pas.1 a 2 1
O
~
EVALUATION RESEARCH CORPORATION L
CONANCHE PEAK RESPONSE TEAM PROJECT PROCEDURE FOR QA/QC ISSUE-SPECIFIC ACTION PLANS UNCONTROLLED COPY CHANGE NOTICE: 002 PROCEDURE NO: CPP-012 REVISION: 2 EFFECTIVE DATE: 11/10/86 0
QA/QC INTERFACE WITH CONSTRUCTOR AND TUGC0 The CPP identified above is hereby changed as shown on the attached page of this notice.
l
~
PREPARED BY:
4W DATE:
a 2, 16 APPROVED BY:.JD,d b M
DATE: /// '/ / P/,
, ON-SITE QA REPRESEN"GWIVE
/ /
APPROVED BY:
[
/11 DATE:
H!9!8C lO
$gaigggg 738 3
A
Pega 2 of 2 l O
\\s_/
1.
Sec. 5.3.1 add the following:
If the preparer and approver decide that another request is required the preparer may prepare a QA/QC-RT- --- memorandum describing the inadequacy of the initial TIR response and what additional information is required.
The memorandum will be clearly identified as a continuation of the original TIR and will be processed through the Records Administrator in the same manner as TIRs. The memorandum will be approved in the same manner as a TIR prior to issuance.
2.
Sec. 5.3.2 change the second para. to read:
The Records Administrator maintains the Information Request file (marked XXX- [ applicable ISAP No.}) and denotes applicable requests " Superseded by TIR-XXX" or continued by memorandum QA/QC-RT-XXI, dated XX-XI-XX.
The Records Administrator will file a copy of the memorandum with the original TIR and process as if the memorandum were a TIR.
()
3.
Sec. 5.3.2 change 1st, 3rd and 4th para. to read:
Technical Information Request / Memorandum (TIR)
O O
s