ML16343B008

From kanterella
Jump to navigation Jump to search

Final Safety Evaluation of Technical Specifications Task Force Traveler TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control (Tac No. MF3487)
ML16343B008
Person / Time
Site: Technical Specifications Task Force
Issue date: 12/20/2016
From: Klein A
NRC/NRR/DSS
To:
Technical Specifications Task Force
Honcharik M
Shared Package
ML16343B066 List:
References
TAC MF3487
Download: ML16343B008 (58)


Text

December 20, 2016 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852

SUBJECT:

FINAL SAFETY EVALUATION OF TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-542, REVISION 2, "REACTOR PRESSURE VESSEL WATER INVENTORY CONTROL" (TAC NO. MF3487)

Dear Members of the Technical Specifications Task Force:

By letter dated March 14, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16074A448), the Technical Specifications Task Force (TSTF) submitted to the U.S. Nuclear Regulatory Commission (NRC) for review and approval traveler TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control.

By letter dated October 11, 2016 (ADAMS Package Accession No. ML16250A231), an NRC draft safety evaluation (SE) and draft Model SE of traveler TSTF-542 were provided for your review and comments. By letter dated November 4, 2016 (ADAMS Accession No. ML16309A015), you commented on the SEs and provided editorial corrections to the traveler. The NRC staffs final SE and final Model SE are enclosed with this letter.

The traveler TSTF-542, Revision 2, is applicable to boiling water reactor (BWR) nuclear power plants and was submitted as part of the consolidated line item improvement process (CLIIP).

The proposed change revises Revision 4 of the Standard Technical Specifications (STS),

Volumes 1 and 2 of NUREG-1433, Standard Technical Specifications General Electric Plants BWR/4, and NUREG-1434, Standard Technical Specifications General Electric Plants, BWR/6. Volume 1 of these NUREGs can be accessed in ADAMS under Accession Nos. ML12104A192 and ML12104A195, respectively. Volume 2 of these NUREGs can be accessed in ADAMS under Accession Nos. ML12104A193 and ML12104A196, respectively.

Our SE applies only to material provided in the subject traveler. When a licensee submits a license amendment request (LAR) to adopt the traveler, the NRC staff review will ensure that the material presented applies to the specific plant involved. We do not intend to repeat a technical review of the material provided in the traveler. Licensees are responsible for reviewing the NRC staffs SEs and the applicable technical justifications, providing any necessary plant-specific information, and assessing the completeness and accuracy of their LAR. The NRC will process each LAR to adopt this traveler according to applicable NRC rules and procedures. Even though TSTF-542 was submitted under the CLIIP, due to the anticipated size and quantity of LARs, the NRC staff may not be able to complete the LAR reviews in the typical 6-month timeframe for CLIIP LARs.

The traveler TSTF-542, Revision 2, does not prevent licensees from requesting an alternate approach or proposing changes other than those in TSTF-542, Revision 2. However, significant changes from the approach recommended or the inclusion of additional changes in the LAR will require additional NRC staff review, remove the LAR from the CLIIP, increase the time and

TSTF resources needed for the review, and/or result in non-acceptance of the LAR. Licensees desiring significant or additional changes should instead submit an LAR that does not claim to adopt TSTF-542, Revision 2.

If you have any questions, please contact Michelle Honcharik at 301-415-1774 or via e-mail at Michelle.Honcharik@nrc.gov.

Sincerely,

/RA/

Alexander R. Klein, Chief Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation Project No.: 753

Enclosures:

As stated cc: See next page

Package: ML16343B066; Cover letter and final traveler SE: ML16343B008; Final Model SE: ML16343B065, *concurred via e-mail NRR-106 OFFICE NRR/DPR/PLPB NRR/DPR/PLPB* NRR/DSS/SRXB* NRR/DE/EICB* NRR/DORL/BC NAME MHoncharik DHarrison EOesterle MWaters DWrona DATE 11/22/16 6/27/16 9/23/16 9/23/16 9/23/16 OFFICE DRA/ARCB* DSS/SBPB* OGC* DPR/PLPB DSS/STSB NAME UShoop RDennig DRoth MHoncharik AKlein DATE 9/23/16 9/22/16 12/9/16 12/14/16 12/20/16 Technical Specifications Task Force Project No. 753 cc:

Technical Specifications Task Force Otto W. Gustafson c/o EXCEL Services Corporation Entergy Nuclear Operations, Inc.

11921 Rockville Pike, Suite 100 Palisades Nuclear Power Plant Rockville, MD 20852 27780 Blue Star Memorial Highway Attention: Brian D. Mann Covert, MI 49043 E-mail: brian.mann@excelservices.com E-mail: ogustaf@entergy.com James R. Morris Michael K. Leisure Diablo Canyon Power Plant Duke Energy Building 104/5/21A 526 S. Church Street P.O. Box 56 Mail Code EC2ZF Avila Beach, CA 93424 Charlotte, NC 28202 E-mail: JY1E@pge.com E-mail: mike.leisure@duke-energy.com Lisa L. Williams Jason P. Redd Energy Northwest Southern Nuclear Operating Company Columbia Generating Station 42 Inverness Center Parkway PO Box 968 Bin B234 Mail Drop PE20 Birmingham, AL 35242-4809 Richland, WA 99352-0968 E-mail: jpredd@southernco.com E-mail: llwilliams@energy-northwest.com

FINAL SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-542, REVISION 2, REACTOR PRESSURE VESSEL WATER INVENTORY CONTROL

1.0 INTRODUCTION

By letter dated December 31, 2013 (Agencywide Document Access and Management System (ADAMS) Accession No. ML14002A112), the Technical Specifications (TS) Task Force (TSTF) submitted traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 0, for U.S. Nuclear Regulatory Commission review and approval. By letter dated September 15, 2015, the TSTF submitted Revision 1 to traveler TSTF-542 (ADAMS Accession No. ML15258A850), and by letter dated March 14, 2016, submitted Revision 2 to traveler TSTF-542 (ADAMS Accession No. ML16074A448). Traveler TSTF-542 proposes changes to the Standard Technical Specifications (STSs) and Bases for boiling water reactor (BWR) designs BWR/4 and BWR/6.1 The changes would be incorporated into future revisions of NUREG-1433, Volumes 1 and 2 and NUREG-1434, Volumes 1 and 2. NUREG-1433 is based on the BWR/4 plant design, but is also representative of the BWR/2, BWR/3, and, in some cases, BWR/5 designs. NUREG-1434 is based on the BWR/6 plant design, and is representative, in many cases, of the BWR/5 design.

The proposed changes would replace the existing specifications related to Operation with a Potential for Draining the Reactor Vessels (OPDRVs) with revised specifications for Reactor Pressure Vessel Water Inventory Control (RPV WIC).

Throughout this safety evaluation (SE), items that are enclosed in square brackets signify plant-specific nomenclature or values. Individual licensees would furnish site-specific nomenclature or values for bracketed items when submitting a license amendment request (LAR) to adopt the changes described in this SE.

1 U.S. Nuclear Regulatory Commission, Standard Technical Specifications, General Electric BWR/4 Plants, NUREG-1433, Vol. 1, Specifications, Rev. 4.0, April 2012, ADAMS Accession No. ML12104A192.

U.S. Nuclear Regulatory Commission, Standard Technical Specifications, General Electric BWR/4 Plants, NUREG-1433, Vol. 2, Bases, Rev. 4.0, April 2012, ADAMS Accession No. ML12104A193.

U.S. Nuclear Regulatory Commission, Standard Technical Specifications, General Electric BWR/6 Plants, NUREG-1434, Vol. 1, Specifications, Rev. 4.0, April 2012, ADAMS Accession No. ML12104A195.

U.S. Nuclear Regulatory Commission, Standard Technical Specifications, General Electric BWR/6 Plants, NUREG-1434, Vol. 2, Bases, Rev. 4.0, April 2012, ADAMS Accession No. ML12104A196.

ENCLOSURE 1

2.0 REGULATORY EVALUATION

2.1 TECHNICAL SPECIFICATIONS Section IV, The Commission Policy, of the Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors (58 Federal Register 39132), dated July 22, 1993, states in part:

The purpose of Technical Specifications is to impose those conditions or limitations upon reactor operation necessary to obviate the possibility of an abnormal situation or event giving rise to an immediate threat to the public health and safety by identifying those features that are of controlling importance to safety and establishing on them certain conditions of operation which cannot be changed without prior Commission approval.

[T]he Commission will also entertain requests to adopt portions of the improved STS [(e.g., TSTF-542)], even if the licensee does not adopt all STS improvements The Commission encourages all licensees who submit Technical Specification related submittals based on this Policy Statement to emphasize human factors principles In accordance with this Policy Statement, improved STS have been developed and will be maintained for [BWR designs]. The Commission encourages licensees to use the STS as the basis for plant-specific Technical Specifications

[I]t is the Commission intent that the wording and Bases of the improved STS be used [] to the extent practicable.

2.2 SYSTEM DESCRIPTION The BWR RPVs have a number of penetrations located below the top of active fuel (TAF).

These penetrations provide entry for control rods, recirculation flow, and shutdown cooling.

Since these penetrations are below the TAF, this creates a potential to drain the reactor vessel water inventory and lose effective core cooling. The loss of water inventory and effective core cooling can potentially lead to fuel cladding failure and radioactive release.

During operation in Modes 1 (Power Operation - Reactor Mode Switch in Run), 2 (Startup -

Reactor Mode Switch in Refuel (with all reactor vessel head closure bolts fully tensioned or Startup/Hot Standby), and 3 (Hot Shutdown - Reactor Mode Switch in Run and average reactor coolant temperature > [200] Fahrenheit (F)), the TS for instrumentation and emergency core cooling systems (ECCS) require operability of sufficient equipment to ensure large quantities of water will be injected into the vessel should level decrease below the preselected value. These requirements are designed to mitigate the effects of a loss-of-coolant accident (LOCA), but also provide protection for other accidents and transients that involve a water inventory loss.

During BWR operation in Mode 4 (Cold Shutdown - Reactor Mode Switch in Shutdown with all reactor vessel head closure bolts fully tensioned and average reactor coolant temperature

[200] °F), and Mode 5 (Refueling - One or more reactor vessel head closure bolts less than fully tensioned and Reactor Mode Switch in Shutdown or Refuel), the pressures and temperatures that could cause a LOCA are not present. During certain phases of refueling (Mode 5) a large volume of water is available above the RPV (i.e., the RPV head is removed, the water level is [23 feet] over the top of the RPV flange, and the spent fuel storage pool gates are removed in NUREG-1433, or the upper containment pool is connected to the RPV in NUREG-1434.

The large volume of water available in and above the RPV (during much of the time when in Mode 5) provides time for operator detection and manual operator action to stop and mitigate an RPV draining event. However, typically at other times during a refueling outage, during cold shutdown (Mode 4) or refueling (Mode 5), there may be a potential for significant drainage paths from certain outage activities, human error, and other events when it is more likely to have some normally available equipment, instrumentation, and systems inoperable due to maintenance and outage activities. There may not be as much time for operator action as compared to times when there are large volumes of water above the RPV.

In comparison to Modes 1, 2, and 3, with typical high temperatures and pressures (especially in Modes 1 and 2), Modes 4 and 5 generally do not have the high pressure and temperature considered necessary for a LOCA envisioned from a high energy pipe failure. Thus, while the potential sudden loss of large volumes of water from a LOCA are not expected, operators monitor for BWR RPV water level decrease from potential significant or even unexpected drainage paths. These potential drainage paths in Modes 4 and 5 generally would require less water replacement capability to maintain water above TAF.

To address the drain down potential during Modes 4 and 5, the current BWR STS contain specifications that are applicable during an OPDRV, or require suspension of OPDRVs if certain equipment is inoperable. The term OPDRV is not specifically defined in the TS and historically has been subject to inconsistent application by licensees. The changes discussed in this SE are intended to resolve any ambiguity by creating a new RPV water inventory control TS with attendant equipment operability requirements, required actions and surveillance requirements (SR) and deleting references to OPDRVs throughout the TS.

2.3 CHANGES TO THE STS The proposed changes would (1) provide a definition of a new term, DRAIN TIME; (2) revise and rename STS 3.5.2 as Reactor Pressure Vessel Water Inventory Control; (3) provide a new TS 3.3.5.2, Reactor Pressure Vessel Water Inventory Control Instrumentation; and (4) delete existing references to operations with the potential to drain the reactor pressure vessel throughout the STS. The descriptions of the proposed changes are provided in this section.

Corresponding changes are proposed to the STS Bases. A summary of the revised STS Bases and the staffs evaluation of the revised Bases are provided in an attachment of this SE.

2.3.1 Insertion of New Definition of DRAIN TIME The following definition of DRAIN TIME would be added to Section 1.1, Definitions Section of the STS:

The DRAIN TIME is the time it would take for the water inventory in and above the Reactor Pressure Vessel (RPV) to drain to the top of the active fuel (TAF) seated in the RPV assuming:

a) The water inventory above the TAF is divided by the limiting drain rate; b) The limiting drain rate is the larger of the drain rate through a single penetration flow path with the highest flow rate, or the sum of the drain rates through multiple penetration flow paths susceptible to a common Mode failure (e.g., seismic event, loss of normal power, single human error), for all penetration flow paths below the TAF except:

1. Penetration flow paths connected to an intact closed system, or isolated by manual or automatic valves that are locked, sealed, or otherwise secured in the closed position, blank flanges, or other devices that prevent flow of reactor coolant through the penetration flow paths;
2. Penetration flow paths capable of being isolated by valves that will close automatically without offsite power prior to the RPV water level being equal to the TAF when actuated by RPV water level isolation instrumentation; or
3. Penetration flow paths with isolation devices that can be closed prior to the RPV water level being equal to the TAF by a dedicated operator trained in the task, who is in continuous communication with the control room, is stationed at the controls, and is capable of closing the penetration flow path isolation device without offsite power.

c) The penetration flow paths required to be evaluated per paragraph b) are assumed to open instantaneously and are not subsequently isolated, and no water is assumed to be subsequently added to the RPV water inventory; d) No additional draining events occur; and e) Realistic cross-sectional areas and drain rates are used.

A bounding DRAIN TIME may be used in lieu of a calculated value.

2.3.2 Changes to STS Section 3.5:

2.3.2.1 Title of TS 3.5 The title of Section 3.5 is being revised from Emergency Core Cooling System (ECCS) and Reactor Core Isolation Cooling System (RCIC) to Emergency Core Cooling Systems (ECCS),

RPV Water Inventory Control, and Reactor Core Isolation Cooling (RCIC) System.

2.3.2.2 Title of TS 3.5.2 The title of TS 3.5.2 is being revised from ECCS - Shutdown to Reactor Pressure Vessel (RPV) Water Inventory Control.

