GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-170

From kanterella
Jump to navigation Jump to search
Supplement to Reply to a Notice of Violation: EA-21-170
ML23208A331
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/27/2023
From: David Brown
Energy Northwest
To:
Office of Nuclear Reactor Regulation, NRC Region 4, Document Control Desk
References
GO2-23-093
Download: ML23208A331 (1)


Text

David P. Brown ENERGY Site Vice President P.O. Box 968, PE23 Richland, WA 99352-0968 NORTHWEST Ph. 509-377-8385 F. 509-377-4150 dpbrown@energy -northwest.com

July 27, 2023 GO2 093 10 CFR 2.201

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555- 0001

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 SUPPLEME NT TO REPLY TO A NOTICE OF VIOLATION ; EA 170

References:

(1) Letter from D Brown (Energy Northwest) to US Nuclear Regulatory Commission, "Reply to a Notice of Violation; EA 170,"

ML23193 B032, GO2-23- 090, dated July 12, 2023.

(2) Letter from R Lewis (NRC) to R Schuetz (Energy Northwest),

C olumbia G enerating Station - F inal Significance Determination of a White Finding, N otice of Violation and F ollow-Up Assessment Letter; NRC Inspection R eport 05000397/2023090, ML 23111A 237, dated June 1, 2023.

Dear Sir or Madam:

Energy Northwest is hereby submitting this supplem ent to its July 12, 2023, letter (Reference 1) in accordance with the July 6, 2023, telecon with U.S. Nuclear Regulatory Commission ( NRC) Region IV.

This response contains additional information not availa ble at the time of the initial letter pertaining to the second and third vio lations noted in the NRC letter date d June 1, 2023 (Reference 2). The responses for the se cond and third violations, described in the enclosure, include the reason for the violation, the corrective steps that have been taken and the results achieved, the corrective steps that will be taken, and the date when full compliance was achieved.

There are no commitments being made to the NRC by this letter. Should you have any questions, please contact IR Bitner, Regulatory Compliance Supervisor, at (509) 377-4204.

GO2-23-090 Page 2 of 2

Executed this17t';).. day of J"\\2\\~, 2023

David P. Brown Site Vice President

Enclosure:

Supplement to Reply to EA-21-170 Notice of Violation

cc: NRC Director-Division of Operating Reactor Safety, Region IV NRC Region IV Administrator NRC NRR Project Manager NRC Resident lnspector/988C NRC Enforcement, Region IV CD Sonoda - BPA/1399 w/o enclosure GO2-23-093 Enclosure

Columbia Generating Station - Energy Northwest Supplement to Reply to EA-21-170 Notice of Violation GO2-23-093 Enclosure Page 2 of 5

As noted in Energy Northwests July 12, 2023, letter to the U.S. Nuclear Regulatory Commission (NRC) (Reference 1), Energy Northwest accepts these violations, has taken prompt action to return to f ull compliance and has implemented comprehensive corrective actions for long-term sustained compliance related to the violation of 10 CFR 20.1701.

The root cause evaluation conducted to better evaluate the violations of Technical Specification 5.7.2.b and 10 CFR 20.1501(a)(2) was completed and required responses for these two violations are show below.

NRC letter dated J une 1, 2023, (Reference 2) cited three violations of NRC requirements.

A. Violation of 10 CFR 20.1701

The reason for the violation, the corrective steps that have been taken and the results achieved, the corrective steps that will be taken, and the date when full compliance was achiev ed for this violation were submitted as part of the July 12, 2023, letter from Energy Northwest to the NRC (Reference 1) and therefore will not be duplicated as part of this supplement.

B. Violation of Technical Specification 5.7.2.b Notice of Violation

Technical Sp ecification 5.7.2.b requires, in part, that access to, and activities in, each high radiation area with dose rates greater than 1.0 rem/hour at 30 centimeters from the radiation source shall be controlled by means of a radiation work permit.

Radiation work permit 30004732, created to control activities in a Technical Specification 5.7.2.b high radiation area, required, in part, that continu ous Hea lth Physics job coverage is provided when personnel are entering and working i n areas with dose rates greater tha n 0.8 rem/hour.

