ML20302A231

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000397/2020003
ML20302A231
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/28/2020
From: Jeffrey Josey
NRC/RGN-IV/DRP/RPB-A
To: Sawatzke B
Energy Northwest
References
IR 2020003
Download: ML20302A231 (34)


See also: IR 05000397/2020003

Text

October 28, 2020

Mr. Brad Sawatzke

Chief Executive Officer

Energy Northwest

MD 1023

P.O. Box 968

Richland, WA 99352-0968

SUBJECT:

COLUMBIA GENERATING STATION - INTEGRATED INSPECTION

REPORT 05000397/2020003

Dear Mr. Sawatzke:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at Columbia Generating Station. On October 15, 2020, the NRC inspectors

discussed the results of this inspection with Mr. G. Hettel, Chief Nuclear Officer/Vice President

Nuclear Generation, and other members of your staff. The results of this inspection are

documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Both

findings involved violations of NRC requirements. We are treating these violations as non-cited

violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector

at Columbia Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the

NRC Resident Inspector at Columbia Generating Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

B. Sawatzke

2

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Jeffrey E. Josey, Chief

Reactor Projects Branch A

Division of Reactor Projects

Docket No. 5000397

License No. NPF-21

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

Jeffrey

Josey

Digitally signed by

Jeffrey Josey

Date: 2020.10.28

15:52:30 -05'00'

ML20302A231

SUNSI Review

Non-Sensitive

Sensitive

Pu

No

OFFICE

SRI:DRP/A

RI:DRP/A LNM

TL:DRS/IPAT

C:DRS/EB1

C:DRS/EB2

NAME

APatz

LMerker

AAgrawal ANA

VGaddy VGG

NTaylor NHT

DATE

10/22/2020

10/20/2020

10/20/2020

10/20/2020

10/20/2020

OFFICE

C:DRS/RCB

C:DRS/OB

C:DNMS/RxIB

SPE:DRP/A

C:DRP/A

NAME

MHaire

GWerner GEW

GWarnick GGW

HFreeman HAF

JJosey

DATE

10/21/2020

10/20/2020

10/20/2020

10/20/2020

10/28/2020

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000397

License Number:

NPF-21

Report Number:

05000397/2020003

Enterprise Identifier: I-2020-003-0011

Licensee:

Energy Northwest

Facility:

Columbia Generating Station

Location:

Richland, WA

Inspection Dates:

July 01, 2020 to September 30, 2020

Inspectors:

A. Patz, Senior Resident Inspector

C. Roettgen, Senior Resident Inspector

L. Merker, Resident Inspector

N. Greene, Senior Health Physicist

J. ODonnell, Senior Health Physicist

D. Antonangeli, Health Physicist

B. Tharakan, Technical Assistant

Approved By:

Jeffrey E. Josey, Chief

Reactor Projects Branch A

Division of Reactor Projects

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Columbia Generating Station, in

accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Perform an Adequate Radiation Survey to Identify and Control a High Radiation

Area

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Occupational

Radiation Safety

Green

NCV 05000397/2020003-01

Open/Closed

[H.14] -

Conservative

Bias

71124.01

The inspectors reviewed a self-revealed, Green, non-cited violation of 10 CFR 20.1501(a), for

the licensees failure to perform an adequate radiological survey and identify a high radiation

area. Specifically, on May 30, 2019, Radiation Protection personnel were notified by a

radiation worker about an unanticipated self-reading dosimeter dose rate alarm while the

worker was decontaminating equipment within a posted high contamination area (HCA) on the

refuel floor (606-foot elevation of the reactor building). Radiation Protection personnel did not

perform a survey to verify the radiological conditions in the work area and allowed the work to

continue. The workers were later asked to exit the area when it was determined that the work

could not be completed within the allotted dose limit set point.

Failure to Follow ALARA Planning Procedures Resulting in Unplanned Dose on a Work

Activity

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Occupational

Radiation Safety

Green

NCV 05000397/202003-02

Open/Closed

[H.5] - Work

Management

71124.02

The inspectors reviewed a self-revealed, Green, non-cited violation Technical

Specification (TS) 5.4.1 because the licensee failed to follow their as low is reasonably

achievable (ALARA) planning procedures resulting in unplanned dose while performing the

control rod drive mechanism (CRDM) replacement work. Specifically, the licensees

procedure instructed them to obtain data on the actual radiological conditions in the work area

prior to commencement of the job and determine the effective dose rate using corrected

historical data for the current scope and radiological conditions in the radiation work permit

(RWP) planning phase. The licensee initially planned the job for approximately

6.850-person Rem, including under vessel work, whereas the actual dose accrued to

complete the work activity was 10.752-person Rem.

Additional Tracking Items

None.

3

PLANT STATUS

The reactor unit began the inspection period at 40 percent power per economic dispatch. On

July 5, 2020, reactor power was raised to 85 percent power. On July 6, 2020, the reactor was

returned to 100 percent power. On July 7, 2020, reactor power was reduced to 85 percent for a

control rod pattern adjustment and then returned to 100 percent power. On September 15,

2020, plant power was reduced to 81 percent due to a high level trip of feedwater heater 2B with

subsequent trips of feedwater heaters 2C, 3C, 4A, 4B, and 4C. On September 16, 2020, the

reactor was returned to 100 percent power. On September 26, 2020, plant power was reduced

to 80 percent to perform a control rod sequence exchange and maintenance on an adjustable

speed drive channel before returning to 90 percent power; plant power was again reduced to 79

percent to recover the adjustable speed drive channel and then returned to 100 percent power,

where it stayed for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection

activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor

Inspection Program - Operations Phase. The inspectors reviewed selected procedures and

records, observed activities, and interviewed personnel to assess licensee performance and

compliance with Commission rules and regulations, license conditions, site procedures, and

standards. Starting on March 20, 2020, in response to the National Emergency declared by the

President of the United States on the public health risks of the coronavirus (COVID-19), resident

and regional inspectors were directed to begin telework and to remotely access licensee

information using available technology. During this time, the resident inspectors performed

periodic site visits each week, increasing the amount of time on site as local COVID-19

conditions permitted. As part of their onsite activities, resident inspectors conducted plant

status activities as described in IMC 2515, Appendix D; observed risk significant activities; and

completed onsite portions of IPs. In addition, resident and regional baseline inspections were

evaluated to determine if all or portions of the objectives and requirements stated in the IP could

be performed remotely. If the inspections could be performed remotely, they were conducted

per the applicable IP. In some cases, portions of an IP were completed remotely and on

site. The inspections documented below met the objectives and requirements for completion of

the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

High pressure core spray system following annual maintenance on August 3, 2020

(2)

Diesel generator 2 during diesel generator 1 annual maintenance on August 13, 2020

4

(3)

Standby service water system A during standby service water system B annual

maintenance on September 21, 2020

(4)

Reactor core isolation cooling system following annual maintenance on

September 24, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated system configurations during a complete walkdown of

diesel generator 1 following annual maintenance on August 6, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

Fire Area RC-10/U, main control room, on July 14, 2020

(2)

Fire Areas DG-3/2, DG-5/2, and DG-9/2; diesel generator 2 room, diesel oil storage

tank access room, and day tank room; on July 27, 2020

(3)

Fire Area R-3/#, high pressure core spray system pump room, on July 28, 2020

(4)

Fire Area DG-2/1, diesel generator 1 room, on August 4, 2020

(5)

Fire Area RC-3/1, vertical cable chase room, on September 11, 2020

(6)

Fire Areas DG-1/1 and DG-10/#, diesel generator 3 room and deluge valve

equipment room, on September 22, 2020

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated fire brigade performance during an annual fire drill on

August 26, 2020.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated readiness and performance of diesel generator 2 heat

exchangers DCW-HX-1B1 and DCW-HX-1B2 on September 30, 2020.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1)

The inspectors observed and evaluated licensed operator performance in the control

room during reactor power changes for an unexpected loss of feedwater level

controller 5A on September 15, 2020, and to perform a control rod sequence

exchange and maintenance on an adjustable speed drive channel on

September 26, 2020.

