ML20107C416

From kanterella
Jump to navigation Jump to search
Rev 29 to Procedure QI-QP-11.4-5, Insp of Steel Substrate Primer Repair & Seal & Finish Coat Application & Repair
ML20107C416
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/04/1984
From: Dunham F
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
Shared Package
ML20106F959 List:
References
QI-QP-11.4-5, NUDOCS 8502210307
Download: ML20107C416 (32)


Text

r a' ..

TEXAS UT!UTIES GENERATING Co. g REVIS!CN FAGE CPSES ,

29 1 f 32 lQI-QP-11.4,5 MAY 0 41984 INSPECTION OF STEEL PREPARED BY: eg gt 64/- 5[?/

j CAic, SUBSTRATE PRIMER l REPAIR AND SEAL AND APPROVED SY: _. f S- d-F/ i FINISH C0AT APPLICATION g a CAIE '

AND REPAIR / ,f APPROVED S :

N '

~ jff7

, OATE

1.0 REFERENCES

l 1-A QI-QP-11.4-1, " Inspection of Steel Substrate S'irfac e Preparation and Primer Application and Repair" 1-B CCP-30, "Ccating Steel Substrates Inside Reactor Buildings ' j

! and Radiat'.n Areas" 1-C CCP-30A, " Coating Steel Substrates Inside Reactor Buildings '

and Radiation Areas" ,

i.

1-0 CP-QP-18.0, " Inspection Reports" f i.

1-E QI-QP-11.4-22 "QC Verification of Protective Coatings

, Unique Identification Number Verification" s

1-F CP-QP-15.0, " Tagging Systea" I '

, 1-G CP-QP-16.0, "Nonconfomances" ' '

1-H GIbbs & Hill Specification 2323-AS-31, " Protective Coatings",

latest revision '

I

. 2.0 GENERAL [ .

i 2.1 PURPOSE AND SCOPE i

  1. 0#Q The purpose of this instruction is to outline methods utilized by Quality Control personnel in inspection of primer repair and seal and finish coat. application and ,

repair in the safety ,relsted areas of Unit 2 and the paint i shop.

j

/ 3.0

, INSTRUCTION l

Visual inspection of surfaces as addressed by this  !

g instruction shall 'ce made at approximately an ams length'or i B502210307 850213 PDR S ADOCK 05000445 PDR

%,, TUGCC CA

i i .

TEXAS UTILmES GENERATING CO.

, CPSES QI-QP-11.4-5 29 MM O 1 lc84 2 of 32 I

I 30" in distance from the surface being inspected where possible.The area of inspection shall be adequately lighted l during the inspection activity. Adequate li i as the minimum light produced by a two (2)ghting D-cellisbattery defined I flashlight. -

y l Visual aids fabricated on site and approved by Quali ty Assurance and Engineering may be used by Inspectors as an aid in the perfonnance of their inspections. For definitions, refer to Attachment 6.

If a conflict arises between the requi rements of this procedure and the requirements of the site specification, the requirements of the site specification shall prevail, Reference 1-H.

3.1 INSPECTION OF PRIMER i

! 3.1.1 Primer Inspections Prior to Application of Seal or Finish Coat a) QC shall verify that construction has identified each piece with a unique nunber in accordance with References 1-A, 1-B and 1-C. The QC Inspector shall maintain a Protective Coating Unique Identification Nunber Log for all protective coatings application on all steel designated for use in the Reactor Building. Subsequent subdivision of coating steel in'the field or shop shall

, be witnessed by QC in accordance with Reference 1-E.

NOTE: .

y A. Unique nunber may be assigned to a lot of material to be prime coated at the same time.

For example, six pieces steel to be coated -

at same time may all have same unique number.

B. Liner plate is excluded fran QP c nunbers.

Equipment which is identified with pennanent plant identification number need not be identified wi th a Protecti"1, Coatings unique identification number.

b) For all prime coated itens which do not have adequate l I

documentation, the Inspector shall perfonn an Adhesion test. A calibrated Elcometer 106 Adhesion Tester shall .

be used to verify that the minim = acceptable tensile of x-f adhesion to the steel substrate has been attained. Each .

test shall consist of three individual' dollies tested. .

Adhesion test shall be perfonned per QI-QF-11.4-23, Sec.

3.2. ,

l Penn fees t . TUGCC CA

INSTRUCTICN ISSUE NUMBER REVISION PAGE TEXAS UTILITIES

  • GENERATING CO. DATE OPSES QI-QP-11.4-5 29 MAY 01 1924 3 of 32 l

Criteria: The minimum acceptable strength per dolly shall be 250 psi. If any one of the three dollies should test below the minimum acceptable strength, the condition shall be recorded on a nonconfomance repo rt in accordance with Sec. 3.11.

c) Verify the primer has cured sufficiently for the finish coating (as determined by use of the coin test for D-6 and CZ-11). Cure to finish coat of Carboline 191 shall i

be the same as time to recoat for Phenoline 305, stated in Section 3.6.1.

l d) Perfom a visual inspection of the primed surf ace in j accordance with the following:  ;

1. Runs / sags - Runs / sags 7.0 mils for CZ-11, 5.5 mils for D-6, and 7.0 mils for Carboline 191 or less thick (DFT) which show no evidence of rruderacking or loss of adhesion are acceptable. Refer to '

Section 3.2.1 for repair of unacceptable runs / sags.

2. Dry Spray - Must be removed before overcoating.
3. Contamination - Unacceptable, Iij Oil and crease - unacceptable
4. Skips / damaged areas / gross discontinuities such as holidays or voids - unacceptable.
5. Orange peel - Moderate amounts are acceptable.

Other than moderate amounts; repair per Sec. 3.2.3. l

6. Bubbling - unacceptable (does not apply to D-6 or CZ-11).

e) The inspector shall perfom a DFT inspection of the cured primer film. A calibrated 0-25 Elcometer Inspector DFT gage Model III/IE, or equivalent, shall be used. Separate spot measurements (See Note 1) spaced evenly over the structure or item (See Note 2) '

shall be taken. Since the magnetic gage is sensitive  !

i

' to geometric discontinuities in the steel, measurements less than 1 inch from the edge or a hole should be avoided where possible. (See Note 3) l

% m, , TUGCC CA

O i ,

INSTRUCTION I NUMBER REVISICN PAGE TEXAS UTIUTIES GENERATING CO.

,,, CPSES QI-QP-11.4-5 29

, MAY 0 4 1984 4 of 32 Dry Film Thickness shall be as follows:

Min.(mils) Max.(mils)

Carboline 191 spot test 1.6 7.0 CZ-11 spot test 1.5 7.0 06 spot test 1.5 5.5 D6 average DFT 2.0 5.0 CZ-11 average DFT 2.0 6.0 Carboline 191 average DFT 2.0 6.0 NOTE 1: A spot measurement is' a series of three  :

gage readings in the same general area. The probe should be moved a short distance for l i each gage reading. Discard any unusually high ,

l or icw gage reading that cannot be repeated consistently. Take an average of these three gage readings as one spot measurement.

