Passed. Initial Written Exam Submittal Was Determined Not to Meet NRC Guidelines in Certain Instances ML20205R9071999-04-20020 April 1999 Forwards Second Request for Addl Info Re Response to GL 95-07, Pressure-Locking & Thermal-Binding of Safety-Related Power-Operated Gate Valves, for Beaver Valley Power Station,Units 1 & 2 ML20205Q8311999-04-14014 April 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-11 & 50-412/98-11 Issued on 990225.Actions Will Be Examined During Future Insp of Licensed Program ML20205L0341999-04-0909 April 1999 Forwards SER Accepting Util 971209 & 980729 Submittal of Second 10-year Interval ISI Program Plan & Associated Relief Requests for Beaver Valley Power Station,Unit 2.TER Also Encl ML20205P2431999-04-0909 April 1999 Discusses 990225 PPR & Forwards Plant Issues Matrix & Insp Plan.Ltr Provided to Minimize Resource Impact on Staff & to Allow for Scheduling Conflicts & Personnel Availability to Be Resolved in Advance of Inspector Arrival ML20205K0901999-04-0505 April 1999 Informs of Individual Exam Result on Initial Retake Exam Conducted on 990322-25 at Licensee Facility.Three Individuals Were Administered Exam & All Three Passed. Forwards Encl Re Exam.Without Encl ML20205R1791999-03-30030 March 1999 Responds to Issue Re Generic Implication of part-length Control Rod Drive Mechanism Housing Leak at Praire Island, Unit 2 & Beaver Valley Power Station,Units 1 & 2 ML20205C0301999-03-26026 March 1999 Informs That Util Responses to GL 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling & Containment Heat Removal Pumps Acceptable ML20204D7371999-03-16016 March 1999 Advises That RW Lindsey Authorized to Administer Initial Written Exams to Sh Cencic,Tf Lardin & Ta Pittas on 990322. Region I Operator Licensing Staff Will Administer Operating Tests ML20207E0201999-02-25025 February 1999 Forwards Insp Repts 50-334/98-11 & 50-412/98-11 on 981227- 990206 & Forwards Notice of Violations Re Uncontrolled Reduction of Main Condenser Vacuum ML20203D0691999-02-10010 February 1999 Forwards SE Accepting Approval of Proposed Revs to Plant QA Program Description in Chapter 17.2 of Updated Fsar,Per Util 981224 Submittal ML20206U3011999-02-0505 February 1999 Forwards Insp Repts 50-334/98-09 & 50-412/98-09 on 981116-1217 & Nov.Violation Identified Re Inadequate Design Control in Unit 2 Dc Voltage Drop Calculation ML20203A0811999-02-0404 February 1999 Forwards Request for Addl Info Re Review of Beaver Valley Power Station,Unit 1 License Amend to Allow one-time Extension of Steam Generator Insp Interval ML20199E6681999-01-14014 January 1999 Forwards RAI Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Plant,Units 1 & 2 ML20199F1961999-01-13013 January 1999 Forwards Insp Repts 50-334/98-10 & 50-412/98-10 on 981115-1226.No Violations Noted.Informs That Overall Fire Protection Program Functioning Well ML20199F5101998-12-29029 December 1998 Discusses Third 10-year Interval ISI Program Plan & Associated Relief Requests for BVPS-1 Submitted by Dlc on 970917 & 980618.Informs That NRC Has Adopted Ineel Recommendations in TER INEEL-98-00893.Forwards SE & TER ML20198K5911998-12-24024 December 1998 Forwards Emergency Response Data Sys Implementation Documents Which Include Data Point Library Updates for Fermi (Number 268),Peach Bottom (Number 269) & Beaver Valley (Number 270).Without Encls ML20198K8251998-12-21021 December 1998 Forwards SER Granting Licensee 980611,as Suppl 981015 Pump Relief Request PRR-5 for Third 10-year IST Interval for Beaver Valley Power Station,Unit 1 Pursuant 10CFR50.55(a)(f)(6)(i) ML20198B1301998-12-0909 December 