2.3.2.3 LCO 3.5.2 STS Limiting Condition for Operation (LCO) 3.5.2 currently states Two low pressure ECCS injection/spray subsystems shall be OPERABLE. The LCO note currently states: One LPCI subsystem may be considered OPERABLE during alignment and operation for decay heat removal if capable of being manually realigned and not otherwise inoperable.

STS LCO 3.5.2 for NUREG-1433 would be revised to state:

DRAIN TIME of RPV water inventory to the top of active fuel (TAF) shall be 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

AND One low pressure ECCS injection/spray subsystem shall be OPERABLE.

The note for LCO 3.5.2 would be revised to state:

A Low Pressure Coolant Injection (LPCI) subsystem may be considered OPERABLE during alignment and operation for decay heat removal if capable of being manually realigned and not otherwise inoperable.

For NUREG-1434, the phrase low pressure is omitted because the High Pressure Core Spray system (HPCS) may be used to satisfy this requirement.

2.3.2.4 Applicability of TS LCO 3.5.2 For NUREG-1433, LCO 3.5.2 is currently applicable in Mode 4 and in Mode 5, except with the spent fuel storage pool gates removed and water level [23 ft] over the top of the reactor pressure vessel flange.

For NUREG-1434, LCO 3.5.2 is currently applicable in Mode 4 and Mode 5 except with the upper containment [cavity to dryer] pool [gate] removed and water level [22 ft 8 inches] over the top of the reactor pressure vessel flange.

The applicability would be revised to be MODES 4 and 5, with no exceptions.

2.3.2.5 Actions Table of TS 3.5.2 The existing Actions Table of TS 3.5.2 for NUREG-1433 states:

CONDITION REQUIRED ACTION COMPLETION TIME A. One required ECCS A.1 Restore required ECCS 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> injection/spray injection/spray subsystem to subsystem inoperable. OPERABLE status.

B. Required Action and B.1 Initiate action to suspend Immediately associated Completion operations with a potential for Time of Condition A not draining the reactor vessel met. (OPDRVs).

C. Two required ECCS C.1 Initiate action to suspend Immediately injection/spray OPDRVs.

subsystems inoperable.

AND C.2 Restore one ECCS injection/spray 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> subsystem to OPERABLE status.

D. Required Action C.2 and D.1 Initiate action to restore Immediately associated Completion [secondary] containment to Time not met. OPERABLE status.

AND D.2 [Initiate action to restore one Immediately]

standby gas treatment subsystem to OPERABLE status.

AND D.3 Initiate action to restore isolation Immediately capability in each required

[secondary] containment penetration flow path not isolated.

The revised TS 3.5.2 Actions Table for NUREG-1433 would state:

CONDITION REQUIRED ACTION COMPLETION TIME A. Required ECCS A.1 Restore required ECCS 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> injection/spray subsystem injection/spray subsystem to inoperable. OPERABLE status.

B. Required Action and B.1 Initiate action to establish a Immediately associated Completion method of water injection capable

Time of Condition A not of operating without offsite met. electrical power.

C. DRAIN TIME < 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> C.1 Verify [secondary] containment 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. boundary is capable of being established in less than the DRAIN TIME.

AND C.2 Verify each [secondary] 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> containment penetration flow path is capable of being isolated in less than the DRAIN TIME.

AND C.3 Verify one standby gas treatment 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> subsystem is capable of being placed in operation in less than the DRAIN TIME.

D. DRAIN TIME < 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. D.1 --------------NOTE------------

Required ECCS injection/spray subsystem or additional method of water injection shall be capable of operating without offsite electrical power.

Initiate action to establish an Immediately additional method of water injection with water sources capable of maintaining RPV water level > TAF for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

AND D.2 Initiate action to establish Immediately

[secondary] containment boundary AND D.3 Initiate action to isolate each Immediately

[secondary] containment penetration flow path or verify it can be manually isolated from the control room.

AND

D.4 Initiate action to verify one Immediately standby gas treatment subsystem is capable of being placed in operation.

E. Required Action and E.1 Initiate action to restore DRAIN Immediately associated Completion TIME to 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

Time of Condition C or D not met.

OR DRAIN TIME < 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

The existing Actions Table of TS 3.5.2 for NUREG-1434 states:

CONDITION REQUIRED ACTION COMPLETION TIME A. One required ECCS A.1 Restore required ECCS 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> injection/spray subsystem injection/spray subsystem to inoperable. OPERABLE status.

B. Required Action and B.1 Initiate action to suspend Immediately associated Completion operations with a potential for Time of Condition A not draining the reactor vessel met. (OPDRVs).

C. Two required ECCS C.1 Initiate action to suspend Immediately injection/spray subsystems OPDRVs.

inoperable.

AND C.2 Restore one ECCS 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> injection/spray subsystem to OPERABLE status.

D. Required Action C.2 and D.1 Initiate action to restore Immediately associated Completion [secondary containment] to Time not met. OPERABLE status.

AND D.2 [Initiate action to restore one Immediately]

standby gas treatment subsystem to OPERABLE status.

AND D.3 Initiate action to restore Immediately isolation capability in each required [secondary

containment] penetration flow path not isolated.

The revised TS 3.5.2 ACTIONS Table for NUREG-1434 would state:

CONDITION REQUIRED ACTION COMPLETION TIME A. Required ECCS A.1 Restore required ECCS 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> injection/spray subsystem injection/spray subsystem to inoperable. OPERABLE status.

B. Required Action and B.1 Initiate action to establish a Immediately associated Completion method of water injection Time of Condition A not capable of operating without met. offsite electrical power.

C. DRAIN TIME < 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> C.1 Verify [secondary containment] 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. boundary is capable of being established in less than the DRAIN TIME.

AND C.2 Verify each [secondary 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> containment] penetration flow path is capable of being isolated in less than the DRAIN TIME.

AND C.3 [Verify one standby gas 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />s]

treatment subsystem is capable of being placed in operation in less than the DRAIN TIME.

D. DRAIN TIME < 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. D.1 --------------NOTE------------

Required ECCS injection/spray subsystem or additional method of water injection shall be capable of operating without offsite electrical power.

Initiate action to establish an additional method of water Immediately injection with water sources capable of maintaining RPV water level > TAF for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

AND

D.2 Initiate action to establish Immediately

[secondary containment]

boundary.

AND D.3 Initiate action to isolate each Immediately

[secondary containment]

penetration flow path or verify it can be manually isolated from the control room.

AND D.4 [Initiate action to verify one Immediately]

standby gas treatment subsystem is capable of being placed in operation.

E. Required Action and E.1 Initiate action to restore DRAIN Immediately associated Completion TIME to 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

Time of Condition C or D not met.

OR DRAIN TIME < 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

2.3.2.6 TS 3.5.2 Surveillance Requirements The NUREG-1433 TS 3.5.2 currently contains the following SRs:

SURVEILLANCE FREQUENCY SR 3.5.2.1 Verify, for each required low pressure coolant [12 hours injection (LPCI) subsystem, the suppression pool water level is [12 ft 2 inches]. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.2 Verify, for each required core spray (CS) [12 hours subsystem, the:

OR

a. Suppression pool water level is

[12 ft 2 inches] or In accordance with the Surveillance Frequency

b. -----------------NOTE----------------------------- Control Program]

Only one required CS subsystem may take credit for this option during OPDRVS.

Condensate storage tank water level is [12 ft].

SR 3.5.2.3 Verify, for each required ECCS injection/spray [31 days subsystem, the piping is filled with water from the pump discharge valve to the injection valve. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.4 Verify each required ECCS injection/spray [31 days subsystem manual, power operated, and automatic valve in the flow path, that is not locked, sealed, or OR otherwise secured in position, is in the correct position. In accordance with the Surveillance Frequency Control Program]

The revised SRs for NUREG-1433 would be:

SURVEILLANCE FREQUENCY SR 3.5.2.1 Verify DRAIN TIME 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. [12 hours OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.2 Verify, for a required low pressure ECCS [12 hours injection/spray subsystem, the suppression pool water level is [12 ft 2 inches]. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.3 Verify, for a required Core Spray (CS) System, the: [12 hours

a. Suppression pool water level is OR

[12 ft 2 inches] or In accordance with the

b. Condensate storage tank water level is Surveillance Frequency

[12 ft]. Control Program]

SR 3.5.2.4 Verify, for the required ECCS injection/spray [31 days subsystem, the piping is filled with water from the pump discharge valve to the injection valve. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.5 Verify, for the required ECCS injection/spray [31 days subsystem each manual, power operated, and automatic valve in the flow path, that is not locked, OR sealed, or otherwise secured in position, is in the correct position. In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.6 Operate the required ECCS injection/spray [92 days subsystem through the recirculation line for 10 minutes. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.7 Verify each valve credited for automatically isolating ((18] months a penetration flow path actuates to the isolation position on an actual or simulated isolation signal. OR

In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.8 --------------------------------------NOTE----------------------- ((18] months Vessel injection/spray may be excluded.


OR Verify the required ECCS injection/spray subsystem actuates on a manual initiation signal. In accordance with the Surveillance Frequency Control Program ]

The corresponding NUREG-1434 TS 3.5.2 currently contains the following SRs:

SURVEILLANCE FREQUENCY SR 3.5.2.1 Verify, for each required low pressure ECCS [12 hours injection/spray subsystem, the suppression pool water level is [12.67 ft]. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.2 Verify, for the required High Pressure Core Spray [12 hours (HPCS) subsystem, the:

OR

a. Suppression pool water level is [12.67 ft] or In accordance with the
b. Condensate storage tank water level is [18 ft]. Surveillance Frequency Control Program]

SR 3.5.2.3 Verify, for the required ECCS injection/spray [31 days subsystem, the piping is filled with water from the pump discharge valve to the injection valve. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.4 Verify each required ECCS injection/spray subsystem [31 days manual, power operated, and automatic valve in the flow path, that is not locked, sealed, or otherwise OR secured in position, is in the correct position.

In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.5 Verify each required ECCS pump develops the [In accordance with specified flow rate [against a system head the Inservice Testing corresponding to the specified reactor pressure]. Program

[System Head OR Corresponding to A Reactor [92 days]

System Flow Rate Pressure of]

LPCS [7115]gpm [290]psig OR LPCI [7450]gpm [125]psig HPCS [7115]gpm [445]psig In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.6 ------------------------------------NOTE--------------------------- [18months Vessel injection/spray may be excluded.


OR Verify each required ECCS injection /spray In accordance with the subsystem actuates on an actual or simulated Surveillance automatic initiation signal. Frequency Control Program]

The revised SRs for NUREG-1434 would be:

SURVEILLANCE FREQUENCY SR 3.5.2.1 Verify DRAIN TIME 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. [12 hours OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.2 Verify, for a required low pressure ECCS [12 hours injection/spray subsystem, the suppression pool water level is [12.67 ft]. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.3 Verify, for a required High Pressure Core Spray [12 hours (HPCS) System, the:

OR

a. Suppression pool water level is [12.67 ft] or In accordance with the Surveillance
b. Condensate storage tank water level is Frequency Control

[18 ft]. Program]

SR 3.5.2.4 Verify, for the required ECCS injection/spray [31 days subsystem, the piping is filled with water from the pump discharge valve to the injection valve. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.5 Verify, for the required ECCS injection/spray [31 days subsystem each manual, power operated, and automatic valve in the flow path, that is not locked, OR sealed, or otherwise secured in position, is in the correct position. In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.6 Operate the required ECCS injection/spray [92 days subsystem through the recirculation line for 10 minutes. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.7 Verify each valve credited for automatically isolating a ((18] months penetration flow path actuates to the isolation position on an actual or simulated isolation signal. OR In accordance with the Surveillance Frequency Control Program]

SR 3.5.2.8 --------------------------------------NOTE------------------------- ((18] months Vessel injection/spray may be excluded.


OR Verify the required ECCS injection/spray subsystem actuates on a manual initiation signal. In accordance with the Surveillance Frequency Control Program]

2.3.3 Changes to STS Section 3.3 Both NUREG-1433 and NUREG-1434 STS contain two versions of certain specifications in Section 3.3, Instrumentation. One is applicable for licensees that have not adopted a Setpoint Control Program (the A version) and the other is applicable for licensees that have adopted a

Setpoint Control Program (the B version). In the A version of the STS, the Allowable Value column is retained in the Instrumentation Table, and the Instrumentation Table contains footnotes that provide details regarding SRs. In the B version of the STS, the Allowable Value has been relocated to the licensee-controlled Setpoint Control Program, and this column does not appear in the Instrumentation Table. Additionally, in the B version, the footnotes that provide details regarding SRs are not necessary. This convention is retained in the revised STS LCOs discussed in this section.

For simplicity, the description of changes in this section is presented with the A and B versions combined.

2.3.3.1 Changes to STS LCOs 3.3.5.1A and 3.3.5.1B, Emergency Core Cooling System (EECS) Instrumentation (Without and With Setpoint Control Program),

respectively The STS LCOs 3.3.5.1A and 3.3.5.1B state that "the ECCS instrumentation for each Function in Table 3.3.5.1-1, [Emergency Core Cooling System Instrumentation,] shall be OPERABLE with the applicability as stated in the table. Table 3.3.5.1-1 currently contains requirements for function operability during Modes 4 and 5 when associated ECCS subsystem(s) are required to be operable per LCO 3.5.2, ECCS - Shutdown. Throughout this table, the applicability in Modes 4 and 5 is being deleted because the instrumentation requirements during shutdown are being consolidated into the new STS 3.3.5.2. Conforming changes are made to the ACTIONS Table of STS LCO 3.3.5.1A and 3.3.5.1B.

2.3.3.2 Insertion of new STS 3.3.5.2A and 3.3.5.2B, Reactor Pressure Vessel (RPV)

Water Inventory Control Instrumentation (Without and With Setpoint Control Program), respectively A new STS 3.3.5.2 is proposed to provide alternative instrumentation requirements to support manual initiation of the ECCS injection/spray subsystem required in new STS 3.5.2 and automatic isolation of penetration flow paths that may be credited in the determination of drain time. The current STS contain instrumentation requirements related to OPDRVs in four TS.

These requirements are being consolidated into new STS 3.3.5.2.

The existing STS 3.3.5.2, Reactor Core Isolation Cooling (RCIC) System Instrumentation, is being renumbered to 3.3.5.3 in order to maintain the STS numbering conventions in the NUREGs.

2.3.3.2.1 New TS 3.3.5.2A and B LCO and Applicability The proposed LCO 3.3.5.2 states:

The RPV Water Inventory Control instrumentation for each Function in Table 3.3.5.2-1 shall be OPERABLE.

The applicability states, "According to Table 3.3.5.2-1."

The following sections describe the instrumentation functions contained in the new Table 3.3.5.2-1.

