Walter Nelson Manager, Site Training Holtec Decommissioning International, LLC Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530
SUBJECT:
PALISADES NUCLEAR PLANT - PLANT REFERENCE SIMULATOR INSPECTION REQUEST FOR INFORMATION
Dear Walter Nelson:
The U.S. Nuclear Regulatory Commission (NRC) will perform an inspection in January and February 2024 of the simulation facility (control room simulator) with an onsite portion conducted during the week of February 6, 2024, at the Palisades Nuclear Plant.
On December 13, 2023, April Nguyen, Chief, Operations Branch for the NRC, and yourself, had a phone conversation where final arrangements were confirmed to inspect the simulation facility. NRC inspectors will perform an inspection of the simulation facility to verify the design, maintenance, and suitability of the simulator using NRC Inspection Procedure (IP) 41502, Nuclear Power Plant Simulation Facilities. This inspection is focused on the simulator and its use in operations training. Regulatory requirements for the simulator facility are described in Title 10 of the Code of Federal Regulations (10 CFR) Part 55.
On June 13, 2022, Palisades ceased permanent power operations and subsequently removed all fuel from the reactor, as detailed in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML22164A067. Upon Palisades transition into a decommissioning status, maintenance and modifications on the simulator stopped and specific parts of the simulator were used for other applications. On September 28, 2023, Holtec Decommissioning International, LLC (Holtec) submitted a letter to the NRC requesting exemptions from certain portions of the requirements of 10 CFR 50.82(a)(2) to pursue the potential reauthorization of power operations at Palisades, detailed in ADAMS at Accession No. ML23271A140. The NRCs initial acceptance to review Palisades request for exemptions was documented in ADAMS at Accession No. ML23291A440 on November 3, 2023.
We have discussed the schedule for these inspection activities with your staff. This inspection is resource-intensive for both the NRC inspectors and your staff. To minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents need for this inspection. It is important that all these documents are up-to-date and complete, to minimize the number of additional documents requested during the preparation, and/or during the onsite portions of the inspection.
December 21, 2023
W. Nelson 2
If there are any questions about this inspection or the material requested, please contact the lead inspector, Bryan Bergeon at 630-829-9719 (Bryan.Bergeon@nrc.gov), or the Chief, Operations Branch, April Nguyen at 630-829-9587 (April.Nguyen@nrc.gov).
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 31500011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.
This letter and its enclosure will be available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, April M. Nguyen, Chief Operations Branch Division of Operating Reactor Safety Docket Nos. 50-255 and 72-007 License No. DPR-20
Enclosure:
REQUESTED INFORMATION TO SUPPORT PLANT REFERENCE SIMULATOR INSPECTION (IP 41502) cc: Distribution via LISTSERV W. Nelson, Training Manager Signed by Nguyen, April on 12/21/23
W. Nelson 3
Letter to Walter Nelson from April Nguyen dated December 21, 2023.
SUBJECT:
PALISADES NUCLEAR PLANT - PLANT REFERENCE SIMULATOR INSPECTION REQUEST FOR INFORMATION DISTRIBUTION:
RidsNrrPMPalisades Resource RidsNrrDorlLpl3 RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Jason Kozal Diana Betancourt-Roldan Allan Barker Harral Logaras David Curtis Jared Heck R3-DORS Ikeda Betts Lauren Nist Maryia Bahdanovich-Kniazkova Jamie Pelton Russell Felts Philip McKenna Prema Chandrathil Viktoria Mitlyng Carolyn Wolf Justin Poole Jennifer Dalzell Gehan Flanders Valerie Myers Aaron McCraw ADAMS Accession Number: ML23354A260 OFFICE RIII/DORS/OB/CE RIII/DORS/OB/BC NAME BBergeon:mb ANguyen DATE 12/20/2023 12/21/2023 OFFICIAL RECORD COPY
Enclosure REQUESTED INFORMATION TO SUPPORT PLANT REFERENCE SIMULATOR INSPECTION (IP 41502)
Inspection Dates:
January 29 - February 9, 2024 Inspection Procedure (IP):
41502, Nuclear Power Plant Simulation Facilities Note: This is a list of the documents to be provided or to have available for the inspection team.
The current version of these documents is expected unless specified otherwise. The preferred file format is Word or searchable pdf files. [Note that the inspectors cannot accept data provided on USB or flash drives due to NRC IT security policies]. It is recommended to use the NRCs secure file sharing program, BOX, for file transfers, otherwise a CD/DVD is acceptable. It is not the intent that large or burdensome data be scanned for this. This data will be inspected using original documentation.
Initial Document Request (Due January 26, 2024)
All procedures associated with testing and maintaining the Plant Reference Simulator
A list of all completed simulator tests
A list of all simulator open and closed Deficiency Reports, April 2020 - current
A list of all simulator open and closed modifications, April 2020 - current
A list of all simulator Training Needs Assessments
A list of all simulator and plant differences
A list of all Corrective Action Program documents related to simulator performance and fidelity, April 2020 - current Subsequent Document Request (Due February 6, 2024, for the onsite inspection)
Normal evolutions o
Startup from cold shutdown to 100 percent rated power o
Shutdown from 100 percent rated power to cold shutdown o
Power operations and load changes o
Operator-conducted surveillance testing on safety related equipment or systems, as applicable
Malfunction Testing o
Demonstrate the ability to model malfunctions as described in ANSI/ANS-3.5-2009, Section 3.1.4
Post-Event Testing, if applicable o
Post-event testing from April 2020-current, if applicable
Scenario Based Testing o
(1) 2020 Initial License Exam scenario o
Any scenarios used for reactivity control manipulations for the 2020 initial license exam, if applicable o
(1) 2021 Continuing training annual operating test scenario o
(1) 2022 Continuing training annual operating test scenario o
(1) 2024 Continuing training annual operating test scenario
Simulator Operability Testing o
Steady state operation
(3) Steady State Performance, various power levels (at least 50 percent power) o Transient Performance Tests
Manual Reactor Trip
Simultaneous trip of all feedwater pumps
2
Simultaneous closure of all main steam isolation valves
Simultaneous trip of all reactor coolant pumps
Trip of any single reactor coolant pump
Main turbine trip from maximum power level that does not result in immediate reactor trip
Maximum rate power ramp from 100 percent down to ~75 percent and back up to 100 percent
Maximum size reactor coolant system rupture combined with loss of all offsite power
Maximum size unisolable main steam line rupture
Slow primary system depressurization to saturated condition with pressurizer relief or safety valve stuck open (inhibit activation of high pressure emergency core cooling system)
Maximum design load rejection
Core Performance Testing o
Core performance testing, using the last designated core load
Complete deficiency reports for items of interest (Corrective Action program and simulator deficiency reports)
Lead Inspector Contact Information:
Bryan A. Bergeon 630-829-9719 Bryan.Bergeon@nrc.gov