IR 05000482/1998004

From kanterella
Jump to navigation Jump to search
Insp Rept 50-482/98-04 on 980125-0307.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support
ML20217H651
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/01/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20217H636 List:
References
50-482-98-04, 50-482-98-4, NUDOCS 9804060021
Download: ML20217H651 (19)


Text

. .

ENCLOSURE 2 U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.: 50-482 NPF-42 -

Report No.: 50-482/98-04 Licensee: Wolf Creek Nuclear Operating Corporation Facility: Wolf Creek Generating Station -

Location: 1550 Oxen Lane, NE Burlington, Kansas Dates: January 25 through March 7,1998 Inspectors: J. F. Ringwald, Senior Resident inspector B. A. Smalldridge, Resident inspector Approved By: W. D. Johnson, Chief, Project Branch B ATTACHMENT: SupplementalInformation

,

i

\

9804060021 980401

- PDR ADOCK 05000482 G pop

.

>

.

EXECUTIVE SUMMARY

~

Wolf Creek Generating Station NRC Inspection Report 50-482/98-04 Operations

- Operators did not recognize that, during surveillance testing, inserting shutdown control rods below the rod insertion limit required them to enter into Technical Specification Action Statement 3.1.3.5. The surveillance procedure also failed to prompt operators to recognize the applicability of the Technical Specification. The operations department had to overcome the mind set that the exception contained in the action statement precluded the need to comply with the limiting conditions for operation during the surveillance test (Section 04.1).

Appropriate questions in late 1997 resulted in the identification of an historical failure of

'

...

operations and engineering personnel to set refueling machine load settings as required by Technical Specifications between 1988 and 1994 due to an inappropriate procedure and a mind set that failed to question the setting methodology (Section 08.9).

. When appropriate questions in 1996 resulted in the identification of surveillance tests on the auxiliary feedwater pumps that were not being performed on a staggered test basis, the initial corrective action to identify additional examples was not effective. The licensee event report (LER) supplement reported a similar failure for the emergency diesel generators (Section 08.12).

Maintenance

. The material condition of those plant systems and components evaluated during this inspection period were good, with few equipment deficiencies. Effective coordination between operations, maintenance, engineering, and other groups resulted in the licensee achieving a condition where no annunciators were illuminated with very few instrument out-of-service tags on annunciators (Section M2.1).

Enaineerina a A 10 CFR 50.59 evaluation was not performed during preparations to filter the emergency diesel fuel oil storage tank contents without declaring the emergency diesel generators inoperable. While the plant manager and operations manager raised questions regarding the operability of the diesel generator during this planned work activity, personnel involved in the preparation of this work failed to recognize the need for the 10 CFR 50.59 evaluation until prompted by the inspector and the Chief Operating Officer (Section E1.1).

.. . ..The procurement of replacement seals for the control room door in accordance with Revision 1 of Specification 16577-A-075A, " Technical Specification for Bullet-Resisting

,

b c }' .

-2-

- Door for the Standardized Nuclear Power Plant System," and the failure to revise the Updated Safety Analysis Report coincident with the revision to this specification in.1991, was a violation of 10 CFR 50.71(e) (Section E8.3).

. Plant Sunoort

.: A quality controlinspector performed a boroscope examination of a containment spray pump room cooler within 18 inches of two posted hot spots without adequate cognizance

'

of the radiological conditions in the room and without dosimetry adequate to monitor the highest whole-body dose. The radiation protection program did not require, the quality control inspector did not request, and radiation protection personnel did not provide

- start-of-the-job coverage and, therefore, the quality contrcl inspector did not receive guidance on job specific ALARA (as low as reasonably achievable) practices or the intermittent job coverage required by the radiation work permit. (Section R1.1).

- Progressively more aggressive corrective actions to address 11 licensee-identified instances where radiation workers entered the radiologically controlled area without required dosimetry over an 8-month period have resulted in more than 4 months without recurrence (Section R8.1).

,

%

is

'

. - .i2..

, . . . .

.

. , . ., .. . . . . , i

'

!

.

.

i Report Details )

!

