ML18032A754

From kanterella
Jump to navigation Jump to search
NRC Supplemental Inspection Report and Assessment Follow-Up Letter; 05000397/2017011
ML18032A754
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/30/2018
From: Heather Gepford
NRC/RGN-IV/DRS/PSB-2
To: Reddemann M
Energy Northwest
References
EA-17-028 IR 2017011
Download: ML18032A754 (19)


See also: IR 05000397/2017011

Text

January 30, 2018

EA-17-028

Mr. Mark E. Reddemann

Chief Executive Officer

Energy Northwest

P.O. Box 968 (Mail Drop 1023)

Richland, WA 99352-0968

SUBJECT: COLUMBIA GENERATING STATION - NRC SUPPLEMENTAL INSPECTION

REPORT AND ASSESSMENT FOLLOW-UP LETTER; 05000397/2017011

Dear Mr. Reddemann:

On December 1, 2017, the United States Nuclear Regulatory Commission (NRC) completed a

supplemental inspection using NRC Inspection Procedure 95001, Supplemental Inspection

Response to Action Matrix Column 2 Inputs. On December 19, 2017, the NRC inspection team

discussed the results of this inspection with you and other members of your staff. The results of

this inspection are documented in the enclosed report.

The NRC performed this inspection to review your stations actions in response to a White

finding in the Public Radiation Safety cornerstone which was documented in NRC Inspection

Report 05000397/2016009, dated April 10, 2017, (Agencywide Documents Access and

Management System (ADAMS) Accession No. ML17100A499), and finalized in a Notice of

Violation letter to you from Kriss Kennedy, Regional Administrator, dated July 16, 2017

(ADAMS Accession No. ML17187A364). On September 26, 2017, Mr. W. G. Hettel,

Vice President, Operations, informed the NRC that Columbia Generating Station was ready for

the supplemental inspection.

The NRC performed this supplemental inspection to determine if (1) the root and contributing

causes for the significant issues were understood, (2) the extent of condition and extent of

cause for the identified issues were understood, and (3) your completed or planned corrective

actions were sufficient to address and preclude repetition of the root and contributing causes.

The NRC determined that the root, contributing, and apparent cause evaluations were

conducted to a level of detail commensurate with the significance of the problems and, taken as

a whole, reached reasonable conclusions as to the root, contributing, and apparent causes of

the event. The NRC also concluded that you identified reasonable and appropriate corrective

actions for each root, contributing, and apparent cause and that the corrective actions appeared

to be prioritized commensurate with the safety-significance of the issues.

After reviewing Columbia Generating Stations performance in addressing the White finding, the

NRC concluded that your actions met the objectives of Inspection Procedure 95001,

Supplemental Inspection Response to Action Matrix Column 2 Inputs.

M. Reddemann 2

Therefore, in accordance with the guidance in Inspection Manual Chapter 0305, Operating

Reactor Assessment Program, the White finding will only be considered in assessing plant

performance for a total of four quarters. Further, the White finding and associated violation will

be closed effective January 1, 2018.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Heather J. Gepford, Ph.D., CHP

Chief, Plant Support Branch 2

Division of Reactor Safety

Docket No. 50-397

License No. NPF-21

Enclosure:

Inspection Report 05000397/2017011

w/Attachment: Supplemental Information

cc: Electronic Distribution

ML18032A754

SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: HGepford Yes No Publicly Available Sensitive NRC-002

OFFICE HP:DRS/PSB2 HP:DNMS BC:PBA BC:DRS/PSB2

NAME JODonnell PHernandez MHaire HGepford

SIGNATURE /RA/ /RA/ /RA/ /RA/

DATE 1/29/18 1/29/18 1/29/18 1/30/18

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000397

License: NPF-21

Report: 05000397/2017011

Licensee: Energy Northwest

Facility: Columbia Generating Station

Location: North Power Plant Loop

Richland, WA 99354

Dates: November 28 through December 19, 2017

Inspectors: P. Hernandez, Health Physicist

J. ODonnell, CHP, Health Physicist

Approved Heather Gepford, Ph.D., CHP

By: Chief, Plant Support Branch 2

Division of Reactor Safety

Enclosure

SUMMARY

Inspection Report (IR) 05000397/2017011; 11/28/2017 - 12/19/2017; Columbia Generating

Station; Supplemental Inspection - Inspection Procedure 95001

This report covers a one-week announced supplemental inspection of a White finding in the

Public Radiation Safety Cornerstone. The inspection was conducted by two health physics

inspectors from the NRC Region IV office. The NRC's program for overseeing the safe

operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor

Oversight Process.