5

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed and evaluated a licensed operator requalification training

drill (Crew E) on July 27, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (4 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1)

High pressure core spray system on July 31, 2020

(2)

Diesel generator 1 on August 13, 2020

(3)

Reactor core isolation cooling system on September 21, 2020

(4)

Standby service water system B on September 28, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1)

Yellow risk for backup transformer maintenance, week of July 20, 2020

(2)

Yellow risk for high pressure core spray system maintenance, week of July 27, 2020

(3)

Yellow risk for diesel generator 1 maintenance, week of August 5, 2020

(4)

High risk for transformer E-TR-8A/1 replacement on September 13, 2020

(5)

Yellow risk for reactor core isolation cooling system maintenance, week of

September 14, 2020

(6)

Yellow risk for standby service water system B maintenance, week of

September 21, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensees justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

Low oil pressure and metal shavings in oil filter of control room emergency chiller 1B

on August 4, 2020

(2)

Containment vacuum breaker 1EF abnormal indication on August 6, 2020

(3)

Inverter 3B abnormal indication and voltage transient following attempted transfer

from inverter 3A on August 13, 2020

(4)

Annual standby service water flow balance out of specification on August 25, 2020

(5)

Isolation capability of motor-operated valves RHR-V-9 and RCIC-V-22 on

August 27, 2020

(6)

Electrical power panel E-PP-8AE low voltage on September 1, 2020

6

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system

operability and functionality:

(1)

Control room emergency chiller 1B low oil pressure on July 28, 2020

(2)

High pressure core spray system on July 31, 2020

(3)

Diesel generator 1 on August 5, 2020

(4)

Control room emergency chiller 1B low oil pressure on August 26, 2020

(5)

Reactor core isolation cooling system on September 21, 2020

(6)

Standby service water system B on September 22, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01) (2 Samples)

(1)

Work Orders 02140807 and 02140808, condensate storage tanks A and B inspection

for license renewal, on September 28, 2020

(2)

OSP-FLEX-Q704, diesel generator 4 quarterly surveillance, on September 30, 2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1)

OSP-SGT/IST-Q701, standby gas treatment valve quarterly surveillance, on

August 10, 2020

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1 Sample)

(1)

The inspectors evaluated the emergency planning drill (Emergency Response

Organization Team B) on August 25, 2020.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

COVID-19 pandemic conditions impacted the NRCs ability to conduct the inspection as

scheduled. As a result, onsite inspection of appropriately risk-informed samples was not

available. Therefore, IP 71124.01 is considered complete in accordance with IMC 0306,

Section 06.08.f.3.

Radiological Hazard Assessment (IP Section 03.01) (1 Partial)

(1)

(Partial)

7

The inspectors remotely evaluated how the licensee identifies the magnitude and

extent of radiation levels and the concentrations and quantities of radioactive

materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Partial)

(1)

(Partial)

The inspectors remotely evaluated radiological protection-related instructions to plant

workers.

Contamination and Radioactive Material Control (IP Section 03.03) (1 Partial)

The inspectors evaluated licensee processes for monitoring and controlling contamination

and radioactive material.

(1)

(Partial)

Inspectors reviewed condition reports, procedures, inventory, and surveys remotely

for items stored in the spent fuel pool.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (2 Partials)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and

observation of radiological work activities.

(1)

(Partial)

Inspectors remotely reviewed monitoring data, procedures, and radiation work

permits. The radiation work permits associated with Refueling Outage 24 in-vessel

work, wet work, spent fuel pool work, and Rx Cavity work were reviewed.

(2)

(Partial)

The inspectors remotely reviewed electronic alarming dosimeter set points for

radiation work permits associated with Refueling Outage 24 and verified set points

were based on operating experience or historical outage data.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Partials)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very

High Radiation Areas:

(1)

(Partial)

Inspectors remotely reviewed high radiation area condition reports relative to areas

on the 606-foot elevation of the reactor building.

(2)

(Partial)

Inspectors remotely reviewed high radiation area condition reports relative to areas

on the 441-foot elevation of the turbine building.

Radiation Worker Performance and Radiation Protection Technician Proficiency

(IP Section 03.06) (1 Partial)

(1)

(Partial)

Inspectors remotely reviewed job coverage procedures, surveys, and radiation work

permits.

8

71124.02 - Occupational ALARA Planning and Controls

Radiological Work Planning (IP Section 03.01) (5 Samples)

The inspectors evaluated the integration of as low as is reasonably achievable planning into

the following work activities:

(1)

RWP 30004256, R24 Wet Work/Reactor Dive Inspection (Divers) - LHRA/High Risk

(2)

RWP 30004318, R24 Control Rod Drive Mechanism (CRDM) Undervessel Remove

and Replace - LHRA/High Risk

(3)

RWP 30004328, R24 Steam Tunnel (ST)/VR/DCA/Rebuild Room Miscellaneous

Work - High Risk

(4)

RWP 30004336, R24 Drywell/ST Shielding Install/REM and Support Tasks - LHRA

(5)

RWP 30004347, R24 Drywell Main Steam Relief Valve (MSRV) Maintenance -

LHRA

Verification of Dose Estimates and Exposure Tracking Systems (IP Section 03.02) (5 Samples)

The inspectors evaluated dose estimates and exposure tracking.

(1)

RWP 30004256, R24 Wet Work / Reactor Dive Inspection (Divers) - LHRA/High

Risk

(2)

RWP 30004318, R24 Control Rod Drive Mechanism (CRDM) Undervessel (UV)

Remove and Replace - LHRA/High Risk

(3)

RWP 30004319, R24 CRDM UV Support - LHRA

(4)

RWP 30004347, R24 Drywell MSRV Maintenance - LHRA

(5)

RWP 30004350, R24 Steam Tunnel MSIV Maintenance and Refurb Tasks - LHRA

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01)

The inspectors were unable to evaluate the configuration of permanently installed ventilation

systems.

Temporary Ventilation Systems (IP Section 03.02)

The inspectors were unable to evaluate the configuration of temporary ventilation systems.

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1)

The inspectors remotely evaluated the licensees use of respiratory protection

devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1)

The inspectors remotely evaluated the licensees use and maintenance of self-

contained breathing apparatuses.

9

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated licensee performance as it pertains to radioactive source

term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated licensee performance as it pertains to external dosimetry

that is used to assign occupational dose.

Internal Dosimetry (IP Section 03.03) (1 Sample)

The inspectors evaluated the following internal dose assessments for actual internal

exposures:

(1)

Dose assessment for an individual potentially exposed to airborne radioactivity while

working on bleed steam valves in the TG 471-foot building on June 8, 2019. The

licensee documented the issue in AR 00395101.

Special Dosimetric Situations (IP Section 03.04) (3 Samples)

The inspectors evaluated the following special dosimetric situations:

(1)

EDEX dose assessment and redacted NRC Form 5 for individuals using multipack

dosimetry during the following RWP activity:

RWP 30004258, R24 Wetwork/Reactor Dive Inspection (Divers) - LHRA/High

Risk

(2)

EDEX dose assessment and redacted NRC Form 5 for individuals using multipack

dosimetry during the following RWP activity:

RWP 30004447, 2018 Reactor 606 Badger Testing

(3)

EDEX dose assessment and redacted NRC Form 5 for individuals using multipack

dosimetry during the following RWP activity:

RWP 30004470, 2019 Reactor 522 and Reactor 548 RWCU Flow -

LHRA/High Risk

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1)

(07/01/2019 - 06/30/2020)

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1)

(07/01/2019 - 06/30/2020)

10

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1)

(07/01/2019 - 06/30/2020)

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1)

(07/01/2019 - 06/30/2020)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1)

(07/01/2019 - 06/30/2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1)

(04/01/2019 - 06/30/2020)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual

Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample

(IP Section 02.16) (1 Sample)

(1)

(04/01/2019 - 06/30/2020)

71153 - Follow-up of Events and Notices of Enforcement Discretion

Event Follow-up (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated operator response to a rapid downpower due to a high level

trip of feedwater heater 2B with subsequent trips of feedwater heaters 2C, 3C, 4A,

4B, and 4C on September 15, 2020.

