IR 05000482/1999011

From kanterella
Jump to navigation Jump to search
Insp Rept 50-482/99-11 on 990712-16.No Violations Noted. Major Areas Inspected:Review of Radiological Environ Monitoring Program,Meterological Monitoring Prgram & Results of Licensee Investigation of 990525 Personnel Event
ML20210U112
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 08/13/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20210U103 List:
References
50-482-99-11, NUDOCS 9908200008
Download: ML20210U112 (12)


Text

. i

,

.

ENCLOSURE U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.: 50-482 License No.: NPF-42 Report No.: 50-482/99-11 t

Licensee: Wolf Creek Nuclear Operating Corporation Facility: Wolf Creek Generating Station Location: .1550 Oxen Lane, NE Burlington, Kansas Dates: July 12-16,1999 Inspector: Larry Ricketson, P.E., Senior Radiation Specialist Plant Support Branch Approved By: Gail M. Good, Chief Plant Support Branch Division of Reactor Safety Attachment: Supplemental Information l

9908200000 990g13

{DR ADOCK 05000482 PDR

.

i I EXECUTIVE SUMMARY Wolf Creek Generating Station NRC Inspection Report No. 50-482/99-11 The inspection reviewed the radiological environmental monitoring program, the meteorological monitoring program, and the results of the licensee's investigation of the May 25,1999, personnel contamination even Maintenance

With the exception of the temperature channels, the meteorologicalinstrumentation was correctly calibrated and maintained (Section M1.1).

The failure to restore temperature measuring instrumentation to operable status within seven days was a violation of Technical Specification 6.8.1. This Severity Level IV >

violation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance improvement Request 99-2474 (Section M1.1). l

The performance improvement request process was implemented poorly with respect to a meteorologicalinstrumentation problem. (Section M7).

{

Plant Support

The licensee's radiological environmental monitoring program was correctly implemented. The radiological environmental monitoring program results were properly documented in an annual report (Section R1.1). i

!

Based on incorrect internal dose calculations, the licensee reported a suspected overexposure to the NRC. During the subsequent review of the event, the licensee determined no regulatory dose limit had been exceeded. However, the licensee identified weaknesses in radiological surveys, radiation worker practices, work planning, communications, radiation work permits, and procedural guidance for dose calculations (Section R1.1).

  • The licensee identified a violation involving a failure to make surveys in accordance with 10 CFR 20.1501(a). Radiation protection personnel failed to evaluate airborne radioactivity concentrations in a work area. This Severity Level IV violation is being treated as a Nor-Cited Violation, consistent with Appendix C of the NRC Enforcement i Policy. This violation is in the licensee's corrective action program as Performance improvement Request 99-2319 (Section R1.2).
  • The licensee identified two examples of a violation involving a worker that failed to follow radiation protection procedural guidance in accordance with Technical Specification 6.8.1. A radiation worker failed to follow radiation work permit protective clothing requirements and failed to frisk properly for radioactive contamination after leaving a high contamination area. This Severity Level IV violation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This .

-3-violation is in the licensee's corrective action program as Performance Improvement Requests 99-2319 and 99-2437 (Section R1.2),

t

!

I i

l l

L

f )

.

-4-Report Details ll. Maintenance M1 Conduct of Maintenance M1.1 Meteoroloaical Monitorina Instruments Insoection Scoce (84750)

