IR 05000313/2018012

From kanterella
Jump to navigation Jump to search
NRC Confirmatory Action Letter (EA-16-124) Follow-Up Inspection Report 05000313/2018012 and 05000368/2018012
ML18092A005
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 03/29/2018
From: O'Keefe N
NRC/RGN-IV/DRP/RPB-E
To: Richard Anderson
Entergy Operations
O'Keefe C
References
EA-14-008, EA-14-088, EA-16-124, ML14174A832, ML15023A076, ML16169A193, ML18040A918, ML18078B153 IR 2018012
Download: ML18092A005 (74)


Text

rch 29, 2018

SUBJECT:

ARKANSAS NUCLEAR ONE - NRC CONFIRMATORY ACTION LETTER (EA-16-124) FOLLOW-UP INSPECTION REPORT 05000313/2018012 AND 05000368/2018012

Dear Mr. Anderson:

From February 12, 2018, to March 8, 2018, the U.S. Nuclear Regulatory Commission (NRC)

reviewed your progress in implementing the specific actions from the Arkansas Nuclear One (ANO) Comprehensive Recovery Plan that were committed to in a Confirmatory Action Letter (CAL) dated June 17, 2016, (NRCs Agencywide Documents Access and Management System (ADAMS) Accession No. ML16169A193) (EA-16-124). On February 15, 2018, the NRC inspection team discussed the initial results of this inspection with you and other members of your staff. On March 8, 2018, the team discussed the final results of this inspection with Mr. J. Kirkpatrick, General Manager-Plant Operations, and other members of your staff. The team documented the results of this inspection in the enclosed inspection report.

The team reviewed ANOs progress in implementing the ANO Comprehensive Recovery Plan, focusing on 19 actions that ANO management had concluded were complete and effective. The team also reviewed progress made toward closing one action, and will continue to inspect this action during a future inspection. The attached report documents the basis for closing 18 CAL actions, as well as observations related to the stations progress in addressing the action that was not sufficiently complete and effective to close at this time.

On February 2, 2018, you notified the NRC by letter that the actions taken to address two inspection focus areas identified in the CAL were completed and effective, and requested the NRC to inspect these areas for possible closure (ML18040A918). Therefore, the team reviewed the Significant Performance Deficiencies (SPD) and the Identification, Assessment, and Correction of Performance Deficiencies (IACPD) inspection focus areas to determine whether the actions taken, in aggregate, achieved the safety performance improvement objectives stated in the ANO Comprehensive Recovery Plan. Based on this inspection, the NRC concluded that your actions were effective in achieving the stated objectives. Therefore, the SPD and IACPD inspection focus areas are closed. The remaining four areas will be inspected during a future inspection. Your February 2, 2018, letter also notified the NRC of ANOs readiness for a final inspection of the actions taken to address the two findings of substantial safety significance (Yellow) for each unit. Therefore, this inspection included a review of the corrective actions to address the Yellow findings in each unit involving the failure to adequately approve the design and to load test a temporary lift assembly (EA-14-008) and the failure to maintain required flood mitigation design features (EA-14-088). The final significance determinations and Notices of Violation (NOVs)

associated with these findings were documented in NRC Inspection Reports 05000313/2014008 and 05000368/2014008 (ML14174A832), and 05000313/2014010 and 05000368/2014010 (ML15023A076), respectively. These findings resulted in the station being placed into Column 4, the Multiple/Repetitive Degraded Cornerstone column, of the NRCs Reactor Oversight Process Action Matrix in the first quarter of 2015.

Starting in January 2016, the NRC used a phased approach to review your actions using Inspection Procedure 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area. Your identification of the problems, evaluations of causes, extent of condition and extent of causes, safety culture impacts, and corrective actions plans were documented in NRC Inspection Report 05000313/2016007 and 05000368/2016007 (ML16161B279). The corrective actions that were not yet complete were included in the SPD inspection focus area of the CAL, and have been inspected as they were completed during quarterly CAL follow-up inspections. In the current inspection, the team closed the remaining SPD actions, verified that all SPD actions were complete and effective, and concluded that your actions met the objectives of Inspection Procedure 95002. Therefore, the Yellow findings involving the failure to approve the design and to load test a temporary lift assembly (EA-14-008) and failure to maintain required flood mitigation design features (EA-14-088) are closed.

In accordance with the guidance in Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, these Yellow findings will no longer be considered in assessing plant performance. However, ANO Units 1 and 2 will remain within the Multiple/Repetitive Degraded Cornerstone column of the NRCs Reactor Oversight Process Action Matrix pending completion of the actions needed to close the CAL. On March 19, 2018, you notified the NRC that ANO is ready for the NRC to inspect the final CAL actions and the remaining inspection focus areas (ML18078B153). Therefore, the NRC plans to inspect all remaining CAL actions and inspection focus areas beginning on April 2, 2018. The NRC will use the results of that inspection and the previous CAL follow-up inspections, and the NRCs Reactor Oversight Process Action Matrix to determine the appropriate changes to oversight of ANO. The NRC plans to communicate the results of this determination at a public meeting following the successful completion of these CAL closure activities.

The NRC team did not identify any findings or violations of more than minor significance. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Neil F. OKeefe, Branch Chief Project Branch E Division of Reactor Projects Docket Nos. 50-313; 50-368 License Nos. DPR-51; NPF-6 Enclosure:

Inspection Report 05000313/2018012 and 05000368/2018012 w/ Attachments:

1. Supplemental Information 2. Confirmatory Action Letter Item Status

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Dockets: 05000313; 05000368 Licenses: DPR-51; NPF-6 Report: 05000313/2018012; 05000368/2018012 EPID: I-2018-012-0005 Licensee: Entergy Operations, Inc.

Facility: Arkansas Nuclear One, Units 1 and 2 Location: Junction of Highway 64 West and Highway 333 South Russellville, Arkansas Dates: February 12 through March 8, 2018 Team Lead: G. George, Senior Reactor Inspector, Engineering Branch 1 Inspectors: W. Cullum, Reactor Inspector, Engineering Branch 1 J. Dixon, Senior Project Engineer, Project Branch D C. Henderson, Senior Resident Inspector, Project Branch E C. Smith, Reactor Inspector, Engineering Branch 1 C. Stott, Reactor Inspector, Engineering Branch 1 Approved By: N. OKeefe Chief, Project Branch E Division of Reactor Projects Enclosure

SUMMARY

IR 05000313/2018012; 05000368/2018012; 2/12/2018 - 3/8/2018; Arkansas Nuclear One,

Units 1 and 2; Confirmatory Action Letter (CAL) Follow-up Inspection (Inspection Procedure 92702), Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area (Inspection Procedure 95002).

The inspection activities described in this report were performed by a team of regional inspectors and the Senior Resident Inspector at Arkansas Nuclear One. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, dated July 2016.

On June 17, 2016, the NRC issued a Confirmatory Action Letter (CAL) (ML16169A193)

(EA-16-124) confirming actions that Entergy committed to take in Arkansas Nuclear One (ANO)

Comprehensive Recovery Plan (CRP). The team reviewed 19 actions from the CAL. The team concluded that 18 of the actions reviewed were complete and were effective in achieving the associated performance improvement objectives, so these actions are closed. The team reviewed six completed sub-actions for one action (PH-13), but will continue to review sub-actions as they are completed. The team also concluded that one action (DB-11) was not sufficiently complete to close during this inspection.

On February 2, 2018, the licensee notified the NRC by letter that the actions taken to address two inspection focus areas identified in the CAL were completed and effective, and requested the NRC to inspect these areas for possible closure (ML18040A918). The team reviewed the Significant Performance Deficiencies (SPD) and the Identification, Assessment, and Correction of Performance Deficiencies (IACPD) inspection focus areas concluded that the actions were effective in achieving the CRP objectives. Therefore, the SPD and IACPD inspection focus areas are closed.

The team used Inspection Procedure (IP) 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area, to review the licensees response to each of the two Yellow findings pertaining to each unit. The team reviewed the completed actions and determined that the inspection objectives of IP 95002 have been satisfied. Therefore, the Yellow findings are closed.

No findings were identified.

REPORT DETAILS

OTHER ACTIVITIES

4OA5 Other Activities

.1 Review of Yellow Findings

Scope of Review On February 26, 2016, the NRC completed the onsite portion of IP 95003, Supplemental Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input, dated December 18, 2015. As part of the 95003 Inspection, the NRC team included an assessment of completed and planned actions for the two Yellow findings relating to each unit using IP 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area, dated February 9, 2011. IP 95002 has four objectives:

  • Objective 1 - To provide assurance that the root and contributing causes of individual and collective risk-significant performance issues are understood.
  • Objective 2 - To independently assess and provide assurance that the extent of condition and the extent of cause of individual and collective risk-significant performance issues are identified.
  • Objective 3 - To independently determine if safety culture components caused or significantly contributed to the individual and collective risk-significant performance issues.
  • Objective 4 - To provide assurance that a licensees corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.

a. Yellow Stator Drop Finding Background On March 31, 2013, a temporary lifting rig failed and caused the drop of the 525-ton Unit 1 main generator stator. The stator drop resulted in a loss of offsite power (LOOP)for Unit 1, which was in a refueling outage, and a reactor trip and partial LOOP for Unit 2, which had been operating at full power. There was structural damage to the turbine building and the fire protection system. The NRC performed inspections on both the stator drop event and the subsequent flooding event that followed. On August 1, 2014, the NRC documented preliminary Yellow findings in NRC Inspection Report 05000313/2014009 and 05000368/2014009 (ADAMS Accession No. ML14253A122). On June 23, 2014, the NRC issued the final Yellow safety significance determination and Notice of Violation (EA-14-008) in NRC Inspection Report 05000313/2014008 and 05000368/2014008 (ADAMS Accession No. ML14174A832). During the IP 95003 Inspection, the NRC team confirmed that ANOs root cause evaluation (RCE) and planned and implemented corrective actions adequately addressed the stated violations. Subsequent CAL follow-up inspections reviewed all of the corrective actions following successful completion.

Objective 1 - To provide assurance that the root and contributing causes of individual and collective risk-significant performance issues are understood.