Contrary to the above, on May 28, 2021, the licensee failed to control the activities in a high radiation area with dos e rates greater than 1.0 rem/hour at 30 centimeters from the radiation source in acc ordance with radiation work permit 30004732. Specifically, the licensee failed to follow radiation work permit 30004732 and provide continuous Health Physics job coverage when personnel entered and worked in an area with dose rates greater than 0.8 rem/hour (i.e.,

1.3 rem/hour at 30 centimet ers from the radiation source). A radiation protection technician, scheduled to provide the continuous Health Physics job coverage, was unable t o physically fit on the work area platform and left the workers unattended in the area. A second radiation protection technician subsequentl y GO2-23-093 Enclosure Page 3 of 5

replaced the original technician as the workers were conducting job activities in the work area.

Reason for Violation

The direct cause identified was i nadequate adherence and implementation of station and department-level instructions, policies, and procedures which resulted in approval and implementation of plans that were not appropriate to support successful performances of infrequently performed activities, were insufficient to mitigate risk, or included error traps.

Additionally, disposition of adverse events by the Radiological Services group (by application of the station corrective action program) was not performed in a manner which facilitated identification and resolution of systemic level shortcomings in station radiological controls.

Radiological Services resources were challenged to ensure correct implementation of planned work in all cases.

Corrective Steps and Results Achieved

Energy Northwest recently completed an additional root cause evaluation as noted in the original response (Reference 1). Additional corrective actions including those to prevent recurrence have been identified below.

Correct ive Steps that Will be Taken Actions to be taken include:

  • Develop and implement a required formal as low as reasonably achievable (ALARA) plan review tool for elevated and high radiological risk activities.
  • Revise Corrective Action program procedures, instructions, and related guidance to preclude use of human error or culpabilit y for root, apparent, and contributin g causes and analytical products.
  • Develop a job familiarization guide (JFG) with specific focus on management of Radiological Services outage resources.

Date of Full Compliance

Full compliance was achieved on May 29, 2021, upon approval of return-to-work criteria.

GO2-23-093 Enclosure Page 4 of 5

C. Violation of 10 CFR 20.1501(a) (2)

Notice of Violation

10 CFR 20.1501(a)(2) re quires, in part, that licensees shall make surveys of areas that are reasonable under the circumstances to evaluate the magnitude and extent of radiation levels; a nd concent rations or quantities of residual radioactivity.

Contrary to the above, on May 27, 2021, the licensee failed to make surveys of areas that were reasonable under the circumstances to evaluate the magnitude and extent of radiation levels; and concentrations or quantities of residual radioactivity. Specifically, the licensee failed to adequately determine the work area radiation levels as documented in survey M-20210528-13, which stated, the survey was not an extensive search for the highest exposure r ate. In addition, the licensee failed t o adequately eval uate the extent of contamination levels on the piping prior to the work activity. The surveys completed prior to the event did not adequately identify work area dose rates and did not identify appropriate contamination levels, resulting in a lower risk rat ing to the job and less rigorous radiological controls for the activity.

Reason for Violatio n The cause identified was ineffective enforcement of station/department standards, policies, and administrative controls, due to inadequate review and approval processes.

Additionally, disposition of adverse events by the Radiological Services group (by application of the station corrective action program) was not performed in a manner which facilitated identi fication and resolution of systemic level shortcomings in station radiological controls.

Radiological Services resources were challenged to ensure correct implementation of planned work in all cases.

Corrective Steps and Results Achieved Energy Northwest recently completed an additional root cause evaluation as noted in the original response (Reference 1). Additional corrective actions including those to prevent recurrence have been identified below.

GO2-23-093 Enclosure Page 5 of 5

Correct ive Step s that Will be Taken

Actions to be taken include:

  • Develop and implement a formal survey review tool required to be completed for approving surveys. Completed reviews should be attached to surveys for periodic quality reviews.
  • Revise Corrective Action program procedures, instructions, and related guidance to preclude use of human error or culpabilit y for root, apparent, and contributing causes and analytical products.
  • Develop a job familiarization guide (JFG) with specific focus on management of Radiological Services outage resources.

Date of Full Compliance Full compliance was achieved on May 29, 2021, upon approval of return-to-work criteria.