Category:License-Monthly Operating Report
MONTHYEARML0505500712005-02-10010 February 2005 January 2005 Monthly Operating Report for Palisades Nuclear Plant ML0501902512005-01-12012 January 2005 December 2004 Monthly Operating Report Palisades Nuclear Plant ML0435601822004-12-14014 December 2004 November 2004 Monthly Operating Report for Palisades Nuclear Plant ML0432203912004-11-0404 November 2004 October 2004 Monthly Operating Report for Palisades Nuclear Plant ML0429903792004-10-13013 October 2004 September 2004 Monthly Operating Report for Palisades Nuclear Plant ML0426600672004-09-13013 September 2004 August 2004 Monthly Operating Report for Palisades Nuclear Plant ML0423004282004-08-0909 August 2004 July 2004 Monthly Operating Report for Palisades Nuclear Plant ML0420302972004-07-14014 July 2004 June 2004 Monthly Operating Report for the Palisades Nuclear Plant ML0416803822004-06-0909 June 2004 May 2004 Monthly Operating Report for Palisades Nuclear Plant ML0414103012004-05-10010 May 2004 April 2004 Monthly Operating Report for Palisades Nuclear Plant ML0412101652004-04-13013 April 2004 March 2004 Monthly Operating Report for Palisades ML0407607002004-03-0808 March 2004 February 2004 Monthly Operating Report for Palisades Nuclear Plant ML0402107242004-01-0909 January 2004 December 2003 Monthly Operating Report for Palisades Nuclear Plant ML0335704012003-12-11011 December 2003 November 2003 Monthly Operating Report for Palisades Nuclear Plant ML0332800252003-11-11011 November 2003 October 2003 Monthly Operating Report for Palisades Nuclear Plant ML0329405702003-10-10010 October 2003 September 2003 Monthly Operating Report for Palisades Nuclear Plant ML0326009042003-09-0909 September 2003 August 2003 Monthly Operating Report for Palisades Nuclear Plant ML0325205712003-08-13013 August 2003 July 2003 Monthly Operating Report for Palisades ML0320500212003-07-15015 July 2003 June 2003 Monthly Operating Report for Palisades Nuclear Plant ML0316903632003-06-10010 June 2003 May 2003 Monthly Operating Report for Palisades Nuclear Plant ML0314005582003-05-12012 May 2003 April 2003 Monthly Operating Report for Palisades Nuclear Plant ML0311203512003-04-14014 April 2003 March 2003 Monthly Operating Report for Palisades ML0307808442003-03-12012 March 2003 February 2003 Monthly Operating Report for Palisades Nuclear Plant ML0305202512003-02-11011 February 2003 January 2003 Monthly Operating Report for Palisades Nuclear Plant ML0302304392003-01-13013 January 2003 December 2002 Monthly Operating Report for Palisades ML0236002102002-12-13013 December 2002 November 2002 Monthly Operating Report for Palisades Nuclear Plant ML0232503422002-11-11011 November 2002 October 2002 Monthly Operating Report for Palisades Nuclear Plant ML0229805102002-10-0909 October 2002 September 2002 Monthly Operating Report for Palisades ML0226202212002-09-11011 September 2002 August 2002 Monthly Operating Report for Palisades ML0223300442002-08-12012 August 2002 July 2002 Monthly Operating Report for Palisades Nuclear Plant ML0220406522002-07-12012 July 2002 June 2002 Monthly Operating Report for Palisades Plant ML0217203922002-06-13013 June 2002 May 2002 Monthly Operating Report for Palisades ML0214404942002-05-0909 May 2002 April 2002 Monthly Operating Report for Palisades Nuclear Plant ML0219303972002-04-11011 April 2002 March 2002 Monthly Operating Report for Palisades Nuclear Plant ML0208604302002-03-13013 March 2002 February 2002 Monthly Operating Report for Palisades Nuclear Plant ML0206504692002-02-15015 February 2002 January 2002 Monthly Operating Report for Palisades Nuclear Plant ML0204402332002-01-14014 January 2002 December 2001 Monthly Operating Report for Palisades 2005-02-10
[Table view] |
Text
Comm to N1ted or Palisades Nuclear Plant Operated by Nuclear Management Company, LLC May 10, 2004 Technical Specification 5.6.4 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Palisades Nuclear Plant Docket 50-255 License No. DPR-20 Monthly Operating Report In accordance with Technical Specification 5.6.4, attached is the Monthly Operating Report for April 2004, for the Palisades Nuclear Plant.
Summary of Commitments This letter contains no new commitments and no revisions to existing commitments.
Daniel J. Malone Site Vice President, Palisades Nuclear Plant Nuclear Management Company, LLC Enclosure (1)
CC Administrator, Region Ill, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC LBrandon, Michigan Department of Environmental Quality RJAben, Michigan Department of Labor RDWhale, Michigan Public Service Commission Records Center, INPO TLShillair, P-26-305 27780 Blue Star Memorial Highway
- Covert, Michigan 49043-9530 Telephone: 269.764.2000
ENCLOSURE OPERATING DATA REPORT DOCKET NO: 50-255 DATE: 05-02-04 COMPLETED BY: SDCheatom TELEPHONE (269) 764-2103 NOTES:
Operating Data:
UNIT NAME Palisades REPORTING PERIOD: April 2004
- 1. DESIGN ELECTRICAL RATING (NET Mwe) 805
- 2. MAXIMUM DEPENDABLE CAPACITY (NET Mwe)
- 730 This Month Yr-to-Date Cumulative
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 719.0 2903.0 180374.5
- 4. HOURS GENERATOR ON-LINE 719.0 2903.0 174796.8
- 5. UNIT RESERVE SHUTDOWN HOURS 0 0 0
- 6. NET ELECTRICAL ENERGY GENERATED (MWH) 569271 2299647 120520987 Based on condenser backpressure Page 1 of 2
ENCLOSURE OPERATING DATA REPORT REPORT MONTH Aoril 2004 DOCKET NO. 255 UNIT NAME Palisades DATE(MoIDalYr)_ 05/02/04 COMPLETED BY SOCheatom TELEPHONE 269-764-2103 UNIT SHUTDOWNS No. Date Type Duration Reason' Method of Cause / Corrective 2
(YrMoDa) F: Forced (Hours) Shutting Down Actions Comments S: Scheduled NONE
- 1. Reason: 2. Method:
A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Other (Explain)
E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain)
SUMMARY
- The plant operated at essentially full power until April 29, 2004, when power was reduced to 88% for turbine governor valve repairs. Power was eventually reduced to 87%
to complete repairs and testing. Full power was restored on April 30, 2004, and the plant completed the month at essentially full power.
Page 2 of 2