IR 05000528/2003007

From kanterella
Jump to navigation Jump to search
IR 05000528-03-007, IR 05000529-03-007, and IR 05000530-03-007, on 06/09-27/2003; 07/07-11/2003; 07/21-25/2003 & 08/04-20/2003; Palo Verde Nuclear Generating Station, Units 1, 2, and 3; Triennial Fire Protection Inspection
ML032591171
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 09/15/2003
From: Nease R
NRC/RGN-IV/DRS/EMB
To: Overbeck G
Arizona Public Service Co
References
FOIA/PA-2004-0277 IR-03-007
Download: ML032591171 (26)


Text

ber 15, 2003

SUBJECT:

PALO VERDE NUCLEAR GENERATING STATION - NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000528/2003-007; 05000529/2003-007; 05000530/2003-007

Dear Mr. Overbeck:

On June 27, 2003, the U. S. Nuclear Regulatory Commission (NRC) completed a 2-week onsite team triennial fire protection baseline inspection of your Palo Verde Nuclear Generating Station, Units 1, 2, and 3. Additional in-office inspection was performed during the weeks of June 16, July 7, July 21, and August 4, 2003. The enclosed report presents the results of this inspection.

We discussed the preliminary results of the onsite inspection with you and members of your staff on June 27, 2003. On August 20, 2003, we conducted a telephonic exit meeting with you and members of your staff to inform you of the results of the inspection.

The inspection involved an examination of the effectiveness of activities conducted under your license as they related to the implementation of your NRC-approved fire protection program and compliance with the Commissions rules and regulations and with the conditions of your license.

Within these areas, the inspection consisted of selected examination of procedures and representative records, observations of activities, and interviews with personnel.

Based on the results of this inspection, no findings of significance were identified. However, a licensee-identified violation, which was determined to be of very low safety significance, is discussed in Section 4OA7. If you contest the violation or significance of the noncited violation, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Palo Verde Nuclear Generating Station, Units 1, 2, and 3.

Arizona Public Service Company -2-In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Rebecca L. Nease, Team Leader Engineering and Maintenance Branch Division of Reactor Safety Dockets: 50-528; 50-529; 50-530 Licenses: NPF-41; NPF-51; NPF-74

Enclosure:

NRC Inspection Report 05000528/2003-007; 05000529/2003-007; 05000530/2003-007

REGION IV==

Docket Nos.: 50-528; 50-529; 50-530 License Nos.: NPF-41; NPF-51; NPF-74 Report No.: 05000528/2003-007; 05000529/2003-007; 05000530/2003-007 Licensee: Arizona Public Service Company Facility: Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Location: 5951 S. Wintersburg Road Tonopah, Arizona Dates: June 9-27, 2003; additional in-office inspection was conducted during the weeks of July 7, July 21, August 4, and a telephonic exit meeting was conducted August 20, 2003 Team Leader: C. E. Johnson, Senior Reactor Inspector Engineering and Maintenance Branch Inspectors: R. P. Mullikin, Senior Reactor Inspector Engineering and Maintenance Branch J. Mateychick, Reactor Inspector Engineering and Maintenance Branch J. Taylor, Reactor Inspector Engineering and Maintenance Branch Accompanying S. Meyers, Engineering Associate Personnel: A. Kana, Engineering Associate Approved By: Rebecca L. Nease, Team Leader Engineering and Maintenance Branch Division of Reactor Safety

-2-SUMMARY OF FINDINGS IR 05000528/2003-007, IR 05000529/2003-007, IR 05000530/2003-007; 06/9-27/2003; 07/7-11/2003; 07/21-25/2003; 8/4-20/2003; Palo Verde Nuclear Generating Station, Units 1, 2, and 3; Triennial Fire Protection Inspection.

The inspection was conducted by a team of four regional inspectors and accompanied by two engineering associates. The inspection identified one (Green) finding, which was a violation of NRC regulatory requirements. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609, "Significance Determination Process." Findings for which the significance determination process does not apply may be Green or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.

A. NRC-Identified and Self-Revealing Findings No findings of significance were identified.

B. Licensee-Identified Violation Violations of very low safety significance, which were identified by the licensee, have been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. This violation and corrective action tracking numbers are listed in Section 4OA7 of this report.

C License Conditions 2.C(6), 2.C(7) and 2.F (Units 1, 2, and 3, respectively),

require the licensee to implement and maintain all provisions of their approved fire protection program as described in the Updated Final Safety Analysis Report for the facility. In Section 9.5.1.1 of the Updated Safety Analysis Report the licensee committed to Branch Technical Position 9.5-1, Guidelines For Fire Protection For Nuclear Power Plants. Branch Technical Position 9.5-1 states that measures should be established to assure that conditions adverse to fire protection, such as, failures, malfunctions, deficiencies, deviations, defective components, uncontrolled combustible material and nonconformances are promptly identified, reported ,and corrected. Contrary to the above, from September 1997 to the present, a condition adverse to fire protection was identified, but not corrected in order to prevent recurrence. The plant maintenance radio system used for alternative shutdown outside of the control room included a design feature, which adversely impacted the availability and reliability of the system when security performed radio checks. The licensees failure to correct the ongoing deficiency with the plant maintenance radio system resulted in periods of time where the requirements of 10 CFR Part 50, Appendix R, Section III.L, were not met. Specifically, disruption of communications to operations via the radio system could prevent the completion of operator actions for an alternative shutdown outside the control room. The failure to correct and prevent recurrence of these deficiencies was identified in the licensees corrective action program as Condition Report/Disposition

-3-Request 2589540. This finding was of very low significance because the probability of the disruption of the operations radio communications as a result of security radio checks and a fire occurring concurrently is very low.

