IR 05000313/2022001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000313/2022001 and 05000368/2022001
ML22122A290
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 05/10/2022
From: John Dixon
NRC/RGN-IV/DORS
To: Sullivan J
Entergy Operations
References
IR 2022001
Download: ML22122A290 (17)


Text

May 10, 2022

SUBJECT:

ARKANSAS NUCLEAR ONE - INTEGRATED INSPECTION REPORT 05000313/2022001 AND 05000368/2022001

Dear Mr. Sullivan:

On March 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Arkansas Nuclear One. On April 14, 2022, the NRC inspectors discussed the results of this inspection with Mr. G. Flynn, Director, Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Dixon, Jr., Chief Projects Branch D Division of Operating Reactor Safety Docket Nos. 05000313 and 05000368 License Nos. DPR-51 and NPF-6 Enclosure:

Integrated Inspection Report Signed by Dixon, John on 05/10/22

ML22122A290 X SUNSI Review By: AAS ADAMS:

X Yes No Sensitive X Non-Sensitive Non-Publicly Available X Publicly Available Keyword NRC-002 OFFICE SRI:DORS/D RI:DORS/D BC:DORS/EB1 BC:DORS/EB2 BC/DORS NAME RBywater NBrown VGaddy NTaylor HGepford SIGNATURE RLB NLB VGG NHT HJG DATE 5/3/2022 5/3/2022 5/3/2022 5/3/2022 5/3/2022 OFFICE BC:DRSS TL:DORS BC:DRSS/RxIB SPE:DORS/D BC:DORS/D NAME MHaire AAgrawal GWarnick ASanchez JDixon SIGNATURE MSH ARP GGW AAS JLD DATE 05/03/2022 5/3/2022 5/3/2022 5/3/2022 5/10/2022

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000313 and 05000368

License Numbers:

DPR-51 and NPF-6

Report Numbers:

05000313/2022001 and 05000368/2022001

Enterprise Identifier:

I-2022-001-0009

Licensee:

Entergy Operations, Inc.

Facility:

Arkansas Nuclear One

Location:

Russellville, AR

Inspection Dates:

January 1, 2022, to March 31, 2022

Inspectors:

N. Brown, Resident Inspector

R. Bywater, Senior Resident Inspector

T. DeBey, Resident Inspector

S. Hedger, Senior Emergency Preparedness Inspector

Approved By:

John L. Dixon, Jr., Chief

Projects Branch D

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Arkansas Nuclear One, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 operated at or near full power for the entire inspection period.

Unit 2 operated at or near full power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:

Unit 1 service water intake structure, including fire protection pumps on February 2, 2022

Unit 2 service water intake structure on February 2, 2022

Unit 1 upper south electrical penetration room on February 2, 2022

Unit 1 heat trace panels on February 2, 2022

Unit 2 heat trace panels on February 2, 2022

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from a tornado warning and a severe thunderstorm warning on March 30, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 emergency diesel generator A during emergency diesel generator B testing on February 12, 2022
(2) Unit 1 service water pumps (P-4A, P-4B, and P-4C) and intake structure sluice gate alignment after pump vent line repair on March 11, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1 control room, Fire Area G, Fire Zone 129-F, on January 31, 2022
(2) Unit 1 lower north electrical penetration room, Fire Area I-3, Fire Zone 112-I, on February 8, 2022
(3) Unit 1 emergency diesel generator corridor 98, Fire Area I, Fire Zone 98-J, on February 8, 2022
(4) Unit 2 A3 4160 VAC vital switchgear room, Fire Area II, Fire Zone 2101-AA, on February 12, 2022
(5) Unit 2 auxiliary building 354-foot level, Fire Area HH, Fire Zone 2038, on March 23, 2022

Fire Brigade Drill Performance Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated the onsite fire brigade training and performance during the Unit 2 A3 4160 VAC vital switchgear room announced fire drill, Fire Area II, Fire Zone 2101-AA, on February 15, 2022.
(2) The inspectors evaluated the onsite fire brigade training and performance during a fire brigade live fire training on February 22, 2022.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit 2 auxiliary building flooding features on March 23, 2022