The NRC staff performed the supplemental inspection in accordance with Inspection

Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 Inputs,

to assess the licensees evaluation associated with the failure to ensure that the contents of a

radioactive waste container did not exceed the radiation level requirements for shipping. The

NRC staff previously characterized this issue as having low to moderate safety significance

(White), as documented in NRC IR 05000397/2017009.

During this supplemental inspection, the inspectors determined that, taken as a whole, the

licensee performed an adequate evaluation of the causes of the self-revealed failure to comply

with the external radiation limits for shipping radioactive materials, which occurred for a

shipment of radioactive waste to the US Ecology waste disposal facility. The licensee identified

the primary root cause of the issue to be that Columbia Generating Station management did not

have the organizational alignment in place that would ensure proper decision-making, effective

supervisor oversight, and programmatic validation to assure execution of critical radioactive

waste packaging and shipping activities in accordance with regulations. The licensee has taken

corrective actions to address the organizational alignment to ensure proper decision-making,

effective supervisor oversight, and programmatic validation of radwaste packaging and shipping

activities.

Given the licensees acceptable performance in evaluating the cause of a package exceeding

the radiation levels for shipping low specific activity material, the White finding associated with

this issue will only be considered in assessing plant performance for a total of four quarters in

accordance with the guidance in Inspection Manual Chapter 0305, Operating Reactor

Assessment Program. Inspectors will review the licensees implementation of corrective

actions during a future inspection.

No findings were identified.

2

REPORT DETAILS

4. OTHER ACTIVITIES

Cornerstone: Public Radiation Safety

4OA4 Supplemental Inspection (95001)

.01 Inspection Scope

The NRC staff performed this supplemental inspection in accordance with Inspection

Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2

Inputs, to assess the licensees evaluation of one White finding in the Public Radiation

Safety Cornerstone. The inspection objectives were to:

  • Provide assurance that the root and contributing causes of significant performance

issues were understood.

  • Provide assurance that the extent of condition and extent of cause of significant

performance issues were identified.

  • Provide assurance that corrective actions taken to address and preclude repetition of

significant performance issues were prompt and effective.

  • Provide assurance that corrective plans directed prompt actions to effectively

address and preclude repetition of significant performance issues.

Columbia Generating Station entered the Regulatory Response Column (Column 2)

of the NRCs Action Matrix in the first quarter of 2017 as a result of a White

(low-to-moderate safety significance) finding in the Public Radiation Safety Cornerstone.

The finding was associated with the November 9, 2016, shipment of radioactive material

as low specific activity (LSA) material that exceeded the LSA external dose rate limit of

1.0 rem/hr at 3 meters from the unshielded material. Specifically, the licensee

transported a package as LSA material with an external radiation level of 2.1 rem/hr at a

distance of 3 meters from the unshielded material. The finding was characterized as

having low to moderate safety significance (White) using the NRC Inspection Manual

Chapter 0609, Appendix M, Significance Determination Process Using Qualitative

Criteria. This issue was documented in NRC Inspection Reports 05000397/2016009

and 05000397/2017009.

The licensee staff informed the NRC by letter on September 26, 2017, of their readiness

for the supplemental inspection. In preparation for this inspection, the licensee

performed a root cause evaluation documented in Action Request (AR) 360236,

Radwaste Liner Dose Rate Exceeds 1 rem/hr at 3 meters, to identify weaknesses that

existed in various organizations and processes. The licensee indicated that the final

version, Revision 7, dated November 16, 2017, documented their conclusions.

