MONTHYEARML24271A1872024-10-25025 October 2024 Summary of May 29, 2024 Public Comment Gathering Meeting on Performance Based Engineering ML24283A2092024-10-10010 October 2024 Summary of Oct 9 2024 Public Meeting with Trtr to Endorse NEI 23 03 ML24102A1942024-03-0808 March 2024 Summary of the March 8, 2024 RG 1-183 Update Workshop (3 of 3) ML24061A0702024-03-0202 March 2024 Summary of February 15, 2024, Public Meeting to Discuss Sections of NEI 23-03 Guidance on the 50.59 Process for Digital Applications ML23312A1722024-02-23023 February 2024 October 27, 2023, Summary of Draft Regulatory Guide (DG)-4034, Public Meeting ML24103A2332024-02-13013 February 2024 Summary of the February 13, 2024 RG 1-183 Update Workshop (2 of 3) ML24029A0172024-01-30030 January 2024 Summary of Public Meeting to Discuss NRC Hybrid Workshop (1 of 3) - Update to RG 1.183, Rev. 1, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors ML23311A3442023-11-0202 November 2023 Summary of September 12 2023 Meeting with the National Organization of Test, Research, and Training Reactors ML23230A0212023-08-30030 August 2023 LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting ML23208A2062023-07-31031 July 2023 NRC Public Meeting Summary GEH Pol Jun 1, 2023 ML23193A3472023-07-12012 July 2023 Abilene Christian University, Summary of the April 13, 2023, Closed Meeting Between the U.S. Nuclear Regulatory Commission Staff and Abilene Christian University to Discuss Security Topics for the Molten Salt Research Reactor ML23146A1542023-06-0505 June 2023 Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company ML23132A0412023-05-18018 May 2023 Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company ML22298A1612022-11-17017 November 2022 Summary of Public Meeting on SAMA with TVA ML22298A2712022-10-0303 October 2022 NRC-TVA Public Meeting Summary ML21320A3532021-11-0505 November 2021 NRC Presentation for the Public Meeting - 2021-11-05 - Rev. 1.5 ML21246A2752021-09-22022 September 2021 Summary of Public Meeting Held August 11, 2021, on Proposed Revision 5 to Regulatory Guide 1.9 ML21119A1282021-04-28028 April 2021 Final RG 1.183 Revision March 5 2021 Public Meeting Summary ML21035A2312021-02-18018 February 2021 Physical Security Plan - RAI Clarification Meeting ML20351A2822020-12-10010 December 2020 Summary of Public Meeting with Southern Nuclear Operating Co ML20342A1982020-12-0808 December 2020 Revision November 19 2020 Public Meeting Summary ML20252A2112020-09-0808 September 2020 Summary of Category 2 Public Meeting on the Risk-Informed Process for Evaluations (RIPE) ML20212L5342020-08-0505 August 2020 Summary of July 20,2020 Public Meeting with NEI and IEEE to Discuss New Regulatory Guidance Framework for IEEE Electrical Standards ML20161A0402020-06-0505 June 2020 Summary of May 14, 2020, Category 2 Public Meeting on the Risk-Informed Process for Exemptions (RIPE) ML20091H1142020-03-25025 March 2020 February 11, 2020, Summary of Category 2 Public Meeting on the American Society of Mechanical Engineers (ASME) Code Streamlining Initiative ML20065M8022020-03-0909 March 2020 Summary of Meeting with Eden Radioisotopes, Llc., to Discuss Licensing Topics Regarding Eden'S Proposed Medical Radioisotope Project ML19296C5852019-10-24024 October 2019 Summary of the Category 2 Public Meeting on Section 106 of the Nuclear Energy Innovation and Modernization Act ML19158A0142019-06-0707 June 2019 Summary of May 24, 2019, Teleconference Regarding May 21, 2019, Indigo Snake Mortality at Turkey Point ML19127A1362019-05-0707 May 2019 04/30/19 Summary of Meeting with the National Marine Fisheries Service Regarding Endangered Species Act Section 7 Consultation for the Proposed License Renewal of Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML18317A1702018-11-14014 November 2018 Summary of Meeting with Nuclear Energy Institute (NEI) Regulatory Issues Task Force (RITF) ML18297A1992018-10-25025 October 2018 NRC Action Item Response from Sept. 11 Public Meeting Notes ML18299A0292018-10-24024 October 2018 10/24/2018 Summary of Teleconference with the Fws Regarding Endangered Species Act Section 7 for Peach Bottom Subsequent License Renewal ML18214A6762018-08-0202 August 2018 Enclosure 1, Nuclear Energy Institute (NEI) Summary of 7/11/2018 Public Meeting ML18214A6752018-08-0202 August 2018 July 11, 2018, Summary of Meeting with Nuclear Energy Institute (NEI) Regulatory Issues Task Force (RITF) ML18060A3092018-03-0606 March 2018 Summary of Meeting on Fire Probabilistic Risk Assessment ML17293A6152017-10-19019 October 2017 09/19/2017 Summary of Meting to Describe License Renewal and Allow Members of the Public the Opportunity to Provide Comments Environmental Issues with Us NRC Should Consider During Environmental Review of River Bend Statin License Renewal A ML17233A3262017-08-22022 August 2017 July 26, 2017, Summary of Meeting with Nuclear Energy Institute (NEI) Regulatory Issues Task Force (RITF) ML17132A0932017-05-11011 May 2017 Attendees from May 11, 2017, TSTF Meeting ML17033A2582017-01-31031 January 2017 Pre-Submittal Meeting TSTF-567 Attendees ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15233A4912015-09-0101 September 2015 August 5, 2015, Public Scoping Meetings for the Environmental Review of the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Application ML15104A6322015-05-15015 May 2015 Summary of Telephone Conference Call Held on November 17, 2014 Between NRC and DTE Electric Co Re Requests for Additional Information on Fermi 2 License Renewal Application ML15091A3292015-04-0101 April 2015 March 10, 2015, Public Scoping Meetings for Environmental Review of LaSalle County Station (LSCS) Units 1 and 2, License Renewal Application ML13158A1972013-06-0707 June 2013 5/30/2013 Summary of Teleconference Between NRC Staff and NextEra Energy Staff Regarding Decommissioning Funding Status Report for Seabrook ML12171A3082012-06-18018 June 2012 E-mail Re Draft Summary of 05-31-12 Phone Call ML13246A3802012-05-0808 May 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, May 8, 2012 ML13246A3782012-02-16016 February 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Thursday, February 16, 2012 ML13246A3772012-01-31031 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, January 31, 2012 ML13246A3762012-01-23023 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Monday, January 23, 2012 ML13246A3742012-01-17017 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, January 17, 2012 2024-03-08
[Table view]Some use of "" in your query was not closed by a matching "". Category:Memoranda
MONTHYEARML24289A0872024-11-0505 November 2024 Updated Dispositioning of Safety Culture Program Effectiveness Review Recommendations ML24271A1872024-10-25025 October 2024 Summary of May 29, 2024 Public Comment Gathering Meeting on Performance Based Engineering ML24283A2092024-10-10010 October 2024 Summary of Oct 9 2024 Public Meeting with Trtr to Endorse NEI 23 03 ML24197A1312024-09-0909 September 2024 NUREG 1022 Rev 3 Supplement 2 Comment Resolution Memo.Docx ML24061A0702024-03-0202 March 2024 Summary of February 15, 2024, Public Meeting to Discuss Sections of NEI 23-03 Guidance on the 50.59 Process for Digital Applications ML23312A1722024-02-23023 February 2024 October 27, 2023, Summary of Draft Regulatory Guide (DG)-4034, Public Meeting ML23313A1442023-12-15015 December 2023 Status of Recommendations- Office of the Inspector Generals Audit of the U.S. Nuclear Regulatory Commissions Oversight