Report Details 1. REACTOR SAFETY Cornerstones: Initiating Events and Mitigating Systems 1R05 Fire Protection The purpose of this inspection was to review the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, fire protection program for selected risk-significant fire areas.

Emphasis was placed on verification of the licensees post-fire safe shutdown capability.

The inspection was performed in accordance with the new NRC regulatory oversight process using a risk-informed approach for selecting the fire areas and attributes to be inspected. The team leader and a Region IV senior reactor analyst used the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, Individual Plant Examination for External Events (IPEEE) to choose several risk-significant areas for detailed inspection and review. The fire zones chosen for review during this inspection were:

  • Fire Zone 5B (Train B engineered safety feature switchgear room)
  • Fire Zone 7B (Channel B dc equipment room)
  • Fire Zone 47A (Channel A containment electrical penetration room)
  • Fire Zone 42D (Auxiliary Building 100' west corridor area)

For each of these fire zones, the inspection was focused on the fire protection features, the systems and equipment necessary to achieve and maintain safe shutdown conditions, determination of license commitments, and changes to the fire protection program. The primary inspection focus was on Unit 1. However, any differences between the units were considered in the review. The team also toured and inspected several of the same fire areas in Units 2 and 3.

.1 Systems Required to Achieve and Maintain Post-Fire Safe Shutdown a. Inspection Scope The team reviewed the functional requirements identified by the licensee as necessary for achieving and maintaining hot shutdown conditions to ensure that at least one post-fire safe shutdown success path was available in the event of a fire in each of the selected areas. The team reviewed piping and instrumentation diagrams of systems credited in accomplishing safe shutdown functions to independently verify whether the licensee's shutdown methodology had properly identified the required components. The team focused on the following functions that must be ensured to achieve and maintain post-fire safe shutdown conditions:

  • Reactivity control capable of achieving and maintaining cold shutdown reactivity conditions,

-2-

  • Supporting systems capable of providing all other services necessary to permit extended operation of equipment necessary to achieve and maintain hot shutdown conditions.

A review was also conducted to ensure that all required electrical components in the selected systems were included in the licensees safe shutdown analysis. The team identified the systems required for each of the primary safety functions necessary to shut down the reactor. These systems were then evaluated to identify the systems that interfaced with the fire areas inspected and were the most risk significant systems required for reaching both hot and cold shutdown conditions. The systems selected for review were the chemical and volume control system, reactor coolant system, and the safety injection system.

b. Findings No findings of significance were identified.

.2 Fire Protection of Safe Shutdown Capability and Post-fire Safe Shutdown Circuit Analysis a. Inspection Scope The team reviewed licensee documentation to verify that at least one post-fire safe shutdown success path was free of fire damage in the event of a fire in the selected fire areas. Specifically, the team examined the separation of safe shutdown cables, equipment, and components within the same fire areas. The team reviewed, on a sample basis, the analysis of electrical protective devices (e.g., circuit breakers, fuses, relays), coordination, and adequacy of electrical protection provided for nonessential cables, which share a common enclosure (e.g., cable trays) with cables of equipment required to achieve and maintain safe shutdown conditions. Additionally, the team reviewed the protection of diagnostic instrumentation required for safe shutdown for fires in the selected areas. A sample of fire barrier penetration seals in the selected fire areas was reviewed by the team. The team reviewed the licensee's methodology for meeting the requirements of 10 CFR 50.48, and the bases for the NRC's acceptance of this methodology as documented in NRC safety evaluation reports. In addition, the team reviewed license documentation, such as, the Palo Verde Updated Final Safety Evaluation Report, submittals made to the NRC by the licensee in support of the NRC's review of their fire protection program, and deviations from NRC regulations to verify that the licensee met license commitments.

The team reviewed a comprehensive list of design changes that resulted in removal of Thermo-Lag fire barriers, focusing on instances where manual actions were substituted in lieu of installing another fire barrier.

-3-b. Findings Manual Actions in Lieu of Physical Protection Requirements Introduction: The team identified an unresolved item concerning the use of manual actions for a fire outside of the control room. These manual actions were used in lieu of physical protection of equipment required for post-fire safe shutdown, and some of these actions did not appear to be approved by the NRC. This issue is unresolved pending further NRC review of the licensees fire protection program licensing basis regarding the use of manual actions.