Personnel Performance (IP Section 03.03) (1 Sample)

(1)

The inspectors evaluated licensee response to an inverter 3B abnormal indication

and voltage transient following attempted transfer from inverter 3A and resultant

8-hour and 12-hour technical specification shutdown action statement entries on

July 10, 2020.

INSPECTION RESULTS

Failure to Perform an Adequate Radiation Survey to Identify and Control a High Radiation

Area

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Occupational

Radiation Safety

Green

NCV 05000397/202003-01

Open/Closed

[H.14] -

Conservative

Bias

71124.01

The inspectors reviewed a self-revealed, Green, non-cited violation of 10 CFR 20.1501(a), for

the licensees failure to perform an adequate radiological survey and identify a high radiation

area. Specifically, on May 30, 2019, radiation protection personnel were notified by a

radiation worker about an unanticipated self-reading dosimeter dose rate alarm while the

worker was decontaminating equipment within a posted high contamination area (HCA) on

11

the refuel floor (606-foot elevation of the reactor building). Radiation protection personnel did

not perform a survey to verify the radiological conditions in the work area and allowed the

work to continue. The workers were later asked to exit the area when it was determined that

the work could not be completed within the allotted dose limit set point.

Description: On May 30, 2019, two laborers were assigned the task of decontaminating a

highly contaminated component removed from the reactor vessel. The component was a ring

track used for mounting a specialty camera used to perform in-vessel visual inspections.

During the dayshift, the ring track was removed from the reactor cavity and placed in a high

contamination area (HCA) within a posted radiation area (RA) on the refuel floor (606-

foot elevation of the reactor building). At approximately 5:30 p.m., dayshift radiation

protection personnel began turnover to nightshift; however, a face-to-face turnover between

the dayshift and nightshift Refuel Lead Techs (RLTs) did not occur. A telephone discussion

was held instead. The postings around the ring track were not discussed during the

telephone turnover. The nightshift RLT assumed the ring track was within a posted high

radiation area, but did not attempt to validate this assumption.

At approximately 6:30 p.m., the nightshift RLT briefed the two laborers about the ring track

decontamination work. The Radiation Work Permit (RWP) authorized entry into posted high

radiation areas (HRAs) and HCAs; however, the laborers were not briefed on area dose rates

exceeding 100 millirem per hour and the briefing did not cover the potential for

decontamination rags to generate significant dose rates. Prior to the decontamination work,

surveys of the HCA indicated dose rates up to 60 millirem per hour at 30 cm from the ring

track. The RWP established self-reading dosimeter (SRD) alarm setpoints at 40 millirem for

dose and 200 millirem per hour for dose rate. The laborers were instructed to use multiple

radioactive material (RAM) bags to ensure that the rags did not aggregate and create a dose

concern; however, previous operating experience where aggregated decontamination rags

created unposted HRAs was not discussed. At the briefing, the RLT did not specify which

technician on the refuel floor would be providing coverage in the field, and no one on the

refuel floor was assigned this responsibility. Initially, there were two radiation protection

technicians (RPTs A&B) assigned to the refuel floor and later a second crew (RPTs C&D)

arrived to relieve RPTs A&B.

When the laborers arrived at the refuel floor to prepare for the decontamination work, RPT B

helped them don the proper protective clothing and equipment, including powered

air-purifying respirators. After gathering additional supplies, the decontamination work

commenced and RPT B left to attend to another job. The dose accrued by the laborers was

also being monitored remotely by the RPTs.

At approximately 8:06 p.m., as the laborers worked to decontaminate the ring track and

placed the decontamination rags into a RAM bag, one of the laborers lanyards came undone,

falling with the SRD and badge inside of the protective clothing to their knee. During this

motion, the SRD experienced a dose rate alarm for approximately three seconds. The alarm,

vibration, and SRD movement went unnoticed by the laborer. The alarm was not locked in

long enough to register on the remote monitoring system. Around this same time is when the

RAM bag became an HRA.

At approximately 8:14 p.m., the laborer noticed the SRD was vibrating against his leg. He

informed the other laborer and informed RPT A that he believed his SRD was alarming.

RPT A escorted the laborers to the step-off pad and contacted the RPTs at the remote

monitoring station to check if a dose rate alarm occurred. No locked in alarms were noted, so

it was relayed there was no alarm present. RPT A discovered the laborers SRD had fallen

12

and assumed the vibration was caused by the dropped SRD. The laborers SRD and lanyard

were relocated to the pocket of the inner set of his protective clothing and work was allowed

to continue without validating that an alarm occurred by logging out the SRD or performing a

survey of the work area to verify dose rates had not increased.

Work continued until about 8:50 p.m., when RPT C notified the laborers to exit based on the

dose accrued and amount of decontamination work that remained to be done on the ring

track. Upon exiting, the laborer who believed he had received an alarm, informed an RPT

that was not involved in the work about the alarm he received. The licensee performed a

follow-up survey that identified an unposted HRA with dose rates up to 1,600 millirem per

hour on contact and 180 millirem per hour at 30 centimeters from the source, which

happened to be the RAM bag where the laborers were disposing of the decontamination

rags. The RAM bag was subsequently taped, labeled, and relocated to a posted HRA.

The inspectors reviewed the condition report, RWPs, surveys, and investigation details

associated with this event and determined that the failure to perform a survey to verify

radiological conditions prior to allowing work to continue was a violation of

10 CFR 20.1501(a).

Corrective Actions: The licensee counseled the radiation protection technicians involved and

developed a preferred process for decontamination of highly contaminated items for the

refuel floor, wetwell, and undervessel to be used during the outage. Specific precautions

were added to identify and monitor RAM bags containing cleaning rags and mop heads that

can quickly become high radiation areas.

Corrective Action References: Action Request (AR) 00394579 and AR 00409248

Performance Assessment:

Performance Deficiency: Failure to perform a survey on the refuel floor to identify an

unposted High Radiation Area and evaluate the magnitude and extent of radiation levels as

required by 10 CFR 20.1501(a) was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because if left uncorrected, it would have the potential to lead to a more significant safety

concern. Specifically, the failure to perform a survey resulted in an unposted HRA where an

uninformed worker was allowed to continue working with an SRD dose rate alarm setpoint

that was not sufficiently low enough to allow the worker to take appropriate action before

encountering dose rates exceeding 100 millirem per hour.

Significance: The inspectors assessed the significance of the finding using Appendix C,

Occupational Radiation Safety SDP. The finding was of very low safety significance

(Green) because it was not an as low as reasonably achievable (ALARA) planning issue,

there was no overexposure nor potential for an overexposure (due to availability of alarming

dosimetry being worn), and the licensees ability to assess dose was not compromised.

Cross-Cutting Aspect: H.14 - Conservative Bias: Individuals use decision-making practices

that emphasize prudent choices over those that are simply allowable. A proposed action is

determined to be safe in order to proceed, rather than unsafe in order to stop. Specifically,

the licensees decision-making practices that allowed work to continue without performing an

adequate radiation survey to verify the magnitude and extent of radiation dose rates had not

increased is not reflective of an organization with a bias for conservative decision-making.

13

Enforcement:

Violation: 10 CFR 20.1003, defines a survey as an evaluation of the radiological conditions

and potential hazards incident to the production, use, transfer, release, disposal, or presence

of radioactive material or other sources of radiation.