-i

Summarv of Plant Statta The plant operated at essentially 100 percent power throughout the inspection period.'

l. Operations

' 04 Operator Knowledge and Performance 04.1 Procedures and Documentation Insoection Scone (71707)

The inspector observed the conduct of Procedure STS SF-001, " Control and Shutdown

' Rod Operability Verification," . Revision 14, pursuant to surveillance testing required by Technical Specification 4.1.3. Observations and Findinos l

On February 18,1998, the inspector observed the conduct of Procedure STS SF-001,

" Control and Shutdown Rod Operability Verification," Revisior: 14. During the conduct of this test, shutdown control rods were inser1ed beyond the limits specified in the core operating limits report in accordance with the surveillance test procedure. The core i operating limits report limits shutdown rod insertion to no less than 222 step j On February 23,1998, the inspectors contacted operations management personnel and inquired whether the limiting conditions for operation requirements of Technical Specification 3.1.3.5 were met during the conduct of control and shutdown rod operability j'

testing. The operations department responded that the exception for surveillance testing pursuant to Technical Specification 4.1.3.1.2 contained in the action statement precluded I

the need to enter into the limiting conditions for operation; therefore, they did not consider entry into the Technical Specification Action Statement necessar . Technical Specification 3.1.3.5 states that "All shutdown rods shall be limited in physical insertion as specified in the core operating limits report" in Modes 1 and 2. The action statement associated with Technical Specification 3.1.3.5 limited the number of shutdown rods inserted beyond the insertion limit to a maximum of one rod, except for surveillance testing pursuant to Technical Specification 4.1.3.1.2. The action statement

' required that rods be restored to above the rod insertion limit within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. The inspectors noted that any time the limiting conditions for operation requirements were not

. met, the Technical Specification Action Statement applied. Therefore, the 1-hour limit for rods inserted below the limits of the core operating limits report remained in effect during surveillance testin ' The inspectors identified that the operations department had to overcome the mind set that the exception contained in the action statement precluded the need to comply with

. the limiting conditions for operation during the surveillance test. The surveillance e

,

.

l m-2- q i

I procedure failed to prompt operators to recognize the applicability of the Technical ' 1 Specification. The operations manager agreed that the applicable Technical

.

. Specification Action Statement should have been entered at the time the surveillance

. was conducted. Operations personnel initiated PlR 98-0486 to address this issu ' Procedure AP 21-001, " Operations Watch Standing Practices," Revision 8, required that all entries into short term limiting conditions for operation be logged in and out of the control room log. The operators' failure to log entry into Technical Specification 3.1.3.5 -

when shutdown rods were inserted beyond the rod insertion limits is a violation of Technical Specification 6.8.1.1.a. (50482/9804-01). Conclusion Operators did not recognize that, during surveillance testing, inserting shutdown control rods below the rod insertion limit required them to enter into Technical Specification-

- Action Statement 3.1.3.5. The surveillance procedure failed to prompt operators to recognize the applicability of the Technical Specification. The operations department had to overcome the mind set that the exception contained in the action statement precluded the need to comply with the limiting conditions for operation during the surveillance tes . Miscellaneous Operations issues (92901)

O8.1 ' lClosed) Violation 50-482/9708-01: Radwaste operators not following procedure. The inspector verified the corrective actions described in the licensee's response letter, dated i May 23,1997, to be reasonable and complete. No similar problems were identifie .2 (Closed) Violation 50-482/9709-01: Failure to identify and remove loose debris from the containment. The inspector verified the corrective actions described in the licensee's response letter, dated July 7,1997, to be reasonable and complete. No similar problems were identifie .3 (Closed) Violation 50-482/9709-03: Failure to properly document an operability determination for debris and other material in the containment. The inspectors reviewed the corrective actions described in the licensee's response letter, dated July 7,199 The licensee's response stated that Administrative Procedure AP 26C-004, " Technical Specification Operability," Revision 0, would be revised to provide improved guidance on when Form APF 26C-004-01, " Technical Specification Screening Checklist," should be use Procedure AP 260-004, Revision 1, stated that, if the shift supervisor cannot - '

" expediently" resolve an operability concern, then the checklist should be used. The inspectors did not identify a definitive statement in the procedure stating when the checklist was required. The inspectors questioned the licensee's definition of the term

" expediently." The licensee stated that the length of time to " expediently resolve an operability concern" was at the discretion of each of the shift supervisors. However, the

.x 1..1in ,

.

