MONTHYEARML17153A2852017-05-25025 May 2017 License Renewal Application Project stage: Other ML17153A2862017-05-31031 May 2017 River Bend Station, Unit 1, License Renewal Application Project stage: Other ML17156A0932017-06-20020 June 2017 Receipt and Availability of the License Renewal Application for River Bend Station, Unit 1 Project stage: Other ML17186A1592017-07-10010 July 2017 License Renewal Application - Supplemental Information Needed for Acceptance of Requested Licensing Action, Regarding the Application from Entergy Operations, Inc. for Renewal of the Operating License for River Bend Station, Unit 1 Project stage: Acceptance Review ML17180A0772017-07-27027 July 2017 Correction Letter for the Receipt and Availability of the License Renewal Application for the River Bend Station, Unit 1 Project stage: Other ML17157B3672017-07-31031 July 2017 License Renewal Application Online Reference Portal Project stage: Other ML17187A0462017-08-0202 August 2017 License Renewal Pre- Application Coordination Meeting 1 River Bend Nuclear Generating Station Unit 1 - Summary of Meeting Held on April 25, 2017 Project stage: Meeting ML17187A0272017-08-0202 August 2017 License Renewal Application, NRC Presentation Summary of Meeting Held on May 25, 2017 Project stage: Meeting ML17187A0352017-08-0707 August 2017 Determination of Acceptability and Sufficiency for Docketing and Proposed Review Schedule Regarding the Application from Entergy Operations, Inc. for Renewal of the Operating License for River Bend Station, Unit 1 (CAC No. MF9747 and MF9778 Project stage: Other ML17180A1362017-08-0909 August 2017 05/25/2017 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Entergy Operations, Inc. Representatives to Discuss the River Bend Station, Unit 1 License Renewal Application Project stage: Meeting ML17187A0372017-08-0909 August 2017 04/25/2017 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Entergy Operations, Inc. Representatives to Discuss the River Bend Station, Unit 1 License Renewal Application Project stage: Meeting ML17173A1332017-08-0909 August 2017 FRN River Bend Acceptability for Docketing and Opportunity to Request a Hearing and to Petition for Leave to Intervene Project stage: Request ML17240A3322017-09-0707 September 2017 License Renewal Application Review Status Letter (CAC No. MF9747 and MF9778) Project stage: Other ML17293A5032017-09-12012 September 2017 License Renewal Application Review Public Scoping Meeting 9-19-2017 Project stage: Meeting ML17262A2002017-09-25025 September 2017 Plan for the Operating Experience Review Regarding the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML17269A0512017-10-10010 October 2017 Plan for the Aging Management Program Regulatory Audit Regarding the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML17279A8742017-10-11011 October 2017 Plan for the Scoping and Screening Methodology Regulatory Audit Regarding the License Renewal Application Review Project stage: Other ML17284A1002017-10-13013 October 2017 License Renewal Severe Accident Management Alternatives Audit Regarding River Bend Station, Unit 1 Project stage: Other ML17278A7752017-10-13013 October 2017 License Renewal Environmental Site Audit Regarding River Bend Station, Unit 1 Project stage: Other ML17293A6152017-10-19019 October 2017 09/19/2017 Summary of Meting to Describe License Renewal and Allow Members of the Public the Opportunity to Provide Comments Environmental Issues with Us NRC Should Consider During Environmental Review of River Bend Statin License Renewal A Project stage: Approval ML17298B1742017-10-31031 October 2017 Audit Plan for the Onsite Aging Management Program Regulatory Audit for the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML17348B1672018-01-0404 January 2018 Status Letter - December Project stage: Other ML18002A3692018-01-0808 January 2018 Extension Letter Request Response Project stage: Other ML18233A1822018-08-23023 August 2018 License Renewal Application Review Updated Budget Estimate and Status Letter (CAC Nos. MF9747 and MF9778) Project stage: Acceptance Review 2017-07-27