Description: In reviewing Procedure 40DP-9ZZ19, Operational Considerations due to Plant Fire, and Calculation 13-MC-FP-316, Appendix R Manual Action Feasibility, the team found that in the event of a fire in numerous fire areas outside of the control room, the licensee credited the use of manual actions in lieu of providing physical protection of equipment required for post-fire safe shutdown. Many of these manual actions were found to have been submitted to the NRC and approved in the Updated Final Safety Analysis Report, Safety Evaluation Report, Supplement 7, dated December 1984.

However, the team could not verify that all manual actions taken in lieu of providing the required physical protection were formally submitted to and approved by the NRC. For example, one action is to align the refueling water tank as an alternate suction path to the charging pumps in order to prevent gas binding. The team could not verify that this manual action had been approved by the NRC.

The team reviewed the manual actions credited in the event of a fire in the selected fire areas, and found that all were described in procedures and appeared to be reasonable and feasible.

Analysis: The significance of this issue will be evaluated if the team determines that any manual actions credited for post-fire safe shutdown were not submitted and approved by the NRC. This item is unresolved pending completion of further NRC review of the licensee's fire protection licensing basis.

Enforcement: License Conditions 2.C(6), 2.C(7) and 2.F (Units 1, 2, and 3, respectively), require the licensee to implement and maintain all provisions of their approved fire protection program as described in the Updated Final Safety Analysis Report for the facility. In the Updated Final Safety Analysis Report, the licensee committed to 10 CFR Part 50, Appendix R, Section III.G, III.J, and III.O.Section III.G.2 of Appendix R to 10 CFR Part 50 describes three methods acceptable for ensuring that at least one train of redundant safe shutdown equipment is free of fire damage: (a)

redundant trains be located in different fire areas separated by 3-hour rated fire barriers; (b) redundant trains in the same fire area be separated by 20 feet of horizontal distance with no intervening combustible or fire hazards, and the fire area be equipped with area-wide detection and suppression; or (c) one redundant train be separated from the other redundant trains by enclosing it in a 1-hour fire-rated barrier, and the fire area be equipped with area-wide detection and suppression. However, the licensee credited operator actions in lieu of providing the physical protection requirements of Section III.G.2. The NRC will perform further review of the licensing basis documents to determine whether all manual actions credited in lieu of the physical protection specified

-4-in Appendix R,Section III.G 2, were submitted to and approved by the NRC. Whether this issue is a violation remains unresolved pending completion of this review (URI 05000528; -529; -530/2003007-01).

.3 Alternative Safe Shutdown Capability and Implementation a. Inspection Scope The team reviewed the licensees alternative shutdown methodology to determine if the licensee has properly identified the components and systems necessary to achieve and maintain safe shutdown conditions from the remote shutdown panel and alternative shutdown locations for a fire in the units control room. The team focused on the adequacy of the systems selected for reactivity control, reactor coolant makeup, reactor heat removal, process monitoring and support system functions. The team verified that hot and cold shutdown from outside the control room can be achieved and maintained with off-site power available or not available. The team verified that the transfer of control from the control room to the alternative locations has been demonstrated and not affected by fire-induced circuit faults by reviewing the provision of separate fuses for alternative shutdown control circuits.

b. Findings No findings of significance were identified.

.4 Operational Implementation of Alternate Shutdown Capability a. Inspection Scope The team verified that the training program for licensed and non-licensed personnel has been expanded to include the alternative safe shutdown capability through review of sample Job Performance Measure packages used for operator training evaluations and operator training lesson plans.

The team performed walkdowns of the actions defined in Procedure 40AO-9ZZ19 with licensed and non-licensed operators. Procedure 40AO-9ZZ19, "Control Room Fire," provides instructions for performing an alternative shutdown from the remote shutdown panel and for manipulating equipment locally in the plant. The team verified that operators could reasonably be expected to perform the procedure actions within the identified applicable plant shutdown time requirements, and that equipment labeling was consistent with the procedure. Also, the team verified that the licensee had adequate staffing for performing Procedure 40AO-9ZZ19.

The team reviewed the results of several completed Surveillance Test Packages 40ST 9ZZ20 performed for Units 1 and 3. The testing is required to be performed every 18 months in accordance with Technical Specifications Surveillance Requirement 3.3.11.2. The review verified that: (1) the licensee conducted periodic operational tests of the alternative shutdown transfer capability and instrumentation and control functions; and (2) the tests were adequate to show that if called upon, the alternative shutdown capability would be functional upon transfer.

-5-The teams review of the adequacy of communications and emergency lighting associated with this procedure are documented in Sections .5, .6, and 4AO7 of this report.

b. Findings No findings of significance were identified.

.5 Communications a. Inspection Scope The team reviewed the communications required to implement the alternative shutdown Procedure 40AO-9ZZ19, Control Room Fire. The plant maintenance radio system is used by operations to perform an alternative shutdown outside of the control room. The team verified that: (1) the design of the radio system will assure that damage from a control room fire will not impact the performance of the rest of the system; and (2) the radio system is sufficient to perform the required communications identified in the alternative shutdown procedure.

b. Findings A licensee-identified finding involving timely disposition of emergency communication deficiencies is discussed in Section 4OA7 of this report.

.6 Emergency Lighting a. Inspection Scope The team reviewed the adequacy of emergency lighting for performing actions required in Procedure 40AO-9ZZ19, "Control Room Fire," which included access and egress routes. The team reviewed test procedures and test data to verify that the fluorescent lights powered by inverters and 8-hour batteries and the individual battery operated units were able to supply light for the required 8-hour period.

b. Findings No findings of significance were identified.

.7 Cold Shutdown Repairs a. Inspection Scope The team reviewed equipment operations and capability to determine if any repairs were required in order to achieve cold shutdown. The team noted that the licensee did not require the repair of equipment to reach cold shutdown based on the safe shutdown methodology implemented.

-6-b. Findings No findings of significance were identified.

.8 Compensatory Measures a. Inspection Scope The team verified, by sampling, that adequate compensatory measures were put in place by the licensee for out-of-service, degraded, or inoperable fire protection features and post-fire safe shutdown equipment, and systems.

b. Findings No findings of significance were identified.

.9 Fire Protection Systems, Features and Equipment a. Inspection Scope For the selected fire areas, the team evaluated the adequacy of fire protection features (e.g., detection and suppression systems, or passive fire barrier features), such as, fire suppression and detection systems, fire area barriers, penetration seals, and fire doors.

The team observed the material condition and configuration of the installed fire detection and suppression systems, fire barriers, and construction details and supporting fire tests for the installed fire barriers. In addition, the team reviewed license documentation, such as NRC safety evaluation reports and deviations from NRC regulations and the National Fire Protection Association (NFPA) codes to verify that fire protection features met license commitments.

The team noted that all four of the fire zones selected contained fire detection systems.

Two of the fire zones contained automatic pre-action water sprinkler systems and one fire zone contained an automatic carbon dioxide total flooding system. The team walked down the areas to verify that the detection and suppression system location drawings agreed with the as-installed configurations. The team reviewed the original suppression systems specifications, the hydraulic calculations for the pre-action water systems, and the carbon dioxide system design calculations. The team reviewed the periodic testing performed on the automatic carbon dioxide total flooding system including the interfacing fire detection systems and ventilation system dampers. The team also reviewed the original testing performed to confirm that the design concentration of carbon dioxide was sufficient.

b. Findings No findings of significance were identified.

-7-4OA2 Identification and Resolution of Problems (71152)

a. Inspection Scope The team selected a sample of the licensees condition reports/disposition requests associated with the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, fire protection program. The team verified that the licensee had an appropriate threshold for identifying issues. The team also reviewed several licensee audits performed for the fire protection program. The team evaluated the effectiveness of the corrective actions for the identified issues.

b. Findings No findings of significance were identified. A licensee-identified finding involving the timely resolution of emergency communications deficiencies is discussed in Section 4OA7 of this report.

4OA6 Meetings, including Exit On June 27, 2003, at the conclusion of the teams onsite inspection, the team leader debriefed Gregg R. Overbeck, Senior Vice President, Nuclear, and other licensee management and staff members on the triennial fire protection inspection results.

On July 22, 2003, the team leader and other members of the inspection team conducted an telephonic conference call with the licensees regulatory affairs and fire protection staff (at the licensees request) to discuss additional information forwarded to the team and to clarify the basis for the inspection findings.

On August 6, 2003, the team leader, accompanied by the Engineering and Maintenance Branch Chief, conducted an additional onsite meeting to give the licensee an opportunity to clarify and present new information to support their position on an issue pertaining to the location of fire detectors in Fire Zone 7B. At the conclusion of this meeting the team leader informed the licensee that the team would review the additional information provided.

On August 20, 2003, the team leader conducted an telephonic exit with licensee management and staff members on the triennial fire protection inspection results.

The licensee was asked whether any materials examined during the inspection should be considered proprietary. A proprietary document was identified and the inspectors agreed to properly dispose of the document immediately.

4OA7 Licensee-Identified Violations The following violation of very low safety significance (Green) is identified by the licensee and is a violation of NRC requirements which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as a noncited violation.

-8-

  • License Conditions 2.C(6), 2.C(7) and 2.F (Units 1, 2, and 3, respectively),

require the licensee to implement and maintain all provisions of their approved fire protection program as described in the Updated Final Safety Analysis Report for the facility. In Section 9.5.1.1 of the Updated Safety Analysis Report the licensee committed to Branch Technical Position 9.5-1, Guidelines For Fire Protection For Nuclear Power Plants. Branch Technical Position 9.5-1 states that measures should be established to assure that conditions adverse to fire protection, such as, failures, malfunctions, deficiencies, deviations, defective components, uncontrolled combustible material and nonconformances are promptly identified, reported ,and corrected. Contrary to the above, from September 1997 to the present, a condition adverse to fire protection was identified, but not corrected in order to prevent recurrence. The plant maintenance radio system used for alternative shutdown outside of the control room included a design feature, which adversely impacted the availability and reliability of the system when security performed radio checks. The licensees failure to correct the ongoing deficiency with the plant maintenance radio system resulted in periods of time where the requirements of 10 CFR Part 50, Appendix R, Section III.L, were not met. Specifically, disruption of communications to operations via the radio system could prevent the completion of operator actions for an alternative shutdown outside the control room. The failure to correct and prevent recurrence of these deficiencies was identified in the licensees corrective action program as Condition Report/Disposition Request 2589540. This finding was of very low significance because the probability of the disruption of the operations radio communications as a result of security radio checks and a fire occurring concurrently is very low.