2.3.3.2.2 NUREG-1433 New Table 3.3.5.2-1, RPV Water Inventory Control Instrumentation 2.3.3.2.2.1 Function 1.a, Core Spray System, Reactor Steam Dome Pressure - Low (Injection Permissive), and Function 2.a, Low Pressure Coolant Injection (LPCI)

System, Reactor Steam Dome Pressure - Low (Injection Permissive)

These functions were moved from current STS 3.3.5.1, Function 1.c and Function 2.c. The following changes are made:

  • The applicability is changed. The existing STS 3.3.5.1 applicability for these functions in Modes 4 and 5 is modified by a note that limits the applicability to when the associated ECCS subsystem(s) are required to be operable per LCO 3.5.2, "ECCS - Shutdown.

The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control."

  • The number of required channels per function is unchanged.
  • In the new table, a Channel Check and Channel Functional Test are required at the existing frequency. Calibration of the trip units, Channel Calibration, Logic System Functional Test, and ECCS Response Time tests are no longer required in Modes 4 and 5.
  • In new LCO 3.3.5.2A, the Allowable Value is revised to eliminate the low pressure limit and to retain the high pressure limit. The RPV pressure is well below the lower limit in Modes 4 and 5, so the low pressure limit is not needed.

2.3.3.2.2.2 Function 1.b, Core Spray System, Core Spray Pump Discharge Flow - Low (Bypass) and Function 2.b, Low Pressure Coolant Injection (LPCI) System, Low Pressure Coolant Injection Pump Discharge Flow - Low (Bypass)

These functions were moved from current STS 3.3.5.1, Function 1.d and Function 2.g, respectively. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for these functions in Modes 4 and 5 is modified by a note that limits the applicability to when the associated ECCS subsystem(s) are required to be operable per current LCO 3.5.2, "ECCS -

Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control."

  • For Function 1.b, the number of required channels per function is changed from [2] or

[1 per pump], to [1 per pump]. For Function 2.b, the number of required channels per function is changed from [4] or [1 per pump], to [1 per pump]. Both are modified by a note stating "Associated with an ECCS subsystem required to be OPERABLE by LCO 3.5.2, 'Reactor Pressure Vessel Water Inventory Control.'

  • In the new table, a Channel Check and Channel Functional Test are required at the existing frequency. A Channel Calibration and Logic System Functional Test are no longer required in Modes 4 and 5.
  • In new LCO 3.3.5.2A, the allowable value is unchanged.

2.3.3.2.2.3 Function 1.c, Core Spray System, Manual Initiation and Function 2.c, Low Pressure Coolant Injection (LPCI) System, Manual Initiation These functions were moved from current STS 3.3.5.1, Function 1.e and Function 2.h. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for these functions in Modes 4 and 5 is modified by a note that limits the applicability to when the associated ECCS subsystem(s) are required to be operable per current LCO 3.5.2, "ECCS -

Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control.

  • The number of required channels per function is changed from [2] or [1 per subsystem],

to [1 per subsystem] and is modified by a note stating "Associated with an ECCS subsystem required to be OPERABLE by LCO 3.5.2, 'Reactor Pressure Vessel Water Inventory Control.' New LCO 3.5.2 only requires a single ECCS subsystem and the change in required channels reflects that requirement.

  • Both the existing STS 3.3.5.1 and the revised STS 3.3.5.2 require a Logic System Functional Test on this function at the same frequency.
  • There is no allowable value for this function.

2.3.3.2.2.4 Function 3.a, RHR System Isolation, Reactor Vessel Water Level - Low, Level 3 This function was moved from current STS 3.3.6.1, Function 6.b. The following changes are made:

  • The applicability is changed. The existing STS 3.3.6.1 applicability for this function in Modes 4 and 5 is being deleted. The revised applicability is "when automatic isolation of the associated penetration flow path is credited in calculating Drain Time." In other words, if the drain time calculation assumes the RHR system will be automatically isolated, this function must be operable to perform that function. This is consistent with the definition of drain time and the TS 3.5.2 requirements.
  • The number of required channels is changed from [2], with a column header that states "Required Channels per Trip System," to [2 in one trip system]. This retains the requirement that the two channels must be associated with the same trip system.
  • In the new table, a Channel Check and Channel Functional Test are required at the existing frequency. A calibration of the trip unit, Channel Calibration, and Logic System Functional Test are no longer required in Modes 4 and 5.
  • The allowable value is unchanged.

2.3.3.2.2.5 Function 4.a, Reactor Water Cleanup (RWCU) System Isolation, Reactor Vessel Water Level - Low Low, Level 2 This function was relocated from current STS 3.3.6.1, Function 5.e. The following changes are made:

  • The applicability is changed. The current STS 3.3.6.1 applicability for this function is Modes 1, 2, and 3. The revised applicability is "when automatic isolation of the associated penetration flow path is credited in calculating Drain Time. In other words, if the drain time calculation assumes the RWCU system will be automatically isolated, this function must be operable to perform that function. This is consistent with the definition of drain time and the TS 3.5.2 requirements.
  • The number of required channels is changed from [2], with a column header that states "Required Channels per Trip System," to [2 in one trip system]. This retains the requirement that the two channels must be associated with the same trip system. Only one trip system is required to ensure that automatic isolation of one of the two isolation valves will occur on low reactor vessel water level.
  • A Channel Check and Channel Functional Test are required at the existing frequency. A calibration of the trip unit, Channel Calibration, Logic System Functional Test, and Isolation System Response Time tests are no longer required in Modes 4 and 5.
  • The allowable value is unchanged.

2.2.3.2.3 NUREG-1434 New Table 3.3.5.2-1, RPV Water Inventory Control Instrumentation 2.3.3.2.3.1 Function 1.a, Low Pressure Coolant Injection-A (LPCI) and Low Pressure Core Spray (LPCS) Subsystems, Reactor Steam Dome Pressure - Low (Injection Permissive) and Function 2.a, LPCI B and LPCI C Subsystems, Reactor Steam Dome Pressure - Low (Injection Permissive)

These functions were moved from current STS 3.3.5.1, Function 1.d and Function 2.d. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for these functions in Modes 4 and 5 is modified by a note that limits the applicability to when the associated

ECCS subsystem(s) are required to be operable per current LCO 3.5.2, "ECCS -

Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control. Note that NUREG-1434 does not include the Mode 4 and 5 applicability of this function. This apparently was an oversight in development of the NUREG.

  • A Channel Check and Channel Functional Test are required at the existing frequency.

Calibration of the trip units, Channel Calibration, Logic System Functional Test, and ECCS Response Time tests are no longer required in Modes 4 and 5.

  • In new LCO 3.3.5.2A, the allowable value is revised to eliminate the low pressure limit and to retain the high pressure limit.

2.3.3.2.3.2 Functions 1.b and 1.c, Low Pressure Coolant Injection-A (LPCI) and Low Pressure Core Spray (LPCS) Subsystems, LPCS Pump Discharge Flow - Low (Bypass) and LPCI Pump A Discharge Flow - Low (Bypass), and Function 2.b, LPCI B and LPCI C Subsystems, LPCI Pump B and LPCI Pump C Discharge Flow - Low (Bypass)

These functions were moved from current STS 3.3.5.1, Function 1.e, 1.f, and 2.e. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for these functions is Modes 4 and 5 when the associated ECCS subsystem(s) are required to be operable per LCO 3.5.2, "ECCS - Shutdown. The revised Applicability is Modes 4 and 5 without exception, to be consistent with the Applicability of new LCO 3.5.2, "RPV Water Inventory Control."
  • A Channel Check and Channel Functional Test are required at the existing frequency.

Calibrating the trip unit, Channel Calibration and Logic System Functional Test are no longer required in Modes 4 and 5.

  • In new LCO 3.3.5.2A, the allowable value is unchanged.

2.3.3.2.3.3 Function 1.d, Low Pressure Coolant Injection-A (LPCI) and Low Pressure Core Spray (LPCS) Subsystems, Manual Initiation, and Function 2.c, LPCI B and LPCI C Subsystems, Manual Initiation

These functions were moved from current STS 3.3.5.1, Function 1.g and Function 2.f. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 Applicability for these Functions in Modes 4 and 5 is modified by a note that limits the applicability to when the associated ECCS subsystem(s) are required to be operable per current LCO 3.5.2, "ECCS -

Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control."

  • The number of required channels per function is changed from [1] to [1 per subsystem]

and is modified by a note stating "Associated with an ECCS subsystem required to be OPERABLE by LCO 3.5.2, 'Reactor Pressure Vessel Water Inventory Control'. New STS 3.5.2 only requires a single ECCS subsystem and the change in required channels reflects that requirement.

  • Both the existing STS 3.3.5.1 and the revised STS 3.3.5.2 require a Logic System Functional Test on this function at the same frequency.
  • There is no allowable value for this function.

2.3.3.2.3.4 Function 3.a, High Pressure Core Spray(HPCS) System, Reactor Vessel Water Level - High, Level 8 This function was moved from current STS 3.3.5.1, Function 3.c. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for this function is Modes 4 and 5 when the associated ECCS subsystem(s) are required to be operable per existing LCO 3.5.2, "ECCS - Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control."
  • A Channel Check and Channel Functional Test are required at the existing frequency.

Calibration of the trip units, Channel Calibration, and Logic System Functional Test tests are no longer required in Modes 4 and 5.

  • The allowable value in new LCO 3.3.5.2A is unchanged.

2.3.3.2.3.5 Function 3.b, High Pressure Core Spray (HPCS) System, Condensate Storage Tank Level - Low This function was moved from current STS 3.3.5.1, Function 3.d. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for this function is Modes 4 and 5 when the associated ECCS subsystem(s) are required to be operable per current LCO 3.5.2, "ECCS - Shutdown. The revised applicability is Modes 4 and 5 when HPCS is operable for compliance with new LCO 3.5.2 and aligned to the Condensate Storage Tank. If HPCS is not being credited for meeting the new LCO 3.5.2 requirement for an operable ECCS subsystem, or if HPCS is being credited but is aligned to the suppression pool, this function is unneeded.
  • The number of required channels per function is changed from [2] to [1]. New STS 3.5.2 only requires a single ECCS subsystem to be operable, and the change in required channels reflects that requirement.
  • A Channel Check and Channel Functional Test are required at the existing frequency.

Calibration of the trip units, Channel Calibration, and Logic System Functional Test are no longer required in Modes 4 and 5.

  • The allowable value in new LCO 3.3.5.2A is unchanged.

2.3.3.2.3.6 Functions 3.c and 3.d, High Pressure Core Spray (HPCS) System, HPCS Pump Discharge Pressure - High (Bypass) and HPCS System Flow Rate - Low (Bypass)

These functions were moved from current STS 3.3.5.1, Function 3.f and 3.g. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for this function is Modes 4 and 5 when the associated ECCS subsystem(s) are required to be operable per current LCO 3.5.2, "ECCS - Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control."
  • A Channel Check and Channel Functional Test are required at the existing frequency.

Calibration of the trip units, Channel Calibration, and Logic System Functional Test are no longer required in Modes 4 and 5.

  • The allowable value is unchanged.

2.3.3.2.3.7 Function 3.e, High Pressure Core Spray (HPCS) System, Manual Initiation This function is moved from current STS 3.3.5.1, Function 3.h. The following changes are made:

  • The applicability is changed. The current STS 3.3.5.1 applicability for these functions in Modes 4 and 5 is modified by a note that limits the applicability to when the associated ECCS subsystem(s) are required to be operable per existing LCO 3.5.2, "ECCS -

Shutdown. The revised applicability is Modes 4 and 5 without exception, to be consistent with the applicability of new LCO 3.5.2, "RPV Water Inventory Control."

  • The number of required channels per function is changed from [1] to [1 per subsystem]

and is modified by a note stating "Associated with an ECCS subsystem required to be OPERABLE by LCO 3.5.2, 'Reactor Pressure Vessel Water Inventory Control'. New STS 3.5.2 only requires a single ECCS subsystem and the change in required channels reflects that requirement.

  • Both the existing STS 3.3.5.1 and the revised STS 3.3.5.2 require a Logic System Functional Test on this function at the same frequency.
  • There is no allowable value for this function.

2.3.3.2.3.8 Function 4.a, RHR System Isolation Reactor Vessel Water Level - Low, Level 3 This function was moved from current STS 3.3.6.1, Function 5.c. The following changes are made:

  • The applicability is changed. The current STS 3.3.6.1 applicability for this function is Modes 4 and 5. The revised applicability is "when automatic isolation of the associated penetration flow path is credited in calculating drain time.
  • The number of required channels is changed from [2], with a column header that states "Required Channels per Trip System," to [2 in one trip system]. This retains the requirement that the two channels must be associated with the same trip system. Only one trip system is required to ensure automatic isolation of one of the two isolation valves will occur on low reactor vessel water level.
  • A Channel Check and Channel Functional Test are required at the existing frequency. A calibration of the trip unit, Channel Calibration, Logic System Functional Test, and Isolation System Response Time tests are no longer required in Modes 4 and 5.
  • The existing allowable value is retained in new STS 3.3.5.2.

2.3.3.2.3.9 Function 5.a, Reactor Water Cleanup (RWCU) System Isolation, Reactor Vessel Water Level - Low Low, Level 2 This function was relocated from current STS 3.3.6.1, Function 4.k. The following changes are made:

  • The applicability is changed. The current STS 3.3.6.1 applicability is Modes 1, 2, and 3.

The applicability is "when automatic isolation of the associated penetration flow path is credited in calculating Drain Time. In other words, if the drain time calculation assumes the RWCU system would be automatically isolated, this function must be operable to perform that function. This is consistent with the definition of drain time and the new STS 3.5.2 requirements.

  • The number of required channels is changed from [2], with a column header that states "Required Channels per Trip System," to [2 in one trip system]. This retains the requirement that the two channels must be associated with the same trip system. Only one trip system is required to ensure that automatic isolation of one of the two isolation valves will occur on low reactor vessel water level.
  • A Channel Check and Channel Functional Test are required at the existing frequency. A calibration of the trip unit, Channel Calibration, Logic System Functional Test, and Isolation System Response Time tests are no longer required in Modes 4 and 5.
  • The existing allowable value is retained in LCO 3.3.5.2A.

2.3.3.2.4 New TS 3.3.5.2A and B ACTIONS Table Condition A is applicable when one or more instrument channels are inoperable from Table 3.3.5.2-1. Required Action A.1 directs immediate entry into the condition referenced in Table 3.3.5.2-1 for that channel.

Condition B is entered when the RHR system isolation and RWCU system isolation functions operability requirements are not met when automatic isolation of the associated penetration flow path is credited in calculating drain time. If the instrumentation is inoperable, Required Action B.1 directs an immediate declaration that the associated penetration flow path(s) are incapable of automatic isolation. Required Action B.2 requires an immediate calculation of drain time.

Condition C is entered when the Low Reactor Steam Dome Pressure Injection Permissive Functions necessary for ECCS subsystem manual initiation operability requirements are not met. The channel must be placed in the trip condition within one hour.