1998 Advises of Planned Insp Effort Resulting from Beaver Valley Power Station mid-year Insp Resource Planning Meeting Held on 981110.Historical Listing of Plant Issues & Details of Insp Plan for Next 6 Months Encl ML20198A1301998-12-0909 December 1998 Forwards SE Re USI A-46 Program Implentation for Plant Unit 1.Staff Concludes Program Implementation Met Purpose & Intent of Criteria in Generic Implementation Procedure 2 & Suppl SER 2 for Resolution of USI A-46 ML20196J2761998-12-0404 December 1998 Forwards Corrected Pages 17 & 18 of NRC Integrated Insp Repts 50-334/98-06 & 50-412/98-06 for Exercise of Enforcement Discretion ML20196H3051998-12-0202 December 1998 Forwards Insp Repts 50-334/98-06 & 50-412/98-06 on 981004-1114.No Violations Noted.Conduct of Activities at Beaver Valley Power Station Facilities Characterized by Safe Plant Operations ML20196H2781998-12-0202 December 1998 Forwards Insp Repts 50-334/98-08 & 50-412/98-08 on 981026- 30.No Violations Noted.Plant Operations Witnessed by Team Were Conducted in Safe & Controlled Manner ML20196G9921998-12-0101 December 1998 Forwards Ltrs from Fk Koob, to JW Pack & CF Wynne Re Plant Deficiencies Assessed During 981006 Exercise Against Hancock County,Wv & Beaver County,Pa,Respectively ML20196D4371998-11-25025 November 1998 Discusses Concerns Re Announced Asset Transfer Between Firstenergy Corp & Duquesne Light Co ML20196A7101998-11-24024 November 1998 Forwards Notice of Withdrawal of Amend to License NPF-73. Proposed Change Would Have Extended on one-time Only Basis, Surveillance Interval for TSs 4.8.1.1.1.b & 4.8.1.2 Until First Entry Into Mode 4 Following Seventh Refueling Outage ML20195K3331998-11-18018 November 1998 Informs That Effective 981214,DS Collins Will Become Project Manager for Beaver Valley Power Station,Units 1 & 2 IR 05000334/19980041998-11-13013 November 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-04 & 50-412/98-04 Issued on 980915.C/As Will Be Examined During Future Insp of Licensed Program ML20195J2941998-11-12012 November 1998 Forwards Safety Evaluation Re First & Second 10-year Interval Inservice Insp Request for Relief ML20155K4041998-11-0505 November 1998 Forwards Insp Repts 50-334/98-07 & 50-412/98-07 on 981006- 07.No Violations Noted.Overall Performance of Emergency Response Organization Was Good 1999-09-08
[Table view] |
Text
g**p r. erg %
b 0" '
p *a UNITED STATES 6o--33y g- j R
NUCLEAR REGULATORY COMMISSION l o WASHINGTON, D.C. 30086 4001
% * * * * * +o April 8, 1998 Mr. J. E. Cross President-Generation Group Duquesne Light Company Post Office Bor 4 .
i Shippingport, PA 15077
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING REACTOR PRESSURE VESSEL INTEGRITY AT BEAVER VALLEY POWER STATION, UNIT NOS.1 AND 2 (TAC NOS. MA0525 AND MA0526)
Dear Cross:
Generic Letter (GL) 92-01, Revision 1, Supplement 1 (GL 92-01, Rev.1, Supp.1), " Reactor Vessel Structural Integrity," was issued in May 1995. This GL requested licensees to perform a review of their reactor pressure vessel (RPV) structural integrity assessments in order to identify, collect, and report any new data pertinent to the analysis of the structural integrity of their RPVs and to assess the impact of those data en their RPV integrity analyses relative to the requirements of Section 50.60 of Title 10 of the Code of Federal Reaulations (10 CFR 50.60),10 CFR 50.61, Appendices G and H to 10 CFR Part 50 (which encompass pressurized thermal shock (PTS) and upper shelf energy (USE) evaluations), and any potential impact on low temperature overpressure (LTOP) limits or pressure-temperature (PT) limits.