In the event that any spot is found to be i,

outside of the acceptable thickness range, three addi tional spo ts shall be taken at '

approximately 6 inches from the failing spot and spaced radially at approximately 120 degree intervals to detemine the extent of the unacceptable area. Dimensions and locations of una:ceptable areas and results of additional testin; shall be documented on the IR.

Unacceptable areas shall be repaired per Sec.

3.2.3 or 3.2.4 as applicable.

NOTE 2: Five spot tests shall be taken on each item for every 100 square feet of coated surface.

For areas or items less than 100 square feet, -

the following shall apply:

Area Sq. Ft. No. Spots 100-80 5 80-50 4 50-10 3 10-3 3-0 1 NOTE 3: Items with appreciable surface curvature and other geometrical discontinuities, such as handrails, gra tings, s tai rs, sway struts,

, checkerplate, etc. , shall be exempt fran dry Perun see. t TUGCO CA

t I I I INSTRUCTION ISSUE NUMSER M SION PAGE TEXAS UTILITIES GENERATING CO. DATE CPSES QI-QP-11.4-5 29 l MAY 0 419e4 t 5 of 32 l

l film thickness :neasu rement. Fc e piping, struts, spring canisters, etc., appreciable curvature will be, considered as less than 4" in diameter.

3.2 PRIMER REPAIRS 3.2.1 Sans and Runs Sags and runs over 7.0 mils DFT for CZ-11, over 5.5 mils for D-6, and over 7.0 mils DFT for Carboline 191 may be abraded by sanding or aluminun sc reening . Runs / sags which are within the acceptable dry film thickness range and show no evidence of nudcracking or loss of adhesion are acceptable, i If surface is unacceptable, remove unsatisfactory coatings.

Refer to Se:. 3.2 as applicable.

3.2.2 Primer Touch-uo Repair (primer Damaaed to Steel Surface)

The coating inspector shall conduct the following inspections to document primer touch-up repair operations whan the damage is to the steel su rface and spo t sandblasting or power tool abrading is required for surface i preparation. I t

a) Ambient Concitions The inspector shall detennine air temperature, surface temperature, relative humidity and dew-point of substrate structures. A calibrated non-mercury filled dry bulb thermometer or a calibrated tempera ture recorder (Bristol 4069TH or equivalent) shall be used for air temperature detennination. A calibrated non-mercury wet bulb thennometer or a calibrated humidity recorder (Bristol 4069TH or equivalent) shall be used to detennine relative humidity. The dew point shall be detennined by the difference in dry and wet bulb tenperatures using the U.S. Department .of Conmerce l

Weather Bureau Psychrometric Tables, WB No. 235. When dry bulb readings are greater than 100*F, the dew point and relative humidity should be determined using the l 100*F reading. If the dry bulb thennameter exceeds

! 100*F, the instrument shall be returned to the L

calibration lab for recalibration. The su rface i

temperature shall be determined by placing a calibrated surface temperature thennometer (0mega-Amprobe Fastenp,

. 7 range of 10*-250 *F) in contact with the substrate t

l Penn me , TUGCC CA

7 TEXAS UTILITIES GENERATING CO.

" ^

CPSES QI-QP-11.4-5 29 6 of 32 R0 4 M su rface. The thermometer probe shall remain in contact with the surface until the temperature reading stabilizes.

Final surface preparation shall not begin unless the temperature of the surface is a minimum of 5* above l the dew point. i l

Nonnal conditions of ambient and surface temperature I for application of primer shall be as follows:

Ambient Temo. (*F) Surface Temo. (*F)

Dimetcote 6 40-120 40-130 l Carbozinc 11 40-95 40-110 Carboline 191 50-120 50-120 Inonganic zinc primers may be applied within an ambient range of 0*F to 130*F and surface temperature range of 0*F to 200*F.

Coating material (if thinned) shall be ' thinned in accordance with Reference 1-B or 1-C.

For inonganic zines humidity values may vary fran 0 to 95%; however, primer shall not be applied to a wet or I

damp surface. For Cartoline 191 humidity value may vary from 0 to 85%.

l The surface temperature shall be a minimum of 5* above j the dew point.

-b) Verify abrasive acceptablility (if used) by obtaining a sample of the abrasive to be used. The abrasive shall be verified to be dry by feel with no grease, oil or deleterious . material s. Verify that proper blast l

abrasive is used.

c) Verify acceptability of blast cleaning equipment (if used) prior to use by: )

1. Verifying that water separators are installed in l .

the air supply system and that separators have been drained of acetnulated water and drains lef t l partially open.

l

!  %, Tuoco c4

T INSTRUCTION '

DD ISSUE TEXAS UTILITIES GENERATING CO.

N SER DATE NE CPSES 01 -0 P-11.4-5 29 04m i 7 of 32 j i

2. Air supply shall be checked at the nozzle prior to use by exposing a white cloth to the blast of l air (no sand) for approximately 30 seconds. The cloth shall be examined for evidence of contamina-tion (oil, water, foreign na tter, etc.). No evidence of contamination is acceptable.

d) Verify that the blasted or power tooled surface has been high pressure air blowdown and/or solvent wiped to the extent required for final surface inspection.

The adjacent areas shall be cleaned to the extent necessary to avoid contamination during subsequent coating applications.

e) Veri fy acceptability of the bla s t cleaned or power tooled surfaces by performing the following inspections:

. 1. Absence of Foreign Matter -- A visual inspection shall be perfomed to detemine that all oil and grease, dirt, millscale, rust, corrosion products, axides, paint or other foreign matter have been completely removed from the surface except fo r light shadows, very slight streaks or slight discolorations caused by rust stains, mill scale, oxides, or slignt, tight residues of paint or coating that may remain. At least 95 percent of each square inch of surface area shall be free of all residues, and the remainder shall be limited to light discolorations as mentioned above.

NOTE: For power tooled surfaces, in addition to the 5 percent of tight residue of paint or coating which is penni ssible , shadows or tightly adhering residues of primer may remain (without limit) in the profile of the previously prepared substrate. However, areas with residues of Carboline 191 primer shall be recoated with Carboline 191 primer. Areas with residues of inorganic zinc may be coated wi th either inorganic zinc or Carboline 191 primer.

2. Shan Projections --

An inspection for sharp projections that were not rounded during blast cleaning or power tooling shall be pe rfo med .

Sharp projections are unacceptable and shall be ground to rounded contour.

g, TUGCC CA

t 1 INSTRUCTION l REVISICN ISSUE TEXAS UTILITIES GENERATING CO. NUMBER DATE PAGE CPSES ,

~

QI-QP-11.4-5 29 f,83v 0 : 1Sc4 8 of 32 Weld splatter on structural steel shall be renoved by either grinding or sand blasting. However, if the weld splatter should renain after the above operation, the weld splatter will be acceptable.

I

3. Anchor Pattern Depth -- The anchor pattern depth of the blasted surface shall be inspected at random locations using a Keane-Tator Su rfs.ce Profile Comparator (model 373) or approved equal.

The anchor pattern depth for all surfaces shall be a minimum of 1.0 mils.

Surfaces that have been powe r tooled wi th "3M Clean-N-Strip", 60 grit and coarser " flapper wheels", provide acceptable surface profile, when precerly used over previously blasted anc coated surfaces.