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24052A2572024-02-26026 February 2024 Summary of January 17, 2024, Partially Closed Teleconference Meeting with Entergy Operations, Inc. to Discuss Proposed License Amendment Request for Entergy Fleet Regarding Implementation of an Online Monitoring Methodology ML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22167A0882022-06-24024 June 2022 Summary of June 14, 2022, Public Meeting with Entergy Operations, Inc. to Discuss Upcoming Relief Request to Use Code Case N-752 for Grand Gulf Nuclear Station, Unit 1, River Bend Station, Unit 1, and Waterford Steam Electric Station, Unit ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML21323A0472021-12-0606 December 2021 Summary of Public Meeting on November 5, 2021, with the National Organization of Test, Research, and Training Reactors on Operator Licensing for Research and Test Reactors ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21027A2312021-02-0909 February 2021 Summary of January 25, 2021 Presubmittal Meeting with Entergy Operations, Inc. Planned LAR to Allow Receipt, Possession, and Use of Byproduct Materials from Other Entergy Stations for River Bend Station, Unit 1 ML20317A0372020-11-18018 November 2020 Summary of September 22, 2020, Presubmittal Meeting with Entergy Operations, Inc., a Request for a One-Time Exemption from 10 CFR Part 50, Appendix E Biennial Emergency Preparedness Evaluated Offsite Exercise ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML20107F7332020-04-27027 April 2020 Summary of April 3, 2020 Meeting with Industry Regarding Changes to Subsequent License Renewal Guidance Documents ML20015A2692020-02-0505 February 2020 December 17, 2019, Summary of Meeting with Entergy Operations, Inc. on Planned License Amendment Request to Incorporate the Tornado Missile Risk Evaluator Methodology at River Bend Station, Unit 1 ML18270A1582018-10-10010 October 2018 Summary of Meeting with Entergy Operations Inc. on Its Intent to Change Neutron Absorbers for the River Bend Station, Unit 1 Spent Fuel Pool ML18155A5502018-06-14014 June 2018 Summary of a Telephone Conference Call Held on May 17, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station Unit 1 License Renewal Application Revie ML18143B3962018-06-0404 June 2018 05/03/2018 Summary Telephone Conference with Entergy Regarding the Need for Additional Information to Support the River Bend Station Unit 1 License Renewal Application Review. ML18129A3562018-05-29029 May 2018 April 26, 2018 Summary of a Telephone Conference Call Between NRC and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Review ML18127A0342018-05-25025 May 2018 Summary of Public Telephone Conference Call Held on April 18, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the RBS Unit 1 License Renewal Application Review ML18124A1902018-05-25025 May 2018 Summary of a Telephone Conference Call Held on April 25, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Re ML18120A1352018-05-10010 May 2018 Call Summary - Fuel Oil, Ext.-Int. Surf. Monitoring, FAC & Others 041018, Rev2 ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18107A5042018-04-24024 April 2018 03/29/2018 Summary of Public Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Review ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18089A0762018-04-12012 April 2018 03/13/2018 Summary of Public Telephone Conference Call Held on Between the U.S. Nuclear Regulatory Commission and Entergy Regarding Requests for Additional Information Pertaining to the River Bend Station, Unit 1 License Renewal Application ML18059A8222018-03-0808 March 2018 Summary of Public Telephone Conference Call Held on February 27, 2018 Between the U.S. Nuclear Regulatory Commission and Entergy Regarding Requests for Additional Information Pertaining to the River Bend Station Unit 1 ML18057A4532018-03-0707 March 2018 Summary of Telephone Conference Call Held on February 20, 2018 Between the U.S. Nuclear Regulatory Commission and Energy Regarding RAI Pertaining to the River Bend Station, Unit 1 License Renewal Application Review ML17353A1542017-12-22022 December 2017 Summary of Public Meeting with Entergy Operations, Inc., on Proposed Changes to Emergency Plans to Revise Emergency Action Levels for Arkansas; Grand Gulf; River Bend; and Waterford (EPID-L-2017-LRM-0060) ML17293A6152017-10-19019 October 2017 09/19/2017 Summary of Meting to Describe License Renewal and Allow Members of the Public the Opportunity to Provide Comments Environmental Issues with Us NRC Should Consider During Environmental Review of River Bend Statin License Renewal A ML17234A5442017-08-30030 August 2017 Summary of Public Meeting with Entergy Operations, Inc. to Discuss a Proposed New Technical Specification for River Bend Station, Unit 1 ML17180A1362017-08-0909 August 2017 05/25/2017 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Entergy Operations, Inc. Representatives to Discuss the River Bend Station, Unit 1 License Renewal Application ML17187A0372017-08-0909 August 2017 04/25/2017 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Entergy Operations, Inc. Representatives to Discuss the River Bend Station, Unit 1 License Renewal Application ML17152A2442017-06-0101 June 2017 Summary of Public Meeting - River Bend Station ML17152A3772017-06-0101 June 2017 Errata for Summary of Public Meeting ML16119A3422016-04-28028 April 2016 Summary of