of Counterfeit, Fraudulent, and Suspect Items at Nuclear Power Reactors (OIG 22-A-06) ML23297A0532023-11-27027 November 2023 Restart Panel Charter ML23263A6392023-09-20020 September 2023 DPO Case File DPO-2021-001 -- Redacted-Public ML23193A3472023-07-12012 July 2023 Abilene Christian University, Summary of the April 13, 2023, Closed Meeting Between the U.S. Nuclear Regulatory Commission Staff and Abilene Christian University to Discuss Security Topics for the Molten Salt Research Reactor ML23122A1642023-05-26026 May 2023 OEDO-22-00428 Status of Recommendations from Office of the Inspector Generals Audit of the U.S. Nuclear Regulatory Commissions Oversight of Counterfeit, Fraudulent, and Suspect Items at Nuclear Power Reactors (OIG-22-A-06) ML23082A1062023-04-21021 April 2023 Cancellation of Inspection Programs Memoranda Regarding the Public Health Emergency for the Reactor Safety Program ML23046A3982023-03-10010 March 2023 ASME Code Inservice Inspection of Steel Containment or Liners Covered by Insulation ML22348A2882022-12-15015 December 2022 Amir Afzali Speaker Invitation Letter ML22307A3052022-11-0606 November 2022 University of Texas at the Austin Research Reactor Special Inspection Team Charter ML22300A2192022-10-28028 October 2022 Telework Policy and Implementation Working Group Final Report ML22237A2272022-09-21021 September 2022 OEDO-22-00160 - Status of Recommendations: Office of the Inspector General'S Audit of the U.S. Nuclear Regulatory Commission'S Oversight of Counterfeit, Fraudulent, and Suspect Items at Nuclear Power Reactors ML22241A0382022-09-20020 September 2022 Memorandum 737 Max Digital Lessons and Learned Report ML22062A0082022-05-13013 May 2022 OEDO-22-00085/86/87 - Transmittal Memo of NRR Response to Taskings in EDO DPO Appeal Decision Concerning DPO-2020-004 ML22108A1672022-05-0303 May 2022 Staff Assessment of OIG Event Inquiry Into the NRCs Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML22108A0932022-04-28028 April 2022 OEDO-21-00226 - Status of Recommendations Audit of the NRCs Nuclear Power Reactor Inspection Issue Screening (OIG-21-A-07) ML22080A1112022-04-22022 April 2022 OEDO-22-0084 - Letter to Daniel Dorman - U.S. Nuclear Regulatory Commission Assessment Regarding Mitigation of Risk Posed by Counterfeit, Fraudulent, and Suspect Items ML22077A7752022-04-11011 April 2022 Memorandum to Eric Rivera - OIG 22 a 06 - Staff Response to the Office of the Inspector Generals Audit of the U.S. Nuclear Regulatory Commissions Oversight of Counterfeit, Fraudulent, and Suspect Items at Nuclear Power Plant (OIG 22 a 06) CLI-22-04, Change Letter to Peach Bottom Subsequent Renewed Licenses March 17 2022 Rev 12022-03-25025 March 2022 Change Letter to Peach Bottom Subsequent Renewed Licenses_March 17 2022_Rev 1 ML22038A2192022-03-15015 March 2022 Generic Issue Management Control System Report for the First Half of Fiscal Year 2022 ML22060A1532022-03-0404 March 2022 OEDO-22-00082 - Evaluation of Special Inquiry Report Findings on Counterfeit, Fraudulent, and Suspect Items for Immediate Safety Concerns at Nuclear Power Plants and Nuclear Materials Facilities ML21341B0272022-01-24024 January 2022 OEDO-21-00182 - Memo to Eric Rivera - Status of Recommendations: Audit of the U.S. Nuclear Regulatory Commissions Oversight of Supplemental Inspection Corrective Actions (OIG-19-A-19) ML21350A2862021-12-21021 December 2021 Response to Advisory Committee on Reactor Safeguards Letter Regarding the Review of the Draft NUREG CR-XXXX, Fuel Qualification for Molten Salt Reactors ML21295A3082021-10-22022 October 2021 Public Meeting Summary - MAP-X Public Meeting (Q3 CY2021) September 21, 2021 ML21064A3502021-07-26026 July 2021 OEDO-21-00048 - Oconee Nuclear Station, Units 