  • For power tooled steel surfaces, the 1 mil minimum profile shall be verified by visual comparison to a standard of known profile or other approved method.

f) Verify applicator qualifications per Sec. 3.3.1.

g) Verify air supply acceptability per Sec. 3.3.4.

h) 1. Coating Materials Identification An inspector shall inspect the coating material containers prior to mixing contents for product identification and verify that all materials are correct for coating application.

Approv,ed materials are:

CZ-11 Carbo Zinc base li Carbo Zinc filler Carboline #21 or #33 Thinner Dime tcote-6 Dimetcote 6 base l Diratcote filler Amercoat #65 or #101 thinner

%%, TUGeo CA

INSTRUCT 1CN ISSUE NUMBER 1 REVISlCN AGE TEXAS UTILITIES GENERATING CO. I DATE CPSES QI-QP-11.4-5 29

, MAY 0 4 1984, 9 f 32 I

l Carboline 191 Carboline 191 primer Carboline 191 catalyst Carboline #15 thinner He shall also verify that each component container is identified by batch number and that the shelf life has not expired. Carbo Zinc 11 base and Carboline 191 has a shelf life of 12 months.

Carbo' Zinc filler and Dimetcote 6 base and filler have a shelf life of 24 months.

2. Mixing Operations l An inspector shall witness each mixing / thinning operation. The inspector shall verify that mixing i operations are pe rfo rmed in accordance wi th Reference 1-A and 1-B.
3. Thinning Operation An inspector shall verify that primer thinning complies with thinning requirements established in References 1-A and 1-B.
4. When coating materials are mixed / thinned in locations other than the fi el d , the ins pector verifying the mixing operation shall fill out the I Paint Mixing Slip, Attachment 5. The inspector perfoming the pre-application inspection shall record the information from the Paint Mixing Slip on the Inspection Report, Attachment 3. The Paint Mixing Slip need not be retained.
1) Verify that primer is applied and pot life is not exceeded in accordance with Attachment 7.

NOTE 1: (If applicable Coating interface - at coating interface for finish and/or primer coat, the i existing coating shall be " feathered back" a sufficient distance to en3ure a scooth final coating system. When inspecting coating interface the interface of the coating or systems shall be a maximum of .lis inch in width. Within the interface area, overlapping of any- materials or systems is acceptable.

When inorganic zinc is applied at an interface, the cured inorganic zinc shall be screened or abraded prior to application of next coat, p g, TUGCO CA t .

INSTRUCTICN issue TEXAS UTILITIES GENERATING CO.

8 DATE N CPSES nt no 11.4-5 29 MAY0 4 1C24 l 10 of 32  !

NOTE 2: Monitoring of Primer Application During application operations of D-6 and CZ-11, the QC Inspector shall monitor that the pressure pot is continuously agitated.

CZ-11 and D-6 shall not be brush applied to areas larger than 1 sq. ft.

During application of Carboline 191, the inspector will tronitor to assure that no fisheyes appear in the applied coating. If (

de tected , the inspector shall info na the 1

' paint forerran of their presence and that they l' should be removed while coating is still wet, su rface cleaned with solvent and coating reapplied .

The inspector shall tronitor pot li fe in accordance with Attachment 7.

Verify that hose length is less than 75 feet.

3.2.3 Primer Touch-uo Recair (Primer Damace Does Not Extend to t Steel Surf ace The coating inspector shall conduct the following inspections I for prirar touch-up repair operations when the damage is within t.ie primer coat and sandblasting to the steel substrate is not required.

a) Verif) .u rface is abraded lightly then wiped clean b) Verif) primer is applied in accordance with Section 3.2.2 (a) and (f) through (1).

3.2.4 Repair of Primer by Recoating The coating inspector shall conduct the following inspections for primer recoating repair. Only two (2) overcoats shall be applied.

a) Verify that the surface has been solvent cleaned or cleansed in accordance with Reference 1-B and 1-C. A clean white cloth shall be used to check primed surface cleanliness. Contamination is unacceptable an.d require further cleaning.

%g, TUGCC CA

. 1 I

I INSTRUCTION ISSUE N 6 REVISION PAGE TEXAS UTILITIES GENERATING CO. DATE CPSES QI-Q P-11.4-5 29 M AY 0 4 1984 11 of 32 b) Perfonn inspections (a) and (f) through (1) in Sec. l 3.2.2.

c) Minor defects (mechanical damage such as construction damage or exposing substrate during surface preparation operations, etc.) perfonn inspections in Sec. 3.7.2. I d) Major defects (mechanical damage such as construction damage or exposing substrate during surface preparation operations, e tc. ) perfonn inspections in Sec. 3.2.2.

l 3.2.5 Comolete Primer Recair (Primer Danace to Steel Surface Extends Over Entire Item) l' The coating inspector shall conduct the following inspections to document primer repair when the damage is to the steel surface and requires surface preparation to steel substrate over entire item:

a) Verify ambient conditions per Sec. 3.2.2(a) prior to surface preparation, b) Perfonn inspections in Sec. 3.2.2. l 3.2.6 Documentation of Primer Recair Inscections All inspections required by Sec. 3.2 shall be documented on an IR, Attachment 3, in accordance with Reference 1-0.

The completed IR shall be forwarded to the PPRV for retention.

NOTE 1: If the repair is on an item which is fabricated out of several pieces of steel bearing different QP numbers, all QP ntrnbers will be recorded in the " Remarks" section of the IR.

NOTE 2: All items within the scope of each inspection which are detennined by the Inspector to be satisfactory may be documented on a single IR, NOTE 3: A reject tag will be applied to any unsat area, with the inspection report, inspector's name and phone extension listed per Referuce 1-F.

3.3 FINISH COAT PRE-APPLICATION INSPECTIONS The QC inspector shall verify the following itens prior to applying coatings:

%g, TUGCQ CA

i. '

i '

' INSTRUCTION ISSUE NUMBER 1 REVISION PAGE TEXAS UTILITIES GENERATING CO. I DATE CPSES ,  ;

~

. QI-Qp-11.4-5 29 l M 0 4 E24 12 of 32 i

3.3.1 Coating Apolicator Qualifications I The Inspector shall verify (by Qualification Record or list of qualification reconis in QA File) that the coating applicators on each shift are qualified for safety-related coating work.

3.3.2 Anbient Conditions i

The inspector shall determine air temperatu re, surface temperature, relative humidity and dew point of substrate s tructures. A calibrated non-mercury -filled dry bulb thermometer or a calibrated temperature recorder (Bristol 4069TH or equivalent) shall be used for air temperatu re l determination. A calibrated non-mercury wet bulb l thennometer or a calibrated humidi ty recorder (Bristol 4069TH or equivalent) shall be used to detemine relative humidi ty. The dew point shall be determined by the difference in dry and wet bulb temperatures using the U.S.