10 CFR 20.1501(a), requires in part, that each licensee make or cause to be made surveys of

areas that may be necessary for the licensee to comply with the regulations in Part 20 and

that surveys are reasonable under the circumstances to evaluate the magnitude and extent of

radiation levels, concentrations or quantities of radioactive materials, and the potential

radiological hazards that could be present.

As provided in paragraph 20.1601(c) of 10 CFR Part 20, the following controls shall be

applied to high radiation areas in place of the controls required by paragraph 20.1601(a) and

(b) of 10 CFR Part 20.

Technical Specification 5.7.1 requires, in part, that for High Radiation Areas with Dose Rates

not Exceeding 1.0 rem/hour (at 30 centimeters from the radiation sources or from any surface

penetrated by the radiation), each entryway to such an area shall be barricaded and

conspicuously posted as a high radiation area, and entry into such areas shall be made only

after dose rates in the area have been determined and entry personnel are knowledgeable of

them.

Contrary to the above, on May 30, 2019, for High Radiation Areas with Dose Rates not

Exceeding 1.0 rem/hour (at 30 centimeters from the radiation sources or from any surface

penetrated by the radiation), the licensee failed to ensure that each entryway to such an area

was barricaded and conspicuously posted as a high radiation area, and entry into such areas

was made only after dose rates in the area have been determined and entry personnel are

knowledgeable of them. Specifically, 1) the entryway to an HRA near a RAM bag containing

the ring track decontamination rags on the refuel floor was not barricaded and conspicuously

posted and 2) entry into the area near a RAM bag containing the ring track decontamination

bags on the refuel floor was made before dose rates in the area had been determined and

without entry personnel being made knowledgeable of them.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Follow ALARA Planning Procedures Resulting in Unplanned Dose on a Work

Activity

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Occupational

Radiation Safety

Green

NCV 05000397/202003-02

Open/Closed

[H.5] - Work

Management

71124.02

The inspectors reviewed a self-revealed, Green, non-cited violation Technical Specification (TS) 5.4.1 because the licensee failed to follow their as low is reasonably achievable

(ALARA) planning procedures resulting in unplanned dose while performing the control rod

drive mechanism (CRDM) Replacement work. Specifically, the licensees procedure

instructed them to obtain data on the actual radiological conditions in the work area prior to

commencement of the job and determine the effective dose rate using corrected historical

14

data for the current scope and radiological conditions in the radiation work permit (RWP)

planning phase. The licensee initially planned the job for approximately 6.850-person Rem,

including under vessel work, whereas the actual dose accrued to complete the work activity

was 10.752-person Rem.

Description: From May to June 2019 during Refueling Outage 24, numerous jobs led to

exceeding their overall dose estimate of 139.896-person Rem, and goal of 130-person Rem,

with an actual dose accrued of 161.474-person Rem. One of the primary work activities that

led to this dose exceedance was the CRDM Replacement job to exchange a total of

20 CRDMs from under vessel. This job commenced on May 19, 2019. The licensee

identified they were having issues maintaining doses ALARA and in alignment with their

planned dose estimate. In AR 00395843, the licensee documented that some of the primary

issues resulting in additional unplanned dose were problems with their O-rings leaking and

not properly seating, issues with their use of the special equipment used to more effectively

manipulate the CRDM removals, rework on some equipment, and perhaps most significantly,

elevated dose rates in the work areas. Survey M-20190514-5, DW 501 Under-Vessel Post

H2O Fill-Up, dated May 14, 2019, and characterized as a verification of dose rates survey,

identified the maximum dose rates in the work area as 910 millirem per hour on contact and

320 millirem per hour at 30 cm. The Refueling Outage 24 (R24) Nightshift Logs, dated May

15, 2019, stated that HP Planning has indicated that U/V (under vessel) dose rates in

Drywell are 75% higher than R23 (Refueling Outage 23). In addition, the licensee noted that

the average dose rates for the CRDMs went from approximately 25 Rem/hour in R23 to

approximately 47 Rem/hour during R24. The licensee noted that the primary reason for the

elevated dose rates were attributed to the iron excursion event experienced in August 2017,

and residually caused issues with the O-rings and overall dose increases. To their credit, the

licensee did attempt numerous measures of dose reduction initiatives, but they were not

effective enough to reduce the dose to a planned level of exposure. In response to a request

for information, the licensee stated the following, The work had been planned and it was

decided to follow the contingency plan rather than revise the estimate. This process did not

follow the instructions provided in their ALARA planning procedures.

Procedure PPM 11.2.2.14, Radiological Planning and Reviews, Revision 4, Section 4.1.10,

stated, in part, the following:

Obtain data on the actual or anticipated radiological conditions in the work area using

one of more of the following methods:

o Pre-job surveys

o Recent surveys of the work area

o Historical surveys. Radiological conditions in the work area should be verified

prior to allowing work to commence.

o Data from job history files for similar tasks. Radiological conditions shall be

determined prior to allowing work to commence.

Section 4.1.11 of PPM 11.2.2.14 stated, in part, the following:

Based on the following, DETERMINE AND ENTER an effective dose rate for each

craft on the H213 Panel (of the Passport Computer Program), after considering the

following:

o Current and historical radiological conditions in the work area

o Estimated locations and body positions of the workers during the task

o Review of historical dose information corrected for current scope and

conditions

o Information obtained in Step 4.1.10

15

PPM 11.2.2.14, Section 6.1, defined Effective Dose Rate as An estimated dose rate based

on the actual work area dose rates, worker position, worker movement with the work area,

and planned dose reduction measures. It also stated the historical information may be used

to determine the Effective Dose Rate, but these conditions were explained further in

Section 4.1.10 and 4.1.11, as stated above.

The inspectors determined that the licensee failed to implement the steps in Section 4.1.11

during their planning and implementation process for the CRDM Replacement job, which

included various radiological work permits. Specifically, the licensee determined that the

current radiological conditions were much higher than the historical radiological data from

R23, but the licensee did not use the current higher radiological conditions in the work area to

properly determine an effective dose rate, which is used to determine or revise the dose

estimate, for the craft on the job prior to commencement of the work. Instead, the licensee

stated they decided to follow the contingency plan rather than revise the estimate.

Section 3.9 of PPM 11.2.2.14 stated, in part, that instructions and contingency plans in work

instructions, ALARA plans, and the RWP should be specific and clearly stated with limited

use if as directed by RP. The aim is to help workers focus on the job and respond

appropriately to emergent or changing conditions. Thus, the contingency plans are inferred

for use during the work activity in progress, for emergent or changing conditions, and not for

decisions made prior to the job commencing. The inspectors determined that the failure to

follow these instructions and implement the current radiological conditions into the ALARA

planning permit prior to commencement of the work resulted in not effectively managing the

radiological risk due to the short time span of the job and continuing with work in the midst of

elevated radiological conditions. This ultimately resulted in unplanned dose to the workers for

the CRDM Replacement job and under vessel work.

The NRC reviewed the dose estimate of 6.85-person Rem for the job, as commenced, and

credited an additional 0.251-person Rem for credible emergent work, resulting in an NRC

revised dose estimate of 7.101-person Rem. This NRC revised dose estimate exceeds the

approved revised dose estimate by the licensee, via their in-progress review, of 7.036-person

Rem for the CRDM work. Thus, the actual dose accrued of 10.752-person Rem exceeded

the NRC revised dose estimate by 51.4 percent (51.4%).

Corrective Actions: The licensee documented the issues associated with the CRDM

replacement job in their corrective action program as AR 00395843. The licensee also

evaluated the performance of this job in their Refueling Outage 24 post job review

package. Additionally, the licensee initiated AR 00409249 to address the proposed violation

and assess any additional corrective actions relative to the performance deficiency.

Corrective Action References: AR 00395843 and AR 00409249

Performance Assessment:

Performance Deficiency: The licensees failure to follow their ALARA planning procedures

and properly determine the effective dose rate prior to commencement of the CRDM

Replacement job is a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program & Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

16

radioactive material during routine civilian nuclear reactor operation. Additionally, the finding

was similar to Example 6(i) in Appendix E to Manual Chapter 0612, Power Reactor

Inspection Reports - Examples of Minor Issues.