The inspectors reviewed several revisions of the root cause evaluation, an apparent

cause evaluation (AR 357593), related self-assessments, and supplemental information

that the licensee provided. The inspectors reviewed corrective actions that were taken

or planned to address the identified causes. The inspectors conducted interviews and

3

had discussions with licensee personnel to determine if the root cause and contributing

causes of the issue were understood, and that corrective actions taken or planned were

appropriate to address the causes and preclude repetition. The inspectors also

reviewed related issues that had been identified in the past where the corrective actions

were not implemented correctly to understand process failures and assure that the

proposed corrective actions would be effective.

.02 Evaluation of the Inspection Requirements

02.01 Problem Identification

a. Determine that the licensees evaluation documents who identified the issue and the

conditions under which the issue was identified.

The root cause evaluation documented that the failure to transport LSA material with

external dose rates not exceeding an external radiation level of 10 mSv/hr (1 rem/hr) at

3 meters (10 feet) from the unshielded material was self-revealed on November 9, 2016,

as a result of US Ecology, the low-level radwaste disposal facility, validating the

manifested dose rates during package receipt. US Ecology personnel removed the liner

containing the radioactive material from the shipping cask to conduct radiation survey

measurements. US Ecology personnel measured contact dose rates of 30 rem/hr and

90 rem/hr on opposite sides of the liner, in contrast to the documented dose rate of

11.8 rem/hr. The shipment was rejected and returned to Columbia Generating

Station (CGS) the same day. The licensee performed radiation surveys at 3 meters

from the unshielded material on January 13, 2017, and recorded dose rates of up to

2.1 rem/hr.

The inspectors determined that the self-revealed nature, as well as the conditions under

which the issue was identified, were documented in the licensees evaluation.

b. Determine that the evaluation documents how long the issue existed and prior

opportunities for identification.

The problem statement for the root cause evaluation was defined as the licensees

transport of a radioactive waste container that exceeded the external radiation dose rate

limit required by the Department of Transportation. Based on this problem statement,

the licensee concluded that the issue existed only during the time that the shipment was

in transit on public roads from CGS to US Ecology and back to CGS on November 9,

2016. The inspectors concluded that the licensees determination accurately

documented the duration of the violation of regulatory requirements.

The root cause evaluation discussed prior opportunities for the licensee to correct or

prevent the violation. Examples of these include:

  • On October 20, 2016, the dose rates measured on the outside of the shipping

cask were significantly higher than the regulatory limits for shipping.

  • On November 5, 2016, after removing some items, external dose rates on the

cask were still above the limit to ship as an open transport, so a decision was

made to build a cage around the cask to prevent access to the elevated dose

rates.

4

  • On November 8, 2016, Radiation Protection was uneasy with the shipment, but

the decision to proceed was based on the high confidence that the shipping

specialist had in the shipment meeting all the requirements.

  • On November 8, 2016, the vendor shipping summary calculated dose rate of

11.8 rem/hr for the liner was not validated. The shipment left site on

November 9, 2016, without a direct survey of the liner.

The inspectors determined that the licensee documented how long the issue existed and

prior opportunities to identify it.

c. Determine that the evaluation documents the plant-specific risk consequences, as

applicable, and compliance concerns associated with the issue.

The inspectors determined that this incident had no impact on the core damage

frequency or large early release frequency. Therefore, the documentation of the

plant-specific risk consequences was not applicable.

The causal evaluation discussed how the noncompliance with regulations led to the

White violation (low to moderate safety significance) issued by the NRC for exceeding

the radiation limit for this shipment type and categorized the issue as a significant

condition adverse to quality. In addition to the NRC violation, the licensee received

two violations for noncompliance with the Washington Administrative Code for this

shipment. The immediate consequence of these violations was the suspension of the

licensees permit to dispose low-level radioactive waste at the disposal site operated by

US Ecology. Additional consequences described were increased radiation exposure risk

to the public and decreased NRC and public confidence in the licensees ability to safely

control its radioactive material.

The inspectors concluded that the licensee appropriately documented the risk

consequences and compliance concerns associated with the issue.

d. Findings

No findings were identified.

02.02 Root Cause, Extent of Condition, and Extent of Cause Evaluation

a. Determine that the issue was evaluated using a systematic methodology to identify the

root and contributing causes.