Regulatory Conference to Discuss Safety Significance of River Bend Station Control Building Chilled Water System Apparent Violation ML12275A5492012-10-0101 October 2012 Summary of Meeting with Entergy Operations, Inc., to Discuss the Performance of the Subject Facilities, Recent Organizational Changes, and Current Regulatory Issues ML12240A4162012-08-27027 August 2012 Public Meeting with Entergy Operations, Inc to Discuss the Performance of the Subject Facilities and Current Regulatory Issues ML12195A3282012-07-13013 July 2012 AIT Meeting Summary ML1117906392011-06-28028 June 2011 Summary of Meeting with Entergy Operations Inc ML1117901522011-05-20020 May 2011 Summary of Annual Performance Assessment Meeting for River Bend Station ML1110401712011-04-27027 April 2011 04/5/2011 Summary of Preapplication Meeting with Entergy Operations, Inc. to Discuss Fleetwide Submittal for Proposed Technical Specification and Quality Assurance Program Manual Changes Related to Unit Staff Qualification Requirements ML1033404942010-12-10010 December 2010 November 19, 2010 Summary of Meeting with Entergy Operation Inc, to Discuss River Bend Preliminary Enforcement ML1029403512010-10-19019 October 2010 10/182010 Summary of Public Meeting with Entergy Operations to Discuss Initiatives to Improve Plant Reliability ML1026705452010-09-24024 September 2010 Public Meeting with Entergy, Inc., to Discuss Licensee Activities Associated with Emergency Diesel Generators and Control Building Chillers ML1011209712010-04-16016 April 2010 Summary of Meeting to Discuss the Safety Performance at the River Bend Station Between January 1 and December 31, 2009 ML1009805832010-04-0808 April 2010 Summary of Meeting with Entergy Operations, Inc. to Discuss the 2009 Nuclear Safety Culture Assessment Performed at Arkansas Nuclear One, Grand Gulf Nuclear Station, River Bend Station, and Waterford Steam Electric Station, Unit 3 ML0921510442009-08-19019 August 2009 Summary of Meeting with Entergy Operations, Inc., River Bend Station, Unit 1, Relief Requests Related to Code Case N-716 and RR-ISI-012 to Extend Second Interval ML0918701502009-07-10010 July 2009 Summary of June 29, 2009, Conference Call with Entergy Operations, Inc., Related to Decommission Funding Assurance ML0719002022007-07-0909 July 2007 Summary of Meeting with Entergy Operations, Inc., Regarding Discussion of River Bend Station Plans for Improving Human Performance and Corrective Action Program 2024-02-26
[Table view] |
Text
October 19, 2017 U.S. Nuclear Regulatory Commission Public Meeting Summary Title: Public Scoping Meeting for Environmental Review of River Bend Station, Unit 1 (RBS)
License Renewal Application (LRA) (CAC NO. MF9778)
Meeting Identifier: 20171130 Date of Meeting: Tuesday, September 19, 2017 Location: St. Francisville Town Hall, 11936 Ferdinand Street, St. Francisville LA Type of Meeting: Category 3 Purpose of the Meeting(s):
To describe the license renewal process and to allow members of the public the opportunity to provide comments regarding environmental issues the U.S. Nuclear Regulatory Commission (NRC) should consider during its environmental review of the RBS LRA.
General Details:
The NRC held a public scoping meeting as part of the RBS LRA environmental review. The meeting started at 7:00 p.m. Central Standard Time (CST). The meeting ended at 7:25 p.m.
CST. Six NRC staff members were present. The meeting was facilitated by Dan Mussatti, an NRC in-house facilitator. The meeting began with a review of meeting ground rules and an introduction of NRC staff, followed by a presentation on the license renewal safety review process by Manny Sayoc and the license renewal environmental review process by Bob Hoffman. The presentations emphasized that comments were welcome to help focus the environmental review. Next, there was a question and answer period on the NRC staff presentations. Finally, there was the comment portion of the meeting.
Twenty people (this number includes the six NRC staff) attended the meeting. In addition to two members of the public, meeting participants included Mr. Couhig, the Parish President of West Feliciana Parish, JiYoung Wiley, a representative from the Louisiana Department of Environmental Quality and the applicant.
Summary of Presentation:
The Atomic Energy Act of 1954 authorizes the NRC to grant licenses for commercial power reactors to operate for up to 40 years and allows these licenses to be renewed for up to another 20 years. The 40-year term was based primarily on economic considerations and antitrust factors, not on safety and technical limitations. The NRC has established a license renewal process that has two separate, but parallel review tracks; a safety review and an environmental review.