Department of Cxmerce Weather Bureau psychometric Tables, WB No. 235. When dry bulb readings are greater than 100'F, the dew point and relative humidity should be determined by using the 100*F reading. If the dry bulb thennometer exceeds 100*F, the instrisnent shall be returned to the calibration lab for recalibration. The surface temperature shall be detennined by placing a calibrated surface temperature thennemeter (Omega-Amprobe Fastemp, range of 10*-250*F) in contact wi th . the substrate surface until the temperature reading stabilizes.

The permissible range of surface and ambient temperature for application of finish coat shall be 50-120*F.

Maximum values of relative humidity shall be 85t.

The su ' ce temperature shall be a minimum of 5'F above the dew point.

l 3.3.3 Coated Surface Acceptability t

The Inspector shall visually reinspect the previously coatet surface just prior to finish coat application for evidence of l

contamination (oil, grease, foreign matter). l l

j Contamination is unacceptable. All contamination must be  ;

removed per Reference 1-B or 1-C prior to finish coating. l Perm No,t TUGCC CA

INSTRUCTION ISSUE TEXAS UTIUTIES GENERATING CO. l DATE N CPSES QI-QP-11.4-5 29 MAY 0 41984 13 of 32 l

3.3.4 Air Supply Acceotability The Inspector shall inspect the air supply system (pressure pots and spray guns) for the existence of suitable filters /

traps / separators.

The effectiveness of these itens shall be verified by placing a clean piece of cheesecloth (or white fabric) over the exit of the air lines and allowing air to flow for 30 seconds minimum. The cloth shall show no evidence of moisture, oil or foreign matter when examined.

3.3.5 Finish Coat Mixino Ocerations I

3.3.5.1 prior to mixing, the inspector shall verify that each  :

component is identified by ba tch numbers and that the j 24 month shelf life has not been exceeded. .

3.3.5.2 The inspector shall verify that. mixing / thinning operations are perfonned in accordance with References 1-B and 1-C.

Thinning may be done up to two quarts of phenoline Thinner per gallon of Phenoline 305.

I 3.3.5.3. When coating materials are mixed / thinned in locations other than the field, the inspector verifying the mixing operation shall fill out the Paint Mixing Slip, Attachment 5. The inspector perfonning the pre-application inspection shall record the information fran the Paint Mixing Slip on the Inspection Report, Attachment 1. The Paint Mixing Slip need not be retained.

i 3.4 NNITORING OF SEAL OR FINISH C0AT APPLICATION [

The Inspector shall verify that. hose length is less than 75 feet when applicable.

The inspector shall also veriff that the seal coat (if present) is solvent wiped with Phenoline 305 thinner or Xyloi prior to finish coat application.

The inspector shall monitor to assure that no fish eyes appear in the applied coating. If detected the inspector shall infonn the paint foreman of their presence and they should be renoved while coating is still we t, su rf ace cleaned with solvent and coating reapplied.

p.,,,,,,,,, TUGCC CA

.. L. . . . . - -- -

l I I"0 N I E N REVISION PAGE TEXAS UTILITIES GENERATING CO. g CPSES QI-QP-11.4-5 29 MAY 0 41C24 ,14 of 32 The inspector shall monitor po t life in accordance with Attachment 7.

3.5 DOCUMENTATION OF PRIMER INSPECTION AND FINISH COAT PRE-APPLICATION / APPLICATION INSPECTIONS Results of inspections described in Sec. 3.1, 3. 3, and 3.4 shall be documented on an Inspection Report (IR),

Attachment 1, in accordance wi th Reference 1-D.

The ccmpleted IR shall be forwarded to the PPRV for retention.-

NOTE 1: All items wi thin the secpe of each inspection which are determined by the Inspector to be satisfactory may be documented on a single IR.

3.6 FINISH COAT FINAL ACCEPTA' ICE INSPECTION The inspector hall perfonn a final acceptance inspection of each finisa coated iten in accordance with Paragraphs 3.6.1 through 3.6.5. For finish coated containment liner plate surfaces, the final acceptance inspection shall be perfonned at the completion of the curing period. For all other finish coated itens, the final acceptance inspection shall be performed immediately prior to turnover of each area wi thin the containment building and should be coordinated with Area Managerrent. In addition, finish coated containment liner surfaces shall be vi sually reinspected in accordance with Paragraph 3.6.2 immediately prior to turnover of each containment area.

NOTE 1: (If applicable) Coating interface - at coating interfa;e for finish and/or primer coat, the existing coating shall be " feathered back" a suf ficient distance to ensure a smooth final coating system. When inspecting coating interface the interface of the systens shall be a maximum of Ils inch in width. Within the interface area, overlapping of any materials or systens is acceptable.

When inoganic zinc is applied at an interface, the cured inorganic zinc shall be screened or abraded prior to application of next coat.

NOTE 2: If present, the tie in interface between concrete

- coatings and steel coatings shall be visual ly .

inspected during the finish coat final acceptance of both systens.

, TUGCO CA

, , . . , - - -y- - m ,

I INSTRUCTION ISSUE NUMBER RESION PAGE TEXAS UTILITIES GENERATING CO. DATE CPSES QI-QP-11.4-5 29 MAY 0 4 EN 15 of 32 3.6.1 Finish Coat Cure Final QC inspection may be perfonned after a minimum topcoat cure of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and cure to recoat time has been met.

Curing and -time to recoat Phenoline 305 shall be as shown below:

Between Coats Temperature 'F 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> 50 - 59 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> 60 - 74 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> 75 - 89 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> 90 and above Phenoline thinned at 507, and applied as a seal coat may be recoated after 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of cure at or above 75'F.

3.6.2 Visual Defects Insoection The Inspector shall perfonn a visual inspection of the finish coated surface in accordance with the following: l a) Runs / sags - Runs or sags in which the DFT of the total coating system is 15.0 mils or less thick, which show no evidence of loss of adhesion or mudcracking, are acceptable. Those which show evidence of mudcracking, loss of adhesion or greater than 15.0 mils shall be repaired in accordance with Sec. 3.7 as applicable.

b) Ski ps, damaged areas, holidays, voids, bubbles, and blisters are not acceptable and shall be repaired as per Section 3.7, as applicable.

c) Pinholes - acceptable to the extent allowed by Sec.

3.6.4 and Attachment 2; areas not acceptable shall be repaired as per Section 3.7.5.

d) Contamination - unacceptable; areas shall be repaired as per Section 3.7.4.

e) Dry spray - unacccptable; shall be repaired as per Section 3.7.8. A minor amount of adherent dry spray is acceptable on the final finish coat,

' f) Color and gloss non-uniformity - unacceptable; shall be repaired as per Section 3.7.6. - -

,,,,,,%, Tucco cA

L I i ,

INSTRUCTION ISSUE i - NUMBER ESlON PAGE TEXAS UTILITIES GENERATING CO. DATE 6

CPSES QI-QP-11.4-5 29 /,AY 0 4 1984 16 of 32 g) Orange peel - moderate amount is acceptable, other than moderate amounts to be repaired per Sec. 3.7.7.

a NOTE 1: Top coated areas which have been abraded for various reasons (i.e., runs, sags,highmillage,contamina- I tion etc .) and are within acceptable procedural l thickness following repairs, do not require recoating  ;

for gloss enhancing.

{

NOTE 2: For small repair areas such as pinholes, color and gloss unifonnity is not required, provided the coating is smooth and continuous.