The licensee used the following systematic methods and tools to complete the root

cause analysis AR 360236, Revision 7:

  • Event and Causal Factors Chart
  • Comparative Timeline
  • Human Performance Evaluation Worksheet
  • Nuclear Safety Culture Evaluation Worksheet

5

Predecessor causal evaluations, as reviewed by inspectors, used a variety of systematic

methodologies to complete their analyses, including some of the above and the following

methods and tools:

  • Event Timeline
  • Barrier Analysis
  • Change Analysis
  • WHY Staircase

The inspectors determined that the licensee evaluated the issue using systematic

methodologies to identify root and contributing causes.

b. Determine that the root cause evaluation was conducted to a level of detail

commensurate with the significance of the issue.

The licensees final root cause evaluation included a timeline of events and an event and

causal factor chart. The licensees root cause evaluation documented the root cause of

the issue to be the stations management did not have the organizational alignment in

place to ensure proper decision-making, effective supervisor oversight, and

programmatic validation to assure execution of critical rad waste packaging and shipping

activities in accordance with regulations. The licensee determined the contributing

cause to be that chemistry management did not implement effective corrective actions to

address precursor organizational and programmatic issues within the radwaste shipping

program that were identified by the stations performance improvement and oversight

programs.

The licensee conducted other causal evaluations prior to the final version, Revision 7.

These included an apparent cause evaluation (AR 357593, Radioactive Waste Disposal

Container has Higher Dose Rates than Anticipated, Revision 00, dated December 12,

2016) and a prior version of the root cause evaluation (AR 360236, Incorrect Container

for Radioactive Waste Shipment 16-40, Revision 3a, dated April 17, 2017), both of

which had problem statements that were different from the final version. The inspectors

concluded that the evolution of the problem statement was linked to changes in the

licensees understanding of the issue, beginning with the occurrence of the event and

followed by issuance of the special inspection report with the apparent violation and the

subsequent issuance of the Notice of Violation. The inspectors noted that the revisions

of AR 360236 preceding 3a and 7, respectively, were not substantively different from the

revisions reviewed and discussed.

In addition to these causal evaluations, the licensee conducted self-assessments

focused on the radioactive waste program and the sites readiness for this inspection.

Through these various assessments, causal evaluations, and other corrective action

processes, the licensee identified a number of issues with their radioactive waste

program, as a whole, and several that led to or contributed to the White violation. These

issues included insufficient procedures to implement spent fuel pool cleanup (SFPCU)

activities, flawed waste characterization based on inaccurate survey documentation, and

lack of formal SFP filter management.

6

The licensee found that the circumstances that led to the incident were more complex

than could be addressed by a single, concise statement or single cause evaluation.

The inspectors determined that when these cause evaluations and assessments were

considered as an all-inclusive product, a more complete understanding of the causes

leading to the incident was achieved.

Based on the extensive work performed for this root cause evaluation and associated

with this root cause evaluation, the inspectors concluded that the root cause evaluation

was conducted to a level of detail commensurate with the significance of the problem.

c. Determine that the root cause evaluation included a consideration of prior occurrences

of the issue and knowledge of operating experience.

The final root cause evaluation included a brief review of external operating experience.

The review of operating experience focused on the key words high dose rates,

shipment, and shipping; four events were identified. The licensee determined that these

events were not related to poor organizational alignment, therefore were not applicable.

The inspectors concluded that the licensee had determined the root cause and then

performed the operating experience evaluation, which was contrary to the expectation

that the operating experience inform the root cause determination.

The final root cause evaluation stated that applicable internal operating experience was

included in the analysis and listed in the references section. There was not a discussion

of internal operating experience in the report or attachments, so the inspectors used the

references and operating experience information provided in Revision 3a of AR 360236

which included an evaluation of internal as well as external operating experience.

In Revision 3a of AR 360236, the licensee stated that the review of internal operating

experience identified a range of weaknesses related to radwaste shipping, handling, and

documentation that had been identified in self-assessments and internal audits over the

prior 2-year period. The licensee recognized that corrective actions taken to address

these issues had not been effective, as evidenced by the continued declining

performance culminating in the shipping violation. These radwaste shipping and

handling issues represented missed opportunities for the station to restore the program

to satisfactory performance. The inspectors noted that some of these items included

previous shipments that had been rejected by US Ecology.