ANO initiated the first RCE, CR-ANO-C-2013-0888, in March 2013, to evaluate the collapse of the stator lifting rig. As discussed in NRC Inspection Report 05000313/2015008 and 05000368/2015008 (ADAMS Accession No. ML15180A399),

ANO did not document the apparent violation and the subsequent Notice of Violation (NOV) in the corrective action program until September 2014. The NRC noted in NRC Inspection Report 05000313/2013012 and 05000368/2013012 (ADAMS Accession No. ML14083A409) that the first RCE did not evaluate ANOs failure to adequately review and approve work performed by a contractor. The 95003 inspection team determined that the second RCE, CR-ANO-C-2014-2318, adequately addressed the identification problems, risk consequences, and compliance concerns associated with the stator drop event.

The current team confirmed that the 95003 NRC team concluded that the licensee understood the root and contributing causes of individual and collective risk-significant performance issues associated with the Yellow stator drop finding for both units.

Therefore, the team concluded that Objective 1 was satisfied.

Objective 2 - To independently assess and provide assurance that the extent of condition and the extent of cause of individual and collective risk-significant performance issues are identified.

The 95003 inspection team conducted an independent extent of condition and extent of cause review for the issues associated with the stator drop Yellow findings. The NRC team concluded that, at the time of that inspection, ANOs extent of condition review had not reviewed closed contracts and contracts involving nonsafety work or equipment. As a result, the NRC issued a non-cited violation for failure to complete two of the extent of condition reviews associated with the stator drop event specified in the licensees corrective action plan.

The 95003 inspection team also found that the extent of cause review performed for RCE CR-ANO-C-2014-02318, Root Cause 2, which reviewed technical/administrative procedures to determine whether they provided sufficient guidance for the activity performed, did not provide objective evidence as to why additional corrective actions were not needed to address the area. However, the NRC team determined this issue was of minor safety significance since ANO was able to demonstrate that the problems identified were addressed by corrective actions in the Comprehensive Recovery Plan.

Based on the licensees evaluations, corrective actions taken, and the results of the previous 95003 inspection, the inspection team concluded that the licensee identified the extent of condition and extent of cause of individual and collective risk-significant performance issues associated with the Yellow stator drop finding for both units. The team confirmed that Objective 2 was satisfied.

Objective 3 - To independently determine if safety culture components caused or significantly contributed to the individual and collective risk-significant performance issues.

During the NRCs independent safety culture review during the 95003 inspection, the NRC team concluded that ANO addressed the safety culture components identified in their RCEs that either caused or significantly contributed to the associated performance deficiencies. However, the NRC team determined that ANO did not adequately evaluate or develop corrective actions to address the collective impact of the remaining safety culture components that, while not relating specifically to a root or contributing cause, nonetheless contributed to the problems described in each of the RCE problem statements.

In response to the 95003 inspection teams concerns, ANO performed a common cause analysis of all of the safety culture attributes identified in the recovery RCEs in order to assess the collective significance and causes. The 95003 inspection team reviewed the safety culture common cause assessment and nuclear safety culture area action plan and concluded that ANOs evaluations adequately considered the full set of available safety culture data and identified the common causes associated with safety culture at ANO that had contributed to the problems identified.

The current team concluded that the licensee identified the safety culture components which caused or significantly contributed to the individual and collective risk-significant performance issues associated with the Yellow stator drop finding for both units, and that the licensee developed adequate corrective actions to address these safety culture components. The team concluded that Objective 3 was satisfied.

Objective 4 - To provide assurance that a licensees corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.

As part of their response to the stator drop event review, the licensee initiated 195 corrective actions. During the 95003 inspection, the NRC team reviewed a significant portion of these actions. However, there were multiple planned actions remaining open at the conclusion of the inspection. The licensee consolidated these actions into CAL actions for the NRC to review upon completion. The CAL actions are shown in the table below along with the respective NRC inspection report discussing or closing the item. For a description of each item, see Attachment 2.

CAL Action Items associated with the Yellow Stator Drop Finding Inspection CAL Action Status in Report Report Item 2016008 FP-13 Closed VO-15 Closed VO-23 Closed VO-24 Closed 2016010 VO-1 Closed VO-4 Closed CAL Action Items associated with the Yellow Stator Drop Finding Inspection CAL Action Status in Report Report Item 2017010 VO-10 Closed VO-14 Closed VO-18 Discussed (Closed in 2017013)

VO-20 Discussed (Closed in 2017012)

VO-24 Additional information added after closure 2017011 DM-9 Closed DM-10 Closed VO-5 Closed VO-6 Closed VO-11 Closed VO-21 Closed 2017012 CO-5 Closed DB-1 Closed DB-2 Closed DM-7 Closed DM-8 Closed OC-5 Closed VO-7 Discussed (Closed in 2018012)

VO-9 Closed VO-20 Closed 2017013 DM-1 Closed DM-6 Closed DM-11 Closed VO-8 Closed VO-18 Closed VO-19 Closed 2018012 VO-7 Closed (see below)

During the 95003 inspection, the NRC team concluded that corrective actions for lifting and rigging appeared appropriate and were being tracked in CR-ANO-C-2015-03996. In addition, the NRC team concluded that actions to improve contractor oversight had not yet been fully effective; further action was necessary because oversight plans for contract outage workers were inadequate, qualification requirements for contractors to act as supervisors did not have a consistent standard, and designated ANO oversight personnel lacked adequate guidance and training to perform their oversight role. ANO wrote CR-ANO-C-2015-03788 to enter all of these issues into the corrective action program.

ANO addressed these gaps on vendor oversight in the Vendor Oversight Area Action Plan. The NRC identified in the CAL which vendor oversight actions were considered the most significant contributors. As shown in the table above, the team confirmed that the NRC has reviewed and closed all of the vendor oversight actions in the CAL after determining that these actions were effective.

The NRC team concluded that the licensees corrective actions for risk-significant performance issues were sufficient to address the root and contributing causes associated with the Yellow stator drop finding for both units and prevent recurrence. The team concluded that Objective 4 was satisfied.

Conclusion The NRC has determined that all four inspection objectives stated above have been satisfied. Based on the results of this inspection, the two Yellow stator drop findings (EA-14-008) are closed for both units (NOV 05000313/2013012-04, NOV 05000368/2013012-05).

b. Yellow Flood Protection Finding Background On March 31, 2013, the failure of a temporary lifting rig caused the drop of the Unit 1 main generator stator. The dropped stator damaged fire protection system piping located in the turbine building train bay. Water from the fire protection system migrated to the Unit 1 auxiliary building, filling the auxiliary building sump. Water then leaked into the B decay heat vault, as documented in CR-ANO-1-2013-01286. The NRC performed inspections on both the stator drop event and the subsequent flooding event that followed. On August 1, 2014, the NRC documented preliminary Yellow findings in NRC Inspection Report 05000313/2014009 and 05000368/2014009. On January 22, 2015, the NRC issued the final significance determination and NOV (EA-14-088) in NRC Inspection Report 05000313/2014010 and 05000368/2014010 (ADAMS Accession No. ML15023A076).

Through their review, the 95003 team concluded that information regarding the reasons for the violation, the corrective actions taken and planned to be taken to correct the violation and prevent recurrence, and the date when full compliance was achieved, was addressed in Entergys letter dated February 23, 2015, (ADAMS Accession No. ML15054A607). During the 95003 inspection, the NRC team confirmed that ANOs RCE and planned corrective actions adequately addressed the stated violations.

ANO documented their investigation into the causes in two RCEs:

Root Cause Evaluation CR-ANO-C-2013-1304 Root

Cause:

Inadequate PM strategy to maintain flood hatches and doors in accordance with plant design basis.

Contributing Cause 1: Failure to recognize the significance of passive flood hatches as credited flood barriers for a design basis flooding event.

Contributing Cause 2: Post maintenance testing of flood hatches is not required if the hatch is removed for scheduled or emergent maintenance other than the hatch PM.

Root Cause Evaluation CR-ANO-C-2014-0259 Root Cause 1: When previous opportunities for identification [of degraded flood protection features] occurred, ANO personnel did not sufficiently challenge and verify whether existing plant configuration met licensing basis requirements for mitigation of flooding events.

Root Cause 2: The detailed design requirements of flooding features were not documented.

Contributing Cause 1: Because reviews and responses were narrowly focused, the organization did not identify deficiencies after receiving previous internal and external OE related to flooding.

Contributing Cause 2: The PM strategy in place to maintain flood protection features was inadequate both in frequency and content.

Contributing Cause 3: Entergy personnel provided minimal oversight of ODA activities related to Fukushima walkdowns.

Objective 1 - To provide assurance that the root and contributing causes of individual and collective risk-significant performance issues are understood.

The 95003 inspection team concluded that ANO used appropriate processes in the development of their RCEs, and that ANOs evaluation team and analysis techniques were sufficient to identify the root and contributing causes of degraded flood protection barriers. The 95003 team determined that ANO had performed a comprehensive review and inspection of both units flood protection program, including extensive walkdowns and assessments of the flood protection barriers, and identified multiple degraded flood barriers and flood protection program deficiencies. The 95003 team also concluded that the licensee understood the root and contributing causes of individual and collective risk-significant performance issues associated with the Yellow flood protection finding for both units. During this inspection, the team confirmed that Objective 1 was satisfied.

Objective 2 - To independently assess and provide assurance that the extent of condition and the extent of cause of individual and collective risk-significant performance issues are identified.

The 95003 inspection team conducted an independent extent of condition and extent of cause review of the issues associated with the degraded flood barriers Yellow findings.

The NRC teams independent review focused on the root and contributing causes, and whether ANOs evaluations identified and bounded organizational issues.

Extent of Condition The initial condition evaluated by ANO was external and internal flood protection deficiencies related to Updated Final Safety Analysis Report (UFSAR) requirements for Unit 1 and Unit 2 auxiliary and emergency diesel fuel storage buildings. This was later expanded to include the following passive structures and systems and other acts of nature:

  • Reactor building, intake structure, emergency cooling pond, and post-accident sample building.
  • Barriers used to protect against external and internal floods, high energy line breaks, fire, external events (tornado, icing, seismic, etc.), and radiation.
  • Barriers required to support emergency operating procedure (EOP) actions.
  • Drains, abandoned equipment, and openings that may pose a threat to flood protections.

The extent of condition evaluation included a review of the Security Plan, Technical Specifications, Quality Assurance Manual, Emergency Plan, Offsite Dose Calculation Manual, Core Operating Limits Report, National Pollution Discharge Elimination System Permit, Independent Spent Fuel Storage Installation Certificate of Conformance, and Fire Protection Program.