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the Unit 1 control room during power maneuvers and turbine throttle valve and governor valve testing on March 23, 2022.
(2) The inspectors observed and evaluated licensed operator performance in the Unit 2 control room during plant protection system Channel D calibration on March 24, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated a Unit 2 simulator requalification examination on February 8, 2022.
(2) The inspectors observed and evaluated Unit 1 simulator requalification training for loss of condenser vacuum, loss of feedwater, and cooling with high-pressure injection on February 10, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1 personnel airlock local leak rate test on January 20, 2022
(2) Lake Dardanelle level indicator and alarm switch on March 24, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1 elevated risk due to planned major switchyard work coincident with fire protection pump P-6B outage and Unit 1 emergency diesel generator K-4B maintenance on January 25, 2022
(2) Unit 2 elevated risk during planned battery charger 2D-31B maintenance on March 1, 2022
(3) Units 1 and 2 elevated risk and changes to the planned maintenance schedule during severe weather alert on March 22, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2 pressurizer proportional heaters capacity after refueling outage maintenance on January 24, 2022
(2) Unit 1 emergency diesel generator B operability after extended engine start time on January 24, 2022
(3) Unit 2 low-pressure safety injection header B gas accumulation operability determination on February 8, 2022
(4) Common feedwater system functionality with high condensate storage tank water temperature on February 10, 2022
(5) Unit 1 Loop 1 service water pipe leak initial operability determination on March 31, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Temporary fire pump installation, which had been implemented to provide additional cooling water for planned Unit 2 refueling outage maintenance activities, and its removal on January 27, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) Diesel-driven fire pump P-6B following maintenance on January 1, 2022
(2) Flex diesel generator K-12 following maintenance on January 12, 2022
(3) Unit 1 penetration room ventilation system fan VEF-38A, following planned maintenance, on March 29, 2022
(4) Alternate ac diesel generator starting air compressor 2C-7, following repairs, on March 30, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (5 Samples)

(1) Unit 2 emergency diesel generator B test on February 12, 2022
(2) Unit 1 turbine throttle valve and governor valve stroke testing on March 23, 2022
(3) Unit 1 transformer yard manhole MH-2 cable inspection on March 24, 2022
(4) Unit 2 plant protection system Channel D calibration on March 24, 2022
(5) Unit 1 pressurizer heater checks on March 30, 2022

Inservice Testing (IP Section 03.01) (3 Samples)

(1) Unit 1 reactor building isolation train A quarterly valve stroke tests on February 14, 2022
(2) Unit 2 high-pressure safety injection train A quarterly valve stroke tests on February 22, 2022
(3) Unit 1 turbine-driven emergency feedwater steam valve stroke tests, for steam admission valves CV-2663 and 2667, on March 25, 2022

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The licensee submitted a summary of emergency plan changes (Revision 47) to the NRC on January 11, 2022. The inspectors conducted a review of the changes from January 18 to January 25, 2022. This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Blue team emergency preparedness drill on March 8,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1, 2021, through December 31, 2021)
(2) Unit 2 (January 1, 2021, through December 31, 2021)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 (January 1, 2021, through December 31, 2021)
(2) Unit 2 (January 1, 2021, through December 31, 2021)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 1 (January 1, 2021, through December 31, 2021)
(2) Unit 2 (January 1, 2021, through December 31, 2021)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issue:

(1) Unit 2 Refueling Outage 28 working hour limits on March 10,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 25, 2022, the inspectors presented the in-office emergency plan revision review inspection results to Mr. J. Toben, Manager, Emergency Preparedness, and other members of the licensee staff.

On April 14, 2022, the inspectors presented the integrated inspection results to Mr. G. Flynn, Director, Engineering, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

