MONTHYEARIR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) IR 05000528/20243012024-06-17017 June 2024 NRC Examination Report 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) IR 05000528/20240122024-03-0404 March 2024 Age-Related Degradation Inspection Report 05000528/2024012, 05000529/2024012 and 05000530/2024012 IR 05000528/20230062024-02-28028 February 2024 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2 and 3 Report 05000528/2023006 and 05000529/2023006 and 05000530/2023006 IR 05000528/20230042024-02-12012 February 2024 Integrated Inspection Report Report 05000528/2023004 and 05000529/2023004 and 05000530/2023004 ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 IR 05000528/20233012023-06-0505 June 2023 NRC Examination Report 05000528/2023301, 05000529/2023301 and 05000530/2023301 IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) IR 05000528/20220062023-03-0101 March 2023 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2022006, 05000529/2022006, and 05000530/2022006) IR 05000528/20234012023-02-27027 February 2023 NRC Security Inspection Report 05000528/2023401, 05000529/2023401, 05000530/2023401, and 07200044/2023401 (Full Report) IR 05000528/20220042023-01-30030 January 2023 Integrated Inspection Report 05000528/2022004 and 05000529/2022004 and 05000530/2022004 IR 05000528/20220102023-01-17017 January 2023 Design Basis Assurance Inspection (Teams) Inspection Report 05000528/2022010 and 05000529/2022010 and 05000530/2022010 IR 05000528/20220032022-10-24024 October 2022 Units, 1, 2 and 3 Integrated Inspection Report 05000528/2022003, 05000529/2022003, and 05000530/2022003 IR 05000528/20224032022-10-14014 October 2022 Security Baseline Inspection Report 05000528/2022403 and 05000529/2022403 and 05000530/2022403 ML22235A6662022-08-23023 August 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000528/2022010, 05000529/2022010, and 05000530/2022010) and Request for Information IR 05000528/20220052022-08-23023 August 2022 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2022005 and 05000529/2022005 and 05000530/2022005) IR 05000528/20224022022-08-0808 August 2022 Cover Letter Only - Palo Verde Nuclear Generating Station, Units 1, 2, and 3 NRC Security Inspection Report 05000528 2022402, 05000529 2022402, 05000530 2022402, and 07200044 2022402 IR 05000520/20220022022-08-0505 August 2022 Integrated Inspection Report 05000528/2022002 and 05000529/2022002 and 05000520/2022002 IR 05000528/20223012022-06-21021 June 2022 NRC Examination Report 05000528/2022301, 05000529/2022301, and 05000530/2022301 IR 05000528/20220012022-05-0909 May 2022 Integrated Inspection Report 05000528/2022001, 05000529/2022001 and 05000530/2022001 ML22105A0512022-04-19019 April 2022 Review of the 2021 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20224202022-03-0808 March 2022 Security Baseline Inspection Report 05000528/2022420, 05000529/2022420 and 05000530/2022420, Cover Letter IR 05000528/20210062022-03-0202 March 2022 Annual Assessment Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021006, 05000529/2021006, and 05000530/2021006) IR 05000528/20210042022-02-0707 February 2022 Integrated Inspection Report 05000528/2021004, 05000529/2021004, and 05000530/2021004 IR 05000528/20210032021-11-12012 November 2021 Integrated Inspection Report 05000528/2021003, 05000529/2021003 and 05000530/2021003 IR 05000528/20210152021-10-27027 October 2021 Temporary Instruction 2515/194 Report 05000528/2021015 and 05000529/2021015 and 05000530/2021015 ML21273A3172021-10-0404 October 2021 Station. NON-SENSITIVE IR 05000528/20214042021-09-23023 September 2021 NRC Security Inspection Report 05000528/2021404, 05000529/2021404, 05000530/2021404 and 07200044/2021401 IR 05000528/20214012021-09-14014 September 2021 Security Baseline Inspection Report 05000528/2021401 and 05000529/2021401 and 05000530/2021401 IR 05000528/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021005, 05000529/2021005, and 05000530/2021005) IR 05000528/20210022021-08-0909 August 2021 Integrated Inspection Report 05000528/2021002, 05000529/2021002, and 05000530/2021002 and Exercise of Enforcement Discretion IR 07200044/20214012021-07-21021 July 2021 ISFSI, Information Request, Security Inspection Report 07200044/2021401 IR 05000528/20210142021-07-14014 July 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000528/2021014, 05000529/2021014 and 05000530/2021014 2024-08-08
[Table view] Category:Letter