1, 2, and 3 - Response Memorandum ML21179A3402021-06-28028 June 2021 Fast Code Assessment for TRISO Fuels Summary Memo ML21077A1872021-03-30030 March 2021 Status Update for OIG 19-A-19 Recommendations ML21062A3012021-03-0505 March 2021 Revision to National Institute of Standards and Technology Test Reactor Special Inspection Team Charter ML21027A1692021-02-0303 February 2021 Updates on Actions to Address the Office of the Inspector General'S Audit Recommendations on the U.S. Nuclear Regulatory Commission'S Oversight of Spent Fuel Pools (OIG 15 a 06) ML21027A2742021-01-28028 January 2021 Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions ML21012A1282021-01-22022 January 2021 Approval of the Risk-Informed Process for Evaluations ML20357A0622021-01-13013 January 2021 OEDO-20-00307 NRR Response to Status of Recommendations for the Audit of the NRC Nuclear Power Plant Surveillance Test Inspection Program (OIG-20-A-11) ML21006A3242021-01-0707 January 2021 Approval of the Risk-Informed Process for Evaluations ML20351A2822020-12-10010 December 2020 Summary of Public Meeting with Southern Nuclear Operating Co ML20342A1982020-12-0808 December 2020 Revision November 19 2020 Public Meeting Summary ML20296A5402020-11-12012 November 2020 Closure of User Need Request UNR NRR-2018-004, Support Risk-Informed Reviews of Instrumentation and Control Systems/Components - Technical Basis and Regulatory Approaches ML20290A6262020-10-30030 October 2020 Closure Recommendation Memorandum for Generic Issue 199, Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants ML20255A0922020-10-0101 October 2020 Status Update for OIG 19A-19 Recommendations ML20260H1222020-09-22022 September 2020 Close Out of Generic Issue 204, Flooding of Nuclear Sites Due to Upstream Dam Failure ML20237F5182020-09-18018 September 2020 Nomination of Kenneth See as the Nuclear Regulatory Commissions Dam Safety Officer ML20230A2162020-09-16016 September 2020 Closure Recommendation for Generic Issue 204, Flooding of Nuclear Sites Due to Upstream Dam Failure ML20252A2112020-09-0808 September 2020 Summary of Category 2 Public Meeting on the Risk-Informed Process for Evaluations (RIPE) ML20217L1922020-08-25025 August 2020 Regulatory Information Conference 2021 - Call for Proposed Technical Session and Digital Exhibit Topics ML20164A2222020-08-10010 August 2020 Memo Transmit Cra Forms to OCA ML20212L5342020-08-0505 August 2020 Summary of July 20,2020 Public Meeting with NEI and IEEE to Discuss New Regulatory Guidance Framework for IEEE Electrical Standards 2024-09-09
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
October 24, 2019
SUBJECT:
SUMMARY
OF SEPTEMBER 26, 2019, CATEGORY 2 PUBLIC MEETING ON SECTION 106 OF THE NUCLEAR ENERGY INNOVATION AND MODERNIZATION ACT On September 26, 2019, a Category 2 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and members of the public at the Engineering Innovation Laboratory, 775 MK Simpson Blvd.102, Idaho Falls, Idaho. The purpose of this meeting was to obtain feedback from current holders of licenses for research reactors and other members of the public on the potential impact of changes made to Section 104c of the Atomic Energy Act of 1954, as amended (AEA), by Section 106, Encouraging Private Investment in Research and Test Reactors, of the Nuclear Energy Innovation and Modernization Act (NEIMA), which was signed into law on January 14, 2019. The purpose of collecting this feedback was to inform the NRC staffs consideration of the need for rulemaking to conform the regulations in Part 50, Domestic Licensing of Production and Utilization Facilities, of Title 10 of the Code of Federal Regulations (10 CFR) with the new statutory requirements in Section 104c of the AEA.