CR-ANO-

1-2016-05126, 1-2021-02806, 1-2021-02807, 1-2022-00159,

2-2016-03913, 2-2022-00066, C-2021-02884

71111.01

Miscellaneous

SO-P-NOP-00-

449

Conservative System Operations

EN-FAP-EP-010

Severe Weather Response

EN-WM-104

On Line Risk Assessment

OP-1104.039

Plant Heating and Cold Weather Operations

OP-1104.050

Turbine Building, Intake Structure and Miscellaneous

Ventilation

OP-2106.032

Unit Two Freeze Protection Guide

71111.01

Work Orders

WO 2876, 467951

71111.04

Corrective Action

Documents

CR-ANO-

1-2021-03107, 1-2021-03295, 1-2022-00220, 1-2022-00252,

1-2022-00327, 1-2022-00346, 1-2022-00380, 1-2022-00437,

1-2022-00438, 1-2022-00439

71111.04

Drawings

M-209, Sheet 1

Service Water System/Intake Structure

115

M-2210, Sheet 1

Service Water System

M-2217, Sheet 1

Emergency Diesel Generator Fuel Oil System

M-2217, Sheet 2

Emergency Diesel Generator Starting Air System

M-2217, Sheet 3

Emergency Diesel Generator Auxiliary System

71111.04

Miscellaneous

ULD-1-SYS-10

ANO Unit 1 Service Water System

ULD-2-SYS-01

ANO Unit 2 Emergency Diesel Generator System

OP-1104.029

Service Water and Auxiliary Cooling System

25

OP-2104.036

Emergency Diesel Generator Operations

2

OP-3305.01

Ops System Alignment Tests

71111.05

Calculations

CALC-89-R-

2002-105

Penetration Seal Analysis for Penetration

71111.05

Corrective Action

Documents

CR-ANO-

1-2020-01475, 1-2021-02435, 1-2022-00063, 1-2022-00307,

2-2022-00547, C-2021-00936, C-2022-00438

FP-103, Sheet 1

Fire Zones Intermediate Floor Plan, EL 368-0 and 372-0

71111.05

Drawings

FP-2103, Sheet 1

Intermediate Floor Plan El 368-0 to 372-0

FZ-1052

Fire Zone 129-F

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FZ-2029, Sheet 1

North Switchgear Room

FZ-2038, Sheet 1

Piping Penetration Room, Access Area, Tank and Pump

Room, Sample Room, Stair No. 2001, Hot Machine Shop

FZ-98-I

Fire Zone 98-1

71111.05

Miscellaneous

Technical Basis Document for ANO-1 Fires in Areas

Affecting Safe Shutdown

ANO-Unit 1 Pre Fire Plan

PFP-U2

ANO Pre Fire Plan (Unit 2)

ULD-0-SYS-09

ANO Fire Protection System

71111.05

Procedures

ASOTH-FP-

FBDRLS

Instructors Guide for Fire Brigade Drills

EN-OP-115-17

Fire Brigade Organization and Responsibilities

EN-OP-125

Fire Brigade Drills

OP-1015.007

Fire Brigade Organization and Responsibilities

OP-1104.032

Fire Protection Systems

OP-1306.005

Unit 1 Fire Door Inspection Procedure 71111.06

Calculations

CALC-15-E-0007-

ANO 317 Elevation Ponding Level Due to Postulated Pipe

Crack

CALC-95-R-

24-01

Basic Requirements for the Component Database on Station

Doors and Hatches

CALC-ANOC-CS-

15-00012

ANO Flood Protection Room Evaluations - Units 1 and 2

ULD-0-TOP-17

ANO Flooding

OP-1402.243

Inspection of Miscellaneous Internal Flood and HELB

Protection Features

WO 2946626

71111.11Q

Corrective Action

Documents

CR-ANO-

1-2021-00016, 2-2022-00258, 2-2022-00288, C-2021-

00866, C-2021-01497

71111.11Q

Miscellaneous

A1LP-RO-AVAC

Loss of Condenser Vacuum

DG-TRNA-4.5-

SIMTRNG

Simulator Training Aids

SES-2-

ECPE2203

Arkansas Nuclear One Unit 2 Crew Performance Evaluation

Scenario

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.11Q

Procedures

EN-OP-115

Conduct of Operations

EN-OP-115-02

Control Room Conduct and Access Control

EN-TQ-210

Conduct of Simulator Training

OP-1102.004

Power Operation

OP-1102.016

Power Reduction and Plant Shutdown

OP-1106.009

Supplement 2 Throttle Valve Testing

OP-1106.009

Supplement 3 Governor Valve Testing

OP-1202.002

Loss of Subcooling Margin

OP-1202.004

Overheating

OP-1202.005

Inadequate Cooling

OP-1202.011

HPI Cooldown

OP-2102.004

Power Operation

OP-2103.002

Filling and Venting the RCS

OP-2103.011

Draining the Reactor Coolant System

OP-2104.002

Chemical and Volume Control

OP-2202.010

Standard Attachments

71111.12

Corrective Action

Documents

CR-ANO-

1-2018-05389, 1-2019-00031, 1-2019-00201, 1-2019-00436,

1-2019-00797, 1-2019-01047, 1-2019-02356, 1-2020-00832,

1-2020-01318, 1-2021-00442, 1-2021-03190, 1-2022-00068,

1-2022-00216, C-2022-00181

71111.12

Miscellaneous

CEP-APJ-001

Primary Containment Leakage Rate Testing (10CFR50

Appendix J) Program Plan

NEI 99-01

Development of Emergency Action Levels for Non-Passive

Reactors

SEP-APJ-002

Arkansas Nuclear One Primary Containment Leakage Rate

Testing (Appendix J) Program Section

ULD-0-TOP-14

Containment Isolation and Containment Leak Rate Testing

71111.12

Procedures

EN-DC-334

Primary Containment Leakage Rate Testing (Appendix J)