-3-

, licensee also stated that the time for a shift supervisor to resolve a concem without using a checklist should be less than an hour. The inspectors did not identify any additional concern .4 - (Closed)' Violation 50-482/9710-02:- Overtime controls. The inspector verified the corrective actions described in the licensee's response letter, dated August 8,1997, to be reasonable and complete. No similar problems were identified.

08.5 (Closed) Violation 50-482/9710-03 Failure to perform inspection of the containment
building prior to establishing containment integrity. The inspector verified the corrective

"

actions described in the licensee's response letter, dated August 8,1997, to be reasonable and complete. No similar problems were identife .6 - (Closed) Violation 50-482/9722-01: Midioop procedure not followed regarding the containment personnel access hatch. The inspector verified the corrective actions described in the licensee's response letter, dated January 30,1998, to be reasonable and complete. No similar problems were identifie .7 - (Closed) Violation 50-482/9722-02: Posttrip review package error. The inspector verified the corrective actions described in the licensee's response letter, dated January 30,1998, to be reasonable and complete. No similar problems were identifie .8 (Closed) Violation 50-482/9723-01: Operations proce' dure use with field operators. The inspector verified the corrective actions described in the licensee's response letter, dated February 27,1998, to be reasonable and complete. No similar problems were identife .9 (Closed) LER 50-482/94014-00: Refueling machine Technical Specification limiting conditions for operation requirements not met in past outages. This item involved the discovery that the under and overload setpoints for the refueling machine failed to meet Technical Specification 3/4.9.6 requirements during Refueling Outages 3, 6, and 7, between October 7,1988, and November 2,1994. The cause of this event was an inadequate procedure that required the overload setpoint to be 250 pounds above the weight of the heaviest fuel assembly, the automatic load reduction trip to be 250 pounds ;

less than the weight of the lightest fuel assembly, and a mind set that failed to question the procedural guidance. Wht.n the licensee modified the refueling machine in 1996, several refueling machine weight settings were then available so operators and engineers could select appropriate overload and automatic load reduction setpoints that met the Technical Specification requirements. While procedural guidance directed engineering and operations personnel to select the appropriate setting for the fuel assembly being moved, it relied on skill of the craft to ensure that operators selected the proper setting. The report stated that the licensee planned to further review and enhance this process, and the manager of nuclear engineering said that this review will also address this skill-of-the craft question. The failure of the licensee to ensure that the

_ ,

' refueling machine setpoints met Technical Specification requirements is a violation. This x .

.

' ' '

-4-nonrepetitive, licensee-identified and corrected violation is being treated as a noncited 2 violation, consistent with Section Vll.B.1 of the NRC Enforcement Policy (50-482/9804-02).

08.10 (Closedi LER 50-482/96001-01: Loss of circulating water due to icing on traveling -

screens. This report corrected information provided in the initial report regarding the cause of the circulating water system failure. The root cause was determined to be plugged air release valves in the circulating water system. The described corrective actions appear to be appropriate to address the plugged valves. Additional cor"ective actions were also described regarding the operators' failure to meet the Technical Specification Action Statement 3.7.1.2.b. requirements to achieve Mode 4 within G hours -

of reaching Mode 3. No other new information was provide .11. (Closed) LER 50-482/96004-01: Violation of Technical Specification 3.5.4 for power remaining available to Safety injection Pump A discharge valves in Mode 5. This supplement to the LER provided additional corrective actions not discussed in the

~ original LER. No other new information was provide .12 (Closed) LER 50-482/96009-00/01: Failure to perform Technical Specification surveillance requirements on a staggered test basis. On September 20,1996, LER 96-009-00 reported the licensee's failure to perform surveillance testing on the auxiliary feedwater pumps on a staggered test basis. Corrective actions included a comparison of the surveillance testing computer database with Technical Specification requirements which found no similar occurrences. On January 7,1997, the licensee issued Supplement 1 to report that a similar failure was identified associated with the emergency diesel generators. Since the corrective actions described in the initial report were demonstrated to have been inadequate as discussed in the supplement, the licensee's response to the initial violation did not meet the criterion described in the

' NRC's Enforcement Policy, Section Vll.B.1, for enforcement discretion. The failure of the licensee to perform these surveillance tests on a staggered test basis is a violation of Technical Specifications 4.7.1.2.1.a and 4.8.1.1.2 (50-482/9804-03). Since the corrective actions described in the supplement ultimately appeared to be adequate, no response to this violation is require .13 Conclusions Appropriate questions in late 1997 resulted in the identification of an historical failure of I

operations and engineering personnel to set refueling machine load settings as required by Technical Specifications between 1988 and 1994 due to an inappropriate procedure and a mind set that failed to question the setting methodolog : When appropriate questions in 1996 resulted in the identification of surveillance tests on

the auxiliary feedwater pumps that were not being performed on a staggered test basi the initial corrective action to identify additional examples was not effective. The LER supplement reported a similar failure for the emergency diesel generator r

'

~

,.