In NUREG-1433, Condition D is entered when the operability requirements for the Core Spray Pump Discharge Flow - Low Bypass, Low Pressure Coolant Injection Pump Discharge Flow -

Low Bypass, or manual initiation of these functions operability requirements are not met. The Required Action is to restore the channel to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

In NUREG-1434, Condition D is entered when the Condensate Storage Tank Level -Low operability requirements are not met. Required Action D requires declaring the HPCS inoperable and aligning the HPCS pump suction to the suppression pool within one hour.

In NUREG-1433, Condition E is entered if the Required Action and associated Completion Time of Condition C or D, are not met. Required Action E.1 requires the associated low pressure ECCS injection/spray subsystem to be declared inoperable immediately.

In NUREG-1434, Condition E is entered if the Reactor Vessel Water Level - High Level 8 instrumentation operability requirements are not met. Required Action E.1 requires declaring the HCPS system inoperable in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and restoring the channel to Operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

In NUREG-1434, Condition F is entered if the LPCS Pump Discharge Flow Low (Bypass), LPCI Pump A Discharge Flow Low (Bypass), LPCI Pump B and LPCI Pump C Discharge Flow - Low (Bypass), HPCS Pump Discharge Pressure - High (Bypass) HPCS System Flow Rate - Low -

(Bypass) or Manual Initiation associated with these Functions operability requirements are not met. The required action is to restore the channel to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

In NUREG-1434, Condition G is entered if the Required Actions and associated Completion Times of Condition C, D, E, or F is not met. Required Action G.1 requires the associated ECCS injection/spray subsystem to be declared inoperable immediately.

2.3.3.2.5 New Surveillance Requirements SR 3.3.5.2.1, 3.3.5.2.2, and 3.3.5.3 New Table 3.3.5.2-1 specifies which SRs apply for each ECCS function.

SR 3.3.5.2.1 requires the performance of a Channel Check at a Frequency of [12 hours or in accordance with the Surveillance Frequency Control Program.]

SR 3.3.5.2.2 requires the performance of a Channel Functional Test at a Frequency of ((92]

days or in accordance with the Surveillance Frequency Control Program.]

SR 3.3.5.2.3 requires the performance of a Logic System Functional Test at a Frequency of

((18] months or in accordance with the Surveillance Frequency Control Program.]

2.3.3.3 Changes to Containment, Containment Isolation Valve and Standby Gas Treatment System Requirements The following TS are applicable during OPDRVs and/or contain Actions to suspend OPDRVs when the LCO is not met:

NUREG-1433 3.6.1.3, Primary Containment Isolation Valves 3.6.4.1, [Secondary] Containment 3.6.4.2, Secondary Containment Isolation Valves 3.6.4.3, Standby Gas Treatment System

NUREG-1434 3.6.1.3, Primary Containment Isolation Valves 3.6.4.1, [Secondary] Containment 3.6.4.2, Secondary Containment Isolation Valves 3.6.4.3, Standby Gas Treatment System For each of these TS, the applicability and required action sections are being revised to delete references to OPDRVs.

2.3.3.4 Changes to Control Room Habitability and Temperature Control Requirements NUREG-1433 3.7.4, [Main Control Room Environmental Control (MCREC)] System 3.7.5, [Control Room Air Conditioning (AC)] System NUREG-1434 3.7.3, [Control Room Fresh Air (CRFA)] System 3.7.4, [Control Room AC] System These LCOs are currently applicable during OPDRVs and contain required actions to immediately initiate action to suspend OPDRVs when certain conditions of the LCO are not met.

The references to OPDRVs are being deleted from the applicability and required actions of these TS.

2.3.3.5 Changes to Electrical Sources Requirements NUREG-1433 and NUREG-1434 3.8.2, AC Sources - Shutdown 3.8.5, DC Sources - Shutdown 3.8.8, Inverters - Shutdown 3.8.10, Distribution Systems - Shutdown These TS are applicable in Modes 4 and 5 and currently contain a required action to initiate action to suspend operations with a potential for draining the reactor vessel immediately if certain conditions are not met.

TS 3.8.2 currently requires, in part, with one required offsite circuit inoperable or one required diesel generator inoperable, to initiate action to suspend operations with a potential for draining the reactor vessel immediately.

TS 3.8.5 currently requires, in part, with one [or more] required DC electrical power subsystem[s] inoperable for reasons other than an inoperable battery charger, to initiate action to suspend operations with a potential for draining the reactor vessel immediately.

TS 3.8.8 currently requires, in part, with one [or more] [required] inverter[s] inoperable, to initiate action to suspend operations with a potential for draining the reactor vessel immediately.

TS 3.8.10 currently requires, in part, with one or more required AC, DC, [or AC vital bus]

electrical power distribution subsystems inoperable, to initiate action to suspend operations with a potential for draining the reactor vessel immediately.

These required actions are being deleted.

2.4 APPLICABLE REGULATORY REQUIREMENTS The regulation at 10 CFR Section 50.36(a)(1) requires an applicant for an operating license to include in the application proposed TSs in accordance with the requirements of 10 CFR 50.36.

The applicant must include in the application, a summary statement of the bases or reasons for such specifications, other than those covering administrative controls. However, per 10 CFR 50.36(a)(1), these TS bases shall not become part of the technical specifications. Per 10 CFR 50.90, whenever a holder of a license desires to amend the license, application for an amendment must be filed with the Commission, fully describing the changes desired, and following as far as applicable, the form prescribed for original applications.

Additionally, 10 CFR 50.36(b) requires:

Each license authorizing operation of a utilization facility will include technical specifications. The technical specifications will be derived from the analyses and evaluation included in the safety analysis report, and amendments thereto, submitted pursuant to 10 CFR 50.34 [Contents of applications; technical information].

The Commission may include such additional technical specifications as the Commission finds appropriate.

Per 10 CFR 50.92(a), in determining whether an amendment to a license will be issued to the applicant, the Commission will be guided by the considerations which govern the issuance of initial licenses to the extent applicable and appropriate.

The categories of items required to be in the TSs are provided in 10 CFR 50.36(c). As required by 10 CFR 50.36(c)(2)(i), the TSs will include LCOs, which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. Per 10 CFR 50.36(c)(2)(i), when an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs until the condition can be met.

The regulation at 10 CFR 50.36(c)(3) requires TSs to include items in the category of SRs, which are requirements relating to test, calibration, or inspection to assure that the necessary quality of systems and components is maintained, that facility operation will be within safety limits, and that the LCOs will be met. Also, the regulation at 10 CFR 50.36(a)(1) states that a summary statement of the bases or reasons for such specifications, other than those covering administrative controls, shall also be included in the application, but shall not become part of the TSs.

As described in the Commissions Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, recommendations were made by NRC and industry task groups for new STS that include greater emphasis on human factors principles in order to add clarity and understanding to the text of the STS, and provide improvements to the Bases Section of Technical Specifications, which provides the purpose for each requirement in the specification. Subsequently, improved vendor-specific STS were developed and issued by the NRC in September 1992. The improved STS were published as the following NRC Reports:

- NUREG-1430, Standard Technical Specifications, Babcock and Wilcox Plants

- NUREG-1431, Standard Technical Specifications, Westinghouse Plants

- NUREG-1432, Standard Technical Specifications, Combustion Engineering Plants

- NUREG-1433, Standard Technical Specifications, General Electric Plants, BWR/4

- NUREG-1434, Standard Technical Specifications, General Electric Plants, BWR/6 These improved STS were the result of extensive technical meetings and discussions among the NRC staff, industry owners groups, vendors, and NUMARC. The Commission recognizes the advantages of improved TSs. Clarification of the scope and purpose of TSs has provided useful guidance to both the NRC and industry and has served as an important incentive for industry participation in a voluntary program to improve TSs. It has resulted in improved STS that are intended to focus licensee and plant operator attention on those plant conditions most important to safety. This should also result in more efficient use of agency and industry resources.

The NRC staffs guidance for review of TSs is in Chapter 16, Technical Specifications, of NUREG-0800, Revision 3, Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants (SRP), dated March 2010, (ADAMS Accession No. ML100351425). As described therein, as part of the regulatory standardization effort, the NRC staff has prepared STS for each of the light-water reactor nuclear designs. NUREG-1433, Revision 4, contains the STS for BWR/4 plants, and is also applicable to BWR/2, BWR/3, and in some cases, BWR/5 plants, and NUREG 1434, Revision 4, contains the STS for BWR/6 plants, and is also applicable in some cases to BWR/5 plants.

3.0 TECHNICAL EVALUATION

3.1 DRAIN TIME DEFINITION The proposed drain time is the time it would take the RPV water inventory to drain from the current level to the TAF assuming the most limiting of the RPV penetrations flow paths with the largest flow rate, or a combination of penetration flow paths that could open due to a common Mode failure, were to open and the licensee took no mitigating action.

The NRC staff reviewed the proposed drain time definition from the traveler. For the purpose of NRC staff considerations, the term break describes a pathway for water to drain from the RPV that has not been prescribed in the DRAIN TIME definition proposed in TSTF-542. All RPV penetrations below the TAF are included in the determination of drain time as potential

pathways. Attachment 2 to the RAI responses dated March 14, 2016 (ADAMS Accession No. ML16074A448), provided an example bounding drain time calculations for three examples:

(1) water level at or below the reactor flange; (2) water level above RPV flange with fuel pool gates installed, and; (3) water level above reactor flange with fuel pool gates removed. The drain time is calculated by taking the water inventory above the break and dividing by the limiting drain rate until the TAF is reached. The limiting drain rate is a variable parameter depending on the break size and the reduction of elevation head above break location during the drain down event. The discharge point will depend on the lowest potential drain point for each RPV penetration flow path on a plant-specific basis. This calculation provides a conservative approach to determining the drain time of the RPV.

Additionally, Attachment 2 to the RAI responses, provides a proposed example table to pair with the drain time calculation. This table correlates the drain time (hours) to the penetration flow path diameter (inches) and the reactor vessel water level (inches above the TAF). The proposed example table is color coded to visually show if LCO 3.5.2 is met, or which LCO condition the licensee would be in. This proposed example table provides operators with a correlation to relate the calculated drain time to the RPV water level and where in the LCO the operators should be. Based on these considerations, the NRC staff finds the proposed drain time definition with supporting calculation and table to be acceptable.

3.2 WATER SOURCES The proposed LCO 3.5.2 in NUREG-1433 states, one low pressure Emergency Core Cooling System (ECCS) injection/spray subsystem shall be OPERABLE. The NUREG-1434 LCO 3.5.2 states, one ECCS injection/spray subsystem shall be OPERABLE. It should be noted that the term low pressure does not appear in the NUREG-1434 LCO because the BWR/5 and BWR/6 HPCS System may also be used to satisfy the LCO.

The NRC staff reviewed the water sources that would be applicable to the proposed TS 3.5.2.

The ECCS pumps are high-capacity pumps, with flow rates of thousands of gallons per minute (gpm). Most RPV penetration flow paths would have a drain rate on the order of tens or hundreds of gpm. The automatic initiation of an ECCS pump would provide the necessary water source to counter these expected drain rates. The LPCI subsystem is to be considered operable during alignment and operation for decay heat removal if capable of being manually realigned and not otherwise inoperable. Decay heat removal in MODEs 4 and 5 is not affected by the proposed change in TSTF-542 as these requirements on the number of RHR shutdown cooling subsystems that must be operable and in operation to ensure adequate decay heat removal from the core are unchanged. These requirements can be found in the NUREG-1433 TS 3.4.9, Residual Heat Removal (RHR) Shutdown Cooling System - Cold Shutdown, TS 3.9.8, Residual Heat Removal (RHR) - High Water Level, and TS 3.9.10, Residual Heat Removal (RHR) - Low Water Level. For NUREG-1434, the applicable TS are TS 3.4.10, Residual Heat Removal (RHR) Shutdown Cooling System - Cold Shutdown, TS 3.9.8, Residual Heat Removal (RHR) - High Water Level, and TS 3.9.10, Residual Heat Removal (RHR) - Low Water Level. Based on these considerations, the NRC staff finds the water sources provide assurances that the lowest functional capability required for safe operation is maintained and protecting the safety limit.

3.3 TS 3.5.2 - REACTOR PRESSURE VESSEL (RPV) WATER INVENTORY CONTROL The proposed TS 3.5.2, Reactor Pressure Vessel (RPV) Water Inventory Control, LCO contains two parts. The first part states that DRAIN TIME of RPV water inventory to the TAF shall be 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />, and the second part states in NUREG-1433, one low pressure ECCS injection/spray subsystem shall be OPERABLE, and in NURG-1434, one ECCS injection/spray subsystem shall be OPERABLE. The proposed applicability for TS 3.5.2 is MODEs 4 and 5.

The NRC staff reviewed the proposed STS 3.5.2, focusing on ensuring the fuel remains covered with water and the changes made compared to the current STS. The proposed STS 3.5.2 contains Conditions A through E based on either required ECCS injection/spray subsystem operability or drain time.

The current STS LCO in NUREG-1433 and NUREG-1434 states that two ECCS injection/spray subsystems shall be operable, whereas the proposed LCO 3.5.2 states that only one ECCS injection/spray subsystem shall be operable. This change is reflected in Condition A. The change from two ECCS injection/spray subsystem to one ECCS injection/spray subsystem is because this redundancy is not required. With one ECCS injection/spray subsystem and non-safety related injection sources, defense-in-depth will be maintained. The defense-in-depth measure is consistent with other events considered during shutdown with no additional single failure assumed. The drain time controls, in addition to the required ECCS injection/spray subsystem, provide reasonable assurance that an unexpected draining event can be prevented or mitigated before the RPV water level would be lowered to the TAF.

The proposed Mode 4 and 5 applicability of TS 3.5.2 is appropriate given the unaffected TS requirements on ECCS in Modes 1, 2, and 3.

The proposed Condition A states that if the required ECCS injection/spray subsystem is inoperable, it is to be restored to operable status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Proposed Condition B states that if Condition A is not met, a method of water injection capable of operating without offsite electrical power should be established immediately. The proposed Condition B for TS 3.5.2 is different from the STS, which states to initiate action to suspend OPDRVs. The proposed Condition B provides adequate assurance of an available water source should Condition A not be met within the 4-hour completion time.

The proposed Condition C states that for a drain time < 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> and 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, to (1) verify

[secondary containment] boundary is capable of being established in less than 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, and (2) verify each [secondary containment] penetration flow path is capable of being isolated in less than 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, and (3) verify one standby gas treatment subsystem is capable of being placed in operation in less than 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The current STS Condition C states if two ECCS injection/spray subsystem are inoperable then restore one to operable status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The proposed Condition C provides adequate protection should the DRAIN TIME be < 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> and 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> because of the ability to establish secondary containment, isolate additional flow paths, and have the standby gas treatment subsystem operable.

