Supplemental Deficiency Rept CP-85-39 Re Equipment Conduit Interface.Initially Reported on 880111.Requirement for Unsupported Cable Lengths Relaxed for Unit 2
ML20072S446
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 04/05/1991
From: William Cahill, Woodlan D
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CP-85-39, TXX-91128, NUDOCS 9104160002
Download: ML20072S446 (2)


Text

- _ . _ _ _ _ _ - _ _ - _-

M CM Log # TXX 91128 L J file # 10110

= = 903.10 TUELECTRIC wimes J. cahm, Jr. April 5, 1991 urnaon rue nrsos,o V. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington. D.C. 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES), Unit 2 DOCKET NO. 50 446 EQUIPMENT CONDUli INTERFACE SDAR: CP 85 39 (SUPPLEMENTAL RLPORT)

Gentlemen:

On January 11. 1988, we notified you via TXX-88035 of the corrective actions to resolve the subject deficiency. In part the report discussed ceble slack acceptance criteria. Our last report was logged TXX 88773 dated November 9, 1988. This report is submitted to advise you of revised acceptance criteria offecting cable slack.

As stated in TXX 88035, inspections were conducted subsequent to the equipment conduit interface issue. During those inspections some raceway to equipment interface conditions were discovered which did not conform to the requirem9nts of the design documents. The three conditions were (1) cable s1cck inadequacy. (2) conduit to equipment interfaces installed outside of vendor areas and (3) conduit orientation within the vendor approved entry area, inspection requirements for items (2) and (3) will remain unchanged.

Concerning item (1), originally a 2" cable slack was required. This requirement was changed by deleting the 2" slack requirement. Previously, the electrical specification requtrement stated that sufficient slack is achieved by the following cable instal 1aon attributes:

(a) The cable bend radius meets specification requirements for training (forming).

(b) Unsupported cable lengths does not exceed 3 feet 6 inches.

(c) Unacceptable cable indentations do not exist at points of cable transition.

These require * :nts have not changed with exception of item (b),

The requirement for unrupported cable lengths of 3' 6" has been relaxed to 4'*6" for Unit 2 only. The initial requirement 3' 6" was more conservative than the industry standard of 4' 6".

9104160002 910405 PDR S

ADOCK 05000446 PDR /

d -

}, j.g 4 400 Nonh olive street LB. si Dallas, Texas 75201 \

.s

.. iXX91120 Page 2 l

The new requirement of 4' 6" has been evaluated and documented for weight l considerations and assures that cable slack will be maintained.

Documentation supporting the above evaluation is available onsite for your review.

Sincerely, William J. Cahill, Jr.

By: U D. R. Woodlan Docket Licensing Manager RSB/RHS:daj c Mr. R. D. Martin, Region IV Resident Inspectors CPSES (3) i

, .