3.6.3 Dry Film Thickness (DFT)

The Inspector shall perfo nn a DFT of the cured coating system. A calibrated 0-25 Elconeter Inspector DFT Gage Medel III/1E, or equivalent, shall be used. Separate spot measure-ments (See Note 1) spaced evenly over the structure (See Note

2) shall be taken. Since the magnetic gage is sensitive to geometric discontinuities in the steel, measurements less than 1 inch from an edge or a hole should be avoided where possible. (See Note 3).

The average DFT of the total coating system shall be a minimum of 6.0 mils and a maximun of 13.0 mils. The spot test DFT of the total coating system shall be a minimum of 6.0 mils and a maximum of 15.0 mils. l The finish coated system shall exhibit full "hidi ng "

properties of the primecoat.

NOTE 1: A spot measurement is a series of three measure-ments in the same general area. The probe should be moved a short distance for each gage reading.

Discard any unusually high or low gage reading that cannot be repeated consistently. Take an average of these three gage readings as one spot measu rement.

In the event that any spot is found to be outside of the acceptable thickness range, three additional spots shall be taken at approximately 6 inches from the failing spot and spaced radially at approximately 120 degree intervals to detennine the extent of the unacceptable area. Dimensions

  • and locations of unacceptable areas and results of additional testing shall be documented on the IR. '

p.,,,, g , TUGCC CA

.. . .. . . . ' ~~

INSTRUCTION ISSUE NUMBER ESU PAGE TEXAS UTILITIES GENERATING CO. DATE CPSES QI-Q P-11.4-5 29 MAY 0 4 524 17 of 32 NOTE 2: Five spot tests shall be taken on each item for every 100 square feet of coated surface. For areas or items less than 100 square feet, the following shall apply:

Area Sq. Ft. No. Spots 100-80 5 80-50 4 50-10 3 10-3 2 3-0 1 NOTE 3: Items with appreciable surface curvature and other geometrical discontinuities such as hand ra il s, checkerplate, gratings, stairs, sway struts, etc.

shall be exempt from DFT measurement. For piping, struts, spring canisters e tc . , appreciable curvature will be considered as less that 4" in diameter.

3.6.4 Continuity Inspection The Inspector shall test the continuity of the cured finish coat on liner plate using a Tinker and Rasor Mocel M1 (67.5 volt) holiday detector. 100% of the finish coated surface area shall be tested.

The applied film should contain only a minor neber of l

points of discontinuity. No more -than two points of discontinuity should occur within an area having a radius of l 6 inches as measured from a point of discontinuity (pinholes). No more than 40% of the total nunbe r of allowable points of discontinuity should occur within any one area equal to 25% of the total area being coated. The l total number of pinhole discontinuities allowed is defined i

in Attachment 2. No gross discontinuities are allowed.

3.6.5 Documentation of Finish Coat / Seal Coat Acceptance Inspections Results of inspections described in Sections 3.6 shall be L documented on an Inspection Report (IR), Attachment 4, in j accordance with Reference 1-0. The completed IR shall be t forwarded to the PPRV for retention.

NOTE 1
All items wi thin the scope of each inspection per Paragraph 3.6, which are determined by the Ins pector to be satisfactory, may be docu ented

! .on a single IR.

l l

p,,,,, g , - TUGCC CA e -r-+ . - - . . . - . _ , . , , _ . , . - -.y., , . - , ., ,y. ._ __-.c g

I INSTRUCTION ISSUE NUMBER WSION PAGE TEXAS UTILITIES GENERATING CO. l OATE CPSES QI-QP-11.4-5 29 fAAY 0 41984 la of 32 NOTE 2: A reject tag will be applied to any unsat area, with the inspection report, inspector's name and phone extension listed per Reference 1-F.

3.7 REPAIRS OF FINISH COAT 3.7.1 Repairs of Runs and Saqs The QC inspector shall verify that the area is abraded until the DFT of the total coating system is within 6.0 to 15.0 mils, and examined fo r nadcracking. If r:udcracking is preseni., remove unsatisfactory coatings and repair per Sec.

3.7.2 or 3.7.3.

3.7.2 Repair of Minor Defects l

The QC inspector shall perfonn the following inspection when repairing minor defects (Reference Attachment 6):

a) Verify ambient conditions per Sec. 3.2.2(a) prior to surface preparation.

b) Verify that the area surrounding dama J area is blasted or abraded and any exposed steel is hand abraded, power tooled, or blasted and loosely adherent particles removed.

c) Verify damaged area is solvent wiped.

d) Perfonn inspections described in Sec. 3.2.2. 3.3 and i 3.4, as applicable.

e) Minor defects may be repaired at the time of final l inspection without later reinspection of the repair.

f .

3.7.3 Repair of Ma.for Defects The QC inspector shall perfonn the following inspection when repairing major defects (Reference Attachment 6):

a) Verify ambient conditions per Section 3.2.2(a) prior to surface preparation.

b) Verify area is power tooled or spot blasted and all loosely adherent particles removed.

Verify area is solvent wiped.

c) p.,,,, g , TUGCC CA

. l m 3 .

I i

)

! i INSTRUCTION ISSUE ER REVISION PAGE TEXAS UTILITIES GENERATING CO. DATE CPSES l

QI-QP-11.4-5 29

. NAY 01 1984 19 of 32 d) Perfonn inspections in Sec. 3.2 as applicable.

3.7.4 Repair of Contamination The QC inspector shall verify that contamination is removed and the surface recoated per Sec. 3.3 if removal of contamination results in low film thickness.

,. 3.7.5 Repair of Pinholes a) Verify all loose particles are removed and area is solvent wiped.

b) Perform inspections described in 3.7.2, except pinholes may be repaired at the time of final inspection without i a later reinspection of the repair. t 3.7.6 Repair of Gloss and Color Nonunifomity a) Verify the affected area is abraded and solvent wiped.

4 b) Verify the af fected area is recoated without exceeding the eximum film thickness and perfonn inspections in Sections 3.3, 3.4, 3.5 and 3.6.

c) Top coated areas ,hich have been abraded for various reasons (i.e., runs, sags, high millage, contamination, etc.) and are within acceptable procedural thickness, following repairs, do not require recoating for gloss enhancing.

d) For small repair areas such as pinholes, color and gloss uniformity is not required, provided the coating is smooth and continuous.

3.7.7 Repair of Excessive Orange Peel a) Verify the affected area is, abraded and solvent wiped, b) Verify the affected area is refinished and perfom the inspections delineated in Sections 3.3, 3.4, 3.5 and 3.6.

3.7.8 Repair of Dry Spray Repair of dry spray identifiable by vi sual ins pection defined within this procedure shall be removed.

%g, TUGCO CA

. . . . " . :: . .:' ^.t  ::- . . . . .. -. . . . .

l i INSTRUCTION l '

REVISION ISSUE R DATE PAGE TEXAS UTILITIES GENERATING CO.

CPSES QI-QP-11.4-5 29 20 of 32 l MAY04EN i a) Verify all loose particles are removed.

b) Verify coating film thickness is still within allowable range.

c) If film thickness is not within allowable range perfonn' inspections in Sec. 3.3,'3.4, 3.5 and 3.6.