Significance: The inspectors assessed the significance of the finding using Appendix C,

Occupational Radiation Safety SDP. The inspectors determined the finding had very low

safety significance (Green) because, although the finding involved ALARA planning and work

controls, the licensees latest three-year rolling average collective dose was less than

240-person Rem (i.e., 135.44-person Rem).

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of

planning, controlling, and executing work activities such that nuclear safety is the overriding

priority. The work process includes the identification and management of risk commensurate

to the work and the need for coordination with different groups or job activities. Specifically,

the licensee failed to execute the work with the appropriate planning commensurate with the

radiological risk identified, while coordinating and managing all relative under vessel work

activities.

Enforcement:

Violation: Technical Specification 5.4.1 Procedures, states, in part, that written procedures

shall be established, implemented, and maintained covering the following activities: (a) the

applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A,

February 1978. Appendix A Section 7(e) recommends Radiation Protection procedures.

Procedure PPM 11.2.2.14, Revision 4, Section 4.1.11, states, in part, that the licensee is to

DETERMINE AND ENTER an effective dose rate for each craft on the H213 Panel (of the

Passport Computer Program), based on the following:

Current and historical radiological conditions in the work area

Estimated locations and body positions of the workers during the task

Review of historical dose information corrected for current scope and conditions

Information obtained in Step 4.1.10 (obtain data on the actual or anticipated

radiological conditions in the work area)

Contrary to the above, from May to June 2019 during Refueling Outage 24, the licensee

failed to determine an effective dose rate for each craft based on information obtained in

PPM, Step 4.1.10 and the historical data corrected for current scope and conditions.

Specifically, the licensee performed a validation radiological survey five days prior to

commencement of the CRDM Replacement job and determined that dose rates were

significantly higher than the historical data but did not base the effective dose rate for the job

on these current radiological conditions by appropriately revising the dose estimate and work

scope. The licensee specifically stated in their response to the NRC that they decided to

follow the contingency plan rather than revise the estimate, which does not align with the

appropriate use of the contingencies, as stated in Section 3.9 of PPM 11.2.2.14, Revision 4.

At the time, it appears as though the licensee believed they were operating within the scope

of their procedures.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

17

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 15, 2020, the inspectors presented the integrated inspection results to

Mr. G. Hettel, Chief Nuclear Officer/Vice President Nuclear Generation, and other members of

the licensee staff.

On July 27, 2020, the inspectors presented the Occupational Radiation Safety inspection results

to Mr. R. Schuetz, Site Vice President, and other members of the licensee staff.

18

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

Action Requests

(ARs)

409261, 409457, 403099, 400090, 404607, 405359, 407757,

408822, 409196, 409593, 409594, 401237, 401287, 404112,

411017

Drawings

M512-1

Flow Diagram Diesel Oil & Miscellaneous Systems

048

M512-3

Flow Diagram Diesel Oil & Miscellaneous Systems Diesel

Generator Building

041

M519

Flow Diagram: Reactor Core Isolation Cooling System

103

M520

Flow Diagram HPCS and LPCS Systems

105

M524-1

Flow Diagram Standby Service Water System

139

Procedures

10.27.87

RCIC Keepfill Instruments RCIC-PIS-1 and RCIC-PIS-34 -

CFT/CC

012

3.1.6F

Instrument Rack Valve Line-Up Reactor Building 422 and

471 Elevations

007

PPM 1.3.29

Locked Valve Checklist

086

PPM 1.3.62

Use of Cable Ties (Tie Wraps)

007

PPM 1.3.81

Maintaining Plant Component Status Control

016

SOP-DG-DSA

Diesel Starting Air Operations

016

SOP-DG1-LU

Emergency Diesel Generator (DIV 1) Valve and Power

Supply Lineup

006

SOP-DG2-LU

Emergency Diesel Generator (DIV 2) Valve and Power

Supply Lineup

007

SOP-DG2-

START

Emergency Diesel Generator (DIV 2) Start

033

SOP-DG2-STBY

Emergency Diesel Generator (DIV 2) Standby Lineup

023

SOP-DG3-LU

High Pressure Core Spray Diesel Generator Valve and

Power Supply Lineup

009

SOP-DG3-STBY

High Pressure Core Spray Diesel Generator Standby Lineup

019

SOP-HPCS-LU

HPCS Valve and Breaker Lineup

004

SOP-HPCS-

STBY

Placing HPCS in Standby Status

004

SOP-RCIC-LU

RCIC Valve and Breaker Lineup

004

SOP-RCIC-STBY

Placing RCIC in Standby Status

012

19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SOP-SW-LU

Standby Service Water System Valve & Breaker Lineup

013

Work Orders

02162153, 02126439, 02135644, 02155492, 02156217,

02160505, 02132544

71111.05

Calculations

FP-02-85-03

Combustible Loading Calculation

010

Corrective Action

Documents

Action Requests

(ARs)

384793, 409481, 409497, 409505, 403382, 403385, 403450,

403610, 403748, 405319, 405384

Fire Plans

PFP-DG-

BUILDING

Diesel Generator Building

004

PFP-RB-422

Reactor 422

006

PFP-RW-467

Radwaste 467

005

PFP-RW-501-507

Radwaste 501-507

005

PFP-TG-441-456

Turbine Generator 441-456

009

Miscellaneous

Crew B Unannounced Backshift Drill 6/19/20

06/19/2020

Drill Report: Unannounced Backshift Drill 6/19/20 Scenario

OS-002 Crew B

06/19/2020

Drill Report: Unannounced Backshift Drill 8/26/2020

Scenario TG-004 Crew E

08/26/2020

Procedures

1.3.10C

Control of Combustibles

022

1.3.57

Barrier Impairment

039

13.1.1

Classifying the Emergency

049

13.1.1A

Classifying the Emergency - Technical Bases

034

4.FCP.1

FCP.1 Annunciator Panel Alarms

023

4.FCP.2

FCP.2 Annunciator Panel Alarms

016

ABN-FIRE

Fire

041

Work Orders

02163070

71111.07A

Calculations

ME-02-92-231

Evaluation of Heat Exchanger Performance Data - DCW

001

ME-02-92-244

Minimum Heat Transfer Rate Required for DCW Heat

Exchangers A & B

000

ME-02-92-245

RHR Heat Exchanger Tube Side Flowrate and Inlet

Temperature Evaluation

000

Corrective Action

Documents

Action Requests

(ARs)

391148, 391160, 391175, 398502, 411270, 411411

Engineering

17432, 12442

20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Changes

Miscellaneous

MOT-HX-1-1

Maintenance Optimization Template: Heat Exchangers

013

Procedures

8.4.62

Thermal Performance Monitoring of DCW-HX-1B1 and

DCW-HX-1B2

009

Work Orders

02059477, 02059478, 02103773, 02103774, 02132409

71111.11Q Corrective Action

Documents

Action Requests

(ARs)

408746, 408747, 409496, 410023, 410112, 410534, 410833,

411186, 411193, 411194, 411197, 410801

Miscellaneous

AOM-T Roll-up Comments: Cycle 20-04

000

Crew E 4.0 Critique Summary LR002492

07/27/2020

Reactivity Control Plan September 26, 2020, Sequence

Exchange and Scram Time Testing

09/15/2020

Control Rod Withdrawal Deviation Sheet

09/03/2020

LR002492

Cycle 20-4 Evaluated Scenario

000

Procedures

13.1.1

Classifying the Emergency

049

13.1.1A

Classifying the Emergency - Technical Bases

034

3.2.6

Power Maneuvering

015

3.3.1

Reactor Scram

066

5.1.1

RPV Control

022

5.1.2

RPV Control - ATWS

026

ABN-FWH-

HILEVEL/TRIP

Feedwater Heater High Level Trip

007

ABN-POWER

Unplanned Reactor Power Change

016

ABN-ROD

Control Rod Faults

031

OI-09

Operations Standards and Expectation

079

SOP-CR-

MOVEMENT

Control Rod Movement

004

SOP-RRC-

FLOW-QC

Reactor Power Change with RRC Flow Controllers - Quick

Card

005

TSP-CRD-C101

CRD Scram Timing with Auto Scram Timer System

029

Work Orders

02146065, 02159885

71111.12

Corrective Action

Documents

Action Requests

(ARs)