The licensee determined that the external operating experience that applied represented

missed opportunities due to the similarity of the CGS event. The operating experience

referenced a resin shipment that was not fully characterized or surveyed prior to

shipment. The review for this operating experience performed by the licensee stated

that Columbia had procedures in place that required every waste stream going into a

liner to be sampled and used in the characterization and that liners to be shipped are

rigorously surveyed prior to shipment. The gap was identified in this situation because

the SFPCU waste was previously surveyed and could not be sampled, the waste

characterization was performed off-site, and it was an infrequent evolution not performed

by or under the oversight of Radiation Protection.

Based on the licensees detailed evaluation and conclusions, the inspectors determined

that the licensees root cause evaluation included consideration of prior occurrences of

the problem and knowledge of operating experience.

7

d. Determine that the root cause evaluation addressed the extent of condition and the

extent of cause of the issue.

The licensees evaluation considered the extent of condition associated with an offsite

shipment of LSA radioactive material that exceeded the external radiation and dose rate

limits for a Type A container required by Department of Transportation (DOT)

regulations in 49 CFR 173.427(a)(1). The licensee determined that the underlying issue

was not limited to LSA material. Similar activities that could be vulnerable to the same

defect included waste shipments where transport limits could be exceeded, waste

shipments where other regulations could be challenged, hazardous material shipments,

and other non-waste radioactive material shipments. Therefore, the licensee expanded

the extent of condition to include all radioactive shipments. The licensee determined

that non-radioactive hazardous material shipments should not be included in the extent

of condition because hazardous material was transferred to another party onsite who

was then responsible for its removal. The licensee concluded that the corrective actions

implemented for the violation would effectively address similar shipping errors for all

radioactive material shipments.

The licensees evaluation also considered the extent of cause associated with the

organizational alignment to ensure proper decision-making, effective supervisor

oversight, and programmatic validation. The licensee stated that they looked at each

piece individually and in combination to determine other areas that could result in a

future consequential event. The licensee focused on was areas with organizational

alignment in which a specialized position lacked knowledgeable supervision or faced

other programmatic challenges to their decision-making. The licensee reviewed

departments including Operations, Engineering, Maintenance, Emergency

Preparedness, Quality, and Training. The extent of cause contacted nearly every

department to identify circumstances for the vulnerability. Most either did not have the

vulnerability or had identified it previously and were addressing it. The one department

that had the same potential that had not been addressed was Technical Services

Engineering. This has been entered into the corrective action program.

The inspectors concluded that the licensees root cause evaluation addressed the extent

of condition and the extent of cause of the issue.

e. Determine that the root cause, extent of condition, and extent of cause evaluations

appropriately considered safety culture traits.

The licensee demonstrated the complexity of the issue through their evaluation of the

safety culture traits associated with the event. The safety culture assessment performed

for the final root cause evaluation identified four attributes that contributed to the event.

Those attributes were:

  • Leadership Safety Values and Actions attribute of Resources (LA.1): This

related to the failure to select a supervisor with the appropriate skill set to

oversee the radwaste shipping activities.

8

  • Decision-Making attribute of Conservative Bias (DM.2): This related to the

failures in decision-making to 1) not use a Type B cask, 2) construct a fence

around the shipment, and 3) not survey the liner or cask prior to shipment.

  • Personal Accountability attribute of Standards (PA.1): This related to the failures

of 1) management to ensure organizational alignment for radwaste activities,

2) the chemistry supervisor to meet expectations to monitor and enforce

standards of behavior, and 3) the radwaste transportation specialist to be trained,

monitored, or coached to the expected behaviors.

  • Problem Identification and Resolution attribute of Resolution (PI.3): This related

to the failure to take effective and timely corrective actions to correct

organizational weaknesses that were identified prior to the event.

The first three safety culture aspects were addressed by the Revision 7 root cause and

corrective action to prevent recurrence actions. The fourth safety culture aspect was

addressed by the contributing cause and its associated corrective actions.

(See Section 02.03a.)

The inspectors determined that the licensees root cause, extent of condition, and extent

of cause evaluations appropriately considered safety culture traits.

f. Findings

No findings were identified.

02.03 Corrective Actions Taken and Planned

a. Determine that appropriate corrective actions are specified for each root and contributing

cause.