After reviewing your responses of August 17 and November 17,1995, the NRC issued you a letter dated August 2,1996. In this letter we acknowledged receipt of your responses, noted that additional RPV information may become available as a result of Owners Group efforts and requested that you provide us with the results of the Owners Groups' programs relative to your plant. We further indicated that a plant-specific TAC Number may be opened to review this
( material. In July 1997, the Combustion Engineering Owners Group (CEOG) provided a report with additional RPV weld chemistry data for RPVs fabricated by CE. This additional RPV weld - 4 chemistry data may affect previous RPV integrity enslyses supplied by licensees with CE fabricated RPVs. As a follow-up to the letter and the CEOG report, and in order to provide a complete response to items 2,3 and 4 of the GL, the NRC requests that you provide a response to the enclosed RAI within 90 days of receipt of this letter. If a question does not apply to your situation, olease indicate this in your RAI response along with your technical basis and, per GL 92-01, Rev.1, Supp.1, provide a certification that previously submitted evaluations remain valid.
The information provided will be used in updating the Reactor Vessel Integrity Database (RVID).
Also, please note that RPV integrity analyses utilizing newly identified data could result in the need for license amendments in order to maintain compliance with 10 CFR 50.60,10 CFR 50.61 (pressurized thermal shock, PTS), and Appendices G and H to 10 CFR Part 50, and to address any potential impact on low temperature overpressure (LTOP) limits or pressure-temperature (PT) limits. If additionallicense amendments or assessments are necessary, the enclosed requests that you provide a schedule for such submittals.
N\
I l 4O l p 1 9804200520 980408 '~
PDR ADOCK 05000334 P PDR *fd @W L @. 4 : s uI* $9EID (%P)U
.a J. Cross If you should have any questions regarding this request, please contact me at (301) 415-1409.
Sincerely,
/s/
Donald S. Brinkman, Senior Project Manager Project Directorate 1-2 Division of Reactor Projects - 1/II Office of Nuclear Reactor Regulation Docket Nos. 50-334/50-412 Encisaure: RAI cc w/ encl: See next page 1
- i l
i l
l 1
l DISTRIBUTION Docket File MO'Brien PUBLIC OGC -
PDI-2 Reading ACRS JZwolinski ESullivan RCapra AHiser DBrinkman MEvans, RGN-l l OFFICE PDI-2/PM 4 s PDf-2/CVN PDI-2'D E NAME DBrinkman e RCapra W DATE // /7 /98 M/N/98 4 /~1 /98 OFFICIAL RECORD COPY /
DOCUMENT NAME: BV0525.RAI
J. Cross If you should have any questions regarding this request, please contact me at (301) 415-1409.
Sincerely,
& k. b Donald S. Brinkman, Senior Project Manager Project Directorate 1-2 Division of Reactor Projects - 1/il ~
i Office of Nuclear Reactor Regulation Docket Nos. 50-334/50-412
Enclosure:
RAI cc w/ encl: See next page
J. E. Cross Beaver Valley Power Station, Units 1 & '2 Duquesne Light Company cc:
Jay E. Silberg, Esquire Bureau of Radiation Protection Shaw, Pittman, Potts & Trowbridge Pennsylvania Department of 2300 N Street, NW. Environmental Resources Washington, DC 20037
- ATTN: Michael P. Murphy Post Office Box 2063 Director-Safety and Licensing Harrisburg, PA 17120 Department (BV-A)
Duquesne Light Company _ - . .
Mayor of the Borrough of -
Beaver Valley Power Station Shippingport PO Box 4 Post Office Box 3 Shippingport, PA 15077 Shippingport, PA 15077 Commissioner Roy M. Smim Regional Administrator, Region i West Virginia Department of Labor U.S. Nuclear Regulatory Commission Building 3, Room 319 475 Allendale Road Capitol Complex King of Prussia, PA 19406 Charleston, WVA 25305 Resident inspector Director, Utilities Department U.S. Nuclear Regulatory Commission Public Utilities Commission Post Office Box 298 180 East Broad Street Shippingport, PA 15077 Columbus, OH 43266-0573 Director, Pennsylvania Emergency Duquesne Light Company !