408595, 409141, 409156, 409175, 409181, 409215, 409224,

409252, 409260, 409261, 409303, 409313, 408822, 406409,

407757, 409196, 332149, 336395, 410488, 410779, 410800,

21

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

410835, 410865, 410882, 410883, 410913, 410831, 410880,

410981, 411002, 411017, 411019, 411024, 411044, 411050,

411052

Miscellaneous

Instrument Master Data Sheet: RCIC-PS-9B

007

BIP 19-0389

Barrier Impairment Permit for ISP-HPCS-X302 (Calibrate

HPCS-FIS-6)

07/29/2020

BIP 20-0344

Barrier Impairment Permit for Inspection of HPCS-FT-5

Penetration Seal

07/27/2020

ISP 20-0136

Ignition Source Permit for Work Order 02140140

09/17/2020

Procedures

1.3.57

Barrier Impairment

039

1.5.11

Maintenance Rule Program

016

10.16.1

Standby Service Water Pump Overhaul

017

10.2.10

Fastener Torque and Tensioning

028

10.25.4

Lubrication and Inspection of Limitorque MOVS

029

10.27.85

RCIC Turbine Trip on High Turbine Exhaust Pressure B

Calibration

002

ISP-HPCS-X302

HPCS Flow Rate Low Minimum Flow - CC

009

OSP-ELEC-M703

HPCS Diesel Generator Monthly Operability Test

069

OSP-HPCS/IST-

Q701

HPCS System Operability Test

059

OSP-SW-M103

HPCS Service Water Valve Position Verification

026

SOP-RCIC-FILL

RCIC Fill and Vent

020

SOP-RCIC-OIL

RCIC Turbine or Pump Oil Fill and Prime

010

SYS-4-22

Maintenance Rule Program

015

Work Orders

02080473, 02126090, 02120692, 02128969, 02054567,

02089993, 02045665, 02123430, 02153118, 02131518,

02162153, 02156590, 02160239, 02135829, 02136041,

02152183, 02156156, 02156217, 02160285, 02160286,

02134251, 02134544, 02135557, 02140140, 02149943,

02152938, 02153201, 02158395, 02122134, 02139803,

02140165, 02143796, 02146121, 02146129, 02153512

71111.13

Corrective Action

Documents

Action Requests

(ARs)

409466, 409497, 409505

Miscellaneous

FPF-2.4-28

Standpipe and Hose Systems, Evaluation of Long Hose

000

22

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Lengths Using a PROTEK #379 Nozzle

FPSI 20-0169

Fire Protection System Impairment Permit for Inst. Rack E-

IR-P027 Door R415

08/02/2020

FPSI 20-0170

Fire Protection System Impairment Permit for Inst. Rack E-

IR-P021 Door R316

08/02/2020

FPSI 20-0171

Fire Protection System Impairment Permit for Inst. Rack E-

IR-P009 Door R216

08/02/2020

FPSI 20-0172

Fire Protection System Impairment Permit for SW B

Pumphouse Door G201

08/02/2020

FPSI 20-0173

Fire Protection System Impairment Permit for Door C408

Upper Corridor Outside CR

08/02/2020

FPSI 20-0174

Fire Protection System Impairment Permit for Door C223

Vital Island General Area

08/02/2020

FPSI 20-0175

Fire Protection System Impairment Permit for Emergency

Chiller Room Door C502

08/02/2020

FPSI 20-0176

Fire Protection System Impairment Permit for Comm. RM

C503 Door C505

08/02/2020

FPSI 20-0177

Fire Protection System Impairment Permit for Instrument

Shop RM C510 Door C511

08/02/2020

FPSI 20-0178

Fire Protection System Impairment Permit for Div 2 HVAC

Room Door C508

08/02/2020

FPSI 20-0179

Fire Protection System Impairment Permit for Remote

Shutdown Room Door C240

08/02/2020

FPSI 20-0180

Fire Protection System Impairment Permit for SM-8

Switchgear Room Door C242

08/02/2020

FPSI 20-0181

Fire Protection System Impairment Permit for Div 2 RPS RM

Door C222

08/02/2020

FPSI 20-0182

Fire Protection System Impairment Permit for Div 2 Battery

Charger RM C224 Door C238

08/02/2020

FPSI 20-0183

Fire Protection System Impairment Permit for Div 2 Battery

Room Doors C217 or C238

08/02/2020

FPSI 20-0184

Fire Protection System Impairment Permit for Waste Tank

Floor Area RM C106 Door C109

08/02/2020

FPSI 20-0185

Fire Protection System Impairment Permit for South Valve

08/02/2020

23

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RM R405 Door R407

FPSI 20-0186

Fire Protection System Impairment Permit for MCC Div 2

South RM R410 Door R408

08/02/2020

FPSI 20-0187

Fire Protection System Impairment Permit for RCIC Room

Door R5 RM R015

08/02/2020

FPSI 20-0188

Fire Protection System Impairment Permit for Div 2 MCC

ROOM R612 Door R607

08/02/2020

FPSI 20-0189

Fire Protection System Impairment Permit for Inside Door

R217

08/03/2020

FPSI 20-0190

Fire Protection System Impairment Permit for B RHR Pump

Room Doors R7/7A Room R006

08/03/2020

FPSI 20-0191

Fire Protection System Impairment Permit for DFO Day Tank

RM Door D103 RM D111

08/02/2020

FPSI 20-0192

Fire Protection System Impairment Permit for DG 3 Div 2

DFO TK Door D110 Room D102

08/03/2020

FPSI 20-0193

Fire Protection System Impairment Permit for DG2 Diesel

Room Door D104 RM D110

08/02/2020

Procedures

1.3.10

Plant Fire Protection Program Implementation

034

1.3.76

Integrated Risk Management

060

1.3.83

Protected Equipment Program

031, 032

1.3.85

On-line Fire Risk Management

006

ESP-B12-M101

Monthly Battery Testing 125VDC E-B1-2

007

ESP-BAT-W101

Weekly Battery Testing

016

OSP-ELEC-W101 Offsite Station Power Alignment Check

032

Work Orders

02156332, 02156554, 02163069, 02168650

71111.15

Calculations

E/I-02-87-07

Calculation for Load Flow Voltage for Main Buses in AC

Distribution Systems

012

E/I-02-90-01

Low Voltage System Loading, Security System Loading and

Voltage Calculation

016

ME-02-92-43

Flow Reduction Factors Reactor Building

013

ME-02-95-25

Evaluation of Standby Service Water Capability

002

Corrective Action

Documents

Action Requests

(ARs)