In the final version of the root cause evaluation, the licensee identified the following root

cause: Station management did not have the organizational alignment in place that will

ensure proper decision-making, effective supervisor oversight, and programmatic

validation to assure execution of critical radwaste packaging and shipping activities in

accordance with regulations.

As corrective actions, the licensee realigned the Chemistry/Radiation Protection

organization to include oversight positions knowledgeable in radioactive shipments.

Specifically, for both the Radiation Protection Manager and the individual responsible for

oversight of the Radioactive Waste Transportation Specialist, the requirement for

knowledgeable oversight was added to Procedure SWP-RPP-01, Radiation Protection

Program. Position descriptions were modified to include the required knowledge.

Procedural requirements to validate dose rates documented on shipping manifests via

either direct surveys or shielding calculations were added to applicable procedures.

Finally, the lessons learned from this event were added to Manager/Supervisor

SOER 10-2 training.

9

The licensee also identified a contributing cause: Chemistry management did not

implement effective corrective actions to address precursor organizational and

programmatic issues within the radwaste shipping program.

As a corrective action, the licensee updated performance appraisals for

Chemistry/Radiation Protection management and supervision to focus on increasing

proficiency in implementing corrective actions. The licensee will also conduct a

workshop to align Chemistry/Radiation Protection management on how to implement

proper corrective action to address organizational and programmatic issues.

In Revision 3a of the root cause evaluation (AR 360236), the licensee identified the

following root cause: Station procedures to implement SFPCU activities and the

associated radioactive waste surveys, processing, and shipping activities are not

sufficient to ensure compliance with all requirements. The contributing causes were

identified to be: (1) Some key decisions made during the SFPCU project lacked rigorous

challenge and vetting and were not conservative, and (2) Lack of adequate

management/supervisor oversight for SFPCU project and RadWaste processing and

shipping program.

As corrective actions, the licensee inventoried and mapped the remaining Tri Nuclear

filters in the spent fuel pool, conducted a self-assessment of the radwaste shipping and

handling program, began having the Radiation Protection Manager review all radwaste

shipments to validate the surveys and characterization, and developed a procedure for

spent fuel pool clean-up activities integrated with radwaste shipping and handling

In the apparent cause evaluation (AR 357593), the licensee identified the following

apparent cause: Survey documentation was inaccurately recorded and communicated

to the characterization vendor which led to errors in the calculated dose rates on the

characterization used to ship the radioactive waste disposal container. The contributing

causes were identified to be: (1) A formalized process and plan specific to Tri Nuclear

filter management, tracking, and disposal was not developed, (2) Radiological conditions

on the disposal container were not verified and validated prior to shipment, and

(3) Characterization results provided by the vendor based on CGS data were not verified

or validated.

As corrective actions following the event and apparent cause evaluation, the licensee

suspended radwaste shipping activities, conducted an event investigation, benchmarked

another station on Tri Nuclear filter handling and tracking in the spent fuel pool, created

a new procedure for spent fuel pool clean-up container loading, revised the procedure

for processing of irradiated nonfuel material to include Tri Nuclear filters, labeled filter

cans in the spent fuel pool, and evaluated performance gaps for culpability.

The inspectors questioned whether the apparent, root, and contributing causes identified

in the various revisions of the cause evaluations were going to continue to be addressed

and corrected. The licensee stated that all issues identified in this process would be

corrected and that the corrective actions for each of the cause evaluations were being

tracked to completion.

The inspectors determined that the corrective actions were appropriate and addressed

the root and contributing causes identified in each of the licensees causal evaluations.

10

b. Determine that corrective actions have been prioritized with consideration of risk

significance and regulatory compliance.

The licensee categorized AR 360236 as a Severity Level A (high risk) action request,

which requires a root cause evaluation. In accordance with Procedure SWP-CAP-01,

Corrective Action Program, Revision 37, the AR received a significant condition

adverse to quality (SCAQ) priority. This priority requires the issue to be addressed by a

higher level of corrective actions (i.e., corrective actions to preclude repetition known as

CAPRs). The procedure stated that CAPRs should be completed within 180 days.