Extent of Cause ANOs extent of cause review looked for potential deficiencies that went undetected by station personnel. The extent of cause review was subsequently expanded to look for other engineering activities that might be susceptible to causes identified by ANO during the review. This review included:

  • Flood barriers in other Seismic Class 1 structures that could challenge the ability to maintain reactor core cooling.
  • Deficiencies in SSCs that could result in an initiating event.
  • Flood barriers in any structure that could result in an initiating event.
  • Equipment/floor drains or roof drains that could result in challenging the ability to maintain reactor core cooling or result in an initiating event.
  • Passive protection against other external events such as tornado, icing, seismic events, fire, security, etc. that could result in challenging the ability to maintain reactor core cooling or result in an initiating event.
  • Passive barriers that offer radiation protection or air tightness.
  • Equipment required to mitigate beyond design basis accidents or events.
  • Barriers/drains that must function in order to be able to perform EOPs.
  • The scope and content of procedure EN-LI-100, Process Applicability Determination, Revision 16.

The 95003 team identified that ANO did not examine fire protection barriers during the extent of condition reviews, so the NRC team performed visual inspections of over 100 fire seals in safety-related areas and did not identify any discrepancies. The 95003 team also identified that ANO had modified numerous fire seals to perform the dual function of also being a flood seal; however, the modified seals had not been subjected to required testing to demonstrate that the fire resistance was not negatively impacted.

ANO documented this concern in CR-ANO-C-2016-0490 and initiated actions to conduct fire resistance testing. The NRC team identified an unresolved item because some of the actions to correct the degraded flood protection finding resulted in modifying existing fire seals in a way that created an untested configuration. ANO has scheduled fire resistance testing to determine whether there is an actual degraded condition. The NRC subsequently closed this URI because the fire testing demonstrated that fire resistance was not degraded.

The team reviewed the licensees root cause reports, corrective actions, and self-assessments. Overall, the team found that the licensees actions for extent of cause and extent of condition were broad and comprehensive. In particular, the team found that the flooding protection extent of condition was thorough and did not identify any problems.

Based on a review of the licensees evaluations and actions taken, the team concluded that the licensee identified the extent of condition and extent of cause of individual and collective risk-significant performance issues associated with the Yellow flood protection finding for both units. The team concluded that Objective 2 was satisfied.

Objective 3 - To independently determine if safety culture components caused or significantly contributed to the individual and collective risk-significant performance issues.

During the NRCs independent safety culture review during the 95003 inspection, the team concluded that ANO conducted a comprehensive safety culture assessment that properly identified the safety culture components related to the problem and causes.

However, the 95003 team determined that ANO did not adequately evaluate or develop corrective actions to address the collective impact of the remaining safety culture components that, while not relating specifically to a root or contributing cause, nonetheless contributed to the problems described in each of the RCE problem statements.

In response to the 95003 inspection teams concerns, ANO performed a common cause analysis of all of the safety culture attributes identified in the recovery RCEs in order to assess the collective significance and causes. The NRC team reviewed the safety culture common cause assessment and nuclear safety culture area action plan and concluded that ANOs evaluations considered the full set of available safety culture data and identified the common causes associated with safety culture at ANO that had contributed to the problems identified.

The NRC team concluded that safety culture components did cause or significantly contribute to the individual and collective risk-significant performance issues associated with the Yellow flood protection finding for both units, and that the licensee developed adequate corrective actions to address these safety culture components. Therefore, the team concluded that Objective 3 was satisfied.

Objective 4 - To provide assurance that a licensees corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.

As part of their flood protection recovery efforts, the licensee initiated 388 corrective actions. During the 95003 inspection, the NRC team reviewed a significant portion of these actions. However, there were 52 actions remaining open at the conclusion of the inspection. The licensee consolidated these actions into Confirmatory Action Letter (CAL) actions for the NRC to review upon completion. The CAL Action Items are shown in the table below along with the respective NRC inspection report discussing or closing the item. For complete descriptions of each item, see Attachment 2.

CAL Action Items associated with the Yellow Flood Protection Finding Inspection CAL Action Status in Report Report Item 2016008 DB-3 Closed FP-1 Closed FP-2 Discussed (Closed in 2017011)

FP-3 Closed FP-6 Closed FP-7 Discussed (Closed in 2017011)

FP-13 Closed 2017010 FP-5 Closed LF-1 Closed LF-4 Closed LF-8 Closed 2017011 FP-2 Closed FP-7 Closed FP-9 Closed 2017012 DB-1 Closed DB-2 Closed DM-17 Closed FP-4 Closed NF-8 Closed OC-3 Closed PH-12 Information Added PM-18 Closed SC-10 Closed 2017013 FP-8 Discussed (Closed in 2018012)

LF-11 Closed PH-3 Closed PH-4 Closed PH-5 Closed PH-6 Closed PH-12 Information Added 2018012 FP-8 Closed The 95003 inspection team identified that ANO implemented corrective actions associated with flood protection barriers that may have reduced the resistance of fire seals by replacing existing seals with new, dual function fire/flood seals. The resident inspectors later inspected and closed this unresolved item in Inspection Report 05000313/2016004 and 05000368/2016004 (ADAMS Accession No. ML17041A376).

The NRC team concludes that the licensees corrective actions for risk-significant performance issues were sufficient to address the root and contributing causes associated with the Yellow flood protection finding for both units and prevent recurrence.

The team concluded that Objective 4 was satisfied.

Conclusion The NRC has determined that the inspection objectives stated above have been met.

Based on the results of this inspection, the two Yellow flood protection findings (EA-14-088) are closed (NOV 0500313/2014009-01 and 05000368/2014009-01).

.2 Confirmatory Action Letter (CAL) Inspection Focus Area Closures (IP 92702)

Background On March 4, 2015, ANO Units 1 and 2 transitioned to the Multiple/Repetitive Degraded Cornerstone Column (Column 4) of the NRCs Reactor Oversight Process Action Matrix as a result of having two Yellow findings for each unit. In response, the NRC performed IP 95003, concluding the onsite portion of the inspection on February 26, 2016, and provided insights on ANOs performance weaknesses, their causes, and related safety culture issues. The 95003 team reviewed proposed corrective actions and identified the need for additional corrective actions to create prompt and sustained improvement. In a letter dated May 17, 2016, ANO Comprehensive Recovery Plan, (ADAMS Accession No. ML16139A059), Entergy notified the NRC staff of its plan to perform specific actions to resolve the causes for declining performance at ANO, and provided a summary of that plan.

The NRC reviewed Entergys Comprehensive Recovery Plan (CRP) and concluded that Entergys planned corrective actions should correct significant performance deficiencies and result in sustained performance improvement at ANO. The CRP is comprised of 14 Area Action Plans (AAPs) that contain key improvement actions and scheduled completion dates. The NRC grouped the CRP actions into six inspection focus areas to support future inspection activities based on ANO performance concerns documented in NRC Inspection Report 05000313/2016007 and 05000368/2016007 (ADAMS Accession No. ML16161B279).

The NRC issued a Confirmatory Action Letter (CAL) on June 17, 2016, (ADAMS Accession No. ML16169A193) to confirm commitments made by Entergy Operations, Inc. (Entergy). This CAL identified 161 of the 200 commitments made by Entergy that the NRC planned to conduct inspections to verify the actions were completed and were effective in achieving the intended outcomes to improve safety performance at ANO.

These intended outcomes were described in each of the 14 AAPs in specific Desired Behaviors and Outcomes (DB&Os). The CAL listed the 161 actions of interest in the following Inspection Focus Areas:

1. Significant Performance Deficiencies - actions intended to address the root and

contributing causes for the Yellow findings for the stator drop and the flooding events, including plant deficiencies and problems with vendor oversight, change management, conservative decision making, and risk management 2. Identification, Assessment and Correction of Performance Deficiencies - actions intended to address the improvement in the implementation and oversight of the corrective action program, self-assessment, performance monitoring, the quality of problem evaluations, and the use of operating experience 3. Human Performance - actions intended to improve human performance, leadership behaviors, organizational capacity, procedure quality, standards, and accountability 4. Equipment Reliability and Engineering Programs - actions intended to improve implementation of processes and programs that ensure key plant equipment remains available, reliable, and capable of meeting the plant design and licensing bases, including resolving specific equipment conditions 5. Safety Culture - actions intended to improve nuclear safety culture values and behaviors to ensure commitment by leaders and individuals to emphasize safety over competing goals 6. Service Water Self-Assessment - actions intended to ensure conditions adverse to quality are identified and resolved by conducting a focused self-assessment of the Units 1 and 2 service water systems in accordance with station procedures and NRC Inspection Procedure 93810, Service Water System Operational Performance Inspection Starting in August 2016, the NRC conducted quarterly CAL follow-up inspections to review CAL actions that the licensee had determined were complete and effective in achieving the DB&Os. However, many individual DB&Os were intended to be achieved by completing multiple related actions. Since it was desirable to provide prompt feedback after each action was completed, the NRC concluded that it was appropriate to perform a review of each Inspection Focus Area by selecting a sample of the key DB&Os to verify that the actions in aggregate were effective. This inspection performed this review for two of the six Inspection Focus Areas.

a. Review of Inspection Focus Area: Significant Performance Deficiencies Background Using the Reactor Oversight Process (ROP), the NRC reviews safety-significant findings and performance indicators to determine the appropriate regulatory response described in the ROP Action Matrix. ANO was placed into Column 4 oversight on March 4, 2015.

The 95003 inspection team determined that ANO had identified the relevant causes for the stator drop and flood protection issues. ANO determined that the root causes for the stator drop finding involved inadequate guidance and project management oversight of vendors design and testing of the temporary lift assembly. The root causes for the Yellow flood protection finding involved inadequate preventive maintenance strategies, incomplete design documentation, and the failure to verify whether the existing plant configuration met licensing basis requirements for flood mitigation. The NRC team agreed with ANOs root cause evaluation results.

Scope of Review To ensure the licensee adequately addressed the inspection focus area, the NRC team reviewed the focus area for key DB&Os to verify that the licensee showed sustained improvement. Specifically, the following DB&Os where reviewed:

  • Flood Protection (FP) DB&O-1: Degraded or nonconforming flooding design features have been corrected. (Key Actions FP-6, FP-7, FP-8)
  • FP DB&O-3: A Flooding Protection Program Owner is established and the Owner actively engages with plant personnel in helping them to understand and maintain the flood protection features. (Key Action FP-4, FP-9)
  • FP DB&O-5: Flood Protection Program is functional and addresses the following key aspects:

o Configuration control of flood protection features is maintained.

o Flood barrier breaches are evaluated, tracked, and controlled by a barrier impairment process.

o The material condition of flood protection features is monitored and maintained.

o Operating experience is evaluated and addressed.