,

-5-II. Maintenance M1 Coi. 9ct of Maintenance

'

M1.1 General Comments on Maintenance Activities Insoection Scooe (62707)

The inspectors observed all or portions of the following work activitie Task 1 As-Found Valve Operation Test and Evaluation System test on Valve BN HV8806A 126429 Tasks 1 Remove cover and inspect containment sump and 11 126921 Task 2 Clean and inspect Containment Spray Pump A room cooler 127623 Task 0 Test failure troubleshooting Observation and Findinas Except as noted in Sections R1.1 and M2.1, the inspectors found no concerns with the maintenance observed, Conclusions Except as noted in Sections R1.1 and M2.1, the inspectors concluded that the maintenance activities were being performed as required.

M1.2 General Comments on Surveillance Activities Insoection Scooe (61726)

The inspectors observed all or portions of the following surveillance activitie STS AL-103, Revision 31 Turbine-driven auxiliary feedwater pump inservice pump test STS EN-100A, Revision 11 Containment Spray Pump A inservice pump test STS KA-010 Revision 10 Nitrogen accumulator inservice check valve test STS SF-001, Revision 14 Control and shutdown rod operability verification

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

. b. - Observations and Findinas Except.as noted in Sections 04.1 and M2.1, the inspectors found no concerns with the surveillances observe Conclusions Except as noted in Sections O4.1 and M2.1, the inspectors concluded that the surveillance activities were being performed as require M2 Maintenance and Material Condition of Facilities and Equipment

' M2.1 Review of Material Condition Durina Plant Tours Insoection Scoos (61726)

- During this inspection period, routine plant tours were conducted to evaluate plant material conditio ~ Observations and Findinas -

In general, where equipment deficiencies existed, the deficiencies had been identifaxf for corrective actio . During an at-power containment entry on January 28,1998, the inspector noted that the containment sump area was free of debris. Additionally, an inspection of containment, including the adherent condition of paint and sealants on containment walls and components, revealed no notable debris with the potential to collect in the containment sum . During the inspection period, the licensee achieved a condition where no control board annunciators were illuminated. In this condition, four annunciators had instrument out of-service tags indicating that these annunciators had some problem associated with them. Two of the four were removed from service by procedure in that these annunciators were only meaningful when the plant operated in a_ shutdown condition. One annunciator was disabled because the equipment was no longer used and a design change was pending to remove the annunciator frr.,m service. The remaining instrument out-of-service tag represented an annunciator which continued to have an active material condition concer . . On February 2,1998, during surveillance testing'of the turbine-driven auxiliary L feedwater pump, ths inspector observed that the auxiliary feedwater turbine -

casing continued to exhibit some leakage during operation. Subsequent Linspection activities determined that this leakage did not adversely affect the

,

turbine operability nor the moisture content of the turbine oil.

,

, , , , , . . . , , . . . . , , _ . . . . , , . .

_ , _ _ _ _ , . _ _ , _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ . _ _ _ _ _ _ _ _ , _ _ _

,

.

-7-

= On January 30,1998, system engineering personnel identified that the grab sample capability that they relied on to measure the postaccident reactor coolant system dissolved hydrogen concentration could not be performed within 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> because the analysis would have to be performed offsite. The inline analyzer failed in 1992, and the licensee has relied on a grab sample to meet the Updated Safety Analysis Report (USAR) requirements since that time. After identifying this issue, the licensee initiated Performance improvement Request 98-0276 and preliminarily determined that this did not constitute an immediate safety concern because the reactor vessel head vents and reactor vessel level indicating

' systems are operational to mitigate the consequences of postaccident hydrogen production on reactor vessel flow. This issue will be unresolved pending the completion of the licensee's evaluation and additionalinspection to more fully understand associated issues (50-482/9804-04).