The inspectors determined that the corrective actions were prioritized with the

appropriate consideration of significance and regulatory compliance.

c. Determine that corrective actions taken to address and preclude repetition of significant

performance issues are prompt and effective.

The licensee promptly initiated corrective actions as issues were identified throughout

the performance of the cause evaluations. The licensee also initiated corrective actions

that were identified in the apparent cause evaluation and early root cause evaluation

revisions prior to completing the final evaluation and as they identified related issues

throughout the process.

The inspectors determined that the corrective actions taken to address and preclude

repetition of the performance issues were prompt and should be effective.

d. Determine that a corrective action plan and schedule has been established for

implementing and completing the corrective actions.

The inspectors discussed the corrective action plan with the licensee. Some of the due

dates were captured in the final root cause evaluation revision; however, many of the

due dates for corrective actions not directly mentioned in the evaluation were spread

across other performance improvement tools. Specifically, the licensee used a

performance improvement database to track corrective actions. The many facets of the

causal evaluation, including previous revisions, assessments, work orders, and actions,

are being tracked with the AR 360236 identifier with cross-references to other

associated action requests. The licensees database tracks all the associated actions,

due dates, responsible parties, and effectiveness reviews to be performed.

The inspectors determined that a schedule had been established for implementing and

completing the corrective actions.

e. Determine that quantitative or qualitative measures of success have been developed for

determining the effectiveness of the corrective actions to preclude repetition.

As documented in the final root cause evaluation, the licensee established measures for

determining the effectiveness of the corrective actions. These measures included the

following:

  • The trained and knowledgeable Radiation Protection Manager will review

shipment manifests and paperwork to identify deficiencies. Success is defined

as the documents containing less than 5 percent deficiencies.

11

  • A self-assessment of the radwaste shipping and handling program corrective

actions will be performed after an acceptable implementation period with a due

date of April 30, 2018. Areas of focus include compliance with burial site

requirements (i.e., no loss of burial site privileges) and zero regulatory

noncompliance issues related to radwaste shipments.

The effectiveness reviews have been added into the corrective action program as

corrective action items to ensure they are performed.

The inspectors determined that quantitative and qualitative measures of success had

been developed for determining the effectiveness of the corrective actions to preclude

repetition.

f. Determine that the corrective actions planned or taken adequately address a Notice of

Violation (NOV) that was the basis for the supplemental inspection.

During this inspection, the inspectors determined that the corrective actions taken and

planned to correct the identified causes adequately addressed the NOV.

g. Findings

No findings were identified.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On December 1, 2017, the inspectors conducted a technical debrief for Mr. M. Reddemann,

Chief Executive Officer, and other members of the licensee staff. The licensee confirmed that

any proprietary information reviewed by the inspectors had been returned or destroyed.

On December 19, 2017, the inspectors presented the inspection results to Mr. M. Reddemann,

Chief Executive Officer, and other members of the licensee staff. The licensee acknowledged

the issues presented.

12

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

S. Brush, Health Physics Planner, Chemistry/Radiation Protection

M. Davis, Manager, Chemistry/Radiation Protection

K. Gillard, Analyst, Chemistry/Radiation Protection

D. Gregoire, Manager, Regulatory Affairs

T. Hedges, Chemistry/Radiation Support Supervisor, Chemistry/Radiation Protection

G. Hettel, Vice President, Operations

J. Houston, Radwaste Transportation Specialist, Chemistry/Radiation Protection

T. McNabb, Health Physics Planner, Chemistry/Radiation Protection

S. Nappi, Assistant to the Vice President, Operations

M. Nolan, Senior Radwaste Transportation Specialist, Chemistry/Radiation Protection

T. Parmalee, Compliance Engineer, Licensing and Regulatory Affairs

M. Reddeman, Chief Executive Officer

R. Sanker, Radiological Support Supervisor, Chemistry/Radiation Protection

M. Shobe, Chemistry Specialist IV, Chemistry/Radiation Protection

J. C. Smith, Radiological Operations Supervisor, Chemistry/Radiation Protection

C. Smoot, Supervisor, Human Performance/Industrial Safety

D. Wolfgramm, Supervisor, Regulatory Compliance

NRC Personnel

G. Kolcum, Senior Resident Inspector

L. Brandt, Resident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Closed

05000397/2016009-01 VIO Shipment of a Type B Quantity of Radioactive Material in a