The proposed Condition D states that when drain time < 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to (1) immediately initiate action to establish an additional method of water injection with water sources capable of maintaining RPV water level > TAF for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />, (2) immediately initiate action to establish

[secondary] containment boundary, (3) immediately initiate action to isolate each [secondary]

containment penetration flow path or verify it can be manually isolated from the control room, and (4) immediately initiate action to verify one standby gas treatment subsystem is capable of being placed in operation. Additionally, there is a note stating that required ECCS injection/spray subsystem or additional method of water injection shall be capable of operating without offsite electrical power, which is similar to proposed Condition B. The current STS for Condition D are similar to the proposed for when Required Action C.2 is not met. The proposed Condition D provides adequate protection should the DRAIN TIME be < 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> because of the ability to establish additional method of water injection, establish secondary containment, isolate additional flow paths, and have the standby gas treatment subsystem operable.

The proposed Condition E states that when the required action and associated completion time of Condition C or D is not met, or the drain time is < 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, then initiate action to restore drain time to 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> immediately. The proposed Condition E is new, as it is not present in the current STS. The proposed Condition E is acceptable as it provides the necessary step to restore the drain time to 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> should the other conditions not be met, or if the drain time is

< 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

Based on the NRC staffs review, the proposed changes to TS 3.5.2 are acceptable based on the actions taken to mitigate the water level reaching the TAF with the water sources available and maintaining drain time 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The LCO correctly specifies the lowest functional capability or performance levels of equipment required for safe operation of the facility. There is reasonable assurance that the required actions to be taken when the LCO is not met can be conducted without endangering the health and safety of the public.

The existing TS 3.3.5.2, "RCIC System Instrumentation," is renumbered as TS 3.3.5.3. This increases consistency within the BWR STS as the Reactor Core Isolation Cooling (RCIC)

System is discussed in the section on TS 3.5.3.

3.4 STS 3.3.5.2, REACTOR PRESSURE VESSEL WATER INVENTORY CONTROL INSTRUMENTATION The proposed TS and associated LCO in TS Section 3.3, Instrumentation, contains A and B versions of TS 3.3.5.2. The A version is for TS without a Setpoint Control Program and Table 3.3.5.2-1 has a column for listing Allowable Value. The B version is for TS with a Setpoint Control Program and Table 3.3.5.2-1 has no allowable value column, because the Setpoint Control Program dictates the setpoint value. In a like manner the associated LCO 3.3.5.2 has A and B versions. The actions and SRs for both versions A and B are the same in NUREG-1433 and NUREG-1434.

The purpose of the RPV Water Inventory Control Instrumentation is to support the requirements of new STS LCO 3.5.2, and the definition of drain time. There are instrumentation and controls and their signal functions that are required for manual initiation or required as a permissive or operational controls on the equipment of the systems that provide water injection capability, certain start commands, and isolation functions. These instruments are required to be operable if the systems that provide water injection and isolation functions are to be considered operable as described in the SE of new STS 3.5.2. In some cases the reactor operators have alternate, often more complex means, of starting and injecting water than the preferred simple push button start.

Specifically, the NUREG-1433 RPV Water Inventory Control Instrumentation supports operation of the Core Spray and LPCI including manual initiation when needed as well as the system isolation of the RHR system and the RWCU system. The equipment involved with each of these systems is described in the SE of TS 3.5.2 and the Bases for LCO 3.5.2.

Specifically, the NUREG-1434 RPV Water Inventory Control Instrumentation supports operation of the LPCI with subsystems LPCI A, LPCI B, and LPCI C, LPCS, and HPCS, including manual initiation when needed as well as the system isolation of the RHR system and the RWCU system. The equipment involved with each of these systems is described in the SE of TS 3.5.2 and the Bases for LCO 3.5.2.

TSTF-542, Section 3.3, Proposed TS 3.3.5.2, Reactor Pressure Vessel Water Inventory Control Instrumentation, describes and justifies the instrumentation requirements associated with and needed to support TS 3.5.2 and LCO 3.5.2, Reactor Pressure Vessel Water Inventory Control. Section 3.3.1 addresses the proposed TS 3.3.5.2 LCO and applicability. Section 3.3.2 addresses, presents, discusses, and justifies the proposed actions of TS 3.3.5.2. Section 3.3.3, addresses the proposed TS 3.3.5.2 surveillances. Section 3.3.4 addresses, presents, discusses, and justifies the proposed Table 3.3.5.2-1. The NRC staff finds the instrumentation and actions required to support TS 3.3.2, as presented in Section 3.3, sufficient and necessary as discussed below.

3.4.1 Proposed TS 3.3.5.2 LCO and Applicability The proposed LCO 3.3.5.2 states, The RPV Water Inventory Control instrumentation for each Function in Table 3.3.5.2-1 shall be OPERABLE.

The applicability states, "According to Table 3.3.5.2-1."

Section 3.3.1 of TSTF-542, states:

Table 3.3.5.2-1 contains those instrumentation Functions needed to support manual initiation of the ECCS injection/spray subsystem required by LCO 3.5.2, and automatic isolation of penetration flow paths that may be credited in a calculation of Drain Time. The Functions in Table 3.3.5.2-1 are moved from existing TS 3.3.5.1, "ECCS Instrumentation," and TS 3.3.6.1, "Primary Containment Isolation Instrumentation" Functions that are required in Modes 4 or 5 or during OPDRVs. Creation of TS 3.3.5.2 places these Functions in a single location with requirements appropriate to support the safety function for TS 3.5.2.

If plant-specific design and TS require different functions to support manual initiation of an ECCS subsystem, those functions should be included in TS 3.3.5.2.

3.4.2 Proposed TS 3.3.5.2 Actions TS 3.3.5.2 contains actions to be followed when the LCO is not met.

Section 3.3.2, Proposed TS 3.3.5.2 Actions, of TSTF-542 discusses the actions of TS 3.3.5.2 and LCO 3.3.5.2. The NRC staff finds these actions are sufficient and necessary, because when one or more instrument channels are inoperable the equipment and function controlled by these instruments cannot complete the required function in the normal manner and these actions direct the licensee to take appropriate actions as necessary and enter immediately into the Conditions referenced in Table 3.3.5.2-1. These actions satisfy the requirements of 10 CFR 50.36(c)(2)(i) by providing a remedial action permitted by the TS until the LCO can be met. The remedial actions provide reasonable assurance that an unexpected draining event can be prevented or mitigated before the RPV water level would be lowered to the TAF.

3.4.3 Proposed TS 3.3.5.2 Actions for NUREG-1433 The following summarizes the proposed actions of Section 3.3.2 for NUREG-1433.

Section 3.3.2, Proposed TS 3.3.5.2 Actions, of TSTF-542 discusses the actions of TS 3.3.5.2 and LCO 3.3.5.2. The NRC staff finds these actions are sufficient and necessary, because when one or more instrument channels are inoperable the equipment and function controlled by these instruments cannot complete the required function in the normal way, and these actions direct the licensee to take appropriate actions as required. The actions provide reasonable assurance that an unexpected draining event can be prevented or mitigated before the RPV water level would be lowered to the TAF.

Action A is applicable when one or more instrument channels are inoperable from Table 3.3.5.2-1 and directs the licensee to immediately enter the Condition referenced in Table 3.3.5.2-1 for that channel.

Action B (concerning the RHR system Isolation and RWCU system Isolation functions) is applicable when automatic isolation of the associated penetration flow path is credited as a path for potential drainage in calculating drain time. If the instrumentation is inoperable, Required Action B.1 directs an immediate declaration that the associated penetration flow path(s) are incapable of automatic isolation. Required Action B.2 requires a re-calculation of drain time, but automatic isolation of the affected penetration flow paths cannot be credited.

Action C (concerning low reactor steam dome pressure permissive Functions necessary for ECCS subsystem manual initiation) addresses an event in which the permissive is inoperable and manual initiation of ECCS using the control board pushbuttons is prevented. The function must be placed in the trip condition within one hour. With the permissive function instrument in the trip condition, manual initiation may now be performed using the preferred control board pushbuttons. This one-hour completion time is acceptable, because despite the preferred start method being prevented, the reactor operator can take manual control of the pump and the injection valve to inject water into the RPV and achieve the safety function. The time of one hour also provides reasonable time for evaluation and placing the channel in trip.

Action D (concerning pump discharge flow bypass Functions and the manual initiation Functions) addresses actions when the bypass is inoperable and then there is a risk that the associated ECCS pump could overheat when the pump is operating and the associated injection valve is not fully open. In this condition, the operator can take manual control of the pump and the injection. Similar to justification in Action C, while this is not the preferred

method, if a manual initiation function is inoperable, the ECCS subsystem pumps can be started manually and the valves can be opened manually. The 24-hour completion time is acceptable, because the functions can be performed manually and it allows time for the operator to evaluate and have necessary repairs completed. Unlike the failure of a pushbutton that may concern electronic component repairs, mechanical components may be involved in repairs, testing, and return to service of pumps and valves. This further justifies a 24-hour completion time as appropriate.

Action E is needed and becomes necessary, if the Required Actions and associated Completion Times of Condition C or D, are not met. If they are not met, then the associated low pressure ECCS injection/spray subsystem may be incapable of performing the intended function, and the ECCS subsystem must be declared inoperable immediately.

3.4.4 Proposed TS 3.3.5.2 Actions for NUREG-1434 TS 3.3.5.2 contains proposed actions to be followed when the LCO is not met in NUREG-1434.

Section 3.3.2, Proposed TS 3.3.5.2 Actions, of TSTF-542 discusses the Actions of TS 3.3.5.2 and LCO 3.3.5.2. The NRC staff finds these actions are sufficient and necessary, because when one or more instrument channels are inoperable the equipment and function controlled by these instruments cannot complete the required function in the normal way and these actions direct the licensee to take appropriate actions as required. The actions provide reasonable assurance that an unexpected draining event can be prevented or mitigated before the RPV water level would be lowered to the TAF.

Action A is applicable when one or more instrument channels are inoperable from Table 3.3.5.2-1 and directs the licensee to immediately enter the condition referenced in Table 3.3.5.2-1 for that channel.

Action B (concerning the RHR system isolation and RWCU system isolation functions) is applicable when automatic isolation of the associated penetration flow path is credited as a path for potential drainage in calculating drain time. If the instrumentation is inoperable, Required Action B.1 directs an immediate declaration that the associated penetration flow path(s) are incapable of automatic isolation. Required Action B.2 requires a re-calculation of drain time, but automatic isolation of the affected penetration flow paths cannot be credited.

Action C (concerning low reactor steam dome pressure permissive Functions necessary for ECCS subsystem manual initiation) addresses an event in which the permissive is inoperable and manual initiation of ECCS using the control board pushbuttons is prevented. The function must be placed in the trip condition within one hour. With the permissive function instrument in the trip condition, manual initiation may now be performed using the preferred control board pushbuttons. This one hour completion time is acceptable, because despite the preferred start method being prevented, the reactor operator can take manual control of the pump and the injection valve to inject water into the RPV and achieve the safety function. The time of one hour also provides reasonable time for evaluation and placing the channel in trip.

Action D (concerning loss of adequate water supply for the HPCS System), addresses an event in which there is an inadequate water supply. The instrumentation functions have the ability to detect low-water setpoint in the Condensate Storage Tank and actuate valves to realign HPCS

suction water source to the Suppression Pool. The Condensate Storage Tank Level - Low Function indicates multiple, inoperable channels within the same Function resulting in a loss of the automatic ability to swap suction to the Suppression Pool. The HPCS system must be declared inoperable within one hour or the HPCS pump suction must be realigned to the Suppression Pool, since, if realigned, the Function is already performed. This one hour is acceptable, because it provides sufficient time to take the action in order to minimize the risk of HPCS being needed without an adequate water source by allowing time for restoration or alignment of the HPCS pump suction to the suppression pool.

Action E (concerning HPCS high water level Function in the RPV) addresses actions when this instrument function is inoperable. HPCS Reactor Vessel Water Level - High, Level 8 function ensures that appropriate actions are taken if the HPCS Reactor Vessel Water Level - High, Level 8 Function is inoperable. If the inoperability results in the channel being tripped, the HPCS pump discharge valve will not open and HPCS injection is prevented. In that case the HPCS System must be declared inoperable within one hour, and the function must be restored to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The one hour completion time is acceptable, because of the ability to manually start the HPCS pumps and open the discharge valve. The 24-hour completion time is acceptable, because it allows time for the operator to evaluate and arrange for repairs.

Action F (concerning pump discharge flow bypass Functions and the manual initiation Functions) addresses an event in which the bypass is inoperable and there is a risk that the associated ECCS pump could overheat when the pump is operating and the associated injection valve is not fully open. In this condition, the operator can take manual control of the pump and the injection. Similar to justification in Action C, while this is not the preferred method, if a manual initiation function is inoperable, the ECCS subsystem pumps can be started manually and the valves can be opened manually. The 24-hour completion time is acceptable, because the functions can be performed manually and it allows time for the operator to evaluate and have necessary repairs completed. Unlike the failure of a pushbutton that may concern electronic component repairs, mechanical components may be involved in repairs, testing, and return to service of pumps and valves further justifying a 24-hour completion time as appropriate.

Action G is needed and becomes necessary, if the Required Actions and associated Completion Times of Condition C, D, E, or F are not met. If they are not met, then the associated ECCS injection/spray subsystem may be incapable of performing the intended function, and the ECCS subsystem must be declared inoperable immediately.

3.4.5 Proposed TS 3.3.5.2 Surveillances for NUREG-1433 and NUREG-1434 Section 3.3.3, Proposed TS 3.3.5.2 Surveillances, of TSTF-542 discusses the SR of TS 3.3.5.2. The TS 3.3.5.2 SR include Channel Checks, Channel Functional Tests, and Logic System Functional Tests. There are three SRs numbered SR 3.3.5.2.1, SR 3.3.5.2.2, and SR 3.3.5.2.3. The NRC staff finds these tests are sufficient and adequate, because they are essential to ensure the Functions of TS 3.3.5.2 are operable (i.e., capable of performing the specified safety function in support of TS 3.5.2, Drain Time, and the protection from a potential drain down of the RPV in Modes 4 and 5). The NRC staff finds the proposed TS 3.3.5.2 surveillances of LCO 3.5.2 as described in Section 3.3.3 satisfies 10 CFR 50.36(c)(3) by providing the specific SRs relating to test, calibration, or inspection to assure that the necessary quality of systems and components is maintained.

The following summarizes the notable characteristics of the surveillances described in Section 3.3.3 of TSTF-542, which were reviewed by the NRC staff.

SR 3.3.5.2.1 requires a Channel Check and is applied to all functions except manual initiation.

Performance of the Channel Check ensures that a gross failure of instrumentation has not occurred. A Channel Check is normally a comparison of the parameter indicated on one channel to a similar parameter on other related channels. A Channel Check is significant in assuring that there is a low probability of an undetected complete channel failure and is a key safety practice to verifying the instrumentation continues to operate properly between each Channel Functional Test. The frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, or in accordance with the Surveillance Frequency Control Program, is consistent with the existing requirements and supports operating shift situational awareness.