Management Agency Beaver Valley Power Station {
Post Office Box 3321 PO Box 4 l Harrisburg, PA 17105-3321 Shippingport, PA 15077 ,
ATTN: S. C. Jain, Vice President Ohio EPA-DERR Nuclear Services (BV-A) ,
ATTN: Zack A. Clayton !
Post Office Box 1049 Columbus, OH 432GG-Ou9 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 Duquesne Light Company Beaver Valley Power Station PO Box 4 Shippingport, PA 15077 ATTN: R. L. Grand, r + ion Vice President, Nuclear On~'"nns Group and Plant Manager (BV-SOSB-7)
REQUEST FOR ADDITIONAL INFORMATION (RAli REGARDING REACTOR PRESSURE VESSEL INTEGRITY BEAVER VALLEY POWER STATION. UNIT NOS.1 AND 2 DOCKET NOS. 50-334 AND 50-412 1
Section 1.0: Assessment of Best-Estimate Chemistry The staff recently received additionalinformation that may affect the determination of the best- ,
estimate chemistry composition for your RPV welds or your surveillance weld material. This l information was provided to the NRC by the Combustion Engineering Owners' Group in report CE NPSD-1039, Revision 02, "Best Estimate Copper and Nickel Values in CE Fabricated -
Reactor Vessel Welds," dated June 1997.
Based on this information, in accordance with the provisions of Generic Letter 92-01, Revision 1, Supplement 1, the NRC requests the following:
- 1. An evaluation of the information in the reference above and an assessment of its applicability to the determination of the best-estimate chemistry for all of your RPV beltline welds. Based upon this reevaluation, supply the information riecessary to completely fill out the data requested in Table 1 for each RPV beltline weld material. Also provide a discussion for the copper and nickel values chosen for each we!d wire heat noting what heat-specific data were included and excluded from the analysis and the analysis method chosen for determining the best-estimate. If the limiting material fo pur vessel's PTS /PT limits evaluation is not a weld, include the information requested ir, hble 1 (see Attachment 1) for the limiting material also.
Furthermore, you should consider the information provided in Section 2.0 of this RAI on the use of surveillance data when responding.
With respect to your response to this question, the staff notes that some issues regarding the evaluation of the data were discussed in a public meeting between the staff, Nuclear Energy Institute (NEI), and industry representatives on November 12,1997. A summary of this meeting is documented in a meeting summary dated November 19,1997, " Meeting Summary for '
November 12,1997 Meeting with Owners Group Representatives and NEl Regarding Review of Responses to Generic Letter 92-01, Revision 1, Supplement 1 Responses" (Reference 1). The information in Reference 1 may be useful in helping you to prepare your response.
In addition to the issues discussed in the referenced meeting, you should also consider what method should be used for grouping sets of chemistry data (in particular, those from weld qualification tests) as being from "one weld" or from multiple welds. This is an important consideration when a mean-of-the-means or coil-weighted average approach is determined to be the appropriate method for determining the best-estimate chemistry. If a weld (or welds) were fabricated as weld qualification specimens by the same manufacturer, within a short time span, using similar welding input parameters, and using the same coil (or coiis in the case of tandem arc welds) of weld consumables, it may be appropriate to consider all chemistry samples from that weld (or welds) as samples from "one weld" for the purposes of best-estimate chemistry determination. If information is not available to confirm the aforementioned details, but sufficient evidence exists to reasonably assume the details are the same, the best-estimate chemistry should be evaluated both by assuming the data came from "one weld" and by assuming that the data came from an appropriate number of " multiple welds". A justification should then be provided for which assumption was chosen when the best-estimate chemistry was determined.