(Key Actions FP-1, FP-2, FP-4, FP-5, FP-9, FP-11, FP-12, FP-13)

  • FP DB&O-6: The Flooding Upper Level Document is updated and maintained.

An engineering report and flood protection drawings are developed and maintained to clearly document flooding design basis and credited flood protection features (credited internal and external flood protection features and credited operator actions). (Key Actions FP-1, FP-2, FP-5, FP-9, FP-11)

  • Lift Rig Failure and Vendor Oversight (VO) DB&O-4: The roles and responsibilities of the supervisor, whether a station employee or a supplemental supervisor, are clearly defined and vigorously implemented for supervising supplemental personnel. (Key Actions VO-6, VO-7, VO-16, VO-20)
  • VO DB&O-6: Contract/Project Managers support excellent performance of supplemental personnel by ensuring and being accountable for:

o Standards and expectations are thoroughly communicated to and understood by supplemental personnel.

o Contract/Project Managers are commonly seen in working areas of the plant observing, coaching, and reinforcing standards and expectations.

Deviations from standards and expectations are corrected promptly.

o Contract/Project Managers set the example for adherence to process administrative procedures.

o The responsibility for the monitoring and oversight of supplemental personnel is identified clearly and is performed effectively. Responsible managers ensure supervisory and management oversight of work activities, including contractors and supplemental personnel, such that nuclear safety is supported and ensured.

o Service organizations and station line managers clearly identify and reinforce accountabilities for supplemental personnel performance.

Leaders foster an environment that promotes accountability and hold individuals accountable for their actions.

o An effective means of feedback exists that promotes continual improvement in supplemental personnel performance. Leaders actively solicit feedback, listen to concerns, and communicate openly with all individuals.

(Key Actions VO-2, VO-6, VO-13, VO-14, VO-15, VO-16, VO-20)

  • VO DB&O-8: Administrative controls for project risk management are rigorously applied. Risk items with potential high consequences are identified and addressed. (Key Actions VO-6, VO-19, VO-21, VO-23, VO-24)
  • Design and Licensing Basis (DB) DB&O-1: Leaders model and continually reinforce expectations that nuclear safety is the overriding priority in making decisions. Feedback and performance measures focus on nuclear safety.

(Key Actions DB-1, DB-2)

  • DB DB&O-2: Engineering staffing levels are adequate to sustain improved plant operations, maintain high levels of equipment performance, and support excellence in Engineering Program implementation. Changes to staffing levels, workload, skills, proficiency or knowledge level are addressed with nuclear safety as the overriding priority. Engineering backlogs are maintained such that latent risks are minimized. (Key Actions DB-4, DB-5, DB-6, OC-1, OC-2, OC-3 and OC-4)
  • Decision Making and Risk Management (DM) DB&O-5: Decision makers ensure the problem statement driving a decision is well understood with complete facts and validated assumptions. The right people are involved in the decision making process to understand the problem, assess the impact, develop solutions, understand the risk, make a decision, and develop any needed mitigation strategies. (Key Actions DM-5, DM-14, DM-15, DM-16)

It should be noted that the licensee removed the original DM DB&O-5 based on the realization that it was captured in other DM DB&O. The new DM DB&O that encompass the original DB&O-5 are:

  • DM DB&O-2: Senior leaders demonstrate accountability and a bias for action to correct deficiencies and challenges to safe and reliable operation for the long term. Responsible managers present accurate information and thorough solutions that minimize threats to plant performance and safety.
  • DM DB&O-4: The station uses well-defined decision-making processes and tools.
  • DM DB&O-6: Decision makers consistently develop multiple alternatives for decisions that take into account Nuclear Risk, Industrial Risk, Dose Risk, Plant Transit Risk, Equipment Reliability Risk, Enterprise Risk.
  • DM DB&O-8: Workers understand the potential risk impact of plant conditions and work activities. Mitigating actions are applied for identified risks.
  • DM DB&O-9: Risk management processes are applied effectively to manage integrated risk for planned and unplanned activities and events.
  • DM DB&O-10: Risk is minimized through an operational focus led by the Operations Shift Managers and supported by station management. Risk related equipment issues are well understood and addressed in a timely, effective manner.

To evaluate the licensee's corrective action effectiveness, the team reviewed:

  • Flood Protection Area Action Plan Closure Report
  • Lift Rig Failure and Vendor Oversight Area Action Plan Closure Report
  • Closure Readiness Evaluation for Significant Performance Deficiencies
  • Confirmatory Action Letter and Area Action Plan Actions Effectiveness (LO-ALO-2018-00014)
  • Review of Entergy fleet procedures to verify CAL commitments were translated from ANO recovery procedures
  • Interviewed a cross section of station employees and contractors The team evaluated the corrective actions and effectiveness criteria established by the licensee in aggregate for the reviewed DB&Os. The team noted that the flooding protection program, preventive maintenance strategies, and the plant configuration were consistent with the ANO licensing basis requirements for flood mitigation. The team also found that ANOs processes and procedures would provide adequate flood protection if they are maintained. These processes and procedures include a Flood Protection Program with a primary and backup program engineer. The Flood Protection Program includes a series of flood protection drawings, preventive maintenance with appropriate maintenance intervals, and maintenance rule program monitoring. In the plant, ANO has staged flood protection features with contingency supplies and all plant for flood protection features are marked with placards. Additionally, the program has coordinated with the maintenance planning department to identify and track flood protection breach permits. Overall, the team found that all the effectiveness measures and performance improvement indicators are positive.

The team noted the licensee has maintained ANO specific procedures for vendor oversight that are more stringent than the Entergy fleet procedure and that all available plant specific performance improvement data indicates that the station is continuing to improve. Performance improvement data for errors by contractors, greater supervisor field presence, work management process, work completion, etc. are all indicating continued station improvement in procedure and process compliance.

Based on the sampling of DB&Os, having closed all supporting actions taken by the licensee, reviews of performance data, and observations performed on site, the team concluded that the actions taken to address Significant Performances Deficiencies, in aggregate, were effective in achieving the Desired Behaviors and Outcomes. Therefore, Significant Performances Deficiencies inspection focus area is closed.

b. Closure of Inspection Focus Area: Identification, Assessment, and Correction of Performance Deficiencies (IACPD)

Background In performing their RCEs for the stator drop and flood protection issues, the 95003 inspection team determined that ANO identified most of their performance problems.

ANO concluded that leaders did not make corrective action program (CAP)implementation a priority, did not adequately oversee the CAP, and relied on unverified assumptions. ANO staff did not always assign the appropriate significance level to condition reports, resulting in problems not being sufficiently understood so that corrective actions would be effective. Cause evaluations tended to focus on addressing the most apparent problem (e.g., equipment issues) without examining organizational and programmatic elements.

The 95003 inspection team concluded that CAP procedures were adequate; however, ANO did not always implement the program as intended. Station personnel at all levels lacked a clear understanding of one or more elements of the CAP process and their roles and responsibilities. There were a number of instances where ANO did not adequately evaluate or use internal and external operating experience to prevent future problems. Some evaluations relied on unverified assumptions, and degraded conditions were accepted through evaluations, resulting in reduced safety margins or long-term compensatory actions. Limited resources led to CAP action backlogs, impacting timely corrective action. ANO was ineffective in using performance assessments and trending to identify declining performance.

Interim actions to improve CAP performance yielded positive results with respect to the quality of documentation; however, the 95003 team noted multiple examples where cause evaluations and extent of condition reviews were narrowly focused, condition reports were closed without completing specified actions, and problems requiring an evaluation for potential operability bypassed the on-shift licensed operator review function.

Scope of Review To ensure the licensee adequately addressed the inspection focus area, the NRC team reviewed the focus area for key desired behaviors and outcomes to verify that the licensee showed sustained improvement. Specifically, the following DB&O where reviewed:

  • CAP DB&O-7: The performance review group (PRG) members demonstrate and reinforce high standards of performance through consistent review, constructive feedback, and product grading of station cause evaluations to ensure quality analysis and actions prevent repetition of station events and issues. (Key Actions include CA4, CA5, CA7, and CA8)
  • CAP DB&O-10: During Department Performance Improvement Meeting (DPRMs)and Aggregate Performance Improvement Meetings (APRMs) leaders critically review CAP and operating experience (OE) performance, and identify subtle declines in performance. Senior leaders demonstrate accountability and a bias for action to correct deficiencies and challenges to nuclear safety. Responsible managers present accurate information, present thorough solutions and do not minimize threats to plant performance and safety. Senior Leaders create an environment that is conducive to robust interaction and problem resolution. (Key Actions CA4, CA10, LF-8, LF-11, LF-14)
  • CAP DB&O-11: The Nuclear Safety Culture Monitoring Panel (NSCMP) closely monitors CAP and OE trends and issues and periodically reviews CAP performance to detect indications of performance decline and issues that may affect nuclear safety. The NSCMP and the Senior Leadership Team take prompt action to correct negative trends. (Key Actions include CA-2, SC-02, SC-03, LF-01, LF-05, LF-09)
  • DM DB&O-1: Individuals sue decision-making practices that emphasize prudent choices over those that are simply allowable. Decision makers take into consideration the risk associated with short-term gains versus long-term solutions and consider potential nuclear, radiological and industrial safety consequences when making decisions. (Key Action DM1, DM3, DB1, DB2)

To evaluate the licensee's corrective action effectiveness, the team reviewed:

  • Corrective Action Program Area Action Plan Closure Report
  • Closure Readiness Evaluation for Identification, Assessment, and Correction Performance Area Action Plan Closure Report
  • Training Improvement Organization Performance Area Action Plan Closure Report
  • Corporate and Independent Oversight Area Action Plan Closure Report
  • Entergy fleet procedures to verify CAL commitments were translated from ANO recovery procedures.
  • CAP and OE performance indicators
  • Interviewed PRG members and observed PRG meeting on February 12, 2018.
  • A sample of APRM and DPRM meeting minutes, and observed the Security Department DPRM in December 2017. No adverse conditions identified during the review of APRMs, DPRMs, and during the observation of the Security Department DPRM.
  • NSCMP meeting minutes and observed NSCMP meeting on February 14, 2018 The team evaluated the corrective actions and effectiveness criteria established by ANO in aggregate for the reviewed DB&O. The team noted from July 2017 to December 2017, the licensee reduced its adverse condition report backlog from approximately 500 to 361 (established goal was >450), and the corrective actions open greater than 365 days was below 60 for the entire period (established goal >60). It was also noted by the team that the licensee identified weaknesses during their most recent focused self-assessments conducted in 2017 and early 2018. The licensee initiated condition reports and implemented corrective actions for each identified weakness. The weaknesses where related to causal product quality and oversight provided by PRG. The team reviewed the implemented and planned corrective actions and determined that they were appropriate to the circumstances.

Based on the sampling of DB&Os, previous inspections that closed all supporting actions taken by the licensee, reviews of performance data, and observations performed on site, the team concluded that the actions taken to address Significant Performances Deficiencies, in aggregate, were effective in achieving the Desired Behaviors and Outcomes. Therefore, Significant Performances Deficiencies inspection focus area is closed.

.3 CAL Follow-up (IP 92702)

a. Actions to Address Significant Performance Deficiencies FP-8 Validate that all internal flood gaps identified from the review of documentation for credible flood paths and the follow-up walk downs have been resolved. (CR-ANO-C-2014-00259 CA-19, CA-58, CA-70, CA-73, CA-78, CA-93, CA-127, CA-250 through CA-252)

During the third quarter of 2012, ANO had an outside design agency (ODA)perform walkdowns of the flood protection features required by the licensing basis. These walkdowns were required by an NRC 10 CFR 50.54(f) request for information letter dated March 12, 2012 (ML12053A340). The walkdowns were part of the post-Fukushima flooding design basis verification effort that was intended to identify and address plant-specific vulnerabilities or performance deficiencies, and verify the adequacy of monitoring and maintenance procedures.

A second ODA walkdown was conducted in the third quarter of 2013 as a result of the self-revealing deficiencies from the flooding event. This second walkdown identified more than 100 additional deficiencies. Some of the deficiencies were from original construction, and some involved barriers that had ineffective preventive or corrective maintenance.

During the NRCs first review of FP-8 in Inspection Report 05000313/2017013 and 05000368/2017013 (ML18024A285), the team documented an issue with the procedure used to verify that auxiliary building hatches are watertight.

Specifically, a smoke test was performed; however, the licensee did not record testing data that validated the auxiliary building was at a negative pressure when hatch 492 was tested. The test method relied on the auxiliary building side of the hatch being at a lower pressure than the turbine building side, then create smoke near the seal on the turbine building side. Seal leakage would become apparent because smoke would be drawn to the area of the leak by air being drawn through the area of the leak. In response to the concern, the licensee performed air pressure measurements while the team was onsite, which indicated a slightly positive pressure inside the auxiliary building, contrary to the basis for performing the testing. Therefore, the inspectors concluded that the test method was flawed because it would not have provided indication of seal leakage if it were present.

This resulted in the team questioning the validity of smoke testing in general and the operability/functionality of all auxiliary building penetrations that have been tested using this method. The licensee documented the concerns in Condition Report CR-ANO-1-2017-03673.

For this inspection, the team reviewed corrective actions associated with this item to evaluate the licensee's corrective action effectiveness. After the NRCs first review of Procedure 1402.240, Inspection of Watertight Hatches, the licensee revised the procedure to require verifying that the auxiliary building was at a negative pressure as an initial condition for performing the test. The team observed a performance of Revision 2 of Procedure 1402.240, Inspection of Watertight Hatches, and did not identify any issues. In addition, the team reviewed the closure packages, flooding procedures, corrective action documents, interviewed station personnel, and performed walkdowns to determine that the internal flood gaps identified from the review of documentation for credible flood paths and the follow-up walk downs have been resolved.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address FP-8 were effective. Therefore, FP-8 is closed.

VO-7 Develop and implement initial and continuing training on the procedure for management and oversight of supplemental personnel. Training is for site contract managers and project managers. (CR-ANO-C-2015-02838 CA-14)

The licensee assigned a responsible manager for each project, and then implemented a qualification process to allow the use of supplemental supervisors to perform most vendor supervisory duties. During the 95003 supplemental inspection, the NRC team noted that Procedure EN-OM-126, Management and Oversight of Supplemental Personnel, did not contain guidance to ensure that supervisors or oversight personnel had appropriate technical expertise to be fully capable of providing oversight for the specific project or work. Interviews with ANO personnel assigned oversight roles for supplemental workers commented that they did not always have the technical expertise to provide oversight of supplemental employees assigned to them.

During the NRCs first review of VO-7 in Inspection Report 05000313/2017012 and 05000368/2017012 (ML17282A018), the team found that the licensee tested 20 plant personnel following training and 11 individuals scored below the required 80 percent required to pass the test. However, since the overall average of the 20 tests was an 83 percent, the licensee issued read and sign training modules to the 11 failures with no subsequent test as a corrective action.

The team determined that the licensee did not have an adequate basis to conclude that the training was adequate for the intended purpose or that individuals qualified to conduct management and oversight of supplemental personnel possessed and demonstrated a sufficient level of technical knowledge to effectively perform their roles. This report stated that action VO-7 would be reviewed in a future inspection after the licensee: 1) reviews the adequacy of the training material and makes any appropriate modifications; 2) implements the training, if revised; and 3) concludes that sustained improvement has been demonstrated in individuals who have completed the training on Procedure EN-OM-126, Management and Oversight of Supplemental Personnel.

For this inspection, the team reviewed corrective actions associated with these concern to evaluate the licensee's corrective action effectiveness. As a result of the NRCs first review of the training material, the licensee re-evaluated the procedures using a systematic approach to training concept to determine the appropriate level and testing of the concepts and objectives from the procedures.

The licensee developed computer based training with a required test at the end of the training. In addition, the licensee developed a test question bank, determined the test to be required on an annual basis with a pass/fail of 80 percent, and determined that the current annual requirement was sufficient. At the time of this inspection, the licensee had trained and tested 76 of 195 contract and project managers; 63 passed on the first attempt, 10 passed on the allowed second attempt, 2 individuals were on a remediation plan, and the final person has not utilized the second attempt. The team reviewed the training material, procedures, corrective action documents, and interviewed station personnel to determine that the training for contract and project managers for management and oversight of supplemental personnel was adequate.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address VO-7 were effective. Therefore, VO-7 is closed.

b. Actions to Address Identifying, Assessing, and Correcting Performance Deficiencies DM-12 Conduct benchmarking of a high performing station in the area of operations focus with a plan based on Principles for Effective Operational Decision Making. (CR-ANO-C-2015-02832 CA-24). These principles included:

1. Conditions that potentially challenge safe, reliable operation are recognized and promptly reported for resolution.

2. Roles and responsibilities are established for making and implementing

decisions and are thoroughly understood by plant personnel.

3. Potential consequences of operational challenges are clearly defined, and alternative solutions are rigorously evaluated.

4. Decisions are based on a full understanding of short and long-term risks and the aggregate impact of conditions associated with various options.

5. Implementation plans are developed to effectively communicate actions, responsibilities, compensatory measures, and contingencies to ensure successful outcomes.

6. Decisions and decision-making activities are periodically evaluated.

During the 95003 inspection, the NRC team found that benchmarking was not a common practice at ANO. If benchmarking occurred, it was typically within the Entergy fleet. Plant personnel commented that if benchmarking resulted in suggestions for improvements, improvement items typically had not received priority due to limited resources.

The team evaluated the corrective actions and effectiveness criteria established by the licensee for implementing benchmarking of a high performing station in the area of Operations Focus. The team concluded that benchmarking plan was focused on industry principles for effective operational decision-making. From this benchmarking, the licensee developed improvement actions. The team confirmed that a high performing plant that was not part of the Entergy organization was benchmarked. The benchmarking identified the licensee did not consistently ensure senior leadership ownership of emergent plant issues.

The licensee implemented actions to influence the behaviors of senior leaders within the organization to ensure engagement and responsibility for key operational issues is obtained. They modified existing platforms such as the plant health committee, the plant status report, and operational focus meeting to achieve sustainability. The licensee also implemented an issues response team that incorporates the objectives of existing corporate platforms such as a duty roster, ODMIs, outage control center, and failure modes analysis with the objective of making a centralized process to establish a consistent and reliable response to emergent plant needs.

The team observed that licensee implemented these key actions during recent emergent equipment issues. Additionally, the team reviewed three key performance indicators associated with operational focus. These key indicators are operator aggregate index for non-outage issues (goal less than or equal to 1); on-line risk deviation with planned and actual on-line risk (goal of less than or equal to -0.5); and unplanned limited condition of operations (LCO) entries (goal of less than or equal 1). The team observed improvement in each indicator and met the established goal, demonstrating that the licensee has improved its operational focus.

Based on the actions taken by the licensee, data evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DM-12 were effective. Therefore, DM-12 is closed.

DM-15 Perform a benchmark on a high performing station outside the Entergy Fleet on Operational Decision Making Instruction (ODMI) development, implementation and effectiveness reviews, and develop improvement actions based upon the results. (CR-ANO-2016-01348 CA-3)

During the 95003 supplemental inspection, the NRC team reviewed several long-term degraded conditions that were the subject of ODMIs to assess whether the process was implemented and maintained effectively. The team found that operators, including shift managers and control room supervisors, did not always have a clear understanding of the decisions, action thresholds, and compensatory measures established in existing ODMIs. The team also identified one violation caused by the incompatible actions created from two concurrent ODMIs affecting the Unit 2 safety injection system.

For this inspection, the team evaluated the licensee's corrective action effectiveness. The team reviewed procedures governing the ODMI process.

The team evaluated the corrective actions and effectiveness criteria established by the licensee for implementing benchmarking of a high performing station outside the Entergy fleet and reviewed other nuclear fleet and station procedures on ODMI development, implementation and effectiveness reviews. From this benchmarking the licensee identified improvement actions, including implementing changes to procedure EN-OP-111, Operational Decision-Making Issue Process, to add an ODMI quality review checklist in order to ensure that all the elements necessary for the ODMI were incorporated and the requirement for responsible individual should use this attachment. The team noted that these key actions from the benchmarking where incorporated into the licensees procedures and improved the quality of ODMI. Additionally, the licensee implemented a team approach for developing ODMI, incorporated risk considerations based from the benchmarking conducted at other non-Entergy sites.

Based on the actions taken by the licensee, data evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DM-15 were effective. Therefore, DM-15 is closed.

c. Actions to Address Human Performance Issues DB-17 An engineering standard will be produced to provide sustainable, consistent guidance to station engineers in the performance of their duties. This standard will incorporate best practices for developing engineering products beyond simple procedural compliance and ensure that standards and expectations for performance of engineering duties are clearly articulated to the workforce. (CR-ANO-C-2015-02833 CA-20)

During the 95003 supplemental inspection, the NRC team identified that losses of experienced personnel resulted in engineering having 48 percent of staff having less than 5 years of nuclear power plant experience. Engineers assigned responsibility for multiple systems or programs had difficulty performing all assigned duties. In some cases, engineering program owners had not completed all the required qualifications, and ANO relied on additional oversight and mentoring as bridging strategies.

For this inspection, the team reviewed procedure EN-MS-S-051-A, ANO Engineering Standard for Engineering Change Package Development, which was established as supplemental guidance to maintain a consistent use of the standard design change process using fleet procedures. The licensee created Engineering Standard EN-MS-S-051-A by compiling supplemental desk guides and checklists developed by ANO and Entergy engineers on how to perform their duties using fleet procedures. The licensee solicited the supplemental guidance through a survey, which the team reviewed. The engineering standard also combined guidance for identifying design inputs, expectations for use, and additional guidance on the appropriate procedural forms used in the engineering change procedures. The team reviewed the management briefings, which communicated the expectations for use of this new engineering standard to the engineering staff. The briefing records shows that 106 out of 108 engineers acknowledge attendance at the briefings.

To evaluate the effectiveness and sustainability of this action, the team interviewed two staff engineers and one engineering supervisor. The supervisor and engineers all stated they refer back to the standard when creating an engineering change. Additionally, they stated that the information presented in the standard is useful. They also stated that the licensee reinforced the use of the standard extensively during team discussions and during mentoring sessions with new engineers.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DB-17 were effective. Therefore, DB-17 is closed.

DM-14 Assign a mentor to review all Operational Decision Making Instructions until proficiency is demonstrated. (CR-ANO-C-2016-01348 CA-2)

During the 95003 supplemental inspection, the NRC team reviewed several long-term degraded conditions that were the subject of ODMIs to assess whether the process was implemented and maintained effectively. The team found that operators, including shift managers and control room supervisors, did not always have a clear understanding of the decisions, action thresholds, and compensatory measures established in existing ODMIs. The team also identified one violation caused by the incompatible actions created from two different ODMIs affecting the Unit 2 safety injection system.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this action. Additionally, the team reviewed procedures governing the operation decision-making issue process. The team independently reviewed seven active operational decision-making issue products. The team discussed these products, training requirements, effectiveness reviews, and implementation with the ANO subject matter expert for the operation decision-making issue process.

The team evaluated the corrective actions and effectiveness criteria established by the licensee for assigning a mentor to review and improve current ODMIs.

The mentors reviewed all new ODMIs until such time proficiency was demonstrated based on the following criteria:

  • No long stating ODMI precursors open longer than 60 days.
  • A review of open ODMIs to determine the triggers and actions are clear and executable.
  • Effectiveness reviews where being performed.

The team observed no long standing ODMI precursors, each open ODMI had clearly defined and executable triggers and actions, and effectiveness where performed and assigned as reoccurring corrective actions. Additionally, the ODMIs where of high quality, corrective actions assigned to correct the condition described in the ODMI, and repairs were scheduled.

Based on the actions taken by the licensee, data evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DM-14 were effective. Therefore, DM-14 is closed.

DM-16 Develop and implement training for key personnel on ODMI development, implementation, and effectiveness reviews. (CR-ANO-C-2016-01348 CA-4)

During the 95003 supplemental inspection, the NRC team reviewed several long-term degraded conditions that were the subject of ODMIs to assess whether the process was implemented and maintained effectively. The team found that operators, including shift managers and control room supervisors, did not always have a clear understanding of the decisions, action thresholds, and compensatory measures established in existing ODMIs. The team also identified one violation caused by the incompatible actions created from two different ODMIs affecting the Unit 2 safety injection system.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item. Additionally, the team reviewed training material developed and discussed the training with a sample of personnel who completed the training.

The team evaluated the corrective actions and effectiveness criteria established by the licensee for implementing training for key personnel on ODMI development, implementation, and effectiveness reviews. The training was administered to operations and engineering personnel on a single occasion. The licensee determined that the training would be added to initial senior reactor operator and shift technical advisor required training. Additionally, procedure COPD-035, ANO Emergent Issue Response was revised to assign roles and responsibilities of the ODMI subject matter expert. The licensee has developed knowledge management plan for the subject matter expert to maintain the improved standards for the ODMI process. The team concluded that the training material reflected new standards for ODMIs, appropriate personnel were provided the training, and that trainees felt that the training was helpful in improving the quality and usability of ODMI documents.

Based on the actions taken by the licensee, data evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DM-16 were effective. Therefore, DM-16 is closed.

LF-3 Provide supervisory training on constructive conversation skills. (CR-ANO-C-2015-02829 CA-30)

During the licensees second root cause evaluation following the stator drop event, ANO concluded that there were weaknesses in leaders ability to provide effective communications, build trust with employees, create a vision to arrest the performance decline, reinforce high standards and expectations, foster a learning organization and culture of continuous improvement, and make sound decisions that manage risk. During the 95003 supplemental inspection, the NRC team found that, while communication methods and frequency had improved, most communication came from the supervisor level and that messages from senior management were not communicated consistently to the organization.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item. The licensee updated their initial supervisory development and fleet leadership programs to include required training courses focusing on constructive conversation skills. The licensee administered this training as mandatory for existing supervisors and managers. The team reviewed the training plans, training presentations, and training completion records, noting that 209 of 233 supervisors and managers completed the training in a classroom setting. (The remaining 24 leaders were excepted because of pending retirements or exit from the company.) Additionally, the team interviewed two managers and one supervisor to assess the effectiveness of the training. Based on the interviews and performance metrics on post-effectiveness evaluations, the team concluded that the constructive conversation skills were improved by the training.

Based on the actions taken by the licensee, data evaluated by the team, and observations performed on site, the team concluded that the actions taken to address LF-3 were effective. Therefore, LF-3 is closed.

PM-14 Address gaps in the Preventive Maintenance Program baseline staffing level based on the current levels of experience in the departments and at the site.

(CR-ANO-C-2015-02834 CA-116)

During the licensees second root cause evaluation following the stator drop event, the licensee found that insufficient organizational capacity contributed to high levels of overtime in maintenance, backlogs, teamwork issues, and uncertainty and stress among the workforce. The resulting high workloads and limited staffing made it challenging to train a workforce with over 40 percent of the workers having less than 5 years of experience at ANO. During the 95003 supplemental inspection, the NRC team noted that ANO had experienced difficulty recruiting experienced people in key technical areas, and that ANO had not addressed the challenge of recruiting experienced workers within the Organizational Capacity Area Action Plan.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item. The licensee has had their organizational capacity plan in place, staffed preventive maintenance program positions they deemed necessary, and monitor metrics to ensure their staff is able to keep up with their workload while still producing quality work. The metrics the licensee is monitoring are:

  • 3 month Rolling Sum High Critical Component Failures for Units 1 and 2
  • Open Preventive Maintenance Change Requests
  • Open Craft Feedback Requests The licensee picked the 3-month rolling sum metric for high critical component failures to better depict the current performance. The licensee has set a standard of how many failures will result in green, yellow, and red performance. The licensees goal is to stay below red performance at any time.

If the metric goes to yellow, the licensee will put in place a recovery plan to restore performance.

The Open Preventive Maintenance Change Requests and Open Craft Feedback Requests have metrics to monitor how long it is taking for the staff to respond to change and feedback requests from staff. The metric does not measure how many requests there are, only how many exceed a response time of 90 days. The licensee uses this information to ensure they are at an appropriate staffing level.

The team noted that ANO also put in place the ANO People Health Committee process, which monitors the staffing levels, experience and training needs to support the workload in each work group on a quarterly basis. This process serves as both the assessment tool and the corrective action mechanism for the site.

The licensee selected these metrics in order to provide objective evidence that their Preventive Maintenance Program baseline staff levels are sufficient to keep up with the needed work levels and still produce quality procedures and work orders to maintain an acceptable failure rate for high critical components. The metrics show that feedback from the maintenance and craft staff was being incorporated into procedures and work orders in a timely manner. It also keeps track of high critical component failures to ensure that staff were not pressured to complete inadequate work quality. The team concluded that the metrics adequately reflect the effectiveness of the PM program staffing, and that these metrics were being met.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address PM-14 were effective. Therefore, PM-14 is closed.

PQ-8 Upgrade procedures classified as normal. (CR-ANO-C-2015-03033 CA-26)

During the 95003 supplemental inspection, the NRC team agreed with ANOs assessment that the leadership team had not consistently provided the organizational structure, staff priorities, or dedicated resources to support high quality procedures and work instructions, and had not consistently applied current industry guidance for procedure content, structure, and human factoring.

For this inspection, the team reviewed corrective actions associated with this item to evaluate the licensee's corrective action effectiveness. The licensee has previously completed rewriting all of the stations safety-related procedures and is now working on rewriting the normal procedures for the chemistry and operations departments. The NRC previously concluded that the licensee successfully incorporated an industry standard for procedure writing and grading and trained procedure writers to use the new standards. The standard requires all procedures to have a passing grade of 85 percent or greater. All of the rewritten procedures currently have a passing grade above 85 percent.

The licensee has also combined the procedure writing groups for both the chemistry and operations departments into one centralized organization to reduce the differences between procedure writing styles between organizational groups.

The licensee has not completed the rewriting process for all of the normal procedures within the chemistry and operations departments. They developed a project plan that will be complete by the middle of year 2020, which was consistent with Entergys commitment reflected in the ANO CAL. The team determined that the licensee is currently ahead of this schedule with passing grades for all the applicable procedures being higher than the 85 percent minimum.

Based on the actions taken and scheduled by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address PQ-8 were effective. Therefore, PQ-8 is closed.

PQ-9 Upgrade Critical 1-4 Model Work Orders with a frequency of greater than or equal to two years or two refueling outages. (CR-ANO-C-2015-03033 CA-27)

During the licensees second root cause evaluation following the stator drop event, the licensee identified the following:

  • the level of detail in work orders was not sufficient to prevent plant events
  • the backlog of work order and PM feedback increased
  • PM documents were not updated until the PMs were entering the work scheduling process
  • and sufficient resources were not available to support work planning.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item. The licensee incorporated an industry standard for procedure writing and grading which they have applied to rewriting the Critical 1-4 model work orders. The standard requires all work orders to have a passing grade of 85 percent or greater. All of the rewritten work orders currently have a passing grade above 85 percent.

The licensee has not currently rewritten all Critical 1-4 model work orders. The licensee has a project plan to complete rewriting the last of the targeted work orders by the middle of 2020, which was consistent with Entergys commitment reflected in the ANO CAL. The team determined that the licensee was ahead of this schedule and achieving passing grades for all the applicable work orders (i.e., scoring higher than the 85 percent minimum).

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address PQ-9 were effective. Therefore, PQ-9 is closed.

d. Actions to Address Equipment Reliability and Engineering Program Deficiencies DB-10 Resolve standards performance deficiencies from the engineering program assessments completed during the Preventive Maintenance (PM) Program extent of condition review. (CR-ANO-C-2015-02834 CA-157, CA-160, CA-161, CA-164, CA-165, and CA-168)

ANO completed extent of condition reviews as part of their PM root cause evaluation which included 30 snapshot assessments of engineering programs.

The 95003 supplemental inspection team reviewed 12 of the snapshot assessments, resulting in two violations and one finding. The NRC team also noted issues within the Repair and Replacement, Welding, and Large Motor Programs.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item related to the following programs:

  • Air Operated Valves Program
  • Heat Exchanger Program
  • Obsolescence/Long-term Asset Management Program
  • Microbiologically Influenced Corrosion Program The team reviewed engineering program procedures and documents associated with the standards performance deficiencies identified by the snapshot self-assessments (standards performance deficiency is an Entergy term used to identify a self-assessment finding that may involve failures to meet a requirement or commitment). In addition, the team conducted interviews with engineering program owners and the applicable program health reports were reviewed. The team verified that corrective actions were taken to address the standards performance deficiencies and that resources are being allocated to ensure that engineering programs are effective.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions to address DB-10 were effective. Therefore, DB-10 is closed.

DB-11 Perform one benchmark or one self-assessment between March 1, 2016, and March 1, 2020, for each of 23 selected engineering programs. (CR-ANO-C-2015-02833 CA-28, and CR-ANO-C-2016-00614 CA-8, CA-22 and CA-25)

During the 95003 supplemental inspection, the NRC team found that the ANO snapshot assessments of engineering programs were conducted in a systematic manner, some used industry experts, and identified program deficiencies.

However, the NRC team concluded that ANOs snapshot assessments were not fully effective in assessing whether some programs addressed longstanding equipment performance trends or whether plant components were appropriately included in programs. In response to the NRC teams observations, ANO initiated actions (CR-ANO-C-2016-00614) to conduct benchmarking of engineering programs and assign experienced mentors.

The NRC had been tracking the corrective action to review the High Energy Line Break (HELB) program assessment and completion of the ANO HELB Design Documentation Project Plan (CR-ANO-C-2015-02833 CA-28) as an extent of cause review associated with CAL action FP-2. However, ANO requested that the NRC track and closed it under DB-11 since that was how ANO was tracking it. The NRC agreed and documented the decision in Inspection Report 05000313/2017011 and 05000368/2017011 (ML17195A478) in the section closing FP-2.

For DB-11, the CAL reflects that the licensee committed to complete 23 engineering program benchmarks or self-assessments by mid-2020, and specifically complete these actions for the following five programs listed below by mid-2018, in accordance with procedure EN-LI-104, Self-Assessment and Benchmark Process:

  • ASME Repair and Replacement Program
  • Microbiologically Influenced Corrosion Program
  • Large Motor Program
  • High Energy Line Break Program For this inspection, the team concluded that these benchmark and self-assessments applied a systematic approach to the review of each program.

Each assessment identified standards performance deficiencies, enhancements, and negative observations. These deficiencies and issues were entered into the corrective action program. The team concluded that these deficiencies were corrected or corrective action plans were initiated and will be completed in period commensurate with safety.

The team reviewed the corrective actions associated with the ANO HELB Design Documentation Project Plan, which included the licensees High Energy Line Break Self-Assessment/Effectiveness Review. The team concluded that the self-assessments applied a systematic approach to the review of the program. The licensee specifically identified standards performance deficiencies associated with Entergys fleet procedures for temporary modification and work order planning. These procedures had not included the consideration of the potential impact of design changes to HELB program. The team verified that these conditions were in the Entergy corrective action program and plans are in place to correct the conditions.

The team concluded that the licensee completed a thorough review of the HELB Program through the ANO HELB Design Documentation Project Plan and self-assessment. However, the team identified that the licensee had failed to initiate condition reports or corrective actions for missing design bases calculations or licensing documents identified in CALC-ANOC-CS-16-00004, HELB Program Design Basis Consolidation Report, Table 9-1. Corrective actions were not initiated for the following original design information that could not be located:

  • (Unit 1) No analytical method for identifying the break locations exists for the Unit 1 high energy piping within containment.
  • (Unit 1) No design bases information could be located that records jet impingement forces or pipe whip restraint design or locations for the high energy piping in the Unit 1 containment.
  • (Unit 1) No justification for the adequacy of impingement barriers that protect service water headers could be located.
  • (Unit 2) Documentation to support break locations and thrust loads detailed in FSAR Tables 3.6-2 and 3.6-3 could not be located.
  • (Unit 2) Documentation to support the adequacy of pipe whip restraints and jet impingement barriers for the auxiliary building steam generator piping.
  • (Unit 2) No mass or energy release information in any design and licensing documents.
  • (Unit 2) No basis for the jet impingement effects for safety injection system breaks outside of containment.
  • (Unit 2) No detailed design bases information could be located for pressurizer low temperature overpressure protection line breaks.
  • (Unit 2) No design bases records were located that recorded the environmental effects due to rupture of the steam supply to concentrator lines.
  • (Unit 2) No design bases records were located that recorded pipe whip and jet impingement effects due to a rupture of the steam supply to emergency feedwater (EFW) pump turbine.
  • (Unit 2) No design bases records were located that recorded the environmental effects of breaks in the reactor coolant letdown and make-up system.

Following discussion with the team, the licensee entered these conditions into corrective action program as CR-ANO-C-2018-00643. At the end of the inspection, the licensee had not completed the corrective action project plan to locate or reconstitute the missing design information.

Because no corrective action project plan was available to review, the team could not assess the corrective actions. Therefore, DB-11 will remain open pending the licensees completion of the project plan and the NRC review.

DM-18 Develop and implement work management training for senior managers, managers, and each of the identified work management positions with respect to their roles and responsibilities. (CR-ANO-C-2015-03034 CA-13, CA-14, CA-16, CA-18)

During the 95003 supplemental inspection, the NRC team identified that ANO planned work assuming that all maintenance workers would be available to support work. This necessitated that any emergent work be addressed by the Fix-It-Now (FIN) team, or else some planned work had to be rescheduled. The team noted that planned work was often delayed or removed from the schedule because preparations were not completed prior to equipment being taken out of service. Examples included unavailable workers, missing parts not being available, and incomplete maintenance risk evaluations.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item. The licensee developed several different training presentations for the different roles and responsibilities. For example, the licensee developed a formal lesson plan training for the work management roles and responsibilities of Production personnel. The team reviewed the licensees training plans, training completion records, work management metrics. The team also interviewed workweek planners, schedulers, operations work liaisons, and other station personnel to assess the stations effectiveness in communicating each persons role and responsibility in the work management process. Based on the interviews and work management metrics on work planning, scheduling, and execution, the team concluded that the work management process roles and responsibilities were improved by the training.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DM-18 were effective. Therefore, DM-18 is closed.

DM-20 Develop and implement supply versus demand model and metrics to determine and monitor resource needs to meet work load demand. (CR-ANO-C-2015-03034 CA-22 and CA-28)

During the 95003 supplemental inspection, the NRC team identified that ANO planned work assuming that all maintenance workers would be available to support work. This necessitated that any emergent work be addressed by the FIN team, or else some planned work had to be rescheduled. As a result, emergent maintenance frequently disrupted planned work. Work was frequently delayed or removed from the schedule because preparations were not completed prior to equipment being taken out of service. Examples included unavailable workers, required parts were not available, or incomplete maintenance risk evaluations. The FIN team was expected to work off minor maintenance and backlog work, but because a work plan did not exist, workers often pursued other activities.

During the NRCs first review of DM-20 in Inspection Report 05000313/2016010 and 05000368/2016010 (ML16314C483), the team determined that the new maintenance worker supply vs. demand model did not provide an easily interpretable comparison of the supply of qualified maintenance workers on a given work week and the demand based on the scheduled work activities. The team concluded that the estimates of available work hours relied on unrealistic assumptions and did not account for vacations. The work hours scheduled for planned work frequently exceeded the available work hours with the existing maintenance personnel, necessitating scheduling overtime into weekly plans, or relying on the sharing of resources. The team concluded that DM-20 would be reviewed in a future inspection pending a determination by the licensee that the new tool effectively represents the resources available to perform scheduled work and is being effectively used to match work and available resources.

Based on the results of the first review of the supply and demand model, the licensee implemented multiple changes to better estimate and monitor supply and demand in the work management process. These improvements included:

improving the staffing of the FIN team to improve its capacity to accomplish work; developed a schedule to work down backlogs; implementing work process procedure improvements; ensuring that pre-job walkdowns occurred to improve the accuracy of work scope; implementing the training discussed in DM-18; and implementing work management performance indicators to gage the effectiveness of the new supply versus demand model.

The team reviewed the actions associated with this item and interviewed workweek planners, schedulers, operations work liaisons, and other station personnel to assess the stations effectiveness in implementing the supply vs.

demand model. The team determined that ANO made a number of changes including:

  • Personnel changes, added individuals where appropriate to be able to account for emergent work, advanced training, vacations, sick leave, etc.
  • Establishing a 90 day goal to update a work management document from the date of the identified concern
  • Implementing the use of additional computer software to be able to track work load projections with available resources on a daily basis
  • Holding the station accountable to ensuring completion of the work schedule at all levels through twice-daily work management meetings that identified immediate changes when problems were identified Based on the interviews, work management performance indicators, and roughly 6 months using the current supply versus demand program, the team concluded that the licensees implementation of the supply versus demand model was improved. The team noted that the model goal was not exceeding 110 percent utilization, and the performance improvement metric allowed the indicator to be green up to 115 percent utilization, although the procedure states that work is normally loaded to 100 percent of the available resources. The team determined that this inconsistency was minor and that the actual practice was to ensure available resources before planning or scheduling above 100 percent. The teams review of the work management process and performance indicators demonstrated that the current supply versus demand model and performance indicators were effective in allow the station to determine and monitor resource needs to meet work load demand.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address DM-20 were effective. Therefore, DM-20 is closed.