- On February 18,1998, the inspector noted that the body of Valve GS HV0037, containment atmosphere radiation monitor outside containment isolation, was not insulated and the insulation for the valve body appeared to be on the floor a few feat from the valve. No tags hung from the valve to identify an open work package to reinstall the insulation. A search of the work control database revealed no open work documents tracking the reinstallation of this insulation. A valve label inappropriately described the valve as an inside containment valv The licensee initiated Performance improvement Request 98-0440, Action Request 27537, to reinstall the insulation and an engraving request to correct the labeling erro Conclusion The material condition of those plant systems and components evaluated during this inspection period were good, with few equipment deficiencies. Effective coordination between operations, maintenance, engineering, and other groups resulted in the licensee achieving a condition where no annunciators were illuminated, with very few instrument out-of-service tags on annunciator M8 Miscellaneous Maintenance issues (92902)

M8.1 (Closed) Violation 50-482/9708-02: Failure to update risk assessment. The inspector verified the corrective actions described in the licensee's response letter, dated May 23, 1997, to be reasonable and complete. No similar problems were identifie l M8.2. (Closed) Violation 50-482/9708-03: Failure to perform surveillance testing with essential service water inoperable. The inspector verified the corrective actions described in the

. licensee's response letter, dated May 23,1997, to be reasonable and complete. No similar problems were identifie M8.3 (Closed) Violation 50-482/9723-02: Gurveillance test procedure not followed. The i

'5 .

, ,, ,

?

-8-inspector verified the corrective actions described in the licensee's response letter, dated February 27,1998, to be reasonable and complete. No similar problems were identifie . Engineering

, ,

E1 Conduct of Engineering E1.1 ' Failure to Consider 10 CFR 50.59 in Work Plannina Insoection Scooe (35571)

~

The inspector reviewed the licensee's plan to filter an emergency diesel generator fuel oil tank without declaring the diesel generator inoperabl b; Observations and Findinas On ' January 27,1998, during the 8:30 a.m. management meeting, the inspector noted that the licensee planned to filter the emergency diesel generator Fuel Oil Storage Tank B without declaring Emergency Diesel Generator B inoperable. The plant manager and operations manager questioned whether all appropriate considerations had been made to ensure that the operability determination was appropriate. At approximately c 10:30 a.m., the operations superintendent informed the inspector that, while all the appropriate questions had been asked and answered to support the operability decision, the information had not been documented. In response to the questions from the plant manager and operations manager, licensee staff personnel planned to document the basis for considering the diesel generators operable during this filtration evolution in the work package. The inspector asked to see this documentation when it was complete 1 and also asked to see the 10 CFR 50.59 screening / evaluation in support of the evolutio The inspector subsequently leamed that no plans had been made to perform a 10 CFR 50.59 screening or evaluation. The Chief Operating Officer also asked engineering personnel whether a temporary modification would be used for this evolution about the same time that the inspector asked to see the 10 CFR 50.59 evaluation. After attempting to complete a 10 CFR 50.59 screening, the licensee decided to declare the emergency _ diesel generators inoperable during the filtration evolution. The inspector subsequently determined that, while the work planning process required appropriate considerations for evaluating operability, it did not specifically require consideration for the applicability of 10 CFR 50.59. The licensee noted that most maintenance activities which would require a 10 CFR 50.59 evaluation would be associated with a process which would trigger the need for a 10 CFR 50.59 evaluation, including modifications, temporary modifications, procedures, etc. Since this activity did not have an associated

activity which triggered the 10 CFR 50.59 evaluation, engineering personnel did not consider the need for the evaluation until prompted by the inspector and Chief Operating Office ~ Conclusions

'

. - - -

._ .____U

, <

.