ATTACHMENT PARTIAL LIST OF PERSONS CONTACTED Licensee D. Agazzi, Captain, Fire Department S. Bauer, Department Lead, Regulatory Affairs M. Czarnylas, Fire Protection Operations S. Dodd, Fire Marshal, Fire Department C. Foster, Senior Engineer, Design Engineering - Mechanical E. Garcia, Program Advisor, Emergency Service Department F. Garrett, Management Technical Assistant R. Guron, Senior Engineer, Mechanical Design D. Hautala, Senior Engineer, Regulatory Affairs M. Hodge, Section Leader, Mechanical Design A. Huttie, Department Leader, Emergency Services Division - Programs D. Kanitz, Senior Engineer, Regulatory Affairs S. Kesler, Section Leader, Electrical Design S. Koski, Fire Protection System Engineer, System Engineering A. Krainik, Director, Regulatory Affairs J. Levine, Executive Vice President, Generation D. Marks, Section Leader, Nuclear Regulatory Affairs - Compliance R. Merryman, Senior Advisor, Operations F. Rieder, Department Lead, Nuclear Training Department G. Overbeck, Senior Vice President, Nuclear E. Sterling, Department Lead, Nuclear Assurance Department M. Sontag, Department Lead, Nuclear Assurance Department D. Straka, Senior Consultant, Regulatory Affairs Others R. Henry, Site Representative (Salt River Project)

NRC N. Salgado, Senior Resident Inspector LIST OF ITEMS OPENED Opened 05000528, -529, -530/2003007-01 URI Manual actions taken in lieu of providing physical protection

-2-LIST OF DOCUMENTS REVIEWED Calculations Number Description Revision 01-10407-M650-717 Hydraulic Calculations for Bid Item 38 S.W. Corridor 4 100 Level Zone 42D System Demand 209.5 GPM @

74.94 PSI Pre-action System 01-10407-M650-733 Hydraulic Calculations for Auxiliary Bldg. 120 Level W. 3 Half Channel A - Penetration Room 01-MC-FP-818 Fire Water System Analysis For Unit 1 2 13-104-07-M652-19 Hazard Effective Discharge Period, Design Flow Rate 4 and Storage Requirement 13-104-07-M652-99 Hazard Effective Discharge Period, Design Flow Rate 2 and Storage Requirement 13-MC-FP-205 Verification of CO2 Requirement 1 13-EC-FP-110 Protective Device Coordination - Fire Protection 10 13-MC-FP-315 10CFR50 Appendix R Safe Shutdown 9 13-MC-FP-316 10CFR50 Appendix R - Manual Action Feasibility 10 13-MC-FP-317 10CFR50 Appendix R Operational Considerations 6 13-MC-FP-318 III.G/III.L Compliance Assessment 8 13-MC-FP-803 Combustible Loading Calculations 12 Drawings Number Title Revision 01-E-AFB-003 Elementary Diagram - AFW System AF Reg Valves 8 Sheet 1 Pump B to SG-1 & 2, 1J-AFB-HV-30 01-E-AFB-003 Elementary Diagram - AFW System AF Reg Valves 8 Sheet 2 Pump B to SG-1 & 2, 1J-AFB-HV-31 01-E-CHB-048 Elementary Diagram - CVCS Seal Inj. Vvs. To RCP 3 Sheet 1 1J-CHE-FV-241 01-E-CHB-048 Elementary Diagram - CVCS Seal Inj. Vvs. To RCP 3 Sheet 2 1J-CHE-FV-242