The inspector met with the cognizant system engineer and instruments and controls technician and discussed meteorological instrument operability and meteorological data recover Observations and Findinas Technical Specification 6.8.1 requires that written procedures be established, implemented, and maintained covering the activities recommended in Appendix A, of Regulatory Guide 1.33, Revision 2, February 1978. Section 7.h of Appendix A includes procedures for meteorological monitoring. Procedure 26A-002, " implementation and Revision of Technical Specification Bases, Technical Requirements Manual and Pressure and Temperature Limits Report," Revision 1, Section 6.1.2, states, "The contents of the Technical Requirements Manual are requirements on Wolf Creek Generating Station and its operation and shall be implemented as prescribed in the Technical Requirements Manual." Technical Requirements Manual Section 16.3. (3.3.3.4) states that the meteorological monitoring instrumentation channels in Table 16.3-3 shall be operable at all times. Table 16.3-3 includes a channel that provides the air temperature difference between the 10-meter and 60-meter elevations of the meteorological monitoring tower. The limiting condition for operations requires that, with one or more required meteorological monitoring channels inoperable, the licensee restore the instrument (s) to operable status within seven days. The operability of the meteorological instrumentation ensures that sufficient meteorological data is available for estimating potential radiation doses to the public, as a result of routine or accidental release of radioactive materials to the atmospher Through personnel interviews and performance improvement request reviews, the inspector determined that the temperature monitoring circuitry was out of service from April 19 to June 24,1999. The failure to restore temperature measuring instrumentation to operable status within seven days was a violation of Technical Specification 6. .

l This Severity Level IV violation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance Improvement Request 99-2474 (50-482/9911-01).

The latest annual effluent report stated that 1998 data recovery was 88.7 percent. The licensee's goal for data recovery was 90 percent. Licensee representatives explained that the 1998 data recovery result was below 90 percent because the result was calculated on the availability of data produced by all meteorological instruments, not just

F, i

.

5-the Technical Requirements Manual instrumentation. However, licensee representatives acknowledged that, because of the problems with the temperature circuitry, data recovery in 1999 will not reach 90 percent. Because 90 percent data recovery was only a goal, no regulatory issues were identified related to meteorological data recover Calibration records confirmed that the licensee calibrated meteorological instrument channels listed in the Technical Requirements Manual, Table 16.3-4, semiannually as required. Acceptance criteria were equal to or were more stringent than recommended in Regulatory Guide 1.2 c. Conclusions With the exception of the temperature channels, the meteorologicalinstrumentation was i

'

correctly calibrated and maintaine The failure to restore temperature measuring instrumentation to operable status within seven days was a violation of Technical Specification 6.8.1. This Severity Level IV violation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance Improvement Request 99-247 M7 Quality Assurance in Maintenance Activities a. Insoection Scope (84750)

The inspector reviewed performance improvement requests involving meteorological instrumentatio b. Observations and Findinos Through interviews with licensing representatives, the inspector determined that the meteorological instrumentation was not included in the licensee's 10 CFR Part 50, Appendix B, corrective action program. Nevertheless, Performance Improvement Request 99-1562 was initiated to address the inability to restore all meteorological instruments to operable status in seven days. The inspector noted that the performance improvement request was vaguely worded. It stated, "This work order has not been completed in the required time limit because of weather conditions."

The inspector noted that the initiator of Performance improvement Request 99-1562 did l not meet the expectations of Procedure AP 28A-001," Performance Improvement l Request," Revision 14, Section 6.1.4, because the initiator did not provide the

" consequences or potential consequences" associated with the identified issue. For ;

'

example, the initiator did not provide a regulatory context for the issue by indicating that operable instrumentation was required by Technical Requirement Manual Section 16.3.1.3. According to the procedural expectations, if the initiator did not have this information, the initiator should have discussed the issue with a knowledgeable l individual. Performance improvement Request 99-1562 was closed on May 12,1999,

.

.

6-before the meteorologicalinstruments were repaired on June 24,1999. The performance improvement request was closed, in part, because its significance was not apparent, according to the supervisor who closed i Because the performance improvement request was closed before the condition was corrected, the inspector concluded that the performance improvement process was ineffective, in this example. Because the licensee's meteorological instrumentation is not addressed by the licensee's 10 CFR Part 50, Appendix B, corrective action program, this example is not a regulatory issue. However, the ineffective implementation of the performance improvement request process was a contributing cause of the violation involving meteorologicalinstrumentatio . Conclusions The performance improvement request process was implemented poorly with respect to a meteorological instrumentation proble IV. Plant SuDDort R1 Radiological Protection and Chemistry Controls R1.1 Radiolooical Environmental Monitorino Proaram Insoection Scope (84750)