ENCLOSURE
4 2
Section 2.0: Evaluation and Use of Surveillance Data The chemical composition report referenced in Section 1.0 includes updated chenistry estimates for heats of weld metal. These reports not only provide a suggest.ed best estimate value but also include the source data used in estimating the chemical composition of the heat of material. This permits the determination of the best estimate chemical composition for the various sources of data including surveillance welds. Since the evaluation of surveillance data rely on both the best estimate chemical composition of the RPV weld and the surveillance weld. the information in these reports may result in the need to revise previous evaluations of RPV integrity (including LTOP setpoints and PT limits) per the requirements of 10 CFR 50.60,10 CFR 50.61, and ~ ~ ~ ~~ ~ '
Appendices G and H to 10 CFR Part 50.
Based on this information and consistent with the provisions of Generic Letter 92-01, Revision 1, Supplement 1, the NRC requests the following:
- 2. that (1) the information listed in Table 2, Table 3 (see Attachment 2), and the chemistry factor from the surveillance data be provided for each heat of material for which surveillance weld data are available add a revision in the RPV integrity analyses (i.e., current licensing basis) is needed or (2) a certification that previously submitted evaluations remain valid. Separate tables should be used for each heat of material addressed. If the limiting material for your vessel's PTS /PT limits evaluation is not a weld, include the information requested in the tables for the limiting material (if surveillance data are available for this material).
The information discussed in Section 1.0 of this RAI regarding the chemistry reports should be considered in this response along with the following questions and comments.
All surveillance program results for the heats of material in an RPV should be considered in evaluating its integrity regcrdless of source per 10 CFR 50.61 (" Surveillance program results means any data that demonstrates the embrittlement trends for the limiting beltline material, including but not limited to data from test reactors or from surveillance programs at other plants with or without surveillance program integrated per 10 CFR 50, Appendix H."). If any of the data provided in Table 2 is not used in the calculation of the embrittlement trend for a particular RPV weld, the technical basis for not including /using the data should be provided. '
When assessing credibility of surveillance data that come from more than one source, adjustments to the surveillance data may be needed to account for differences in the chemical composition and irradiation environment of the different sources consistent with the requirements i in 10 CFR 50.61. A method for accounting for there differences is discussed in Reference 1.
Based on the information provided in Table 2, the credibility of the surveillance data can be evaluated. The results of these analyses including the slope of the best fit line through the surveillance data can be provided in a format similar to that of Table 3. If the method for adjusting and/or norma!! zing the surveillance data when assessing credibility differs from the methods documented in Reference 1, provide the technical basis for the adjustment and/or the normalization procedure. If the chemical composition of the surveillance weld is not determined in accordance with Reference 1 (i.e., the mean of all chemistry analyser perfomied on the surveillance weld), provide the technical basis for the estimate.
1 When determining the chemistry factor for an RPV weld fro.. suweillance data, adjustments to the surveillance data may be norded to account for diffs e m in the chemical composition and j irradiation environment between the surveillance specina... 1 the vessel being assessed consistent with the requirements in 10 CFR 50.61. A method to account for these differences is provided in Reference 1.
I in addition,10 CFR 50.61(c)(2) specifies that licensees shall consider plant-specific information (e.g., operating temperature and surveillance data) to voirify that the RTer for each vessel beltline material is a bounding value. Regulatory Guide 1.99, Revision 2, desuibes two methods for determining the amount of margin and the chemistry factor used in determining rte 1 Position 1.1 describes the use of the Generic Tables in the Regulatory Guide. Position 2.1 describes the use of credible surveillance data, if the surveillance data are credible, the o, may be reduced in half to calculate the margin term and the chemistry factor is to be determined from the best-fit line of the surveillance data, if the evaluation of the surveillance data indicates that the surveillance data set is not credible and the measured values of ARTer are less than the projected mean from the Tables plus the generic 203, the chemistry fccior may be calculated j using either Position 1.1 or Position 2.1; however, the full margin term must be applied. The j method chosen must bound all the surveillance data to be in compliance with 10 CFR l
50.61(c)(2).