-3-Number Title Revision 01-E-CHB-048 Elementary Diagram - CVCS Seal Inj. Vvs. To RCP 3 Sheet 3 1J-CHE-FV-243 01-E-CHB-048 Elementary Diagram - CVCS Seal Inj. Vvs. To RCP 3 Sheet 4 1J-CHE-FV-244 01-E-CHB-073 Elementary Diagram - CVCS Regen. HX to Chg Line Vv. 3 1J-CHE-HV-239 01-E-CHB-052 Elementary Diagram - CVCS Regen. HX to Chg Line Vv. 5 1J-CHE-HV-240 01-E-ECB-003 EchilledW Chilled Water Circ. Pumps & Thermocouples 6 01-E-ECB-004 Elementary Diagram - EchilledW Chilled Water Expansion 5 Sheet 1 Tk. Make-up Vv. 1J-ECA-LV-15 01-E-ECB-004 Elementary Diagram - EchilledW Chilled Water Expansion 5 Sheet 2 Tk. Make-up Vv. 1J-ECA-LV-16 01-E-EWB-001 Elementary Diagram - ECLgW Pumps A & B, 1M-EWA- 6 Sheets 1 & 2 P01 & 1M-EWB-P01 01-E-EWB-002, Elementary Diagram - ECLgW Surge Tank Fill Vv. 1J- 4 Sheet 1 EWA-LV-91 01-E-EWB-002, Elementary Diagram - ECLgW Surge Tank Fill Vv. 1J- 4 Sheet 2 EWA-LV-92 01-E-EWB-003 Elementary Diagram - ECLgW Loop A to .from NCW 5 Sheet 1 Cross Tie Vv. IJ-EWA-UV-145 01-E-EWB-003 Elementary Diagram - ECLg W Loop A to .from NCW 5 Sheet 2 Cross Tie Vv. IJ-EWA-UV-65 01-E-EWE-054 Instrument Loop Wiring Diagram ECLgW 9 Sheet 1 01-E-EWE-054 Instrument Loop Wiring Diagram ECLgW 9 Sheet 2 01-E-SIB-001 Elementary Diagram - Safety Injection & Shutdown Clg 6 Sheet 1 Sys HP Safety Injection Pump 1M-SIA-P02 01-E-SIB-001 Elementary Diagram - Safety Injection & Shutdown Clg 6 Sheet 2 Sys HP Safety Injection Pump 1M-SIB-P02 01-E-SIB-003 Elementary Diagram - Safety Injection & Shutdown 8 Sheets 1 & 2 Cooling System - Containment Spray Pump 1M-SIB-P03

-4-Number Title Revision 01-E-SIB-020 Elementary Diagram - Safety Injection & Shutdown 5 Sheet 1 Cooling System - Containment Spray Control Valve 1J-SIB-UV-671 01-E-SIB-020 Elementary Diagram - Safety Injection & Shutdown 5 Sheet 2 Cooling System - Containment Spray Control Valve 1J-SIB-UV-672 01-J-AFE-056 Instrument Loop Wiring Diagram Auxiliary Feedwater 3 System 01-J-AFE-058, Instrument Loop Wiring Diagram Auxiliary Feedwater 5 Sheets 1 & 2 System 01-J-CHE-0A8 Instrument Loop Wiring Diagram CVCS 2 Sheets 1 - 4 01-J-HJE-051 Instrument Loop Wiring Diagram Control Bldg HVAC 5 01-J-RCE-064 Instrument Loop Wiring Diagram Auxiliary Reactor 8 Sheets 1, 2 & 3 Coolant System 01-J-RCE-074 Instrument Loop Wiring Diagram Auxiliary Reactor 7 Sheet 1 Coolant System 01-J-RCE-075 Instrument Loop Wiring Diagram Auxiliary Reactor 10 Sheet 1 Coolant System 01-J-SGE-060 Instrument Loop Wiring Diagram Main Steam System 6 Sheets 1 & 2 01-J-SGE-061 Instrument Loop Wiring Diagram Main Steam System 7 Sheets 1 & 2 01-J-SGE-064 Instrument Loop Wiring Diagram Main Steam 6 Sheet 1 01-J-SGE-065 Instrument Loop Wiring Diagram Main Steam System 7 Sheet 1 02-E-ZPL-001 Power Block Safe Shutdown Emergency Lighting Sheet 1 14 Sheet 1 of 2 02-E-ZPL-001 Power Block Safe Shutdown Emergency Lighting Sheet 1 14 Sheet 2 of 2 02-E-ZPL-002 Power Block Safe Shutdown Emergency Lighting Sheet 2 14 02-E-ZPL-003 Power Block Safe Shutdown Emergency Lighting Sheet 3 7 Sheet 1 of 2

-5-Number Title Revision 02-E-ZPL-003 Power Block Safe Shutdown Emergency Lighting Sheet 3 7 Sheet 2 of 2 02-M-AFP-001 P & I Diagram Auxiliary - Feedwater 24 02-M-CHP-001 P & I Diagram - Chemical & Volume Control System 25 02-M-CHP-002 P & I Diagram - Chemical & Volume Control System 39 Sheet 1 02-M-CHP-003 P & I Diagram - Chemical & Volume Control System 29 02-M-RCP-001 P & I Diagram - Reactor Coolant System 25 02-M-RCP-002 P & I Diagram - Reactor Coolant System 11 02-M-SGP-001 P & I Diagram - Main Steam System 52 02-M-SGP-002 P & I Diagram - Main Steam System 32 02-M-SIP-001 P & I Diagram - Safety Injection and Shutdown Cooling 23 System 02-M-SIP-002 P & I Diagram - Safety Injection and Shutdown Cooling 21 System 02-10407-M650- Auxiliary Building Channel A Cable Trays 120' Elevation 9 416 West Half 02-10407-M650- Auxiliary Building Channel A Cable Trays 120' Elevation 11 418 West Half Piping & Detector Wire 02-10407-M650- Water Spray System Aux. Bldg. 100' Level Corridor Zone 8 445 42D 02-10407-M650- Auxiliary Building 100' Level Corridor Zone 42D Detectors 8 446 13-M-FPZ-001 Appendix R Logic/Safety Function Diagram Legend/Index 1 13-M-FPZ-002 Appendix R Safe Shutdown Logic Diagram 2 13-M-FPZ-003 Appendix R Safety Function Diagram Auxiliary Feedwater 2 System 13-M-FPZ-004 Appendix R Safety Function Diagram Auxiliary Building 1 HVAC 13-M-FPZ-005 Appendix R Safety Function Diagram Chemical & Volume 3 Control System