MONTHYEARML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a IR 05000528/20243012024-06-17017 June 2024 NRC Examination Report 05000528/2024301; 05000529/2024301; 05000530/2024301 ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A ML24157A3392024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium ML24144A2772024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24129A1482024-05-0707 May 2024 and Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 ML24032A1542024-04-0303 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML24089A1892024-03-28028 March 2024 Present Levels of Financial Protection ML24068A2522024-03-0808 March 2024 License Amendment Request to Revise Technical Specifications 3.5.1 and 3.5.2 Using Risk-Informed Process for Evaluations ML24066A0472024-03-0606 March 2024 Response to Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown and TS IR 05000528/20240122024-03-0404 March 2024 Age-Related Degradation Inspection Report 05000528/2024012, 05000529/2024012 and 05000530/2024012 IR 05000528/20230062024-02-28028 February 2024 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2 and 3 Report 05000528/2023006 and 05000529/2023006 and 05000530/2023006 ML24053A3972024-02-22022 February 2024 License Renewal - Alloy 600 Management Program Plan ML24047A3632024-02-16016 February 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX177, AMZDFX178, AMZDFX179 Vertical Concrete Cask Identification No. AMZDNE179, AMZDNE178 2024-09-27
[Table view] |
Text
August 23, 2022
SUBJECT:
UPDATED INSPECTION PLAN FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 (REPORT 05000528/2022005 AND 05000529/2022005 AND 05000530/2022005)
Dear Mr. Heflin:
The enclosed inspection plan lists the inspections scheduled through June 30, 2024, for Palo Verde Nuclear Generating Station, Units 1, 2, and 3. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)1 and three Focused Engineering Inspections (FEIs) that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication and an engineering inspection that reviews age-related degradation and management2.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021 memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as 1 Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the CETI inspection. Attached Report 22 will reference DBAI procedure until the CETI procedure is made publicly available. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from attached Report 22.
2 The age-related degradation and management procedure is under development and will be publicly available by the end of calendar year 2022. we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.
For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The Regional Administrator has approved the staffs plan to conduct Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, at your facility, Unit 1, as indicated in the enclosed inspection plan.
The Regional Administrator has approved the staffs plan to conduct Inspection Procedure 92702 Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders, at your ISFSI facility (related to NRC Letter Confirmatory Order Modifying License, ADAMS Accession Number ML20323A035), as indicated in the enclosed inspection plan.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1574 with any questions you have regarding this letter.
Sincerely, Signed by Dixon, John on 08/23/22 John L. Dixon, Jr., Chief Projects Branch D Division of Operating Reactor Safety Docket Nos. 05000528, 05000529,05000530, 07200044 License Nos. NPF-41, NPF-51,NPF-74 Enclosure:
Inspection Plan Distribution:
cc w/ encl: Distribution via LISTSERV
ML22229A522 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: Yes No Publicly Available Sensitive NRC-002 OFFICE SPE:DORS/D BC:DORS/D NAME ASanchezJLD for JDixon DATE 8/23/2022 8/23/2022
Site Inspection Activity Plan 07200044 - Palo Verde (ISFSI)
07/01/2022 - 06/30/2024 Unit Start End Activity CAC Title Staff Count Palo Verde ISFSI Confirmatory Order Follow-up Inspection (Part 72) 2 10/1/2022 11/30/2022 IP 92702 CONF 001701 Enforcement Related Order Follow-Up-Only Prepared on 8/17/2022 12:43:50 PM 1 of 4
Site Inspection Activity Plan Palo Verde 07/01/2022 - 06/30/2024 Unit Start End Activity CAC Title Staff Count PV 2022 3Q Resident Baseline 5 1,2,3 7/1/2022 9/30/2022 IP 71151 000746 Performance Indicator Verification Security Access Control .02 1 1,2,3 7/25/2022 7/29/2022 IP 71130.02 000734 Access Control 1,2,3 7/25/2022 7/29/2022 IP 71130.09 001656 Security Plan Changes 1,2,3 7/25/2022 7/29/2022 IP 71151 001338 Performance Indicator Verification Target Set Inspection - PV 3 1,2,3 8/1/2022 9/16/2022 IP 71130.14 000743 Review of Power Reactor Target Sets Security Training/Equip Maint .07 and .04 2 1,2,3 9/12/2022 9/16/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2,3 9/12/2022 9/16/2022 IP 71130.07 000739 Security Training PV 2022 BRQ 3 1,2,3 9/25/2022 10/1/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance PV 2022 4Q Resident Baseline 5 1,2,3 10/1/2022 12/31/2022 IP 71151 000746 Performance Indicator Verification Palo Verde ISFSI Confirmatory Order Follow-up Inspection (Part 50) Feeder for Residents' report 2 1,2,3 10/1/2022 10/2/2022 IP 92702 001555 Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders 1,2,3 10/1/2022 10/2/2022 IP 92702 CONF 001701 Enforcement Related Order Follow-Up-Only Inservice Inspection 3RF23 - PV 1 3 10/10/2022 10/21/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
