Notice of Violation from Insp on 861117-21
ML20205B754
Person / Time
Site: Waterford Entergy icon.png
Issue date: 03/17/1987
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20205B729 List:
References
50-382-86-28, NUDOCS 8703300037
Download: ML20205B754 (1)


Text

,

APPENDIX A NOTICE OF VIOLATION Louisiana Power & Light Company Docket: 50-382 Waterford Steam Electric Station, Unit 3 License: NPF-38 During an NRC inspection conducted on November 21,1986, a violation of NRC requirements was identified. This violation involved the failure to follow procedures for control of temporary alterations.

In accordance with the

" General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part2,AppendixC(1986),theviolationislistedbelow:

Failure to Follow Procedures for Control of Temporary Modifications 10 CFR Part 50, Appendix B, Criterion V, requires that activities affecting quality shall be accomplished in accordance with approved procedures. ANSI N18.7-1976, to which the licensee is comitted, Section 5.2.2, requires that procedures shall be followed. Licensee Procedure UNT-5-004, Revision 3, " Administrative Procedure Temporary Alteration Control," identifies specific requirements for the control and restoration of temporary modifications. This procedure specifies that procedures requiring temporary modifications shall either appropriately reference UNT-5-004, or contain the specified controls for temporary modifications.

Contrary to the above, the NRC inspector on November 19, 1986, identified that licensee Procedure ME-7-002, Revision 5, " Maintenance Procedure Molded-Case Circuit Breakers and Thermal Relays," did not contain required controls for temporary removal and replacement of current limiting fuses during performance testing of the circuit breakers, nor reference UNT-5-004.

This is a Severity Level IV violation.

(SupplementI.D.)(50-382/8628-01)

Pursuant to the provisions of 10 CFR 2.201, Louisiana Power & Light Company is hereby required to submit to this office within 30 days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including for each violation:

(1) the reason for the violations if admitted, the corrective steps which have been taken and the results achieved, the corrective steps which will be taken to avoid further violations, and the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time.

Dated at Arlington, Texas this 17th day of March 1987 8703300037 870317 gDR ADOCK 05000382 PDR