-6-Number Title Revision 13-M-FPZ-006 Appendix R Safety Function Diagram Condensate 0 Storage And Transfer System 13-M-FPZ-007 Appendix R Safety Function Diagram Control Building 1 HVAC Sheets 1 and 2 13-M-FPZ-008 Appendix R Safety Function Diagram Diesel Generator A 2 Sheet 1 of 2 13-M-FPZ-008 Appendix R Safety Function Diagram Diesel Generator B 2 Sheet 2 of 2 13-M-FPZ-009 Appendix R Safety Function Diagram Diesel Fuel Oil And 0 Transfer System 13-M-FPZ-010 Appendix R Safety Function Diagram Diesel Generator 0 Buildings HVAC 13-M-FPZ-011 Appendix R Safety Function Diagram Essential Chilled 2 Water System 13-M-FPZ-012 Appendix R Safety Function Diagram Essential Cooling 2 Water Systems Trains A & B 13-M-FPZ-013 Appendix R Safety Function Diagram Essential Spray 3 Pond System 13-M-FPZ-014 Appendix R Safety Function Diagram Main Steam System 3 13-M-FPZ-015 Appendix R Safety Function Diagram Miscellaneous 0 HVAC System 13-M-FPZ-016 Appendix R Safety Function Diagram Nuclear Cooling 1 Water System 13-M-FPZ-017 Appendix R Safety Function Diagram Nuclear Sampling 1 System/Neutron Monitoring System 13-M-FPZ-018 Appendix R Safety Function Diagram Electrical Power 3 Distribution 13-M-FPZ-019 Appendix R Safety Function Diagram Reactor Coolant 3 System 13-M-FPZ-020 Appendix R Safety Function Diagram Safety Injection and 3 Shutdown Cooling 13-M-FPZ-021 Appendix R ESFAS Logic Diagram 1 13-10407-M651-1 Detectors Connections Legend - Typical 3

-7-Number Title Revision 13-10407-M651-4 Fire Detector System - System B Detector Location- 8 Zones 6-13 13-10407-M651-12 Detector Locations - System H Zones 45 & 46 7 13-10407-M652-44 Low Pressure CO2 Fire Extinguishing System Schematic 8 Arrangement 13-10407-M652-45 Low Pressure CO2 Fire Extinguishing System Schematic 6 Arrangement 13-10407-M652-46 Low Pressure CO2 Fire Extinguishing System Schematic 7 Arrangement 13-10407-M652-59 Low Pressure CO2 Fire Extinguishing System Schematic 12 Arrangement Modifications Number Title DM 00831872 Modification of AFW Valves Fuse Deficiencies DM 2386948 Correction of false start problems with Emergency fire pumps 254612 DG Stator Heaters Cable Fuse Modification Cable Routing Data Component ID Component Description 1J-AFA-FI-40A Train A Auxiliary Feedwater (AFW) to Steam Generators Flow Indication 1J-AFB-FI-41A Train B AFW to Steam Generators Flow Indication 1J-AFA-SI-52A Train A Essential Steam Driven AFW Pump Turbine Speed Indication 1J-RCA-LI-110X Train A Pressurizer Level Indication 1J-RCB-LI-110Y Train B Pressurizer Level Indication 1J-RCA-PI-102A Train A Pressurizer Pressure Indication 1J-RCB-PI-102B Train B Pressurizer Pressure Indication 1J-SGA-PI-1013A Train A Steam Generator 1Pressure Indication