Design Bases Assurance Inspection (Team) - 21M - Palo Verde 6 1,2,3 11/28/2022 12/16/2022 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
Cyber Security Inspection - PV 4 1,2,3 12/5/2022 12/9/2022 IP 71130.10 000741 Cybersecurity EP 2023 Exercise Scenario In-Office Rvw 71114.08 - PV 4 1,2,3 1/1/2023 2/7/2023 IP 71114.08 000723 Exercise Evaluation - Scenario Review PV 2023 1Q Resident Baseline 5 1,2,3 1/1/2023 3/31/2023 IP 71151 000746 Performance Indicator Verification Security FFD .08 1 1,2,3 1/23/2023 1/27/2023 IP 71130.08 000740 Fitness For Duty Program Protective Strategy w/Annual FOF sample, IP .05 2 Prepared on 8/17/2022 12:43:50 PM 2 of 4
Site Inspection Activity Plan 1,2,3 1/30/2023 2/3/2023 IP 71130.05 000737 Protective Strategy Evaluation PV 2023 2Q Resident Baseline 5 1,2,3 2/1/2023 8/15/2023 IP 71151 000746 Performance Indicator Verification EP 2023 Biennial Exercise & PI Inspection 4 1,2,3 3/6/2023 3/10/2023 IP 71114.01 000716 Exercise Evaluation 1,2,3 3/6/2023 3/10/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2,3 3/6/2023 3/10/2023 IP 71151 001397 Performance Indicator Verification Inservice Inspection 2R24 1 2 4/17/2023 4/28/2023 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,4,PI - 2 1,2,3 4/17/2023 4/21/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2,3 4/17/2023 4/21/2023 IP 71124.04 000728 Occupational Dose Assessment 1,2,3 4/17/2023 4/21/2023 IP 71151 000746 Performance Indicator Verification PV 2023 INITIAL EXAM 6 1,2,3 3/26/2023 4/1/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1,2,3 4/30/2023 5/6/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
PV 2023 3Q Resident Baseline 5 1,2,3 7/1/2023 9/30/2023 IP 71151 000746 Performance Indicator Verification Palo Verde Biennial PI&R 4 1,2,3 6/26/2023 6/30/2023 IP 71152B 000747 Problem Identification and Resolution 1,2,3 7/10/2023 7/14/2023 IP 71152B 000747 Problem Identification and Resolution Commercial Grade Dedication Inspection - 21N - Palo Verde 3 1,2,3 9/11/2023 9/15/2023 IP 71111.21N.03 001808 Commercial Grade Dedication 1,2,3 9/25/2023 9/29/2023 IP 71111.21N.03 001808 Commercial Grade Dedication PV 2023 4Q Resident Baseline 5 1,2,3 10/1/2023 12/31/2023 IP 71151 000746 Performance Indicator Verification Inservice Inspection - PV (U1) 1 1 10/16/2023 10/27/2023 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
License Renewal Inspection (Phase 1) - PV U1 2 1 10/23/2023 10/27/2023 IP 71003 000687 Post-Approval Site Inspection for License Renewal Security Access Authorization .01 and Access Control .02 + PIV + Plan Change .09 2 1,2,3 10/30/2023 11/3/2023 IP 71130.01 000733 Access Authorization 1,2,3 10/30/2023 11/3/2023 IP 71130.02 000734 Access Control 1,2,3 10/30/2023 11/3/2023 IP 71130.09 001656 Security Plan Changes 1,2,3 10/30/2023 11/3/2023 IP 71151 001338 Performance Indicator Verification RP 5,8 - 2 Prepared on 8/17/2022 12:43:50 PM 3 of 4
Site Inspection Activity Plan 1,2,3 11/13/2023 11/17/2023 IP 71124.05 000729 Radiation Monitoring Instrumentation 1,2,3 11/13/2023 11/17/2023 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Age-Related Engineering Inspection - 21N - Palo Verde 3 1,2,3 1/29/2024 2/2/2024 IP 71111.21N.04 Age Related Focused Engineering Inspection 1,2,3 2/12/2024 2/16/2024 IP 71111.21N.04 Age Related Focused Engineering Inspection EP Program & PI Inspection (2024) - PV 1 1,2,3 3/18/2024 3/22/2024 IP 71114.02 000717 Alert and Notification System Testing 1,2,3 3/18/2024 3/22/2024 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2,3 3/18/2024 3/22/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2,3 3/18/2024 3/22/2024 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2,3 3/18/2024 3/22/2024 IP 71151 001397 Performance Indicator Verification PV 2024 INITIAL EXAM 6 1,2,3 3/24/2024 3/30/2024 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1,2,3 4/28/2024 5/4/2024 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
Inservice Inspection - PV (U3) 1 3 4/8/2024 4/19/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,3,PI 2 1,2,3 4/15/2024 4/19/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2,3 4/15/2024 4/19/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2,3 4/15/2024 4/19/2024 IP 71151 000746 Performance Indicator Verification Prepared on 8/17/2022 12:43:50 PM 4 of 4