MONTHYEARML24022A1172024-01-23023 January 2024 Acceptance of Requested Licensing Action Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24012A2422024-01-16016 January 2024 Acceptance of Requested Licensing Action License Transfer Request ML23236A0042023-12-27027 December 2023 Issuance of Amendment 274 Re Changes to Perm Defueled Emergency Plan and Perm Defueled Emergency Action Level Scheme ML23355A1242023-12-26026 December 2023 Withdrawal of an Amendment Request Re License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML23192A0772023-12-26026 December 2023 Letter Exemption from the Requirements of 10 CFR 140.11(a)(4) Concerning Offsite Primary and Secondary Liability Insurance ML23191A5222023-12-22022 December 2023 Exemption Letter from the Requirements of 10 CFR 50.54(W)(1) Concerning Onsite Property Damage Insurance (EPID - L-2022-LLE-0032) ML23263A9772023-12-22022 December 2023 Exemption from Certain Emergency Planning Requirements and Related Safety Evaluation ML23354A2602023-12-21021 December 2023 Reference Simulator Inspection Request for Information L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23291A4402023-11-0303 November 2023 Acceptance of Requested Licensing Action Request for Exemption from 10 CFR 50.82(a)(2) to Support Reauthorization of Power Operations IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23275A0012023-10-0202 October 2023 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable ML23215A2302023-08-0303 August 2023 Notice of Organization Change - Chief Nuclear Officer IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23087A0362023-05-0202 May 2023 PSDAR Review Letter ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations ML23038A0982023-03-15015 March 2023 Request for Withholding Information from Public Disclosure ML23095A0642023-03-14014 March 2023 American Nuclear Insurers, Notice of Cancellation Rescinded PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23052A1092023-02-17017 February 2023 FEMA Letter to NRC, Proposed Commission Paper Language for Palisades Nuclear Plant Emergency Plan Decommissioning Exemption Request ML23032A3992023-02-0101 February 2023 Regulatory Path to Reauthorize Power Operations IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) Holtec Decommissioning International, LLC, Palisades Nuclear Plant L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 ML22321A2852022-11-17017 November 2022 LLC Master Decommissioning Trust Agreement for Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance ML22292A2572022-10-25025 October 2022 Permanently Defueled Emergency Plan License Amendment RAI Letter 2024-01-23
[Table view] Category:License-Monthly Operating Report
MONTHYEARML0505500712005-02-10010 February 2005 January 2005 Monthly Operating Report for Palisades Nuclear Plant ML0501902512005-01-12012 January 2005 December 2004 Monthly Operating Report Palisades Nuclear Plant ML0435601822004-12-14014 December 2004 November 2004 Monthly Operating Report for Palisades Nuclear Plant ML0432203912004-11-0404 November 2004 October 2004 Monthly Operating Report for Palisades Nuclear Plant ML0429903792004-10-13013 October 2004 September 2004 Monthly Operating Report for Palisades Nuclear Plant ML0426600672004-09-13013 September 2004 August 2004 Monthly Operating Report for Palisades Nuclear Plant ML0423004282004-08-0909 August 2004 July 2004 Monthly Operating Report for Palisades Nuclear Plant ML0420302972004-07-14014 July 2004 June 2004 Monthly Operating Report for the Palisades Nuclear Plant ML0416803822004-06-0909 June 2004 May 2004 Monthly Operating Report for Palisades Nuclear Plant ML0414103012004-05-10010 May 2004 April 2004 Monthly Operating Report for Palisades Nuclear Plant ML0412101652004-04-13013 April 2004 March 2004 Monthly Operating Report for Palisades ML0407607002004-03-0808 March 2004 February 2004 Monthly Operating Report for Palisades Nuclear Plant ML0402107242004-01-0909 January 2004 December 2003 Monthly Operating Report for Palisades Nuclear Plant ML0335704012003-12-11011 December 2003 November 2003 Monthly Operating Report for Palisades Nuclear Plant ML0332800252003-11-11011 November 2003 October 2003 Monthly Operating Report for Palisades Nuclear Plant ML0329405702003-10-10010 October 2003 September 2003 Monthly Operating Report for Palisades Nuclear Plant ML0326009042003-09-0909 September 2003 August 2003 Monthly Operating Report for Palisades Nuclear Plant ML0325205712003-08-13013 August 2003 July 2003 Monthly Operating Report for Palisades ML0320500212003-07-15015 July 2003 June 2003 Monthly Operating Report for Palisades Nuclear Plant ML0316903632003-06-10010 June 2003 May 2003 Monthly Operating Report for Palisades Nuclear Plant ML0314005582003-05-12012 May 2003 April 2003 Monthly Operating Report for Palisades Nuclear Plant ML0311203512003-04-14014 April 2003 March 2003 Monthly Operating Report for Palisades ML0307808442003-03-12012 March 2003 February 2003 Monthly Operating Report for Palisades Nuclear Plant ML0305202512003-02-11011 February 2003 January 2003 Monthly Operating Report for Palisades Nuclear Plant ML0302304392003-01-13013 January 2003 December 2002 Monthly Operating Report for Palisades ML0236002102002-12-13013 December 2002 November 2002 Monthly Operating Report for Palisades Nuclear Plant ML0232503422002-11-11011 November 2002 October 2002 Monthly Operating Report for Palisades Nuclear Plant ML0229805102002-10-0909 October 2002 September 2002 Monthly Operating Report for Palisades ML0226202212002-09-11011 September 2002 August 2002 Monthly Operating Report for Palisades ML0223300442002-08-12012 August 2002 July 2002 Monthly Operating Report for Palisades Nuclear Plant ML0220406522002-07-12012 July 2002 June 2002 Monthly Operating Report for Palisades Plant ML0217203922002-06-13013 June 2002 May 2002 Monthly Operating Report for Palisades ML0214404942002-05-0909 May 2002 April 2002 Monthly Operating Report for Palisades Nuclear Plant ML0219303972002-04-11011 April 2002 March 2002 Monthly Operating Report for Palisades Nuclear Plant ML0208604302002-03-13013 March 2002 February 2002 Monthly Operating Report for Palisades Nuclear Plant ML0206504692002-02-15015 February 2002 January 2002 Monthly Operating Report for Palisades Nuclear Plant ML0204402332002-01-14014 January 2002 December 2001 Monthly Operating Report for Palisades 2005-02-10
[Table view] |
Text
Commfted touerselec Palisades Nuclear Plant Operated by Nuclear Management Company, LLC September 9, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 PALISADES NUCLEAR PLANT DOCKET 50-255 LICENSE No. DPR-20 LICENSEE REPORT OF MONTHLY OPERATING DATA Attached are the Monthly Operating Data and Summary of Operating Experience for the Palisades Nuclear Plant for the month of August 2003.
Please contact Mr. Scott Hawn at (269) 764-3179 with any questions.
oug E.Cooper s
Sr. Vice-President - General Operations CC Regional Administrator, USNRC, Region IlIl NRC Resident Inspector, Palisades LBrandon, Michigan Department of Environmental Quality RJAben, Michigan Department of Labor RDWhale, Michigan Public Service Commission Records Center, INPO SMMclntyre, P-26-204 Attachments
SUMMARY
OF OPERATING EXPERIENCE FOR AUGUST 2003 The plant operated at essentially full power (at greater than 99%) for the entire month.
b.
OPERATING DATA REPORT DOCKET NO: 50-255 DATE (Mo-Da-Yr): 09-04-03 COMPLETED BY: SFPierce TELEPHONE (269) 764-2239 OPERATING STATUS: NOTES:
- 1. UNIT NAME Palisades
- 2. REPORTING PERIOD (YrMoDa-YrMoDa): 030801-030831
- 3. LICENSED THERMAL POWER (Mwt) 2530
- 4. NAMEPLATE RATING (GROSS Mwe) 811.7
- 5. DESIGN ELECTRICAL RATING (NET Mwe) 805
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS Mwe) 770
- 7. MAXIMUM DEPENDABLE CAPACITY (NET Mwe) . 730
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEM NUMBERS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
- 10. REASONS FOR RESTRICTIONS, IF ANY:
This Month Yrto-Date Cumulative
- 11. HOURS IN REPORTING PERIOD 744.0 5831.0 277886.0
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 5014.3 174542.5
- 13. REACTOR RESERVE SHUTDOWN HOURS - - -
- 14. HOURS GENERATOR ON-LINE 744.0 4985.8 168964.8
- 15. UNIT RESERVE SHUTDOWN HOURS - - -
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1882250 12381537 383830005
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 600957 4042705 122480740
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 572715 3855743 115918929
- 19. UNIT SERVICE FACTOR 100.00 85.5% 60.8%
- 20. UNIT AVAILABILITY FACTOR 100.0% 85.5% 60.8%
- 21. UNIT CAPACITY FACTOR (USING MDC NETr 105A% 90.6% 60.0%-
- 22. UNIT CAPACITY FACTOR (USING DER NET) 95.6% 82.1% 51.8%
- 23. UNIT FORCED OUTAGE RATE 0.0% 0.0% .24.8%
Based on condenser backpressure Weighted Average (635 MWe used as MDC Net prior to October 1985)
I REPORT MONTH Auoust 2003 DOCKET NO. 5G255 UNIT NAME Palisades DATE(Mo/DaYr) -09403 COMPLETED BYSFEP TELEPHONE 269-764-2239 UNIT SHUTDOWNS No. Date Type Duration Reason' Method of Cause / Corrective 2
(YrMoDa) F: Forced (Hours) Shutting Down Actions Comments S: Scheduled NONE
- 1. 2.
Reason: Method:
A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Oter (Explain)
E-Operator Training & License Examination F-Administrative G-Operatlonal Error (Explain)
H-Other (Explain)