-8-Component ID Component Description 1J-SGB-PI-1013B Train B Steam Generator 1 Pressure Indication 1J-SGA-LI-1113A Train A Steam Generator Wide Range Pressure Indication 1J-SGB-LI-1113B Train B Steam Generator Wide Range Pressure Indication 1J-SGA-LI-1023A Train A Steam Generator 2 Pressure Indication 1J-SGB-PI-1023B Train B Steam Generator 2 Pressure Indication Condition Reports/Deposition Requests 115571 118061 2369744 2566468 2605708 115639 118196 2369744 2589540 2615396 115740 118480 2409988 2592678 2615408 115986 118490 2415684 2593290 2615959 115997 118504 2428230 2593673 2616096 116685 118510 2510280 2593708 24985553 117292 2310308 2529113 2597191 34780 117716 2354698 Work Orders 2393664 2409154 2559531 2590511 2591760 2564727 2582629 2615475 Miscellaneous Letter dated October 16, 1984, from the Licensee to the NRC. Subject: 10 CFR 50, Appendix R Spurious Actuation Analysis Letter dated November 13, 1984, from the Licensee to the NRC. Subject: 10 CFR 50, Appendix R Spurious Actuation Analysis Letter dated November 13, 1992, from the NRC to the Licensee. Subject: Summary of Meeting Held on November 10, 1992, to Discuss Fire Protection Programs at Palo Verde Letter dated April 29, 1993, from the Licensee to the NRC. Subject: 10 CFR 50 Appendix R, New and Revised Deviations

-9-Letter dated July 27, 1993, from the NRC to the Licensee. Subject: Summary of Meeting Held on July 20, 1993, to Discuss the Appendix R Reevaluation Effort Letter dated September 2, 1994, from the NRC to the Licensee. Subject: Summary of Meeting Held on July 27, 1994, to Discuss Fire Protection Issues Letter dated March 27, 1997, from the NRC to the Licensee. Subject: Summary of Meeting Held on February 19, 1997, to Discuss Thermo-Lag Issues Letter dated June 11, 1998, from the NRC to the Licensee. Subject: Completion of Licensing Actions for Generic Letter 92-08, Thermo-Lag 330-1 Fire Barriers, Dated December 17, 1992 Nuclear Assurance Division Audit 2001-005,Fire Protection Program, issued July 18, 2001 Nuclear Assurance Division Audit Number 2003-004, Fire Protection, issued April 25, 2003 Operations Training Department Simulator Scenario RS005 A DG, SGTR, dated April 14, 2000 Operations Training Department Classroom Lesson Fire Protection Response, Dated May 1, 2001 Operations Training Department Simulator Scenario SCN - 10 Transformer Fire, Dated February 14, 2003 Operations Training Department Simulator Scenario, Appendix R Fire, dated April 4, 2003 Operations Training Department Classroom Lesson C07 - Appendix R Review, dated April 24, 2003 Pre-Fire Strategies Manual, Revision 14 PVNGS Design Basis Manual, Fire Protection System, Revision 6 Job Performance Measures AF003-J-PLT-015 DG003-J-PLT-29 EM001-J-PLT-02 EP017-J-PLN-04 CH009-J-PLT-12 DG008-J-PLT-04 EM004-J-PLT-00 RC004-J-PLT-21 CH011-J-PLT-09 DG009-J-PLT-00 EM-15-J-PLT-00 RC007-J-PLT-16 CH016-J-PLT-05 DG012-J-PLT-00 EP003-J-C/R-15 SG008-J-PLT-12 DG001-J-PLT-01

-10-Lesson Plans Number Description Revision NKASMS319A Control Room Fire 00 NLR03L020100 L01 - Control Room Fire 00 NNR03C0203 AO - Shutdown Outside Control Room and Control 00 Room Fire NNR01T0301 Shutdown Outside Control Room Task Training 00 NNI01C350 Abnormal Operating Procedures For Areas 1 And 2 00 NNI02C350 Abnormal Operating Procedures For Areas 3 And 4 00 Procedures Number Description Revision 14FT-9FP07 CO2 Suppression System Storage Tank Level 3 14FT-9FP08 CO2 Fire Suppression System Functional Test 8 14FT-9FP29 CO2 Fire Suppression System Valve and Test Switch 5 Position Verification 33FT-9FP02 CO2 Fire Suppression System Damper Functional Test 5 38FT-9QK14 Fire Detection/Protection System Supervised Circuits 2 Test and Functional Test - Carbon Dioxide Panels 40AO-9ZZ19 Control Room Fire 9 40DP-9ZZ19 Operational Considerations due to Plant Fire 10 40ST-9ZZ20 Remote Shutdown Disconnect Switch and Control 5 Circuit Operability 73ST-9SG05 ADV Nitrogen Accumulator Drop Test 16 91PE-1FP-03 Carbon Dioxide Flooding Test 0 Miscellaneous Documents Number Description Revision System Training Fire Protection and Dectection Systems (FP/QK) 3 Manual, Volume 64

-11-Number Description Revision Subcontract No. Technical Specification for Fire Protection Sprinkler 4 13-MM-650 and Spray System Specification No. Technical Requirements for Fire Protection Equipment 4 13-MM-652 (CO2)

TS 3.3.11 Remote Shutdown System 117 TRM T3.11.100 Fire Detection Instrumentation 4 TRM T3.11.102 Spray and/or Sprinkler Systems 4 TRM T3.11.103 CO2 Systems 4 TRM Component Remote Shutdown Disconnect Switches 0 List T7.0.100 TRM Component Remote Shutdown Control Circuits 0 List T7.0.200 Audits/Assessments 2003-004, Fire Protection, 4/25/03 2001-005, Fire Protection Program, 7/18/01