-9-A 10 CFR 50.59 evaluation was not performed during preparations to filter the emergency diesel fuel oil storage tank contents without declaring the emergency diesel generators inoperable.;While the plant manager and operations manager raised questions regarding the operability of the diesel generator during this planned work

activity, personnel involved in the preparation of this work also failed to recognize the need for the 10 CFR 50.59 evaluation until prompted by the ins'pector and the Chief

' Operating Office L E8 Miscellaneous Engineering issues (92903)

E (Closed) Violation 50-482/9708-05 USAR discrepancies. The inspector verified the corrective actions describad in the licensee's response letter, dated May 23,1997, to be reasonable and complete. No similar problems were identifie E8.2 (Closed) Violation 50-482/9709-06: Procedure allowed normal charging pump operation at 325'F. The inspector verified the corrective actions described in the licensee' response letter, dated July 7,1997, to be reasonable and complete. No similar problems were identifie E (Closed) Unresolved item 50-482/9714-02: Control room door leaktightness. This item involved the discovery that the engineering specification used to procure the control room door did not require the same leaktightness as described in the USAR descriptio During the subsequent inspection, engineering personnel explained that, while the current revision of Specification 16577-A-075A, " Technical Specification for Bullet-Resisting Door for the Standardized Nuclear Unit Power Plant System,"

Revision 1, did not correspond to the USAR, the original revision did require the same leaktightness as described in the USAR. The procurement documentation available at the end of the inspection period did not clearly demonstrate that the door actually met this specification. In addition, engineering personnel stated that they planned to prepare a revision to the USAR that would delete the leakage criteria because they believed that the differential pressure requirement bounded the leakage criteria. Procurement of replacement seals for this door in accordance with Revision 1 of Specification 16577-A-075A and the failure to update the USAR coincident with the

)j revision to this specification in 1991 are a violation of 10 CFR 50.71(e). This

{

NRC-identified violation is not being cited because the NRC is exercising discretion in '

accordance with Section Vll.B.3 of the Enforcement Policy (50-482/9804-05). This violation would likely have been identified by the licensee in its comprehensive program to review and update the USAR as described in Letter ET97-0010 of February 7,199 The proposed USAR change and procurement documentation issues will be reviewed during a future inspection and will be tracked as an inspection followup item (50-482/9804-06).

..

Y

..-

,;

.

-10- ,

IV. Plant Support R1 Radiological Protection and Chemistry Controls R Radiation Protection Work Plannina a, 'Insoection Scone (71750)

The inspector reviewed the radiation protection personnel involvement associated with work on the Containment Spray Pump A room cooler which occurred on February 18, 199 Observations and Findings A quality control inspector performed a boroscope examination of a sample of the cooler tubes following cleaning. The inspector noted that the quality controlinspector sat near two posted hot spots on the containment spray piping adjacent to the cooler.' One hot spot was posted at 100 millirem per hour on contact and 15 millirem per hour at a distance of 12 inches. The other hot spot was posted at 140 millirem per hour on contact and 15 millirem per hour at a distance of 12 inches. The quality control inspector's head -

was approximately 12-18 inches from the hot spots during the work. When the quality control inspector engaged in activities that did not directly involve the examination of the

' tubes, such as cleaning the boroscope probe, the quality control inspector remained near the hot spot rather than moving to a lower dose area. When the inspector asked the quality control inspector what guidance had been provided regarding the performance of this work with regard to keeping the radiation exposure ALARA, the quality control inspector said that no job specific guidance had been provide The inspector asked radiation protection personnel for the ALARA review documentation associated with this work. The' manager of chemistry and radiation protection responded that since the total expected dose for this job was less than 1 person-rem, the radiation protection program required no job-specific ALARA plannin #

.When the mechanics began work, the lead radiation protection technician provided start-of-job coverage. The work was performed under Radiation Work Permit 98009, Revision 0, which required intermittent health physics coverage. Since the quality control inspector did not discuss the work with the lead radiation protection technician, no health

physics coverage was provided during the 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> the before the inspector. questioned the quality controlinspector's radiation work practices and guidanc '

After the inspector raised these questions, radiation protection personnel interviewed the mechanics and the quality control inspector. They found that while the mechanics were

very knowledgeable of the radiological conditions in the containment spray pump room,

. the quality control inspector was not. Since this did not meet the radiation protection standard for radiation worker knowledge, radiation protection personnel suspended the 4 : quality control inspector's access to the radiological control area pending the completion

,

b !