NOTE: A minor amount of adherent dry spray is acceptable on the final finish coat.

3.7.9 Documentation of Recairs All repairs shall be docunented on an Inspection Report, Attachment 1. Repairs involving application of primer will be documented on Attachment 3.

3.8 MAPPING OF LARGE AREAS For large areas (such ~a s reactor containment liner plate) which have received coatings prior to 10/23/81 (Issuance date of Rev. 5 of this procedure), a unique nunber shall be assigned to the original inspection checklist. This number will be transferred to the area on a map drawing to provide traceability to the original checklist. For any coatings applied after 10/23/81, the IR number shall be transferred to the area on the map drawing.

The map drawing shall be mair.tained by the QC Supervisor, or his designee, until the entire surface has been coated.

At this time, the canpleted map shall be transmi tted to the Permanent Plant Records Vault.

NOTE 1: Separate maps shall be saintained for the prime, seal and finish coats.

If the coated area applicable to a given IR is NOTE 2:

irregular in shape, a sketch should be attached to the IR to indicate the extent of the area inspected.

NOTE 3: Coating repairs requiring recoating shall be mapped, but repairs only requiring touch-up need not be mapped.

NOTE 4: The following parameters (as necessary) should be considered for description of areas on the sketch:

,,,,,,,, TUGCO CA

i s.

INSTRUCTION NUMBER REVISION PAGE TEXAS UTIUTIES GENERATING CO.

CPSES

'g ,

QI-QP-11.4-5 29 21 of 32 MAY 0 41994 a) Bottom and top elevations (vertical and diagonal surfaces) or elevation of surface (horizontal surfaces).

b) Dimensions in relationship to azimuths, column lines, reactor centerline or other components of known location.

c) Quadrant, compartment, cavi ty or roon in which inspection is located.

d) Unit number.

e) Relation of su rface to cardinal di rections (i .e. , North, South, e tc.) .

3.9 SPECIAL COATINGS PROCEDURES Special coatings and instructions set forth in CCP-30-M procedures as applicable under the scope of this procedure, shall be inspected as per the guidelines of this procedure using the criteria established in the special coatings procedures.

3.10 SHOP COATED ITEMS 3.10.1 Itens removed fran the building for coating at the paint shop shall be the responsibility of the craft department.

3.10.1.1 The craft shall be responsible for identifying each piece by work package number.

3.10.1.2 The craft shall be responsile for returning and installing the shop coated iten in the same area it was removed from.

3.10.2 The shop QC Inspector shall inspect the iten(s) in accordance with QI-QP-11.4-1 and QI-QP-11.4-5, as applicable, and docunent his inspections on an Inspection Report (IR) in accordance with those procedures. ,

3.10.2.1 In addition to the infonnation required by QI-QP-11.4-1 or QI-QP-11.4-5, the shop inspector shall reference the work package nunber identified on the iten(s) on the IR.

~

3.10.2.2 The IR, upon completion, shall be transmitted to the Paper Flow Group (PFG) for Unit 1 and/or the Interim Records Vault

, (IRV) for Unit 2 for inclusion in the Wrk package.

s Po,e Ne61 TUGCC CA

r ,

I INSTRUCTION ISSUE NUMBER MSION PAGE TEXAS UTILITIES GENERATING CO. DATE CPSE3 QI-Q P-11.4-5 29 MAY 0 4 E84 22 of 32 3.10.3 The QC ir spector (in the field) shall verify that itens prepared /c >ated in the shop, which are included in the scope of the travele r, have the applicable Inspection Report (s) from the shop included in the work package and ~

correspond with the identification on the iten.

3.11 NONCONFORMANCES Nonconfonning conditions such as coating failure due to loss of adhesion or indetenninate/ unacceptable conditions which cannot be repaired or corrected as per existing procedures shall be documented on a Nonconforrance Reported (NCR) in accordance wi th CP-Q P-16. 0. The NCR ntrabe r shall te referenced on the Inspection Report, if applicable.

s A

%g, TUGCO CA

\ ~

INSTMUCT10N -

ISSUE NUMBEM n SlON PAGc TEXAS UTILITIES GENERATING CO. DATE

. CPSES QI-QP-11.4-5 29 MAY 0 41984 23 of 32 I

I l

ATTACHMENT 1 l

COMAMCNE PCAx 3 TEAM ELE:TRic 3 TAT lCN l

m.er* 1 es - 2 INSPECT!CN REPCMT p iTE3s OE5i;T.47.cas as.apiirmanGa % t&t3 TIM / 3Tisw.aE M6h&T' Gas .

PROTECTIVE CCATINGS r3 .

artan .ne; . ac u s ano. s em u w es .n w u, .a ;w.sa.

As.31 ,l ,lw-QP.11.4-5 QI Rev. ).l ,

C l"se Ty.c', C%"fe.IW."*" CFME u C P="s,ce- e= UPb3cie ,

mest agaul.74 O simpe:9ms cowurro au. usucass.: tross saturac7cav a mmere comu-as, unun=cron erzw urtzo us.ow **'"""" *

.c INSPTOT CN ATTRISUTES  ; Y ,[,fm m- IIgarg - .

l 5EAL CJAi fiNi5n sai 1 l l t i ORIGINAL REPAIR l 6i i

1. I si;CFO ALL PRCCii'.iisi 00 Ail:.G5 uh1GLE wP & 10 NO.'s: 1 ii t 1(FOR MULTIPLE ITEMS IN0!CATE IN " REMARKS WITH l' ! l I iCCRRESPCN0f% CFT RE10fNGS F CM ITE'8 d31Per Para 3.11.s I i l 1 -

1 l i 1 2 :vForry noturo r+me oro eses 1 * $ - l 1l I

3. PERFORM VISUAL INSPECTION CF PRI"ED SURFACE PER PARA. l l l 3.1.1.d I i l I Iorerrew rev er estwes eas* oes esos i
  • i . reas i l i i i MULTIPLE ITEMS INDICATE MIN. SPOT. NAA. SPOT AND AdER- 1 i l I iAGE OFT FOR EACH ITEM IN "REv>RKS*) I i l 1
5. PERFORM VISUAL INSPECTfCNS OF P8EVf 0U$tY CCATED SURFACE I

ptR papa 3.3.3 ' '

I c 'vroerv eteorier oerenego*emer taarp'se,e oro reesa no '

i l l CCP30A l ! I i

7. 1 AMBIENT CCNDITIONS CHEtrED PER PARA. 3.3.2 PRICR 70 l I i l lC0ATING Apof_fCAT!CN l tt l l RECCRD: i i l1 lCATE: IINE: is. a. l l l l l 0. 8 5. T. 0.P. R.M. l l I

i l I l (CONTINUED AN SHEET 2 of 2) l l l

= cosas,sse::,rTcJ

-4 Cfe ata

,g l La. oc C i

sionarwe e

oc m m ::sa .

%g, TUGCC CA

_. .. . . . . . .. + .. .  ;... . - - . . . . - - - - . . .