407977, 407978, 408057, 315816, 408422, 408487, 408559,

408560, 408543, 408697, 409219, 408616, 408618, 408620,

408622, 408724, 408741, 407092, 409590, 409591, 409833,

24

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

409851, 409937, 410056, 410399, 408029

Drawings

E504-1

Vital One Line Diagram

006

EWD-22E-039A

Electrical Wiring Diagram Primary Containment Atmospheric

Control System CVB-V-1ST Front Disk

003

EWD-22E-048A

Electrical Wiring Diagram Primary Containment Atmospheric

Control System CVB-V-1ST Rear Disk

003

M543-1

Flow Diagram - Reactor Bldg. Primary Containment Cooling

and Purging Systems

092

Engineering

Changes

8818

Critical Instrument Bus and Alternate Source Power

11/28/2011

Miscellaneous

Position Paper for Operator Convenience

07/10/2020

Operations and Maintenance Manual 399.5.1, York

Centrifugal Turbopak R-11

09/22/2004

Technical position paper associated with AR 408029408029

07/14/2020

NRC Inspection Reports 05000327/2020010 and

05000328/2020010

Operations Log: July 1 - August 6, 2020

08/06/2020

Operator Logs: July 10 - 11, 2020

07/11/2020

213-05,7

Vacuum Relief Valve and Auxiliaries Owners Manual

005

MOT-CKV-1-1

Check Valves Maintenance Optimization Template

017

Procedures

1.10.11

Technical Assessments Supporting Reportability and

Reportability Evaluations

002

1.16.6B

Voluntary Entry into Technical Specification Action

Statements, Licensee Controlled Specifications

Requirements for Operability

018

1.3.16

Issue Management

002

1.3.66

Operability Determination

034, 035

1.3.9

Temporary Modifications

056

10.25.85

Repair of Wet Well Vacuum Breaker Position Switches

012

4.800.C1

800.C1 Annunciator Panel Alarms

031

ABN-ELEC-INV

120 VAC Critical Distribution System Failures

017

OSP-CVB/IST-

M701

Vacuum Breaker Operability

016, 017,

018

25

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OSP-ELEC-W102 Electrical Distribution Subsystem Breaker Alignment and

Power Availability Verification

031

SOP-CN-CONT-

VENT

Containment Vent, Deinert, Purge, and Ventilating

027

SOP-CN-OPS

Containment Nitrogen System Operations

010

SOP-ELEC-IN3-

OPS

IN3 Operations

013

SWP-OPX-01

Operating Experience Program

001

Work Orders

02155686, 02164937, 02156935, 29155613, 02131744,

02145562, 02042666, 02043384, 02156764, 02157084,

02157376, 02157626, 02167660, 29156112, 29156133

71111.19

Corrective Action

Documents

Action Requests

(ARs)

408595, 409141, 409156, 409175, 409181, 409215, 409224,

409252, 409260, 409261, 409303, 409313, 407977, 407978,

408057, 408466, 408525, 408604, 408639, 408654, 408708,

408761, 408842, 408890, 408947, 408976, 409068, 409107,

409697, 409726, 409842, 409899, 403782, 404272, 404607,

406649, 354988, 355024, 342466, 400409, 410882, 410927,

410928, 410929, 410930, 410931, 410934, 410947, 410949,

410951, 410964, 410965, 410966, 411107

Miscellaneous

Operations Department Narrative Logs for 08/05/2020

BIP 19-0389

Barrier Impairment Permit for ISP-HPCS-X302 (Calibrate

HPCS-FIS-6)

07/29/2020

BIP 20-0344

Barrier Impairment Permit for Inspection of HPCS-FT-5

Penetration Seal

07/27/2020

Procedures

1.3.57

Barrier Impairment

039

10.2.13

Approved Lubricants

077

ABN-HVAC

HVAC Trouble

017

ISP-HPCS-X302

HPCS Flow Rate Low Minimum Flow - CC

009

OSP-CCH/IST-

M702

Control Room Emergency Chiller System B Operability

045

OSP-CONT-C101 Suppression Pool Average Water Temperature Surveillance

002

OSP-ELEC-M701

Diesel Generator 1 -Monthly Operability Test

060

OSP-ELEC-M703

HPCS Diesel Generator Monthly Operability Test

069

OSP-HPCS/IST-

HPCS System Operability Test

059

26

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Q701

OSP-RCIC-M101

RCIC Fill, Flow Controllers, and Valve Lineup Verification

019

OSP-RCIC/IST-

Q701

RCIC Operability Test

063

OSP-RCIC/IST-

Q702

RCIC Valve Operability Test

044

OSP-SW-IST-

Q702

Standby Service Water Loop B Operability

035

OSP-SW-M102

Standby Service Water Loop B Valve Position Verification

043

OSP-SW-M103

HPCS Service Water Valve Position Verification

026

PPM 1.5.1

Surveillance Testing Program

043

SOP-HVAC/CR-

SHUTDOWN

Control, Cable, and Critical Switchgear Rooms HVAC

Shutdown

005

SOP-HVAC/CR-

START

Control, Cable, and Critical Switchgear Rooms HVAC Start

017

SOP-RHR-SPC

Suppression Pool Cooling/Spray/Discharge/Mixing

008

SOP-SW-

SHUTDOWN

Standby Service Water System Shutdown

002

SOP-SW-START

Standby Service Water System Start

008

SOP-SW-STBY

Placing Standby Service Water in Standby Status

003

SWP-TST-01

Post Maintenance Testing Program

017

Work Orders

02080473, 02126090, 02120692, 02128969, 02054567,

02089993, 02045665, 02123430, 02153118, 02131518,

02162153, 02156590, 02160239, 02164274, 02138105,

02124750, 02154772, 02159891, 02915593, 02124750,

02157518, 02167155, 02150225, 02156936, 02160285,

02161982, 02134544, 02134781, 02135563, 02140140,

02147071, 02158410, 02140165, 02153512

71111.22

Calculations

E/I-02-91-03

Calculation for Division 1 and 2 and 3 Diesel Generator

Loading

021

Corrective Action

Documents

Action Requests

(ARs)

291562, 382935, 410110, 410392, 410513, 410610, 410611,

410618, 410724, 410735, 410803, 410823, 409695, 409856,

409857, 409866, 411040, 411419

Drawings

204-00,88,1

Condensate Storage Tank 1A General Plan Detail and Parts

007

27

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

List

204-00,89,1

Condensate Storage Tank 1B General Plan Detail and Parts

List

007

Engineering

Changes

17708

Miscellaneous

Condensate Storage Tanks A & B Inspection Videos

09/24/2020

Operations Department Narrative Logs for 08/10/2020

Procedures

10.25.48

Testing Molded Case Circuit Breakers

017

FLEX-01

FLEX Program

003

OSP-FLEX-Q704

Diesel Generator 4 Quarterly Surveillance

000

OSP-SGT/IST-

Q701

SGT Valve Operability (System A)

010

PPM 1.5.1

Surveillance Testing Program

043

PPM 13.10.1

Control Room Operations and Shift Manager Duties

035

SWP-IST-01

ASME Inservice Testing

004

Work Orders

02160246, 02140807, 02140808, 02145984, 02168133

71114.06

Corrective Action

Documents

Action Requests

(ARs)

410143, 410180, 410323

Procedures

13.1.1

Classifying the Emergency

049

13.1.1A

Classifying the Emergency - Technical Bases

034

13.10.2

TSC Manager Duties

035

13.10.6

Plant / NRC Liaison Duties

025

13.10.9

Operations Support Center Manager and Staff Duties

050

71124.01

Corrective Action

Documents

Action Request

(AR)

00320829, 00394339, 00394466, 00394579, 00395232,

00401615, 00403475, 00404828, 00405114, 00405278,

00409019, 00409248

Procedures

4.840.A3

840.A3 Annunciator Panel Alarms

020

HPI-0.19

Radiation Protection Standards and Expectations

019

HPI-12.96

RCA Access Restriction and Reinstatement

009

PPM 11.2.13.1

Radiation and Contamination Surveys

043

PPM 11.2.6.7

Special Dosimetry

019

Radiation

Surveys

M-20190517-34

RB 606 SFP Inventory Following R24 Fuel Inspections

05/17/2019

M-20190523-28

RB 606 SFP Inventory Following LPRM And Dry Tube

05/23/2019

28

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Replacement

M-20190530-20

RB 606 Removal Of Framatome Hawkeye Ring From Cavity

05/30/2019

M-20190531-4

RB 606 Hawkeye ring post decon/dose rate alarm follow-up

05/30/2019

M-20191024-7

RB 572 Monthly

10/24/2019

Radiation Work

Permits (RWPs)