The inspector compared the licensee's Offsite Dose Calculation Manual with the Radiological Assessment Branch Technical Position on Environmental Monitoring, Revision 1, November 1979, and reviewed the following items:

I

  • Environmental sampling log

1998 Annual Radiological Environmental Operating Report ,

Environmental airborne radioactivity sample collection

Sample station maintenance and equipment operability

Sample preparation for shipment

  • Interlaboratory comparison results Observations and Findinas The licensee's Radiological Environmental Monitoring Program was implemented through Procedure AP 078-004,"Offsite Dose Calculation Manual (Radiological Environmental Monitoring Program)," Revision O. The program agreed closely with the example of an acceptable program outlined in the branch technical position. Licensee representatives discussed the bases for minor differences. The inspector concluded that the difference was based on practical considerations and did not negatively impact the effectiveness of the program. The 1998 Offsite Dose Calculation Manual changes were identified as required by Technical Specification 6.14. The inspector discussed the bases for the changes with licensee representatives and identified no problem !

!

l

q

.

7-The inspector reviewed the licensee's environmental sampling log and confirmed that sample collection was conducted in accordance with the program requirements listed in Table 5.1 of Procedure AP 078-00 The inspector observed the collection and preparation for shipment of airborne particulate and radiciodine samples. The environmental monitoring technician followed the guidance of Procedure Al 078-014," Collection, Preparation, and Shipment of Airborne Particulate and Radioiodine Samples," Revision 1. Sampling stations were maintained, and the sampling equipment was operable and within the calibration interval established by Procedure Al 078-016, " Radiological Environmental Monitoring Equipment Control and Calibration," Revision 2. The licensee had a sufficient supply of replacement air sampling equipmen The licensee sent environmental samples to a vendor laboratory for analysis. The vendor laboratory participated in an interlaboratory comparison program. The Radiological environmental monitoring program results and the interlaboratory comparison results were reported in the Annual Radiological Environmental Operating Report, as required. Thermoluminescent dosimeters were processed by another nuclear power facility. The licensee maintained documentation verifying that the other nuclear power facility's dosimetry program was accredited by the National Voluntary Laboratory Accreditation Program and that the other facility participated in an interlaboratory comparison progra The inspector reviewed the 1998 Annual Radiological Environmental Operating Report and confirmed sampling results did not exceed reporting levels. The radiological environmental monitoring results supported the radiological effluent release program result Conclusions The licensee's Radiological environmental monitoring program was correctly implemented. An acceptable program was estabiished. Changes to the program did not reduce its effectiveness. Sample collection was conducted according to the established program. Sample analyses and environmental dosimetry processing were performed by acceptably qualified laboratories. The radiological environmental monitoring program results were properly documented in an annual repor R1.2 Radiation Protection Insoection Scope (92904)

On June 25,1999, the licensee notified the NRC of an event that resulted in a calculated internal dose of 14.5 rems. The event involved the intake of radioactive material by a decontamination worker in a highly contaminated area. The licensee established an incident investigation team to investigate the event and identify the cause. On June 26,1999, the licensee identified that the initial dose calculations were incorrect and revised its dose estimate to less than 5 millirems. The inspector reviewed the draft findings of the incident investigation tea > .

'

8- Observations and Findinas The incident investigation team reviewed the event and identified violations and program weaknesses in several areas. The areas included: radiological surveys, radiation worker practices, work planning, communications, radiation work permits, and procedural guidance. No weaknesses were identified in general employee training or health physics trainin Radioloaical Survevs No air samples were taken during the decontamination activities. No real time airborne radioactivity monitors were used, either. Therefore, the ongoing radiological hazards associated with airborne radioactivity could not be evaluated. There was no record of an evaluation pedormed before the work starte CFR 20.1501(a) requires each licensee to make or cause to be made, surveys that may be necessary for the licensee to comply with the regulat.ons in 10 CFR Part 20 and are reasonable under the circumstances to evaluate the extent of radiation levels, concentration or quantities of radioactive material, and the potential radiological hazards that could be present.10 CFR 20.1003 defines a survey as a means of evaluation of the radiological conditions and potential hazards incident to the production, use, transfer, release, disposal, or presence of radioactive material or other sources of radiatio The failure to make surveys that may have been necessary to ensure that the licensee complied with regulations such as 10 CFR 20.1201, " Occupational Dose Limits for

. Adults,"is a violation of 10 CFR 20.1501(a). This Severity Level IV violation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance improvement Request 99-2319 (50-482/9911-02).