In its presentation, the NRC staff explained the changes made to Section 104c of the AEA by NEIMA. The NRC staff explained that NEIMA changed the framework by which the NRC determines whether a utilization facility is licensed under Section 103 or Section 104c of the AEA. The new law amended Section 104c of the AEA to include cost recovery requirements to determine whether a utilization facility is licensed for research and development purposes or industrial or commercial purposes. Before NEIMA, the AEA did not limit how these utilization facilities recovered money from commercial activities.
The current requirement in 10 CFR 50.22, Class 103 licenses; for commercial and industrial facilities, considers the amount of money a production or utilization facility spends on commercial activities. Under the current 10 CFR 50.22, a production or utilization facility is licensed for industrial or commercial purposes under Section 103 of the AEA if the facility is to be used so that more than 50 percent of the annual cost of owning and operating the facility is devoted to the production of materials, products, or energy for sale or commercial distribution, or to the sale of services, other than research and development or education or training. If 50 percent or less of the annual cost of owning and operating the facility is devoted to commercial activities, then the facility is licensed under Section 104c of the AEA as a facility for research and development.
Section 106 of NEIMA changed Section 104c of the AEA to focus on how the facility's costs are recovered. Specifically, NEIMA added, The Commission is authorized to issue licenses under this section for utilization facilities useful in the conduct of research and development activities of the types specified in section 31 [of the AEA] in which the licensee sells research and testing services and energy to others, subject to the condition that the licensee shall recover not more than 75 percent of the annual costs to the licensee of owning and operating the facility through sales of nonenergy services, energy, or both, other than research and development or education and training, of which not more than 50 percent may be through sales of energy.
The NRC staff explained that, to implement this revised licensing authority, the NRC will apply the new cost recovery requirements in Section 104c of the AEA to research reactors that are currently in the license renewal process and any applicable new or renewed license applicants.
The changes made to Section 104c of the AEA by NEIMA did not address the applicability of the new cost recovery requirements to current utilization facility licensees that are not in the license renewal process and will not undergo license renewal in the future. The NRC could apply the new cost recovery requirements to these licensees or continue to apply the current requirements in 10 CFR 50.22 to these licensees.
The NRC staff presentation also provided 4 examples of how the requirements in 10 CFR 50.22 and Section 104c of the AEA would apply to facilities with different mixes of expenses and incomes from commercial activities and research and development activities. The NRC staff presentation concluded with a discussion of several potential impacts of the new cost recovery criteria in Section 104c of the AEA on existing research reactor licensees. The NRC staff made the presentation publicly available in advance of the meeting at Agencywide Documents Access and Management System (ADAMS) Accession No. ML19263A651.
Members of the public provided feedback throughout the NRC staffs presentation and during a dedicated feedback session afterwards. The feedback focused on two main topics: 1) applicability of the new cost recovery criteria to existing research reactor licensees and 2) practical aspects of demonstrating compliance with the cost recovery criteria.
Regarding applicability of the new cost recovery criteria to existing licensees, there was not a consensus among the meeting attendees. Most of the feedback expressed the opinion that the new cost recovery criteria should only be applied to future licenses and not to existing licenses issued under 10 CFR 50.22. Some attendees stated that the new cost recovery criteria could negatively impact their research activities by limiting their ability to generate commercial income to cover the costs of the research programs. Other attendees stated that the new cost recovery criteria should be applied equally to all current and future research reactor licensees to avoid a double standard for different holders of the same types of licenses. Some attendees were indifferent because they conduct minimal commercial activities. Several attendees represented research reactors that are in the license renewal process and will therefore have the new cost recovery criteria applied to their renewed licenses, and they expressed frustration that they will be subject to the new cost recovery criteria and the existing regulations in 10 CFR 50.22 just because of the timing of their license renewal and the new law.