30004256

R24 RF Wetwork, Invessel, SFP, DSP *HR*

and Associated Tasks, Pre-Job Briefing, ALARA Plan

001

Self-Assessments 388465-02

10 CFR 20 Annual Program Review Snapshot Self-

Assessment Report

03/15/2019

401808-01

NRC Inspection Procedure 71124.01 Snapshot Self-

Assessment Report

03/05/2020

Work Orders

02109577-01

Calibrate/Repair Outage HP Portable Air Samplers

03/26/2019

02137805-01

Calibrate/Repair HP Portable Air Samplers

04/19/2019

71124.02

Corrective Action

Documents

Action Request

(AR)

00371557; 00373396; 00374279; 00389652; 00393863;

00393987; 00394579; 00395197; 00395232; 00395371;

00395843; 00396076; 00398464; 00401910; 00404386;

00405192; 00405201; 00409249

Miscellaneous

2019 CGS Refueling Outage 24 CRE Report

2019

2017 CGS Refueling Outage 23 CRE Report

2017

EDEX Assessments for RWPs 30004258, 30004447,

30004470

Procedures

GEN-RPP-01

ALARA Program Description

009

GEN-RPP-02

Radiological Planning and Control Process

034

GEN-RPP-13

Senior Site ALARA Committee

013

PPM 11.2.2.11

Exposure Evaluations for Maintaining TEDE ALARA

009

PPM 11.2.2.14

Radiological Planning and Reviews

004

PPM 11.2.2.7

ALARA Procedure Analysis

012

PPM 11.2.2.8

ALARA Engineering Analysis

007

PPM 11.2.8.2

Radiation Work Permit Preparation and Use

002

Radiation Work

Permits (RWPs)

30004256

R24 Refuel Floor Wetwork Invessel, Spent Fuel Pool, and

DSP - High Risk

001

30004258

R24 Wetwork/Reactor Dive Inspection (Divers) - LHRA/High

Risk

000

30004318

R24 CRDM Undervessel Remove and Replace - LHRA/High

000

29

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Risk

30004319

R24 CRDM Undervessel Support - LHRA

001

30004328

R24 ST/VR/DCA/Rebuild Room Miscellaneous Work - High

Risk

000

30004336

R24 Drywell/Steam Tunnel Shielding Install/REM and

Support Tasks - LHRA

000

30004340

R24 DW/ST/VR OPS HC/LC, LLRT and Valve Lineups -

LHRA

001

30004347

R24 Drywell MSRV Maintenance - LHRA

000

30004350

R24 Steam Tunnel MSIV Maintenance and Refurb Tasks -

HRA

002

Self-Assessments 00388465-02

Annual Review of the Columbia Generating Station

Radiation Protection Program that Fulfills the Requirements

of 10 CFR 20.1101(c) for CY2018

03/15/2019

401806

Pre-Inspection (71124.02) ALARA Snapshot Self-

Assessment

02/28/2020

402838

Annual Review of the Columbia Generating Station

Radiation Protection Program to Meet 10 CFR 20.1101(c)

Requirements

03/25/2020

71124.03

Corrective Action

Documents

Action Request

(AR)

00386503, 00387127, 00387272, 00387564, 00388740,

00390148, 00400231, 00401759, 00403834, 00404159,

00404572, 00404573, 00404716, 00404977, 00405381,

00405882

Drawings

SD000195

Radwaste Building HVAC

011

SD000201

Control Room, Cable Room, and Critical Switchgear Rooms

- HVAC

016

Miscellaneous

CAM Locations and Potential Sources

Breathing Air Sample Analysis - SCBA Compressor

03/18/2020

Personal

Qualification Data

(PQD)

Self-Contained Breathing Apparatus qualified personal with

qualification dates

03/17/2020

Procedures

GEN-RPP-05

Respiratory Protection Program Description

015

GEN-RPP-10

Use of Respiratory Equipment

012

HPI-15.1

Inspection and Storage of Respirators and Attachments

012

30

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HPI-15.5

Set-up and Use of Bullard Air Line Filters

003

HPI-8.2

Quantitative Respirator Fit Testing Using the PortaCount

System

029

PPM 11.2.11.3

Issuance of Respiratory Equipment

017

PPM 11.2.15.11

Use and Certification of Portable Air Handling Units

015

PPM 12.5.36

Service Air Sampling

005

Self-Assessments 378162

Respiratory Protection Program Self -Assessment

03/12/2020

402740

71124.03 SnapShot Self-Assessment

Work Orders

0211048501

Sample Plant Breathing Air

01/30/2019

0211048601

Sample Plant Breathing Air

04/25/2019

SCBA Inspections 02142336, 02147151, 0215236, 02133230

71124.04

Corrective Action

Documents

Action Request

(AR)

00339377; 00374271; 00382896; 00393990; 00393998;

00394156; 00394272; 00395067; 00395101; 00397889

Miscellaneous

Summary of Internal Exposure (5/21/2018 to Present)

06/22/2020

Columbia Generating Station Scaling Factors

03/12/2018

Columbia Generating Station Scaling Factor

03/12/2018

Columbia Generating Station CRE/Source Term Reduction

5-Year Plan

2020

100518-0

NVLAP Ionizing Radiation Dosimetry Accreditation

01/01/2020

NRC Form 5

Declared Pregnant Workers Annual Dose Forms

2018-2019

Procedures

11.2.13.8

Airborne Radioactivity Surveys

019

11.2.15.13

Control of Personnel Skin and Clothing Contamination

004

11.2.4.5

Whole Body Counts and Daily Checks Using the

Renaissance FASTSCAN

016

11.2.4.6

In Vitro Bioassay Sampling and Analysis

003

GEN-RPP-06

Dosimetry Program Description

013

HPI-0.19

Radiation Protection Standards and Expectations

019

HPI-5.9

Evaluation of In-Vivo Bioassay Results Following a Potential

Intake

014

SWP-RPP-01

Radiation Protection Program

016

Radiation Work

Permits (RWPs)

30004447

2018 Reactor 606 Badger Testing

000

30004470

2019 Reactor 522 and Reactor 548 RWCU Flow -

LHRA/High Risk

000

31

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Self-Assessments 00401801

Pre-Inspection Self-Assessment of the Columbia Generating

Station Internal and External Dosimetry Programs

04/09/2020

71151

Miscellaneous

MSPI Cooling Water System Derivation Reports

09/02/2020

MSPI Emergency AC Power System Derivation Reports

09/02/2020

MSPI Heat Removal System Derivation Report

09/02/2020

MSPI High Pressure Injection System Derivation Reports

09/02/2020

MSPI Residual Heat Removal System Derivation Reports

09/02/2020

Control Room Operator Logs for 7/1/2019 to 6/30/2020

Procedures

HPI-0.14

Assessing and Reporting NRC Occupational Exposure

Control Effectiveness Performance Indicator Data

006

Self-Assessments 387312

RETS/ODCM PI Verification Snapshot Self-Assessment

Report

05/11/2019

401807

Occupational Exposure Control Performance Indicator

Snapshot Self-Assessment Report

02/11/2020

71153

Corrective Action

Documents

Action Requests

(ARs)

408616, 408618, 408620, 408622, 408724, 408741, 404829,

410817

Drawings

E504-1

Vital One Line Diagram

006

Engineering

Changes

8818

Critical Instrument Bus and Alternate Source Power

11/28/2011

Miscellaneous

Operator Logs: July 10 - 11, 2020

07/11/2020

Position Paper for Operator Convenience

07/10/2020

Procedures

1.3.16

Issue Management

002

4.800.C1

800.C1 Annunciator Panel Alarms

031

ABN-ELEC-INV

120 VAC Critical Distribution System Failures

017

ABN-FWH-

HILEVEL/TRIP

Feedwater Heater High Level Trip

007

ABN-POWER

Unplanned Reactor Power Change

016

SOP-ELEC-IN3-

OPS

IN3 Operations

013

Work Orders

02131744, 02169264, 02169265