SR 3.3.5.2.2 requires a Channel Functional Test and is applied to all functions except manual initiation. A Channel Functional Test is the injection of a simulated or actual signal into the channel as close to the sensor as practicable to verify operability of all devices in the channel required for channel operability. It is performed on each required channel to ensure that the entire channel will perform the intended function. The frequency is in accordance with the Surveillance Frequency Control Program or 92 days. The applicant states, This is acceptable because it is consistent with the existing requirements for these Functions and is based upon operating experience that demonstrates channel failure is rare. Since periods in Modes 4 and 5 as refueling outages are often in the order of 30 days or less, licensees could include this SR, if desired, as part of a refueling activity.

SR 3.3.5.2.3 requires a Logic System Functional Test and is only applied to the manual initiation functions. The Logic System Functional Test is a test of all logic components required for operability of a logic circuit, from as close to the sensor as practicable up to, but not including, the actuated device, and demonstrates the operability of the required manual initiation logic for a specific channel. The ECCS subsystem functional testing performed in proposed SR 3.5.2.7 overlaps this surveillance to complete testing of the assumed safety function. The Section 3.2.4.6 of the traveler states:

The Frequency of [18] months, or in accordance with the Surveillance Frequency Control Program, is consistent with the existing requirements, and is based upon operating experience

that that has shown that these components usually pass the Surveillance when performed at this Frequency.

There are no SRs included to verify or adjust the instrument setpoint derived from the allowable value using a Channel Calibration or a surveillance to calibrate the trip unit. Section 3.3.3 of the traveler states, A draining event in Mode 4 or 5 is not an analyzed accident and, therefore, there is no accident analysis on which to base the calculation of a setpoint. The purpose of the Functions is to allow ECCS manual initiation or to automatically isolate a penetration flow path, but no specific RPV water level is assumed for those actions. Therefore, the Mode 3 Allowable Value was chosen for use in Modes 4 and 5 as it will perform the desired function.

Calibrating the Functions in Modes 4 and 5 is not necessary, as TS 3.3.5.1 and TS 3.3.6.1 continue to require the Functions to be calibrated on an [18] month Frequency.

And:

A draining event in Mode 4 or 5 is not an analyzed accident and, therefore, there are no accident analysis assumptions on response time.

This is acceptable, because this is adequate to ensure the channel responds with the required pumping systems to inject water when needed and isolation equipment to perform when commanded.

ECCS Response Time and Isolation System Response Time testing ensure that the individual channel response times are less than or equal to the maximum values assumed in the accident analysis. TS 3.3.5.2 does not include SRs to participate in any ECCS Response Time testing and Isolation System Response Time testing. This is acceptable because the purpose of these tests are to ensure that the individual channel response times are less than or equal to the maximum values assumed in the accident analysis, but a draining event in Mode 4 or 5 is not an analyzed accident and, therefore, there are no accident analysis assumptions on response time and there are alternate manual methods for achieving the safety function. A potential draining event in MODEs 4 and 5 is a slower event than a LOCA. More significant protective actions are required as the calculated drain time decreases.

3.4.6 Conclusion of NRC Staff Review of TS 3.3.5.2 The NRC staff finds that proposed LCO 3.3.5.2 correctly specifies the lowest functional capability or performance levels of equipment required for safe operation of the facility. There is reasonable assurance that the required actions to be taken when the LCO is not met can be conducted without endangering the health and safety of the public.

3.5 TABLE 3.3.5.2-1, "RPV WATER INVENTORY CONTROL INSTRUMENTATION" In order to support the requirements of TS 3.5.2, and LCO 3.5.2, Reactor Pressure Vessel (RPV) Water Inventory Control, and the definition of DRAIN TIME; the instrumentation requirements are designated in Table 3.3.5.2-1. These instruments are required to be operable if the systems that provide water injection and isolation functions are to be considered operable as described in the NRC staffs SE of TS 3.5.2.

Table 3.3.5.2-1 specifies the instrumentation that shall be operable for each function in the table for Modes 4 and 5 (or other specified conditions), the required number of channels per function, conditions referenced from Required Action A.1, SR for the functions, the allowable value (if version A), and footnotes concerning items of the table.

Table 3.3.5.2-1 in NUREG-1433 and NUREG-1434 differ only in that version A has a column for the allowable value and B does not. Version A has a potential or generic allowable value in brackets. The brackets indicate that a plant-specific value should be used in the LAR to adopt TSTF-542.

Section 3.3.4, Proposed Table TS 3.3.5.2-1, RPV Water Inventory Control Instrumentation of TSTF-542, presents details on the functions required to support the equipment and functions of TS 3.5.2 in NUREG-1433 and NUREG-1434. The NRC staff finds the presentation in this table acceptable, because this section sufficiently discusses the purpose of the functions, the applicability, the number of required channels, the references to the Condition to be entered by letter (e.g., A, B, C) if the function is inoperable, the applicable SRs, the selection of the allowable value, if applicable, and justification of differences between the existing and proposed TS functions. This RPV Water Inventory Control Instrumentation set is acceptable, because it is adequate to ensure the instruments of the channels responds with the required accuracy permitting pumps systems to operate to inject water when needed and isolation of equipment when commanded to support the prevention of or mitigate a potential RPV draining event.

Each of the ECCS subsystems in NUREG-1433 and NUREG-1434 in Modes 4 and 5 are initiated by manual pushbutton. The traveler states, automatic initiation of an ECCS injection/spray subsystem, with injection rates of thousands of gpm, may be undesirable as it can lead to overflowing the RPV cavity. Thus, there is adequate time to take manual actions (e.g., hours versus minutes). Considering the action statements as the drain time decreases (the proposed TS 3.5.2, Action E, prohibits plant conditions that could result in drain times less than one hour), therefore, there is sufficient time for the reactor operators to take manual action to stop the draining event, and to manually start an ECCS injection/spray subsystem or the additional method of water injection as needed. Consequently, there is no need for automatic initiation of ECCS to respond to an unexpected draining event. This is acceptable, because a draining event is a slow evolution when compared to a design basis LOCA assumed to occur at a significant power level.

3.5.1 Proposed Table 3.3.5.2-1 Functions for NUREG-1433 The following summarizes notable characteristics of the RPV Water Inventory Control Instrumentation as discussed in Section 3.3.4 of TSTF-542, Revision 2.

For the NUREG-1433 Table 3.3.5.2-1 Functions 1.a and 2.a, CS and LPCI Systems, Reactor Steam Dome Pressure - Low (Injection Permissive), these signals are used as permissives and protection for these low pressure ECCS injection/spray subsystem manual initiation functions.

This function ensures that the reactor pressure has fallen to a value below these subsystems' maximum design pressure before permitting the operator to open the injection valves of the low pressure ECCS subsystems. Even though during MODEs 4 and 5 the reactor steam dome pressure is expected to virtually always be below the ECCS maximum design pumping pressure, the Reactor Steam Dome Pressure - Low signals are required to be operable and capable of permitting initiation of the ECCS.

For the NUREG-1433 Table 3.3.5.2-1 Functions 1.b and 2.b, CS and LPCI Systems, Pump Discharge Flow - Low (Bypass), these minimum flow instruments are provided to protect the associated low pressure ECCS pumps from overheating when the pump is operating and the associated injection valve is not fully open. The minimum flow line valve is opened when low flow is sensed, and the valve is automatically closed when the flow rate is adequate to protect the pump. Where applicable, allowable values (version A) specified are high enough to ensure that the pump flow rate is sufficient to protect the pump, yet low enough to ensure that the closure of the minimum flow valve is initiated to allow full flow into the core. Brackets around allowable value indicate the actual value is to be plant-specific and dependent on actual equipment. The LPCI minimum flow valves are time delayed such that the valves will not open for 10 seconds after the switches detect low flow. This time delay is acceptable, because it is provided to limit reactor vessel inventory loss during the startup of the RHR shutdown cooling Mode.

For the NUREG-1433 Table 3.3.5.2-1 Functions 1.c and 2.c, CS System Manual Initiation and LPCI, System Manual Initiation, the manual initiation pushbutton channels introduce signals into the appropriate ECCS logic to provide manual initiation capability. There is one push button for each of the CS and LPCI subsystems (i.e., two for CS and two for LPCI). There is no allowable value for this Function since the channels are mechanically actuated based solely on the position of the push buttons. An instrument channel of the Manual Initiation Function (one channel per subsystem) is required to be Operable in MODEs 4 and 5 when the associated ECCS subsystems are required to be Operable per LCO 3.5.2.

For the NUREG-1433, Table 3.3.5.2-1 Function 3.a, RHR System Isolation, Reactor Vessel Water Level - Low, Level 3, the function is only required to be operable when automatic isolation of the associated penetration flow path is credited in the drain time calculation. The number of required instrument channels is [2 in one trip system], which retains the requirement that the two instrument channels must be associated with the same trip system. Each trip system isolates one of two redundant isolation valves, and only one trip system is required to be operable to ensure that automatic isolation of one of the two isolation valves will occur on low reactor vessel water level indication. The allowable value (version A) was chosen to be the same as the Primary Containment Isolation Instrumentation Reactor Vessel Water Level - Low, Level 3 Allowable Value from LCO 3.3.6.1.

For the NUREG-1433, Table 3.3.5.2-1 Function 4.a, RWCU System Isolation, Reactor Vessel Water Level - Low Low, Level 2, the function is only required to be operable when automatic isolation of the associated penetration flow path is credited in the drain time calculation. The number of required channels is [2 in one trip system], which retains the requirement that the two instrument channels must be associated with the same trip system. Only one trip system is

required to be operable to ensure that automatic isolation of one of the two isolation valves will occur on low reactor vessel water level. Allowable value (version A) was chosen to be the same as the ECCS Reactor Vessel Water Level - Low Low, Level 2 Allowable Value from LCO 3.3.5.1.

3.5.2 Proposed Table 3.3.5.2.-1 Functions for NUREG-1434 The following summarizes notable characteristics of the RPV Water Inventory Control Instrumentation as discussed in Section 3.3.4 of TSTF-542, Revision 2.

For the NUREG-1434 Table 3.3.5.2-1 Functions 1.a and 2.a, LPCS and LPCI Systems, Reactor Steam Dome Pressure - Low (Injection Permissive), these signals are used as permissives and protection for these low pressure ECCS injection/spray subsystem manual initiation functions.

This function ensures that the reactor pressure has fallen to a value below these subsystems' maximum design pressure before permitting the operator from opening the injection valves of the low pressure ECCS subsystems. Even though during MODEs 4 and 5 the reactor steam dome pressure is expected to virtually always be below the ECCS maximum design pumping pressure, the Reactor Steam Dome Pressure - Low signals are required to be operable and capable of permitting initiation of the ECCS.

For the NUREG-1434 Table 3.3.5.2-1 Functions 1.b, 1.c, and 2.b, LPCS and LPCI Systems Low Pressure Coolant Injection and Low Pressure Core Spray Pump Discharge Flow - Low (Bypass), these instruments are provided to protect the associated low pressure ECCS pump from overheating when the pump is operating and the associated injection valve is not fully open. The minimum flow line valve is opened when low flow is sensed, and the valve is automatically closed when the flow rate is adequate to protect the pump. Where applicable allowable values (version A) specified are high enough to ensure that the pump flow rate is sufficient to protect the pump, yet low enough to ensure that the closure of the minimum flow valve is initiated to allow full flow into the core. Brackets around allowable value indicate the actual value is to be plant-specific and dependent on actual equipment.

For the NUREG-1434 Table 3.3.5.2-1 Functions 1.d and 2.c, LPCS and LPCI Systems, Manual Initiation, the manual initiation pushbutton channels introduce signals into the appropriate ECCS logic to provide manual initiation capability. There is one pushbutton for each subsystem in the two divisions of low pressure ECCS (i.e., Division 1 ECCS, LPCS and LPCI A; Division 2 ECCS, LPCI B and LPCI C). There are four subsystems, thus four pushbuttons for the low pressure ECCS. The only manual initiation function required to be operable is that associated with the ECCS subsystem that is required to be operable by LCO 3.5.2. Since the channels are mechanically actuated based solely on the position of the pushbuttons, there is no allowable value (version A) for this function. When this instrument function is inoperable, manual initiation with the control board push buttons is inoperable. However, the ECCS pumps can be started manually and valves can be opened manually by the reactor operator. This is not the preferred condition.

For the NUREG-1434 Table 3.3.5.2-1 Functions 3.a, HPCS System Reactor Vessel Water Level

- High, Level 8, the High RPV water level, Level 8 signal, is used to close the HPCS injection valve to prevent overflow into the main steam lines (MSLs). One instrument channel associated with the HPCS system is required to be operable to support LCO 3.5.2. The LCO 3.3.5.2

allowable value (version A) is chosen to isolate flow from the HPCS system prior to water overflowing into the MSLs.

For the NUREG-1434 Table 3.3.5.2-1 Functions 3.b, HPCS System, Condensate Storage Tank Level - Low, the low level signal in the Condensate Storage Tank (CST) indicates the lack of an adequate supply of makeup water from this primary source for HPCS. Normally, the water source for the suction for HPCS is the CST. If the water level in the CST falls below a preselected level, instrumentation logic controls valves so suction is then pulled from the Suppression Pool. First the Suppression Pool suction valve is automatically opened and then the CST suction valve is automatically closed in a manner to ensure that an adequate supply of makeup water is available to the HPCS pump. The Condensate Storage Tank Level - Low signals are initiated from two level transmitters. The Condensate Storage Tank Level - Low Function Allowable Value is high enough to ensure adequate pump suction head while water is being taken from the CST.

For the NUREG-1434 Table 3.3.5.2-1 Functions 3.c and 3.d, HPCS System, HPCS Pump Discharge Pressure - High (Bypass) and HPCS System Flow Rate - Low (Bypass), the minimum flow instruments are provided to protect the HPCS pump from overheating when the pump is operating and the associated injection valve is not fully open. The minimum flow line valve is opened when low flow and high pump discharge pressure are sensed, and the valve is automatically closed when the flow rate is adequate to protect the pump or the discharge pressure is low (indicating the HPCS pump is not operating).

For the NUREG-1434 Table 3.3.5.2-1 Function 3.e, HPCS System, Manual Initiation, the Manual Initiation push button channel introduces a signal into the HPCS logic to provide manual initiation capability. There is one pushbutton for the HPCS system.

For the NUREG-1434 Table 3.3.5.2-1 Function 4.a, RHR System Isolation, Reactor Vessel Water Level - Low, Level 3, the Function is only required to be operable when automatic isolation of the associated RHR system penetration flow path is credited in calculating drain time. The definition of drain time allows crediting the closing of penetration flow paths that are capable of being automatically isolated by RPV water level isolation instrumentation prior to the RPV water level dropping below the TAF, but if the instrument function is inoperable, a closed path cannot be credited and a drain time calculation must be re-performed.