The focus of the safety review stems from the NRCs obligation under the Atomic Energy Act of 1954, and is performed under the regulations of Title 10 of the Code of Federal Regulations (10 CFR), Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plant. The purpose of this review is to verify that each applicant has fully analyzed the management of aging effects in sufficient detail to conclude that the plant can be operated safely during the period of extended operation. The NRCs safety review is documented in the final safety evaluation report.
Under the NRCs environmental protection regulations in 10 CFR Part 51which implement the National Environmental Policy Act (NEPA)issuance of a new nuclear power plant operating license requires the preparation of an environmental impact statement (EIS). The NRC performs plant-specific reviews of environmental impacts of operating life extension in accordance with NEPA and the requirements of 10 CFR Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions. As part of the environmental review, the staff consults with local, State, Federal, and Tribal officials.
The environmental review begins with a scoping process, which is an assessment of specific environmental impacts associated with renewing the RBS operating license. Some environmental impacts are similar, if not identical, at all nuclear power plants, so, to improve efficiency, the NRC staff developed a generic environmental impact statement, NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, that addresses a number of impacts common to all nuclear power plants. The NRC staff supplements the generic EIS with a plant-specific EIS (SEIS), in which all issues that are specific to RBS will be addressed. The staff also re-examines the conclusions reached in the generic EIS to determine if there is any new and significant information that would change those conclusions. The NRC staff will make a recommendation on whether or not the environmental impacts are so great that they preclude maintaining the option of license renewal for energy-planning decisionmakers.
The closing date for submitting scoping comments is October 23, 2017. In addition to providing comments at the meetings, comments can be: (1) mailed to Chief, Rules, Announcements and Directives Branch, Division of Administrative Services, Mailstop TWFN-8-E-21, U.S. Nuclear Regulatory Commission, Washington, DC 20555; (2) submitted online using the Federal Rulemaking website at regulations.gov (keyword: NRC-2017-0141); or emailed to elaine.keegan@nrc.gov. Comments will not be edited to remove any identifying or contact information. Do not include any information in comments that you do not want publicly disclosed.
Public Participation Themes:
The only commenter during the meeting was Mr. Couhig, the Parish President of West Feliciana Parish. He stated: (1) he is in favor of license renewal, (2) he is concerned with ensuring his Parish has adequate funding for nuclear emergency preparedness exercises, and, (3) he wants to understand the long-term plan for spent fuel stored at RBS.
A complete accounting of the comments provided can be found in the meeting transcripts which are available in the NRCs ADAMS public electronic reading room under the accession numbers listed below, http://www.nrc.gov/reading-rm/adams.html.
Action Items/Next Steps:
NRC staff will address the comments provided during this meeting as part of the LRA review process for RBS. A record of how each comment was addressed will be included in the Scoping Summary Report or draft SEIS.
Attachments:
o Meeting description and agenda - ML17249A247 o NRC staff presentation - ML17293A503 o Meeting transcript - ML17293A547
Public Participation Themes:
The only commenter during the meeting was Mr. Couhig, the Parish President of West Feliciana Parish. He stated: (1) he is in favor of license renewal, (2) he is concerned with ensuring his Parish has adequate funding for nuclear emergency preparedness exercises, and, (3) he wants to understand the long-term plan for spent fuel stored at RBS.
A complete accounting of the comments provided can be found in the meeting transcripts which are available in the NRCs ADAMS public electronic reading room under the accession numbers listed below, http://www.nrc.gov/reading-rm/adams.html.
Action Items/Next Steps:
NRC staff will address the comments provided during this meeting as part of the LRA review process for RBS. A record of how each comment was addressed will be included in the Scoping Summary Report or draft SEIS.
Attachments:
OFFICE TR:MENB:DMLR PM:MRPB:DMLR BC:MRPB:DMLR NAME RHoffman DDrucker DDrucker DATE 10/19/17 10/19/17 10/19/17 OFFICE RECORD COPY
DISTRIBUTION:
Listserv David Drucker U.S. Nuclear Regulatory Commission (NRC)
William Burton NRC Ben Beasley NRC Emanuel Sayoc NRC Jeff Sowa NRC Brian Parks NRC Bob Hoffman NRC George Wilson NRC Kevin Couhig Parish President of West Feliciana Parish JiYoung Wiley Louisiana Department of Environmental Quality Cleve Coates Resident Lacey Coates Resident Alyson Coates Entergy Mark Runion Entergy Tom Broussard Entergy Tim Schenk Entergy Garry Young Entergy Rick Buckley Entergy Mandy Halter Entergy Marvin Chase Entergy Bill MacGuire Entergy Erin Gryniak Entergy