Based on the information provided in Table 2 along with the best estimate chemical composition i of the heat of material and the irradiation temperature of the plant whose vesselis being !
assessed, the chemistry factor of the RPV weld can be determined. Note that the adjusted ,
ARTwy for a particular surveillance data point may be one value when determining credibility and I another value when determining the chemistry factor as a result of the different normalization i procedures, if the method for adjusting and/or normalizing the surveillance data when
. determining the chemistry factor diffut from the methods documented in Reference 1, provide !
the technical basis for the adjustment and/or the normalization procedure. i in a meeting between the staff and industry representatives ut the NRC on February 12,1998, an industry representative requested a clarification as to when th:e ratio orocedure should be used to evaluate surveillance data. The ratio procedure is described in the PTS rule and RG 1.99, Revision 2. The ratio procedure is used to adjust the measured value of ARTer to account for differences in the chemical composition between the surveillance weld and the vessel beltline weld. The PTS rule and RG 1.99, Revision 2, indicate that when there is clear evidence that the copper and nickel content of the surveillance weld differs from the vessel weld, i.e. differs from the average for the weld wire heat number associated with the vessel weld and the surveillance weld, the ratio procedure must be used.
Section 3.0: PTS /PT Limit Evaluation
- 3. If the limiting material for your plant changes or if the adjusted reference temperature for the limiting materialincreases as a result of the above evaluations, provide the revised RTris value for the limiting material in accordance with 10 CFR 50.61, in addition, if the adjusted RTm7 value increased, provide a schedule for revising the PT and LTOP limits. The schedule should ensure that compliance with 10 CFR Part 50, Appendix G, is ma'ntained.
o 1
. 4 Reference
- 1. Memorandum from Keith R. Wichman, NRC, to Edmund J. Sullivan, NRC, " Meeting Summary for November 12,1997 Meeting with Owners Group Representatives and NEl Regarding Review of Responses to Generic Letter 92-01, Revision 1, Supplement 1 Responses", dated November 19,1997.
Attachments:
- 1. Table 1
- 2. Tables 2,3 .
l i
, -i ,iigi . ,
l 1
t r n o sL e T PTO h m
RTE c A Rta t t
a A
n ig r
a M
g o
\
s ,
la i
r o _
t e
a )
M g l a TM ) .
i i
t n i iT t
n m mT 1
(
i m i RTR 0 1
L (
r n
/
o i o t t
d g c a n f on e e a in S H 1
d l
e domiM i n e r
E hrF i L W t et eC d e W B V MeD t s d l
A P e u
e T R q W .
n ) e h o dl yF r s c d eatrC nis( a a e r i E t
s gemr l a r e
i sae o t t
i r a f o
u q AsMhc Ca t et a ad d
e e F r mec U s
n n
o gn o De) n a i s
i t
a I c8 it la t a s n0 i l D u m
r Le1 Ou imie l v c s
o r d E R (x eu i f n D I
n hs t
a o omr f d e o
- t l nf h t ae or t
smk e eic it o M i
a BtsN cse s E i f l is it b y r
n et a l a
e er d m
n r
u t a e t i A
smp p a o l
. t c ei i f r
r e a BtsC o h t a
f t ed t e
u E ae f o H n
a min n e M e r e m r o i r
he is yl it e VWiW t t r e s W is P t od u d lcs Rlda e c l e
ae ))
WeH is FV 1 2
(( D W ll11 lllf
Table 2: Heat xxxx Capsule 10 Cu Ni irradiation Fluence Measured Data Used in (including Ternperature ARTmi (x10n/cm2 Assessing Vessel source) (*F) ) (F) (Y or N)
Table 3: Heat xxxx l
Capsule ID Cu Ni irradiation Fluence Measured Adjusted Prodcted 1 (Adjusted .
. (including Temperature Factor ARTet ARTm7 ART , Prodded) ARTmT source) CF) (*F) (*F) (*F) (*F) l I l
l i
I Attachment 2 l
i
-