For the NUREG-1434 Table 3.3.5.2-1 Function 5.a, RWCU System Isolation, Reactor Vessel Water Level - Low Low, Level 2, the Function is only required to be Operable when automatic isolation of the associated RWCU system penetration flow path is credited in calculating drain time. The definition of drain time allows crediting the closing of penetration flow paths that are capable of being automatically isolated by RPV water level isolation instrumentation prior to the RPV water level dropping below the TAF, but if the instrument function is inoperable, a closed path cannot be credited and a drain time calculation must be re-performed. This function is not applicable in MODEs 4 or 5 in TS 3.3.6.1, but is being added to TS 3.3.5.2 to support crediting the automatic isolation of the RWCU system in calculating drain time.

3.6 OTHER DIFFERENCES BETWEEN THE CURRENT AND PROPOSED TS Section 3.4., Evaluation of other Differences between the Current and Proposed TS, of TSTF-542, discusses other differences between the current TS requirements related to

OPDRVs and the proposed TS requirements for RPV WIC. The current STS contain requirements related to instrumentation that are applicable during OPDRVs and are applicable when the existing LCO 3.5.2 is applicable. They do not specifically impact the focus on TS 3.3.5.2 and the associated LCO 3.5.2 and Table 3.3.5.2-1.

3.7 STS 3.5.2 - REACTOR PRESSURE VESSEL (RPV) WATER INVENTORY CONTROL The categories of items required to be in the TSs are provided in 10 CFR 50.36(c). As required by 10 CFR 50.36(c)(2)(i), the TSs will include LCOs, which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. Per 10 CFR 50.36(c)(2)(i), when an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the TSs until the condition can be met.

Technical Specification Safety Limit 2.1.1.3 requires that reactor vessel water level shall be greater than the TAF irradiated fuel. Maintaining water level above the TAF ensures that the fuel cladding fission product barrier is protected during shutdown conditions. The changes to the STS described in traveler TSTF-542 establish specifications for equipment and associated instrumentation that ensure the reactor vessel water level is maintained above the TAF during Mode 4 and 5 operations.

NUREG-0800, Revision 3, Standard Review Plan (March 2010) (ADAMS Accession No. ML100351425), describes LOCAs as postulated accidents that would result from the loss of reactor coolant, at a rate in excess of the capability of the normal reactor coolant makeup system, from piping breaks in the reactor coolant pressure boundary. During operation in Modes 4 and 5, the reactor coolant system is at a low operating temperature (<[200] °F) and is depressurized. An event involving a loss of inventory while in the shutdown condition is judged to not exceed the capacity of one ECCS subsystem. The accidents that are postulated to occur during shutdown conditions, the Fuel Handling Accident and the Waste Gas Decay Tank Rupture, do not involve a loss of inventory. The equipment and instrumentation associated with the Reactor Vessel Water Inventory Control TS do not provide detection or mitigation related to these design basis accidents.

The revised STS LCO 3.5.2 contains requirements for operability of one ECCS subsystem along with requirements to maintain a sufficiently long drain time that plant operators would have time to diagnose and mitigate an unplanned draining event. The NRC staff has determined that the LCO 3.5.2 and 3.3.5.2 provide alternatives for the lowest functional capability or performance levels of equipment required for safe operation of the facility. On this basis, the NRC staff concludes that the requirements of 10 CFR 50.36(c)(2)(i) are met.

Additionally, the revised STS LCOs 3.5.2 and 3.3.5.2 provide remedial actions to be taken in the event the LCO is not satisfied, therefore meeting the requirements of 10 CFR 50.36(c)(2)(i).

The NRC staff has found that the remedial actions provide reasonable assurance that an unexpected draining event can be prevented or mitigated before the RPV water level would be lowered to the TAF.

The regulation at 10 CFR 50.36(c)(3) requires TSs to include items in the category of SRs, which are requirements relating to test, calibration, or inspection to assure that the necessary quality of systems and components is maintained, that facility operation will be within safety limits, and that the LCOs will be met. The NRC staff reviewed the SRs associated with the

revised LCOs 3.5.2 and 3.3.5.2. The NRC staff reviewed the new SRs and determined that they are appropriate for ensuring the operability of the equipment and instrumentation specified in LCOs 3.5.2. Therefore, the NRC staff concludes that 10 CFR 50.36(c)(3) is met.

The regulation at 10 CFR 50.36(a)(1) states that a summary statement of the bases or reasons for such specifications, other than those covering administrative controls, shall also be included in the application, but shall not become part of the TSs. Traveler TSTF-542 contains TS Bases changes that describe the basis for the affected TS. A summary of the NRC staffs evaluation of the TS Bases changes is provided in an attachment to this SE.

The NRC staffs guidance for review of TSs is in Chapter 16, Technical Specifications, of NUREG-0800, Revision 3, Standard Review Plan (March 2010) (ADAMS Accession No. ML100351425). As described therein, as part of the regulatory standardization effort, the NRC staff has prepared STS for each of the light-water reactor nuclear designs. NUREG-1433, Revision 4, contains the STS for BWR/4 plants, and is applicable to BWR/2, BWR/3, and, in some cases, BWR/5 plants, and NUREG 1434, Revision 4, contains the STS for BWR/6 plants and is applicable, in some cases, to BWR/5 plants. The changes to the STS were reviewed for technical clarity and consistency with customary terminology and format with the existing requirements. The NRC staff found that the proposed changes were consistent with the existing framework.

4.0 CONCLUSION

The NRC staff reviewed traveler TSTF-542, Revision 2, "Reactor Pressure Vessel Water Inventory Control, which proposed changes to NUREG-1433, Volumes 1 (STS) and 2 (Bases) and NUREG-1434 Volumes 1 (STS) and 2 (Bases). The NRC staff determined that the proposed changes to the STS met the standards for TS in 10 CFR 50.36(b). The proposed LCOs appropriately specify the lowest functional capability or performance levels of equipment required for safe operation of the facility, as required by 10 CFR 50.36(c)(2)(i). The remedial actions to be taken when an LCO is not met action statements provide adequate protection to the health and safety of the public, thereby satisfy the Act and 10 CFR 50.36(c)(2)(i). The proposed surveillance requirements assure that the necessary quality of systems and components is maintained, that facility operation will be within safety limits, and that the LCOs will be met, and satisfy 10 CFR 50.36(c)(3).

The proposed bases, which will be added to future revisions to NUREG-1433, Volume 2, and NUREG-1434, Volume 2, satisfy the Commissions Policy Statement by addressing the questions specified in the policy statement, and cite references to appropriate licensing documentation to support the Bases.

Technical contacts: Matt Hardgrove, NRR/DSS/SRXB Daniel Warner, NRR/DE/EICB

Attachment:

Basis for Accepting the Proposed Changes to the Standard Technical Specification Bases, Volume 2 of NUREGs 1433 and 1434 Date: December 20, 2016

ATTACHMENT BASIS FOR ACCEPTING THE PROPOSED CHANGES TO THE STANDARD TECHNICAL SPECIFICATION BASES, VOLUME 2 OF NUREGS 1433 AND 1434

1.0 INTRODUCTION

Traveler TSTF-542 proposes changes to Standard Technical Specifications, General Electric BWR/4 Plants, BWR/4, NUREG-1433, Volume 2, Bases, Revision 4.0, April 2012, ADAMS Accession No. ML12104A193 and Standard Technical Specifications, General Electric BWR/6 Plants, BWR/6 NUREG-1434, Volume 2, Bases, Revision 4.0, April 2012, ADAMS Accession No. ML12104A196. The changes would be incorporated into future revisions of NUREG-1433, Volume 2, and NUREG-1434, Volume 2. A summary of the changes and the NRC staffs evaluation of those changes are presented in this Attachment.

2.0 REGULATORY EVALUATION

2.1 Applicable Regulations and Guidance The regulation at 10 CFR 50.36(a)(1) states that each applicant for a license authorizing operation of a production or utilization facility shall include in his application proposed Technical Specifications (TSs) in accordance with the requirements of this section. A summary statement of the bases or reasons for such specifications, other than those covering administrative controls, shall also be included in the application, but shall not become part of the TSs.

In its Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, the Commission presented its policy on the scope and purpose of the TSs. The Commission explained how implementation of the policy statement through implementation of the improved STS is expected to produce an improvement in the safety of nuclear power plants through the use of more operator-oriented TS, improved TS Bases, reduced action-statement-induced plant transients, and more efficient use of NRC and industry resources.

The Final Policy Statement provides the following description of the scope and the purpose of the Technical Specification Bases:

Appropriate Surveillance Requirements and Actions should be retained for each LCO which remains or is included in the Technical Specifications. Each LCO, Action, and Surveillance Requirement should have supporting Bases. The Bases should at a minimum address the following questions and cite references to appropriate licensing documentation (e.g., FSAR, Topical Report) to support the Bases.

1. What is the justification for the Technical Specification, i.e.,

which Policy Statement criterion requires it to be in the Technical Specifications?

ATTACHMENT

2. What are the Bases for each LCO, i.e., why was it determined to be the lowest functional capability or performance level for the system or component in question necessary for safe operation of the facility and, what are the reasons for the Applicability of the LCO?
3. What are the Bases for each Action, i.e., why should this remedial action be taken if the associated LCO cannot be met; how does this Action relate to other Actions associated with the LCO; and what justifies continued operation of the system or component at the reduced state from the state specified in the LCO for the allowed time period?
4. What are the Bases for each Safety Limit?
5. What are the Bases for each Surveillance Requirement and Surveillance Frequency; i.e., what specific functional requirement is the surveillance designed to verify? Why is this surveillance necessary at the specified frequency to assure that the system or component function is maintained, that facility operation will be within the Safety Limits, and that the LCO will be met?

Note: In answering these questions the Bases for each number (e.g., Allowable Value, Response Time, Completion Time, Surveillance Frequency), state, condition, and definition (e.g.,

operability) should be clearly specified. As an example, a number might be based on engineering judgment, past experience, or PSA insights; but this should be clearly stated.

The NRC staff used the guidance contained in the Final Policy Statement during its review of the proposed changes to the Bases.

2.2 Description of Changes Volume 2 of NUREGs-1433 and -1434 contain the Bases for each Safety Limit and each Limiting Condition for Operation (LCO) contained in Volume 1. The Bases for each LCO is organized into sections:

Background

Applicable Safety Analyses, LCO, and Applicability Actions Surveillance Requirements References The Bases for LCOs 3.3.5.2 (A and B) and 3.5.2 were rewritten in their entirety to reflect the changes in the associated LCOs. The Bases for the remainder of the affected LCOs were modified to reflect the deletion of Operation with a Potential for Draining the Reactor Vessels (OPDRVs).

In the following sections, the discussion is applicable to both NUREG-1433 and NUREG-1434 unless otherwise noted. The discussion provides a summary of the revised Bases, followed by the NRC staffs evaluation of the revised Bases.

3.0 TECHNICAL EVALUATION

3.1 Evaluation of B 3.3.5.2 (A) and B 3.3.5.2 (B)

B 3.3.5.2(A) is applicable in the absence of a Setpoint Control Program, and B 3.3.5.2(B) is applicable if a Setpoint Control Program is used. For simplicity in presentation, the description provided below applies to both the (A) and (B) versions, unless otherwise stated.

The Background section provides

  • a description of Safety Limit 2.1.1.3, which requires the RPV water level to be above the TAF fuel

The Applicable Safety Analyses, LCO and Applicability section provides:

  • a statement that indicates that water inventory control is required in Modes 4 and 5 to protect Safety Limit 2.1.1.3 and a discussion that due to the reduced Reactor Coolant System (RCS) pressure in the shutdown condition, a very large break in the RCS is not postulated in the shutdown condition.
  • an explanation that this LCO is applicable in Modes 4 and 5 to support operability of subsystems required to be operable in Modes 4 and 5 as specified in LCO 3.5.2.

o Function 1.a, 2.a Reactor Steam Dome Pressure - Low (Injection Permissive) is required to be Operable to ensure the capability of initiating ECCS when pressure is below the injection subsystems design pressure. The actuation logic is one out of two taken twice, four channels are required to be operable.

o For NUREG-1433:

Function 1.b, 2.b Core Spray and Low Pressure Coolant Injection Pump Discharge Flow - Low (Bypass) is required to be operable to ensure minimum flow line is available to protect the associated low pressure ECCS pump from overheating on low discharge and to ensure closure of the minimum flow valve is initiated at the proper point when the flow rate is adequate to protect the pump. One channel per required pump is required to be operable.

o For NUREG-1434:

Function 1.b, 1.c, 2.b Low Pressure Coolant Injection and Low Pressure Core Spray Pump Discharge Flow - Low (Bypass) is required to be operable to ensure minimum flow line is available to protect the associated low pressure ECCS pump from overheating on low discharge and to ensure closure of the minimum flow valve is initiated at the proper point when the flow rate is adequate to protect the pump. One channel per required pump is required to be operable.

o Function 1.c (for NUREG-1433), 1.d (for NUREG-1434) 2.c, Manual Initiation, is required to be operable to provide manual initiation capability. One channel (pushbutton) per required subsystem is required to be operable per ECCS subsystem required to be operable.

o For NUREG-1434, High Pressure Core Spray System Function 3.a, Reactor Vessel Water Level - High, Level 8 is used to close the HPCS injection valve to prevent overflow into the main steam lines.

One channel associated with the HPCS system required by LCO 3.5.2 is required to be operable. The allowable value is chosen to ensure no overflow into the main steam lines.

Function 3.b, Condensate Storage Tank (CST) Level, Low indicates low supply of makeup water from this source. HPCS is normally aligned to take suction on the CST. On low CST level, the HPCS pump suction valve from the suppression pool open and then the suction valve from the CST close. One channel is required to be operable when HPCS is required per LCO 3.5.2 and the HPCS is aligned to the CST. The allowable value is selected to ensure adequate pump suction head.

Function 3.c., 3.d HPCS Pump Discharge Pressure - High (Bypass) and HPCS System Flow Rate - Low (Bypass) is required to be operable to ensure minimum flow line is available to protect the associated HPCS pump from overheating on low discharge. The allowable value is set to ensure the flow is sufficient to protect the pump, but closes when a minimum flow is adequate to protect the pump or the discharge pressure is low (indicating the HPCS pump is not operating). One channel is required when HPCS is required to be operable per LOC 3.5.2.

Function 3.e, Manual Initiation, is required to be operable to ensure manual initiation capability. One channel is required when the associated ECCS subsystem is required by LCO 3.5.2.

o RHR System Isolation:

o Function 3.a (for NUREG-1433) and 4.a (for NUREG-1434), Reactor Vessel Water Level - Low Level 3 may be credited for automatic isolation of penetration flow paths associated with the RHR system. The function is required to be operable when automatic isolation of the associated penetration flow path is assumed in the calculated Drain Time. Two channels in the same trip system are required to be operable.

o Reactor Water Cleanup (RWCU) System Isolation

o Function 4.a (for NUREG-1433) and 5.a (for NUREG-1434), Reactor Vessel Water level - Low Low, Level 2 may be credited for automatic isolation of penetration flow paths associated with the RWCU System. This function is required to be operable when automatic isolation of the associated penetration flow path is assumed in the calculated Drain Time. Two channels in the same trip system are required to be operable.

o The Allowable Value selected is the same as the Allowable Value during Power Operation.