_ __-

,

-11-of corrective actions.~ Radiation protection personnel also initiated Performance improvement Requests 98-0446, -0447, and -045 Radiation protection personnel also determined that, while the mechanics did stop at access control'and discuss the planned work with the lead radiation protection technician, the quality control inspector did not. ~ Radiation Work Permit 980009 did not require a pre-job briefing, although a discussion with the lead radiation protection technician would have been an appropriate and prudent measur The inspector asked if the quality control inspector's dosimetry, located near the quality control inspector's chest, appropriately' monitored the whole-body dose. Radiation -

protection personnel evaluated this and determined that the. dosimetry did not measure the highest whole-body dose. A survey performed on February 20,1998, immediately

'

following the inspector's questions, revealed that while dosimetry at the chest would have recorded 1.2 millirem, the quality control inspector's back and neck would have received from 3 to 8 millirem as a result of the hot spot Administrative Procedure AP 258-100, Radiation Worker Guidelines, Revision 5, required radiation workers to comply with radiation work permit requirements. Radiation Work Permit 98009, Revision 0, required the worker to avoid all posted hot spot locations, and required intermittent health physics coverage. The failure of the worker to avoid the posted hot spot location, and the failure of radiation protection personnel and the worker to ensure that the work received intermittent health physics coverage, is a violation of Technical Specification 6.11 (50-482/9804-07). Conclusions A quality control inspector performed a boroscope examination of a containment spray pump room cooler within 18 inches of two posted hot spots without adequate cognizance of the radiological conditions in the room and without dosimetry adequate to monitor the highest whole-body dose. The radiation protection program did not require, the quality control inspector did not request, and radiation protection personnel did not provide start-of-the-job coverage and, therefore, the quality control inspector did not receive guidanco on job specific ALARA practices or the intermittent job coverage required by the radiation work permit.

,

R4 - Staff Knowledge and Performance in Radiological Protection and Chemistry

R4.1L Knowledge and Performance a.' insoection Scooe (71750)

!'

1The inspectors observed health physics technician performance during a containment entr ~ ' Observations and Findinas j

m

,K

-

!-

-

i t, [

,

,

-12-On January 28,1998, the inspector noted that the health physics technician supplied by the fix-it-now team maintained positive control over each member of his assigned work ~ l group during a containment entry at-power. The technician continually monitored the radiation survey instrument, looking for possible locations of gamma streaming and general area radiation levels. The technician ensured that those individuals not directly -

involved with a specific task at any point during the evolution positioned themselves in the area of lowest background radiation within eyesigh q c. - ' Conclusion The health physics technician supplied by the fix-it-now team demonstrated strong'

. ownership and skilled use of radiation protection principles to ensure doses to the work group were ALARA during containment entry at powe !

R8 Miscellaneous Radiological Protection and Chemistry issues (92904)  ;

(Closed) Violations 50-482/9710-06. /9711-06. /9714-05. and /9719-05: Radiation l

- R l worker in the radiologically controlled area without required dosimetry. The inspector verified the corrective actions described in the licensee's response letters, dated

]j

- August 8, September 19, October 31, and December 23,1997, to be reasonable and complete. The initial corrective actions which included additional communication of expectations, personnel accountability, and radiation protection technicians' monitoring and challenging of radiation workers were initially ineffective. However, subsequent actions which included "just-in-time training" on radiation worker expectations for all

'

outage workers just prior to the outage, establishing a "no-talk zone" in the vicinity of access control except for radiation protection discussions with the lead radiation protection technician, standards for radiation protection personnel to quiz radiation workers on radiation protection fundamentals, and mandatory meetings between the new radiation protection manager and individuals barred from the radiologically controlled area prior to their reentry have resulted in more than 4 months without recurrence. No similar problems were identifie R8.2 Conclusions Progressively more aggressive corrective actions to address 11 licensee identified instances in which radiation workers entered the radiologically controlled area without required dosimetry over an 8-month period have resulted in more than 4 months without recurrenc P8 ~ Miscellaneous Emergency Planning issues (29204)

P8,1 l (Closed) Violation 50-482/9711-07: Emergency preparedness sirens inoperable. The 7 _ inspector verified the corrective actions described in the licensee's response letter, dated September 19,1997, to be reasonable and complete. No similar problems were identifie , ,

.

. -8

,

.

-13 .

S8 Miscellaneous Security and Safeguards issues S ,,osed) Violation 50-482/9709-07: Vital area escort ratio. The inspector verified the corrective actions described in the licensee's response letter, dated July 7,1997, to be reasonable and complete. No similar problems were identifie V. Management Meetings X1 Exit Meeting Summary The inspectors presented the inspection results to members of licensee management at the conclusion of the inspection on March 10,1998. The licensee acknowledged the findings presente The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

t I

.

