ML021440494

From kanterella
Jump to navigation Jump to search
April 2002 Monthly Operating Report for Palisades Nuclear Plant
ML021440494
Person / Time
Site: Palisades Entergy icon.png
Issue date: 05/09/2002
From: Lahti L
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML021440494 (5)


Text

Committed to NuclearExcellence Palisades Nuclear Plant Operated by Nuclear Management Company, LLC May 9, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 DOCKET 50-255 - LICENSE DPR PALISADES NUCLEAR PLANT LICENSEE REPORT OF MONTHLY OPERATING DATA Attached are the Monthly Operating Data and Summary of Operating Experience for the Palisades Nuclear Plant for the month of April 2002.

If you have any questions, please contact Mr. Rich Schmidt at (616) 764-2185.

Laurie A. Lahti Manager, Licensing CC Regional Administrator, USNRC, Region III NRC Resident Inspector, Palisades LBrandon, Michigan Department of Environmental Quality RJAben, Michigan Department of Labor RDWhale, Michigan Public Service Commission Records Center, INPO SMMclntyre, P-26-204 Attachment 27780 Blue Star Memorial Highway 0 Covert, MI 49043 Telephone: 616.764.2000

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO 50-255 UNIT Palisades DATE 5/03/02 COMPLETED BY SFPierce MONTH April 2002 TELEPHONE (616)764-2239 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe Net) (MWe Net)

1. 805 17. 794
2. 804 18. 792
3. 805 19. 800
4. 806 20. 803
5. 805 21. 805
6. 806 22. 804
7. 805 23. 804
8. 800 24. 800
9. 803 25. 800
10. 804 26. 802
11. 802 27. 807
12. 801 28. 807
13. 804 29. 806
14. 801 30. 804
15. 797 31. N/A
16. 796 INSTRUCTIONS:

On this format, list the average daily unit power level in MWe-NET for each day in the reporting month.

Compute to the nearest whole megawatt.

SUMMARY

OF OPERATING EXPERIENCE FOR APRIL 2002 The Plant operated at a daily average power level of greater than 99% for the entire month.

OPERATING DATA REPORT DOCKET NO: 50-255 DATE (Mo-Da-Yr): 05-03-02 COMPLETED BY: SFPierce TELEPHONE (616) 764-2239 OPERATING STATUS: NOTES:

1. UNIT NAME Palisades
2. REPORTING PERIOD (YrMoDa-YrMoDa): 020401-020430
3. LICENSED THERMAL POWER (Mwt) 2530
4. NAMEPLATE RATING (GROSS Mwe) 811.7
5. DESIGN ELECTRICAL RATING (NET Mwe) 805
6. MAXIMUM DEPENDABLE CAPACITY (GROSS Mwe) 770
7. MAXIMUM DEPENDABLE CAPACITY (NET Mwe)
  • 730
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEM NUMBERS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
10. REASONS FOR RESTRICTIONS, IF ANY:

This Month Yr-to-Date Cumulative

11. HOURS IN REPORTING PERIOD 719.0 2879.0 266174.0
12. NUMBER OF HOURS REACTOR WAS CRITICAL 719.0 2487.4 163714.1
13. REACTOR RESERVE SHUTDOWN HOURS .......
14. HOURS GENERATOR ON-LINE 719.0 2393.6 158184.1
15. UNIT RESERVE SHUTDOWN HOURS
16. GROSS THERMAL ENERGY GENERATED (MWH) 1812744 5964296 357088873
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 604157 1982559 113741587
18. NET ELECTRICAL ENERGY GENERATED (MWH) 576904 1892445 107586260
19. UNIT SERVICE FACTOR 100.0% 83.1% 59.4%
20. UNIT AVAILABILITY FACTOR 100.0% 83.1% 59.4%
21. UNIT CAPACITY FACTOR (USING MDC NET)
  • 109.9% 90.0% 58.4%
22. UNIT CAPACITY FACTOR (USING DER NET) 99.7% 81.7% 50.2%
23. UNIT FORCED OUTAGE RATE 0.0% 16.9% 26.0%
24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
    • Based on condenser backpressure
  • Weighted Average (635 MWe used as MDC Net prior to October 1985)

REPORT MONTH April 2002 DOCKET NO 50-255 UNIT Palisades DATE(Mo/Da/Yr) 05/03/02 COMPLETED BY SFPierce TELEPHONE 616-764-2239 UNIT SHUTDOWNS AND POWER REDUCTIONS No. Date Type' Duration Reason 2 Method of Licensee System Component Cause & Corrective 4

(YrMoDa) (Hours) Shutting Event Code Code' Action to 3

Down Reactor Report # Prevent Recurrence NONE

1. 2. 3. 4. 5.

F: Forced Reason: Method: Exhibit G - Instructions Exhibit I - Same Source S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Other (Explain) (NUREG-0161)

E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain)