January 02, 2024
SUBJECT:
ARKANSAS NUCLEAR ONE - SECURITY BASELINE INSPECTION REPORT 05000313/2023402 AND 05000368/2023402
Dear Doug Pehrson:
On November 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Arkansas Nuclear One and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Ray L. Kellar, P.E., Chief Physical Security Branch Division of Radiological Safety & Security Docket Nos. 05000313, 05000368 License Nos. DPR-51, NPF-6
Enclosure:
As stated
Inspection Report
Docket Nos.
05000313 and 05000368
License Nos.
Report Nos.
05000313/2023402 and 05000368/2023402
Enterprise Identifier:
I-2023-402-0000
Licensee:
Entergy Operations, Inc.
Facility:
Arkansas Nuclear One
Location:
Russellville, AR
Inspection Dates:
November 27, 2023 to November 30, 2023
Inspectors:
T. Weir, Physical Security Inspector
Approved By:
Ray L. Kellar, P.E., Chief
Physical Security Branch
Division of Radiological Safety & Security
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Arkansas Nuclear One, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.08 - Fitness For Duty Program
The inspectors evaluated the fitness for duty program by completing the following inspection
elements: Fitness For Duty Program
(1)
- Tier I: All Requirements
- Tier II: All Requirements (except 02.09 c)
- Tier III: All Requirements
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On November 30, 2023, the inspectors presented the security baseline inspection results to Doug Pehrson and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
22-01857,
22-02888,
23-01956,
23-03207,
23-03229,
23-03601,
23-00037,
23-00463,
23-00630,
23-00777,
23-01515,
23-01303,
23-01324
Corrective Action
Documents
Resulting from
Inspection
23-03922,
23-03923,
23-03948,
23-03958,
23-03959
EN-NS-101-05
Maintaining Unescorted Access Authorization/Unescorted
Access and Critical Group
Rev. 8
Fitness-For Duty Program
Rev. 28
EN-NS-102-01
Fitness-For Duty Random and Follow-up Testing, Selection
and Notification
Rev. 3
EN-NS-102-03
Processing Fitness-For-Duty Test Results
Rev. 5
Procedures
EN-NS-102-04
Blind Sample
Rev. 3
EN-OM-123 R18
Annual Fatigue Review
01/24/2022
EN-OM-123 R19
Annual Fatigue Review
01/20/2023
LO-ALO-2022-
00079
Fitness-For-Duty Self-Assessment
07-20-2023
PQA 22--072
Quest Diagnostics Audit - Lenexa
09/22/2022
Self-Assessments
QS-2023-HQN-
NIOS Surveillance Audit
06/02/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
001 2023
VA23F03
Quest Diagnostics Audit - Norristown
10/04/2023
WTWTHQN-
22-00402
Quest Diagnostics Audit - Norristown
10/22/2022