A

,

ATTACHMENT PARTIAL LIST OF PERSONS CONTACTED Licensee

. M. J. Angus, Manager, Licensing and Corrective Action G. D. Boyer, Chief Administrative Officer J. W. Johnson, Manager, Resource Protection O. L. Maynard, President and Chief Executive Officer B. T. McKinney, Plant Manager R. Muench, Vice President Engineering W. B. Norton, Manager, Performance improvement and Assessment C. C. Warren, Chief Operating Officer INSPECTION PROCEDURES USED IP 37551 Onsite Engineering IP 61726 Surveillance Observations IP 62707 Maintenance Observations IP 71707 Plant Operations IP 71750 Plant Support Activities l IP 92901 Followup - Operations IP 92902 Followup - Maintenance IP 92903 Followup - Engineering IP 92904 Followup - Plant Support ITEMS OPENED. CLOSED. AND DISCUSSED ORftDftd 50-482/9804-01 VIO Procedure and documentation (Section 04.1).

50-482/9804-02 NCV Refueling machine Technical Specifications limiting conditions for operation requirements not met in past outages (Section 08.9)

-50-482/9804-03 VIO Failure to perform Technical Specifications surveillance requirements on a staggered test basis (Section 08.12)

F i

'

..

-2-l 50-482/9804-04 ' URI Review of material condition during plant tours (Section M2.1)

!

50-482/9804 05 NCV Control room door leaktightness (Section E8.3)

50-482/9804-06 IFl Control room door leaktightness (Section E8.3)

50-482/9804-07 VIO Radiation work permit noncompliance (Section R1.1)

Closed 50-482/94014-00 LER Refueling machine Technical Specification limiting conditions for operation requirements not met in past outages (Section 08.9)

50-482/96001-01 LER Loss of circulating water due to icing on traveling screens (Section 08.10)

50-482/96004-01 LER Violation of Technical Specification 3.5.4 for power remaining available to safety injection Pump A discharge '

valves in Mode 5 (Section 08.11)

50-482/96009-00/01 LER Failure to perform Technical Specification surveillance requirements on a staggered test basis (Section 08.12)

50-482/9708-01 VIO Radwaste operators not following procedure (Section 08.1)

50-482/9708-02 VIO Failure to update risk assessment (Section M8.1)

50-482/9708-03 VIO Failure to perform STS with essential service water inoperable (Section M8.2)

50-482/9708-05 VIO Updated Safety Analysis Report discrepancies j (Section E8.1)

50-482/9709-01 VIO Failure to identify and remove loose debris from the j

'

containment (Section 08.2)

50-482/9709-03 VIO Failure to properly document an operability determination for debris and other materialin the containment (Section 08.3)

50-482/9709-06 VIO Procedure allowed normal charging pump operations at

' 325'F (Section E8.2)

50-482/9709-07- VIO Vital area escort ratio (Section S8.1)

50-482/9710-02 VIO Overtime controls (Section 08.4)

I I

l

,

.

-3-50-482/9710-03 VIO Failure to perform inspection of the containment building prior to establishing containment integrity (Section 08.5)

50-482/9710-06 VIO Radiation worker in the radiologically controlled area without required dosimetry (Section R8.1)

50-482/9711-06 VIO Radiation worker in the radiologically controlled area without required dosimetry (Section R8.1)

50-482/9711-07 VIO Emergency Preparedness sirens inoperable (Section P8.1)

50-482/9714-02 URI Control room door leaktightness (Section E8.3)

50-482/9714-05 VIO Radiation worker in the radiologically controlled area without required dosimetry (Section R8.1)

50-482/9719-05 VIO Radiation worker in the radiologically controlled area without required dosimetry (Section R8.1)

50-482/9722-01 VIO Midloop procedure not followed regarding the containment personnel access hatch (Section 08.6)

50-482/9722-02 VIO Posttrip review package error (Section 08.7)

50-482/9723-01 VIO Operations procedure use with field operators (Section 08.8)

50-482/9723-02 VIO Surveillance test procedure not followed (Section M8.3)

50-482/9804-02 NCV Refueling machine Technical Specifications limiting conditions for operation requirements not met in past outages (Section 08.9)

50-482/9804-05 NCV Control room door leaktightness (Section E8.3)

,

J