} INSTRUCTION l i

REVISION ISSUE NUMBER DATE FAGE TEXAS UTILITIES GENEMATING CO.

CPS 8S i .

QI-QP-11.4-5 29 24 of 32 lAAY 0 41984

-f ATTACHMENT 1 (Continued)

I I c:wAncut prax sTrau ELE:Tarc statics INSPECTION REPCRT QI.QP.11.4 5,'R.

(suppqEugNTAd Eheet 2 of 2 FCR FULL HEADIreGS. SEI SHEET 1 NO.

'E INSFECTICN ATTA18uTEs 8.

VERIFY OUALIFICATICW CF ADDtfCATORf5) pro papa. 3.3.1.

t rJu 1 I e *

't!ST-

, 1 i e i .

i i

i 1 i i 9,

t I t i 8 A DDf_ [{ATIFfi Mr?WCM- 1 I I f 1 iSP RA Y BEUSH i t 6 i

10. (VEUTFY AIR ?UDDt' ACCrpTante pro caos_ 3_3 2 . i e t I
11. IVE4frV =0?E '_ ENG?w !S tr$5 ?wng 7c r- .

i + 6 i

12. IVER!FV Mf1TNG CaraAricNs a=g ete ccp.39 ce cc. 3c4 ass . i 1 a 1 i IPARA. 3.3.5. 1 I 1 13 e i
  1. cca'!NS w *rs'p =c-m c taryttrees?fe.g.

I I I e i RECORD BAf tu N'assrot. 1 I I PAR T A:

I i spaar a- e 1 1 I e e e THINNER: l 1 1 1 1 TIME MIXED: CAtE: 4 I I i 14 IVERIF' PCT LIFE AS STATE 3 IN CCP.30 AND CCP.3CA IS NOTiEX.I i l ICEEDED PER PARA. 3,4.

I i 1 e t

  • 1 t g

8 I I t I t i e i s t i 1

I I I i i 1 1 4 '

6 I I t 1 4 i 4 i e i I I I

i e l l j ROdAMx3: (poet, spt:3,g7:J i

I 6

. =a= = 4s

.,l .. e.:,c:

.n , ,, c .

o ., - ..

t .

Pam sea 1 TUGCC CA

..- _ _ _? , _ , _ .

~ + , -

INSTRUCTION ISSUE 8 REVIS!CN PAG:

TEXAS UTILITIES GENERATING CO. DATE CPSES QI-QP-11.4-5 29 MAY 0 41984 25 of 32 i

ATTACHMENT 2 TOTAL NUMBER OF ALLOWABLE POINTS OF DISCONTINUITY SURFACE AREA COND. "C" BEING COATEC CCMMERCIALLY (50. FT.) CONTINUOUS 10 5 10-50 10 50-100 20 100-500 30 500-1000 50 1000-5000 75 Gross Discontinuities - None Allowed.

s h tem,9 , , ,

, . - . = _ _- . _ . - - . - _ ..

\

. ..- ...-.. i 1

i INSTRUCTION NUMBER REVIS!ON PAGE TEXAS UTILITIES GENERATING CO. ISSU{:

DAT CPSES QI-QP-11.4-5 29 MAY 0 4 E84 26 of 32 l l

ATTACHMENT 3-l CcasAMCME SCW STEAnd ELECTRIC S TATICN wr- -r INSPECTION MDCRT p rras _r-+ p irur.a s PROTECTIVE COATINGS n. dsursu e naw.as .sa.eact.m l esa .=

,! sv.

<r u sec. e asv. e t-- ':

  • g ws a :ssr as w r. .e.

AS-31 a!=010811.4-5tev. ,

CI"sa%nt.'c's @,In7c$h'd"*" CYa$d5E C I."=snetro. DsE. g asm .ssu ra b MC"NIN ccM84ETBo , aLL apmUCae6E STOs3 SAfWACTCav t

O =a m e= cew e n. = risnera.7 .rs= us se , * * 'annerca car l iTDs M ci IN SPCT;CN ATTmty*g3 i . L GC j

/ .y 3 llSa7t agna n,,g

1. IFor recair of sags and et;ns outside the acceetable CFT t i ' t i

! rince, eerfer-i 0FT of P*imer Coat in areas which h,ve if I f I been sanded or scree *e1 ce* Para. 3.2.1. (Fer multiefe 1 8 ' I ,

I items. indicate Min. Scot. %x. Scot and Avernoe OFT l 3 I i i i with corresoondino CP & TO No's for each item in i i l I  ?

I "Remarts".) l I i i i RECORD: Minimum Scot Test:

' l i i i I l Maximum Sect Test: l ll l {

l Averace DFT:

i I1l t l

2. lsbensive accest ele eer 8eet. 3.2.2 b. i I l I l h

' 3. Seearsters installed, draired and drains lef t cartially I i l l .

i ooen.

I ii i  :

S. Sie suceiv free of centaminatien. 1 ii I

5. blasted or oower. tooled surface and orofile: 1 ll i I l 4. Surface and surrounding areas cleaned per i Ii I l i Para. 3.2.2.d. I l l 8 1 e. Surface free of 'oreton matter incl. crease & oil.1 e ! l  !

l c. Sharp (non-rounded) projections removed. I l i ld Anemer eatteen deeth 1. 0 ail ainiar 3. 2. 2. e. 3. 1I I I e. Surface lichtly abraded per Para. 3.2.3. '

il I l f. Surface wiped clean oer Para. 3.2.3 or 3.2.4 l ll l I (Renairs Oniv) i ii i i

6. befouenumberstampedonefece(s1 8ecord Unieue 1 I l l i I Numeer(s) in ace ' arts" below. I ii i  ! ,
7. haibient condittens checked per Para. 3.3.2 orier to lll l l '

I orimer aoolication and record below l !l l 8 I DATE: TTME: WET 9t'tB TEwP l l l 1 '

l DRY SULB TEMP: RELATfvE WUwf0ftY: I lI l i l DEW POINT? SUoFACE TEMP: I I I i

8. Substrate sur' ace f*ee of contaminants.  !

I  !

l i 1I i i

.i , ,

, , , TUGCC CA

INSTRUCTION -

ISSUE l NUMBER n ISION -

rAGc-TEXAS UTILITIES GENERATING CO. DATE l

)

QI-QP-il.4-5 29 MAY0 4 W '27 of 32-ATTACHMENT 3 (Sheet 2)

COMANCHE PEAM STEAM ELECTRIC STATICN gg,gp.gg,4,$, g,,,

INSPECTION REPORT sheet of (suom EMENTAL)

  • T ,,

INSPECTION ATTRIsuTES 3 $su

,a i n

9. I free. filte ,er tea =-near int *=11.d a., am e. 3.3.a.
10. Air supoly free of contamination.
11. Ovalfiestica e' neelice*-*. flist Aroiteators?) I t I i

t I I i i 1 i e i

12. I verify Mixino Ceeratiens eer ears. 3. 2. 2.h. I i i 4
13. I Coating Waterial Peacuct identificaticn: 6 I I I I a. Base Lot No.-

e I e I

( 0. Filler Lot No.

t I i I

e. Catalyst: '

4 i

d. Thinner tot No!
e. Time Mixed?