Type A Package (Section 4OA4)

Attachment

LIST OF DOCUMENTS REVIEWED

Section 4OA4: Supplemental Inspection (95001)

Procedures

Number Title Revisions

SWP-RMP-01 Radioactive Waste Management Program 4

PPM 1.11.15 Control of Radioactive Material 11, 12, 13

PPM 6.1.1 Spent Fuel Pool Inventory 9, 10

PPM 11.2.2.12 Radiological Risk Assessment and Management 8

PPM 11.2.13.1 Radiation and Contamination Surveys 36, 37

PPM 11.2.23.1 Shipping Radioactive Materials and Waste 18, 19

PPM 11.2.23.1 Shipping Radioactive Materials and Waste 19

PPM 11.2.23.2 Computerized Radioactive Waste and Material 20, 21

Characterization

PPM 11.2.23.9 Packaging, Transportation and Disposal of 0, 1

Radioactive Waste at the US Ecology, Richland

Radioactive Waste Disposal Facility

PPM 11.2.23.45 Management of Spent Fuel Pool Filters, Irradiated, 0

and Non-Irradiated Items to Support Packaging,

Transportation, and Disposal as Low-Level

Radwaste

CDM-01 Cause Determination Manual 16

SWP-CAP-01 Corrective Action Program 36, 37

GBP-HR-48 Knowledge Retention 0

Audits and Self-Assessments

Number Title Date

361427 Peer Self-Assessment Report February 2, 2017

Radioactive Waste Program

AU-RP-RW-15 Quality Services Audit Report - Radiation November 5, 2015

Protection and Process Controls Program

AR-SA 305111 Focused Self-Assessment Report - Radioactive June 19, 2015

Solid Waste Processing, Radioactive Material

Handling, Storage, and Transportation

AR-SA 337267 Snapshot Self-Assessment Report - Radioactive June 28, 2017

Waste Management and Transportation

A-2

Audits and Self-Assessments

Number Title Date

AR-SA 369058 Focused Self-Assessment Report - Rad-waste September 11, 2017

Shipping 95001 Preparatory Assessment

AR-SA 361427 Peer Self-Assessment Report - Radioactive Waste February 2, 2017

Program

SR-17-12 Radwaste Program Assessment Report April 27, 2017

SR-17-09 Radwaste Processing and Shipping August 23, 2017

Root Cause Evaluations

AR Number Title Revision

Date

360326 RadWaste Liner dose rate exceeds 1 Rem/hr at Rev. 7

3 meters November 16, 2017

360326 RadWaste Liner dose rate exceeds 1 Rem/hr at Rev. 6

3 meters October 30, 2017

360326 Incorrect Container for Radioactive Shipment 16-40 Rev. 3a

April 26, 2017

Apparent Cause Evaluations

AR Number Title Revision

Date

353427 Trend: Radioactive Waste Packing/Shipping Issues Rev. 1

October 20, 2016

352217 RW Box Sent to Disposal Site with Greater than September 12, 2016

15% Voids

357593 Radioactive Waste Disposal Container has Higher December 12, 2016

Dose Rates than Anticipated

369215 Liner 17-084-OT Shipped for Disposal with Incorrect August 29, 2017

Manifest

Action Requests (AR)

338421 352217 357593 360148

360572 369215 370193 371583

Work Orders (WOs)

Number Title Date

02070690 Spent Fuel Pool Clean Up Project Plan February 15, 2016

A-3

Work Orders (WOs)

Number Title Date

02104894 Move SFPCU Liner from Reactor Building Truck December 29, 2016

Bay to Radwaste

02070690 Perform Spent Fuel Pool Cleanup in FY16 February 9, 2016

02095196 Perform Spent Fuel Pool Cleanup in FY17 September 28, 2016

Miscellaneous Documents

Number Title Date

RCE 360326 Roadmap November 30, 2017

Chemistry/Radiation Protection Organization Chart November 28, 2017

WAC 246-249-090 Transfer for Disposal and Manifests November 9, 2017

Excellence Model Handbook 2016

A-4