  • an explanation of each Required Action and Completion Time contained in the Actions Table o For NUREG-1433:

Condition A is entered when a channel is declared inoperable and Required Action A.1 directs entry into the Appropriate Condition.

Condition B is entered when Functions 3.a and 4.a are inoperable. The Required Action is to declare the associated penetration flow path incapable of automatic isolation and to recalculate the Drain Time without taking credit for the automatic isolation of the affect pathway.

Condition C is entered when the steam dome pressure signal permissive is inoperable. Inoperability of the permissive means that the injection function cannot be manually initiated. The Required Action is to place the permissive in the tripped condition within one hour. This enables manual initiation of the injection function. The one hour allowance provides sufficient time for the operator to place the channel in trip.

Condition D is entered when the Core Spray or Low Pressure Coolant Injection Pump Discharge Flow - Low bypass functions are unavailable.

In this condition, the Required Action is to restore the channel to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is judged to be appropriate because manual operation of the pumps and the injection valves is still available, but this is not the preferred condition.

Condition E is entered when the Required Action and associated Completion Time for Condition C or D is not met. In this case, the associated ECCS subsystem may not be capable of performing its intended function, and is declared inoperable immediately.

o For NUREG-1434:

Condition A is entered when a channel is declared inoperable and Required Action A.1 directs entry into the Appropriate Condition.

Condition B is entered when the RHR System Isolation or RWCU System Isolation functions are inoperable. The Required Action is to declare the associated penetration flow path incapable of automatic isolation and to recalculate the Drain Time without taking credit for the automatic isolation of the affect pathway.

Condition C is entered when the Steam Dome Low Pressure Signal (Injection Permissive) is inoperable. Inoperability of the permissive means that the injection function cannot be manually initiated. The Required Action is to place the permissive in the tripped condition within one hour. This enables manual initiation of the injection function. The

one hour allowance provides sufficient time for the operator to place the channel in trip.

Condition D is entered when the CST Level - Low function is inoperable.

The Required Action is to declare HPCS system inoperable and to align the HPCS pump suction to the suppression pool within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

Condition E is entered when the Reactor Vessel Water Level - High -

Level 8 function is inoperable. The Required Action is to declare HPCS system inoperable within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and to restore the channel to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Condition F is entered when the LPCS Pump Discharge Flow - Low (Bypass), LPCI Pump A Discharge Flow - Low (Bypass), LPCI Pump B and LPCI pump C Discharge Flow - Low (Bypass), HPCS Pump Discharge Pressure - High (Bypass), HPCS System Flow rate - Low (Bypass) or any of the required Manual functions are inoperable. The Required Action is to restore the channel to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is judged to be appropriate because manual operation of the pumps and the injection valves is still available, but this is not the preferred condition.

Condition G is entered when the Required Action and associated Completion Time for Condition C, D, E or F is not met. In this case, the associated ECCS subsystem may not be capable of performing its intended function, and is declared inoperable immediately.

The Surveillance Requirements section provides:

  • A description of the purpose of each Surveillance Requirement and the basis for the surveillance frequency selected. For each function, o A channel check is performed to verify that a gross failure of an instrument channel has not occurred. Agreement criteria is established based on channel instrument uncertainties and readability. The surveillance is performed once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or in accordance with the Surveillance Frequency Control Program.

The frequency was selected based on operating experience that indicates channel failure is rare.

o A channel functional test is performed to verify the channel is capable of performing its intended function. The surveillance is performed once per 92 days or in accordance with the Surveillance Frequency Control Program. The frequency was selected based on operating experience that indicates channel failure is rare.

o A logic system functional test is performed to verify proper functioning of the required initiation logic for a channel. The surveillance is performed once per 18 months or in accordance with the Surveillance Frequency Control Program. The frequency was selected because of the preference to perform the surveillance under shutdown conditions.

The References section provides lists Regulatory Guide 1.105, Setpoints for Safety-Related Instrumentation, and NEDE-770-06-2, Addendum to Bases for Changes to Surveillance Test Intervals and Allowed Out-of-Service Times for Selected Instrumentation Technical Specifications.

The staff reviewed the revised bases to ensure the applicable criteria from 10 CFR 50.36 is identified and justified. The reasons for the selection of each instrument function and required number of channels in the LCO is described and the reason for the applicable Modes is stated.

Each instrument function is necessary to support operability of the equipment required by LCO 3.5.2, and the applicable Modes are consistent with those in LCO 3.5.2. The purpose of each required action is described. The purpose of each instrument surveillance and the basis for the performance frequency is addressed, and appropriate references are cited. The staff concluded that each of the elements of the Final Policy Statement were satisfactorily addressed.

Therefore, the staff determined that the revised Bases adheres to the guidance provided in the Final Policy Statement.

3.2 EVALUATION OF B 3.5.2 The Background section provides

  • a description of Safety Limit 2.1.1.3, which requires the RPV water level to be above the TAF The Applicable Safety Analyses, LCO and Applicability section provides:
  • a statement that indicates that water inventory control is required in Modes 4 and 5 to protect Safety Limit 2.1.1.3 and a discussion that due to the reduced RCS pressure in the shutdown condition, a very large break in the RCS is not postulated in the shutdown condition.
  • an explanation that one low pressure ECCS injection/spray subsystem can maintain adequate RPV level (explanation retained from previous Bases for LCO 3.5.2)
  • an explanation that a Drain Time of 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> was selected for the LCO because this time period is reasonable for the operator to identify and initiate remedial measures.
  • an explanation that the LCO also requires one low pressure ECCS injection/spray subsystem to be operable and capable of being manually started so that it is available should an unexpected drain event occur. The ECCS injection/spray subsystem may be considered operable during alignment for decay heat removal because the restriction on drain time ensures sufficient time is available to initiate LPCI operation to maintain inventory if required.
  • an explanation of each Required Action and Completion Time contained in the Actions Table o Condition A is entered if the required ECCS injection/spray subsystem is inoperable. The Required Action is to restore it to Operable status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Completion Time is judged to be appropriate because of the controls on Drain Time and the low probably of a drain event occurring.

o Condition B is entered if the Required Action and Completion Time of Condition A is not met. Condition B requires establishing an alternate method of water injection capable of injecting without the use of offsite power, with attendant necessary support equipment, and access to water inventory capable of maintaining the RPV water level above TAF for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The Completion Time is immediately.

o Condition C is entered if the drain time is less than 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> but greater than or equal to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The Required Actions associated with this Condition ensure the availability of compensatory actions should an unexpected drain event occur.

The Required Actions include actions to ensure the secondary containment boundary can be restored in less than the Drain Time to provide a volume to contain, dilute and process radioactive materials if an unexpected drain event were to occur. The Actions also include verification of the ability to place the Standby Gas Treatment System in service within the Drain Time to provide a means to maintain the secondary containment volume at a negative pressure and to filter the contents prior to release. A Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> was selected for these verifications because this ensures that the actions are completed well within the minimum Drain Time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

o Condition D is entered if the drain time is less than 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. When the Drain Time is this short, mitigating actions as well as compensatory actions are needed. The Required Actions include an immediate action to establish an additional method of water injection. This method is in addition to the injection method required by the LCO. The Required Actions include the compensatory actions of immediately establishing the secondary containment boundary, verifying secondary containment penetrations can be isolated, and verifying that at least one Standby Gas Treatment subsystem can be placed into operation.

These Actions are performed immediately because of the short Drain Time.

o Condition E is also applicable when Drain Time is less than 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. The Required Action is to immediately restore the Drain Time to greater than 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restoration of the Drain Time to 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> is necessary to ensure there is adequate time to perform mitigating actions should an unexpected drain event occur.

The Surveillance Requirements section provides:

  • a description of the purpose of each Surveillance Requirement and the basis for the surveillance frequency selected o The Drain Time is required to be verified to be 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or in accordance with the Surveillance Frequency Control Program. This Surveillance verifies the LCO for Drain Time is met. The frequency is selected based on the fact that numerous indications of changes in RPV level are available to the operator. Changes in RPV level would necessitate recalculation of the Drain Time.

o The suppression pool water level for a required LPCI subsystem, or suppression pool water level or Condensate Storage Tank level for a required core spray subsystem is required to be verified to ensure net positive suction head is available for the ECCS injection/spray subsystem required to be operable by the LCO. This Surveillance is required to be performed once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or in accordance with the Surveillance Frequency Control Program. The frequency was chosen based on the availability of other indications available in the Control Room regarding suppression pool water level and Condensate Storage Tank level.

o The surveillance requirements to verify the piping is full of water and to verify correct valve alignment was retained from the existing TS 3.5.2.

o The required ECCS injection/spray subsystem is required to be operated through its recirculation line for 10 minutes every 92 days or in accordance with the Surveillance Frequency Control Program. This demonstrates that the subsystem is capable for operation. The time limit is based on engineering judgement. The frequency is consistent with other at-power testing.

o Verification that valves credited for automatically isolating a penetration flow path actuate to a simulated actuation signal is required every 18 months or accordance with the Surveillance Frequency Control Program. The frequency was selected because it is desirable to perform the surveillance during shutdown conditions to avoid operational transients.

o Verification that the required ECCS injection/spray subsystem actuate on a manual actuation signal is required every 18 months or accordance with the Surveillance Frequency Control Program. The frequency was selected because it is desirable to perform the surveillance during shutdown conditions to avoid operational transients.

The References section cites the applicable operating generic correspondence describing operating experience related to inventory control during shutdown conditions. It lists Information Notice 84-81 "Inadvertent Reduction in Primary Coolant Inventory in Boiling Water Reactors During Shutdown and Startup," November 1984; Information Notice 86-74, "Reduction of Reactor Coolant Inventory Because of Misalignment of RHR Valves," August 1986; Generic Letter 92-04, "Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Pursuant to 10 CFR 50.54(f), " August 1992; NRC Bulletin 93-03, "Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs," May 1993; Information Notice 94-52, "Inadvertent Containment Spray and Reactor Vessel Draindown at Millstone 1," July 1994; and General Electric Service Information Letter No. 388, "RHR Valve Misalignment During Shutdown Cooling Operation for BWR 3/4/5/6," February 1983.

The revised Bases (Volume 2 of NUREG 1434) for TS 3.5.2 differ from the revised Bases for NUREG-1433. The major difference is that the LCO requires one ECCS injection/spray subsystem to be operable. The ECCS injection/spray subsystem is either one of the three Low Pressure Coolant Injection subsystems, one Low Pressure Core Spray System, or one High Pressure Core Spray System. This difference is reflected throughout the Bases for TS 3.5.2 in NUREG 1434, Volume 2.

The staff reviewed the revised bases to ensure the reasons for the selection of each instrument function and required number of channels in the LCO is described, the reason for the applicable Modes is stated, the purpose of each required action is described, and the purpose of each surveillance and the basis for the performance frequency is addressed, and appropriate references are cited. The staff concluded that each of the elements of the Final Policy Statement were satisfactorily addressed. Therefore, the staff determined that the revised Bases adheres to the guidance provided in the Final Policy Statement.

3.3 EVALUATION OF ADDITIONAL BASES CHANGES 3.3.1 B 3.3.5.1, ECCS Instrumentation The Bases for several instrument functions related to automatic ECCS initiation were revised to reflect a revised Applicability. The functions would no longer be required during Modes 4 and 5

because of the relatively slow transient of unexpected drain events. It is judged that sufficient time is permitted for operators to mitigate such a transient. The instrumentation affected in NUREG-1433 is Reactor Vessel Water Level - Low Low Low, Level 1; Low Pressure Coolant Injection (LPCI) System Reactor Vessel Water Level - Low Low Low, Level 1; and Low Pressure Coolant Injection Pump Start - Time Delay Relay. For NUREG-1434, the affected functions are LPCI A and LPCS: Reactor Vessel Water Level - Low Low Low, Level 1; LPCI Pump A Start - Time Delay Relay; LPCI B and C: Reactor Vessel Water Level - Low Low Low, Level 1; LPCI Pump B Start - Time Delay Relay; and HPCS Reactor Vessel Water Level Low Low, Level 2.

The remainder of the changes to the Bases for this LCO reflect the relocation of instrumentation function requirements to the LCO 3.3.5.2.

3.3.2 B 3.3.6.1, Primary Containment Isolation Instrumentation The Bases for the Shutdown Cooling Isolation, Reactor Vessel Water Level - Low, Level 3 was revised to reflect the relocation of this requirement to LCO 3.3.5.2.

For NUREG-1434s, the function for Primary Containment Isolation, Containment and Drywell Ventilation Exhaust Radiation - High is revised to reflect the deletion of this requirement.

3.3.2 B 3.5.3, RCIC System The Applicability was revised to state that in Modes 4 and 5, RPV water inventory control is provided by LCO 3.5.2.

3.3.3 B 3.6.1.3, PCIVs [Primary Containment Isolation Valves]

The Applicability was changed to replace the statement that certain valves are required to be operable to prevent inadvertent drain down to state that certain valves are required to be operable when the associated instrumentation is required to be operable.

The description of the Applicability and Actions is revised to delete the discussion of OPDRVs.

3.3.4 Other Affected Bases The description of the Applicability, Actions and Applicable Safety Analyses Sections are revised to delete the discussion of OPDRVs, inadvertent drain down of the vessel, or other related administrative changes for the following LCOs:

  • 3.3.7.1 MCREC System Instrumentation
  • 3.5.1 ECCS - Operating
  • 3.6.2.2 Suppression Pool Water Level
  • 3.6.4.1 [Secondary] Containment
  • 3.6.4.2 SCIVs [Secondary Containment Isolation Valves]
  • 3.6.4.3 SGT System [Standby Gas Treatment]
  • 3.7.4 MCREC [Main Control Room Environmental Control] System
  • 3.7.5 Control Room AC [Air Conditioning] System
  • 3.8.2 AC Sources - Shutdown
  • 3.8.5 DC Sources - Shutdown
  • 3.8.8 Inverters - Shutdown
  • 3.8.10 Distribution Systems - Shutdown
  • 3.10.1 Inservice Leak and Hydrostatic Testing Operation The NRC staff reviewed the revised Bases sections and concluded that the revisions accurately reflect the changes contained in the associated LCOs. The Applicability, Actions and Applicable Safety Analyses sections continue to contain information regarding the reasons for each of the LCO requirements. The NRC staff determined that the Bases for the LCOs continue to satisfy the guidance in the Final Policy Statement.

4.0 CONCLUSION

The NRC staff determined that TS Bases changes are consistent with the proposed TS changes and provide an explanation and supporting information for each requirement in the specification.

Therefore, the staff determined that the revised Bases are consistent with the Commission's Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors, dated July 2, 1993 (58 Federal Register 39132).