PH-13 The following list contains equipment reliability issues that are being evaluated by the Plant Health Committee for resolution commensurate with the potential impact on safe and reliable operation of the units by December 20, 2018. For items not resolved by the due date, the Plant Health Committee will provide the safety basis for the extension. (CR-ANO-C-2015-02832 CA-38, and CR-ANO-C-2015-03029 CA-34)

  • Resolution of Unit 1 EDG exhaust stack thinning
  • Resolution of Unit 2 EDG exhaust stack thinning
  • Unit 2 spent fuel pool cooling system performance improvement
  • Correct back-leakage into the Unit 1 boric acid system
  • Unit 2 EFW Terry turbine governor replacement
  • Unit 2 spare SW motor issue resolution
  • Unit 1 high pressure injection pump P-36B motor refurbishment
  • Tornado/missile protection for EFW piping resolution
  • Unit 1 reactor vessel head leak-off line replacement
  • Unit 1 and 2 super particulate iodine and noble gas (SPING) monitor replacement For this inspection, the team reviewed the licensees progress in resolving equipment reliability issues by evaluating the actions taken to address the following:
  • Unit 2 SFP cooling system performance improvement
  • Continued SW piping replacement The team reviewed the work orders and modifications associated with correcting these equipment issues. The team did not identify any issues with the corrective actions taken. However, the service water piping replacement is an ongoing project. The licensee is prioritizing sections of piping that need to be replaced and this will continue for several refueling cycles.

The team also reviewed the safety basis the plant health committee used in deferring the following items to a later date:

  • Unit 2 EFW Terry turbine governor replacement
  • Unit 1 high pressure injection pump P-36B motor refurbishment
  • Tornado/missile protection for EFW piping resolution
  • Unit 1 reactor vessel head leak-off line replacement The team did not identify any issues with the safety basis for extending the repairs to this plant equipment. The licensee has a plan to work all of the items at a later date based on scheduling and prioritization.

Inspectors reviewed the corrective actions taken to date on the equipment and noted that further work on this system will be performed in the future. No issues were identified in the review of this documentation. The addition of this item to the Equipment Reliability Issue List demonstrates commitment to resolving equipment reliability issues.

The team also noted that the only remaining action that the NRC plans to inspect is the Unit 1 and Unit 2 Super Particulate Iodine and Noble Gaseous Monitor (SPINGS) replacement.

This action will remain open pending licensee action on the SPING replacement item. This action will be reviewed during a future inspection to verify the licensee is resolving the equipment reliability issues listed.

PM-7 The Planning Quality Review Team (PQRT) will perform an enhanced review of critical work orders for a minimum of 12 months and feed back the results to the planning staff. (CR-ANO-C-2015-02834 CA-119 and CA-120)

During the Preventive Maintenance root cause evaluation, the licensee identified that work order instructions lacked sufficient detail, including details needed to ensure that the work scope was fully accomplished, steps provided and verified critical attributes, and critical steps were identified.

For this inspection, the team reviewed the effectiveness of corrective actions associated with this item. The licensee established a quorum to hold enhanced Planning Quality Review Team (PQRT) meetings for a minimum of 12 months.

The enhanced PQRT meeting consisted, in part, of the required quorum to grade a percentage of critical or essential online preventive maintenance work orders scheduled to be performed in the upcoming month along with a percentage of critical or essential outage preventive maintenance work orders prior to the outage.

The licensee performed more than the required minimum 12 months of enhanced PQRT meetings. The licensee continues to use PQRT meetings on a monthly basis, although the quorum and sample sizes have been reduced.

The team reviewed the licensees enhanced PQRT grading sheets from these meetings along with all condition reports written for work orders graded as unsatisfactory. The team concluded that the licensee gave feed back to the planning staff with enough detail to adequately address this item.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address PM-7 were effective. Therefore, PM-7 is closed.

PM-15 Review a sample of component criticality classifications to validate that the stations risk significant equipment is classified correctly.

(CR-ANO-C-2015-02834 CA-137)

During the 95003 supplemental inspection, the NRC team identified multiple instances of incorrect PM classifications and supporting basis information. While there was a documented basis for the classification entered into the PM Optimization Software (PMOS), many components in critical systems had little or no description of the component functions, associated maintenance rule functions, credible failure modes, and consequences of failure in the PMOS entry description, contrary to procedure EN-DC-153, Preventive Maintenance Component Classification.

The team reviewed the actions associated with this item. The licensee initially performed a review of a sample of components against current industry guidance for classifying plant components, but found a significant deviation between ANO classifications and the industry norm. Therefore, ANO expanded their review and performed a complete review of all risk significant components for both Units 1 and 2. The licensee reviewed the data in their PMOS database included the required information for each component.

The team reviewed the criticality classification and the associated data within PMOS for a sample of components within containment spray system. The team verified that components for the containment spray system were properly classified, matched the guidance per the appropriate procedure, and correctly entered into PMOS. The team did not find any missing data for the selected components.

Based on the actions taken by the licensee, information evaluated by the team, and observations performed on site, the team concluded that the actions taken to address PM-15 were effective. Therefore, PM-15 is closed.

e. Actions to Address Safety Culture Issues SC-9 Develop and provide training to ANO leaders, including supervisory training on NF-7 nuclear safety culture and safety conscious work environment, constructive conversation skills, and how to foster a strong nuclear safety culture within their organizations. (CR-ANO-C-2015-01445 CA-120, and CR-ANO-C-2015-02829 CA-30)

During the 95003 supplemental inspection, the NRC team reviewed the seven individual root cause evaluations performed by the ANO recovery team and evaluated the safety culture attributes of each. The NRC team noted that ANO identified that some safety culture attributes were contributors to several of the root cause evaluation problem statements, but ANO did not consider the collective significance. The licensee performed a common cause analysis of all identified safety culture attributes and found that ANO did not have an adequate explicit management focus on safety culture and the associated infrastructure to support a healthy nuclear safety culture. The 95003 team also identified that many station personnel did not understand the difference between nuclear safety culture and safety conscious work environment.

The team reviewed the training curriculum, training presentations, training records, and post-training surveys associated with nuclear safety culture and safety conscious work environment training modules. The team verified that 97percent (227 of 234) of the on-site leaders attended classroom training sessions conducted by an external industry experts. Corrective actions to track completion of training for the final seven leaders were in place. The team verified that the training objectives incorporated examples of a positive safety conscious work environment and all nine Traits of Positive Safety Culture, defined in the NRCs Safety Culture Policy Statement. In addition, the team determined the case studies developed were appropriate to reinforce the principles of a positive safety culture.

To evaluate the effectiveness and sustainability of this action, the team interviewed two managers and one supervisor. In addition to the interviews, the team verified that nuclear safety culture and safety conscious work environment training for supervisors is required annually. Based on the interviews and performance metrics on post-effectiveness evaluations, the team concluded that the awareness of safety culture principles, supervisors handling of employee concerns, and constructive conversation skills were improved by the training.

Based on the actions taken by the licensee, data evaluated by the team, and observations performed on site, the team concluded that the actions taken to address SC-9 and NF-7 were effective. Therefore, SC-9 and NF-7 are closed.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On February 15, 2018, the team presented the preliminary inspection results to Mr. Richard Anderson, Site Vice President, and other members of the licensee staff. On March 8, 2018, the team discussed the final results of this inspection with Mr. J. Kirkpatrick, General Manager-Plant Operations, and other members of your staff. The licensee acknowledged the issues presented.

The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the team had been returned or destroyed.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

R. Anderson, Site Vice President
T. Arnold, Recovery Manager
L. Blocker, Recovery Director
P. Butler, Design Engineering Manager
B. Daiber, Engineering Programs and Components Manager
D. Edgell, Recovery Manager
A. Martin, Unit 2 Shift Manager
P. McCray, Senior Manager Site Projects
N. Mosher, Regulatory Assurance
E. Nicholson, Performance Improvement Manager
B. Patrick, Maintenance Manager
S. Pyle, Regulatory Assurance Manager
F. Shewmake, Unit 2 Operations Manager
M. Skartvedt, System Engineering Manager
G. Stephenson, Acting Corrective Action Program Manager
G. Sullins, Recovery Manager
J. Toben, Nuclear Safety Culture Manager
D. Vogt, Operations Manager

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Closed

05000313/2013012-04 NOV EA 14-008 Unit 1-Failure to Follow the Materials Handling Program during the Unit 1 Generator Stator Move (Section 4OA5.1.a)
05000368/2013012-05 NOV EA 14-008 Unit 2-Failure to Follow the Materials Handling Program during the Unit 1 Generator Stator Move (Section 4OA5.1.a)
05000313/ NOV EA 14-088 Inadequate Flood Protection for Auxiliary and
05000368/2014009-01 Emergency Diesel Fuel Storage Buildings (Section 4OA5.1.b)

LIST OF CONFIRMATORY ACTION LETTER FOCUS AREAS CLOSED

Closed

Significant Performance Deficiencies (Section 4OA5.2.a)

Identification, Assessment, and Correction (Section 4OA5.2.b)

of Performance Deficiencies

LIST OF CONFIRMATORY ACTION LETTER ITEMS CLOSED AND DISCUSSED

Closed

Significant Performance Deficiencies FP-8 (Section 4OA5.3.a)

VO-7 (Section 4OA5.3.a)

Identifying, Assessing and Correcting Performance Deficiencies DM-12 (Section 4OA5.3.b)

DM-15 (Section 4OA5.3.b)

Human Performance Issues DB-17 (Section 4OA5.3.c)

DM-14 (Section 4OA5.3.c)

DM-16 (Section 4OA5.3.c)

LF-3 (Section 4OA5.3.c)

PM-14 (Section 4OA5.3.c)

PQ-8 (Section 4OA5.3.c)

PQ-9 (Section 4OA5.3.c)

Equipment Reliability and Engineering Program Deficiencies DB-10 (Section 4OA5.3.d)

DM-18 (Section 4OA5.3.d)

DM-20 (Section 4OA5.3.d)

PM-7 (Section 4OA5.3.d)

PM-15 (Section 4OA5.3.d)

Safety Culture Issues NF-7 (Section 4OA5.3.e)

SC-9 (Section 4OA5.3.e)

Discussed

Equipment Reliability and Engineering Program Deficiencies DB-11 (Section 4OA5.3.d)

PH-13 (Section 4OA5.3.d)

LIST OF DOCUMENTS REVIEWED