Regarding the practical aspects of demonstrating compliance with the new cost recovery criteria, most attendees favored the NRC issuing additional guidance. Several attendees requested that the NRC publish more detailed guidance about how a licensee should calculate the annual cost of owning and operating the facility, especially when it is a small part of a large university organization. Other licensees expressed a need for explicit guidance about what constitutes a commercial activity and what constitutes a research and development activity.
Intermixed in this feedback was a consistent message from the meeting attendees that the NRC should be mindful of the requirement in Section 104c of the AEA that the NRC apply the minimum necessary regulation to research reactor licensees to protect the health and safety of the public and permit the conduct of widespread and diverse research and development.
The meeting notice and agenda, dated May 23, 2019, are available at ADAMS Accession No. ML19254D050. A list of meeting attendees is provided as an enclosure to this summary.
Please direct any inquiries to William B. Kennedy at 301-415-2313 or William.Kennedy@nrc.gov.
ML19296C500 Pkg ML19254D050 Mtg. Notice ML19296C585, Mtg. Summary ML19263A651 Slides *concurred via email NRC-001 OFFICE NRR/DANU/UNPL/PM NRR/DANU/UNPL/LA NRR/DANU/UNPL/BC NAME WKennedy NParker* GCasto*
DATE 10/22/19 10/23/19 10/23/19 LIST OF ATTENDEES SEPTEMBER 26, 2019, CATEGORY 2 PUBLIC MEETING ON SECTION 106 OF NEIMA 10:30 A.M. - 12:30 P.M.
Name Organization In-Person Attendees:
Louise Lund U.S. Nuclear Regulatory Commission Greg Casto U.S. Nuclear Regulatory Commission Alexander Adams, Jr. U.S. Nuclear Regulatory Commission Patrick Boyle U.S. Nuclear Regulatory Commission William Kennedy U.S. Nuclear Regulatory Commission Luke Gilde University of Maryland Amber Johnson University of Maryland C. Corey Hines Washington State University Hillary Bennett Washington State University Meagan Nydegger National Institute of Standards and Technology Scott Miller Texas A&M University Paul M. Whaley University of Texas Jeff Geuther Pennsylvania State University Robert Seymour Kansas State University David M. Slaughter Aerotest Operations Bruce Meffert University of Missouri - Columbia Christopher Farwell United States Geological Survey Marshall Wade Massachusetts Institute of Technology Sarah Don Massachusetts Institute of Technology Ashoak Nagarajan Idaho State University Eric Crapo Fluor Idaho Jay Kunze Idaho State University Les Foyto University of Missouri - Columbia Andrew Smolinski Idaho National Laboratory Michael Ruddell Idaho National Laboratory Leo Bobek University of Massachusetts - Lowell Thomas Regan University of Massachusetts - Lowell Jere Jenkins Idaho National Laboratory Andrew Kauffman Ohio State University Clive Townsend Purdue University Jonathan Wallick University of California - Irvine Melinda Krahenbuhl Reed College Rick Gunderson Idaho National Laboratory Edward Lau Massachusetts Institute of Technology Jordan Hill Atomic Alchemy Thomas Eiden Atomic Alchemy John Peterson Atomic Alchemy Ram Sharma International Atomic Energy Agency Telephone Conference
Participants:
Cynthia Montgomery U.S. Nuclear Regulatory Commission Duane Hardesty U.S. Nuclear Regulatory Commission Enclosure
Michael Balazik U.S. Nuclear Regulatory Commission Gary Becker NuScale Andy Bell Oak Ridge National Laboratory Janet Bergman Curtiss-Wright Ken Brooks University of Missouri Mike Cannon Member of the Public Dan Cronin University of Florida John Foster Massachusetts Institute of Technology Chris Monetta Member of the Public Phil Oliver Atomic Alchemy Pete Robertson University of Missouri Siaka Yusuf Dow Chemical Joe LaPrad SHINE Medical Technologies