,. 14. Pressure Dot agitated. (if aco11 cable) ' I i 15 . Pot life met eveeedad. -

16. Mose less than 75 feet.

t e l l1 41 i

REMARKS: (posS, SPEC 3.ETC) 6

****"" i" es es l i.R. Ctesto O i**" " '

.  ! l CC *NSPEC TC 4 31

' Fenn NeL t 7tJGCC CA

. . . . ~ . . . . . . ,

....,.4 i[i..d * . M. ...s .

. e iNSTRUCTICN ISSUE NUMBER RESION PAGE TEXAS UTIUTIES GENERATING CO. DATE CPSES QI-QP-11.4-5 29 MAY 0 4 198a 28 of 32 ATTACHMENT 4

- CCM AN CHE PEM STEAM EwlCTRIC S TATICN rr- .,

lNS9ECTloN MEPCRT p no. *

  • spux PROTECTi'If CCATINGS J " ~" ' f""""*""'"" .

acs. _: * =<.=g

.lav ee occ. e age. ai rair uwin. . scar.ao.

45-31 e 0f-CP-11.4-5, llev.a e- ,

suSPEC T cm YhC Pfe"'C4 uusF MN ,

JuBP. 87.3iA.T a O -teion ec= ures au. w eastA iro: sarw .c car C mart:m c-mm, enc;cnv ivos ustza sc.a. i ' '" 8'55 7'" M

"'" " 9 JNSPC*'CN ATTN ISU*ES

  • Y Jart 8 1 FINISH COAT FINAL ACCEPTANCE en E ' 3 i 1.

lverifv eurino is oer CCP-30 or 30A and cara. 3.6.1 l '

l 2

lac e'em visual inseaction of eested sur* ace eee ears. I f 13 . 6 . 2.

l l l 1

ll

~

lPerfor=i 0FT en coated surface as eee oars. 3.6.3 (For 1-bwltiele items indicat, min. Soot, max. soot and l l Iavaano, cr? with eeeeetreadfac M8 1 fD ao.'s for eteiv '

I l li taai in "cn eks".) i l) i koatino Syste* Soot Test Minimu n l l l l ICeatime Svstem Teot Test Waxim um l } l l lAverace DFT Coatino System 'l I i l l 4. lPerfor'It e3fttinuitV insCeetion oer Dara. 3.6.4. l l h

1: l 1 i ,

l I

I I l

li l l

)

6 i I

f 8885, SPEC 3, tTCJ Ii i l

3, R CLC3(3 n  ;

e ,

  • StenaP#6

'T W ' 8 GC se M CTGA q i

f ^

l gg g bNN M i

INSTRUCTION l l '

nEVISICN i ISSUE NUMBER DATE PAGc TEXAS UTILITIES GENERATING CO. l-CPSES OI-QP-ll.4-5 29 MAY 0 41984 29of 32 I

ATTACHMENT 5 l

4 4

I PAINT MIILNG SLIP

/

DATE:

BLDC. ELEV.

COATLNG: COLOR.

i TIME MIXED: TEMP.

BATCH # BASE (A)

CAT./FLR (B)

THINNER (C)

GAL. '

MSTE #'s INSP DATE:

e 9 9

, TUGCC CA

r INSTRUCTION ISSu'e NUMBER REVISION EAGE TEXAS UTILITIES GENERATING CO. DATE CPSES l QI-QP-11.4-5 29 MAY0 4 1c24 30 of 32 ,

ATTACHMENT 6 DEFINITIONS Color and Gloss Nonunifonnity: A milky haze or mist in the finish of a recently applied coating.

' Contaminant: A foreign substance, inadvertently added to a coating or found on the substrate that adversely affects the application, adhesion, curing and/or subsequent perfonnance of the applied.

coating.

Dev Soray: A dry powdery primer or finish coat readily removed by light sanding with either sandpaper or a wire screen. A minor amount of adherent dry spray it acceptable on the final finish coat.

Feathering: An area that is roughened and tapered to obtain a smooth and continuous surface with an existing coating.

Fisheyes: Small openings (" fisheyes") in wet film exposing old surface or previous coat. ,

Full Hiding: The coating provides sufficient coverage so that the preceding coat is not readily visible with an unaided eye.

Holiday: A pinhole, ski p, discontinui ty or void in coating film.

j Major Defect: Defined as an area, either circular or linear, in which "

a 1/2" diameter circle could be inscribed at any point or along the entire length which may extend to substrate.

Minor Defect: Defined as an area, either circular or linear, in which a 1/2" diameter circle could not be completely inscribed at any point along the entire length dich tray extend to substrate.

Monitor: Confonnance. verification by physically observing a task being performed on a periodic or random basis.

Muderacking: Irregular cracking as in a dried mud puddle (applicable to inorganic zinc primers).

Orange Peel: Dents in the surface resembling orange skin. A moderate amount is acceptable.

Pinholes: Minor discontinuities in coating which exposes primer or substrate.

, , , , , TUGCC CA

INSTRUCTION ISSUE NUMBER RWISION PAGE TEXAS UTILITIES GENERATING CO. DAT"-

CPSES QI-QP-11.4-5 29 MAY 0 4 bed31 of 32 ATTACHMENT 6 (Cont.)

Seal Coat: Finish coat applied at approximately 1 mil DFT over primer to protect prime coat.

Verify: Confirm or make certain.

Vi sual: To examine with an unaided eye (correctional eye glasses or contact lens are acceptable).

i

, , , , TUGCO CA

i INSTRUCTION ISSUE N SER REVISICN PAG"-

TEXAS UTILITIES GENERATING CO. l l OATE CPSES QI-QP-ll.4-5 29 MAY 0 4 IcB4 32 of 32 ATTACHMENT ?

POT LIFE REFERENCE SHEET Normal Pot life - CZ-ll 8 Hours Pot Life 3 .., -

2ac .

t ar-o a.

e w

L .l.

w

1. .. ,j e w -

un-Pot life stated above for unthinned coatings are the recocrnended times and should be utilized as a guideline for coatings usage times, however,

' actual pot life may be longer. For unthinned coatings or~ coatings thin-ned 50% or less, actual pot life is determined by applicability of the coating.

POT LIFE - DIMETCOTE 6 Pot life for dimetcote 6, thinned or unthinned, shall be 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

POT LIFE PHENOLINE 305 & CARSOLINE 191 TEMPERATURE (O F) UNTHINNED THINNED 50%

50-54 10 hrs. 24 hrs.

55-59 7 hrs. 24 hrs.

60-64 4h hrs.. 24 hrs.

65-69 3h hrs. 24 hrs.

70-74 2 hrs. 24 hrs.

75-79 1 hrs. 24 hrs.

, 80-84 1 hrs. 24 hrs.

85-89 1 hrs. 24 hrs.

90-95 1 hrs. 24 hrs.

Pot life stated above for unthinned coatings are the recomended times and should be utilized as a guideline for coating usage time, however, actual pot life may be longer. For unthinned coatings or coatings thinned 50% or less, actual pot life is determined by '

the applicability of the coating. .

%g, TUGCC CA

. . . . . . .. .