Radiation Worker Practices Radiation Work Permit 990002 was the governing radiation work permit during decontamination activities. This radiation work permit required a cloth hood and face shield to be donned before performing work activities in a highly contaminated are The decontamination worker donned only a skull cap with no cloth hood. Also, the worker failed to don a face shield while working in a highly contaminated are Technical Specification 6.8.1 requires, in part, that written procedures be written, implemented, and maintained covering the applicable procedures in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Section 7.e of Appendix A lists radiation protection procedures for access control and radiation work permit Procedure AP 25B-100," Radiation Worker Guidelines," Revision 9, stated that individuals shall comply with radiation work permit requirement The failure of the worker to comply with the radiation work permit requirements is a violation of Procedure AP 25B-100 and Technical Specification 6.8.1. This Severity Level IV violation is being treated as a Non-Cited Violation, consistent with Appendix C l

l

!

r

.

.

I

!

.9 of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance imp:ovement Request 99-2319 (50-482/9911-03).

Procedure AP 25B-100, " Radiation Worker Guidelines," also stated in Step 6.6.6:

"Upon exiting a highly contaminated area or a potential hot particle area, an individual is required to perform a whole-body frisk at the nearest frisking station." The decontamination worker frisked only the hands and feet. The failure of the radiation worker to perform a whole-body frisk is a second example of a violation of Procedure AP 25B-100 and Technical Specification 6.8.1. This example is in the licensee's corrective action program as Performance improvement Request 99-243 Work Plannina Radiation protection personnel were not aware of the decontamination work until the day of the event. Decontamination activities were not scheduled on the plant work schedul The job was assigned the day before the incident occurred. Therefore, there was no pre job planning. No regulatory issues were identified; however, this item is in the licensee's corrective action program as Performance improvement Request 99-243 Communications Through personnel interviews, the incident investigation team determined that a senior radiation protection technician was not clearly assigned the job coverage responsibilities by the radiation protection shift desk technician. The lack of clear job assignment resulted in the lack of a pre-job survey, air sample, and intermittent job coverage. The incident investigation team concluded that inadequate communication was a significant contributing factor to this event. No regulatory issues were identified; however, this item l is in the licensee's corrective action program as Performance Improvement Request

.

99-2319.

, Radiation Work Permits i

The applicable radiation work permit did not meet procedural expectations. Procedure RPP 02-105," Radiation Work Permit," Revision 14, Sections 9.1.2 and 9.1.3 provided guidelines for assigning tasks to either general or specific radiation work permits. One example of a specific radiation work permit task was one which involved " access / work in i a highly contaminated area." This event involved a worker cleaning a highly j contaminated area. However, the work was controlled by a general radiation work permit (990002), in addition, radiation worker training (GT 12 452 01) indicated that a l~ specific radiation work permit was required for entering a highly contaminated area. No l . regulatory issues were identified; however, this item is in the licensee's corrective action program as Performance Improvement Request 99-2434.

l Procedural Guidance The internal dose calculation and/or the whole-body counter operation procedural guidence were/was not detailed enough to ensure that the individual performing the i whole body counts started with the correct radioactive material intake activity. As a i

!

e

(- .

\

O-10- )

result, an incorrect value was selected and the internal dcse was greatly overestirnated.

, No regulatory issues were identified; however, this item is in the licensee's corrective

!

action program as Performance improvement Requests 99-2351 and 99-232 c. Conclusions Based on incorrect internal dose calculations, the licensee reported a suspected overexposure to the NRC. During the subsequent review of the event, the licensee determined no regulatory limits had been exceeded. However, the licensee identified weaknesses in radiological surveys, radiation worker practices, work planning, communications, radiation work permits, and procedural guidance for dose calculation The licensee identified a violation involving a failure to make surveys, in accordance with 10 CFR 20.1501(a). This Severity Level IV violation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance Improvement Request 99-231 The licensee identified two examples of a violation involving a worker that failed to follow radiation protection procedura! guidance in accordance with Technical Specification l 6.8.1. A radiation worker failed to follow radiation work permit protective clothing i

requirements and failed to frisk properly for radioactive contamination after leaving a high contamination area. This Severity Level IV vioiation is being treated as a Non-Cited Violation, consistent with Appendix C of the NRC Enforcement Policy. This violation is in the licensee's corrective action program as Performance Improvement Requests 99-2319 and 99-243 R7 Quality Assurance in Radiological Protection and Chemistry Activities The 1999 quality assurance audit team included technical specialists from other nuclear power facilities. The audit scope was broad enough to provide an overview of program performance. The findings indicated that the reviews were of sufficient depth to identify potential problems. The audit team documented its findings through use of performance improvement requests. The audit team concluded that the radiological environmental monitoring program was implemented well. No vendor audits were performed since the previous inspection of this are V. Manaaement Meetinos X1 Exit Meeting Summary The inspector presented the inspection results to membere of licensee management at an exit meeting on July 16,1999. The licensee acknowledged the findings presented.

I No proprietary information was identifie ,

L

?.

.

ATTACHMENT SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED Licensee M. Blow, Manager, Chemistry / Radiation Protection R. Butz, Engineer, System Engineering R. Hammond, Supervisor, Health Physics J. Johnson, Manager, Resources Protection A. Mah, Senior Engineer, Corrective Action B. McKinney, Vice President Plant Operations / Plant Manager C. Reekie, Engineering Specialist Ill, Licensing T. Rice, Technician lil, Environmental Management R. Robinson, Assistant Superintendent, Instrumentation and Electrical Maintenance R. Stumbaugh, Health Physics Supervisor D. Williamson, Supervisor, Environmental / Fire Protection C. Warren, Vice President and Chief Operating Officer NRC F. Brush, Senior Resident inspector INSPECTION PROCEDURES USED 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring ITEMS OPENED, CLOSED, AND DISCUSSED Opened 50-482/9911-01 NCV Meteorological instrument channel was inoperable more than seven days (Section M1.1)

50-482/9911-02 NCV Failure to make surveys of airborne radioactivity (Section R1.2)

50-482/9911-03 NCV Failure to follow radiation protection procedures (Section R1.2)

I

,

I l

l l

.

.

,

-2-i i

Closed 50-482/9911-01 NCV Meteorological instrument channel was inoperable more than seven days (Section M1.1)

50-482/9911-02 NCV Failure to make surveys of airborne radioactivity (Section R1.2)

50-482/9911-03 NCV Failure to follow radiation protection procedures (Section R1.2)

Discussed None Documents Reviewed 1998 Annual Radiological Environmental Operating Report WCNOC OE Audit K-510. Environmental Management (March 1 through June 25,1999)

Draft incident investigation Report (llT #99-001) on June 25,1999, Personnel Contamination Event Performance Improvement Reports as listed in the details of this report Procedures Al 07B-014 Collection, Preparation, and Shipment of Airborne Particulate and Radioiodine Samples, Revision 1 Al 078-016 Radiological Environmental Monitoring Equipment Control and Calibration, Revision 2 Al 078-017 Calibration and Maintenance of Air Sampler Pumps, Revision 0  !

AP 078-004 Offsite Dose Calculation Manual (Radiological Environmental Monitoring 1 Program), Revision 0 l AP 25B-100 Radiation Worker Guidelines, Revision 9 AP 25B-300 RWP Program, Revision 8

. AP 28A-001 Performance improvement Request, Revision 14 RPP 02-105 RWP, Revision 14 RPP 02-210 Radiation Survey Methods, Revision 16 RPP 03-210 Internal Exposure Calculations and Evaluations, Revision 5  !

l

.

_ .