OP-1203.012M

Annunciator K15 Corrective Action

OP-1203.025

Natural Emergencies

OP-1305.037

Unit 1 Reactor Building Access and Ventilation Leak Rate

Testing

71111.12

Work Orders

WO 2469385, 52682709, 52869983

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.13

Corrective Action

Documents

CR-ANO-

2-2021-01537, 2-2022-00428, C-2021-01100, C-2021-

220, C-2022-00031, C-2022-00751, C-2022-00764

71111.13

Miscellaneous

Unit 1 and Unit 2 Narrative Logs

03/21/2022

Unit 1 and Unit 2 Narrative Logs

03/22/2022

SO-P-NOP-00-

449

MISO Conservative System Operations

71111.13

Procedures

COPD-13

Operations Maintenance Interface Standards and

Expectations

59, 63

COPD-24

Risk Assessment Guidelines

EN-FAP-EP-010

Severe Weather Response

EN-OP-119

Protected Equipment Postings

EN-WM-104

On Line Risk Assessment

2, 23

CALC-86-E-0036-

201

ANO Unit 2 Pressurizer Heater Electrical Evaluation

2/14/2006

71111.15

Calculations

CALC-12-E-0012-

Determination of Allowable Gas Volumes in GL 2008-01

Systems on Both Units

71111.15

Corrective Action

Documents

CR-ANO-

1-2020-01681, 1-2020-01682, 1-2021-01895, 1-2021-03179,

1-2021-03184, 1-2021-03218, 1-2022-00097, 2-2004-00472,

2-2004-02116, 2-2020-02099, 2-2020-02108, 2-2020-02121,

2-2020-02321, 2-2020-02493, 2-2020-02594, 2-2021-03420,

2-2021-03440, 2-2021-03655, 2-2022-00236, C-2021-

2976, C-2021-02985, C-2022-00237, C-2022-00391, C-

22-00841

71111.15

Drawings

13-SW-134,

Sheet 1

Large Pipe Isometric Service Water Essential

M-209, Sheet 1

Circ. Water, Service Water & Fire Water Intake Structure

Equipment

115

M-2232, Sheet 1

Safety Injection System

23

71111.15

Miscellaneous

STM 1-26

Common Feedwater System

ULD-1-SYS-01

ANO Unit 1 Emergency Diesel Generator (EDG) System

71111.15

Procedures

EN-DC-219

Gas Accumulation Management

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EN-OP-104

Operability Determination Process

EN-OP-201-01

Arkansas Nuclear One Flex Program Document

OP-2307.009

Pressurizer Proportional Heater Checkout

OP-2307.039

Pressurizer Heater Removal and Replacement

71111.15

Work Orders

WO 543070, 570993, 52929081, 52961491, 52985590,

54883716

71111.18

Corrective Action

Documents

CR-ANO-

1-2020-00134, 1-2022-00336, 2-2021-00700, 2-2021-02919,

C-2021-02276,

71111.18

Engineering

Changes

ER-ANO-1999-

1909-008

Temporary Alteration for Temp Fire Pump Usage during Unit

Outages

04/03/2002

71111.18

Procedures

EN-DC-136

Temporary Modifications

71111.18

Work Orders

WO 106317, 566604, 569331, 52885431

71111.19

Calculations

CALC-88-E-0029-

Emergency Penetration Room Ventilation System

10/13/2020

71111.19

Corrective Action

Documents

CR-ANO-

C-2021-02976, C-2021-02985, C-2022-00246, C-2022-

247, C-2022-00269, C-2022-00555, C-2022-00569,

71111.19

Procedures

OP-1104.032

Fire Protection Systems

OP-2104.037

Alternate AC Diesel Generator Operations

71111.19

Work Orders

WO 545697, 566604, 570993, 575233, 52929081, 52956781,

2960533,

71111.22

Corrective Action

Documents

CR-ANO-

2-2020-00819, 2-2021-01691, 2-2022-00293, 2-2022-00294,

2-2022-00299, C-2021-02823

71111.22

Miscellaneous

EN-HU-102

Human Performance Traps & Tools

EN-RE-302

PWR Reactivity Maneuver

ULD-2-SYS-01

ANO Unit 2 Emergency Diesel Generator System

71111.22

Procedures

OP-1106.009

Turbine Startup (Warmup & Roll)

OP-1203.012H

Annunciator K09 Corrective Action

OP-1203.015

Pressurizer Systems Failure

OP-1305.007

RB Isolation and Miscellaneous Valve Stroke Test

OP-1307.009

Unit 1 Emergency Powered Pressurizer Heater Checkout

OP-2104.036

Emergency Diesel Generator Operations

2

OP-2104.039

HPSI System Operations

OP-2304.092

Unit 2 Plant Protection System Channel D Cabinet

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calibration

71111.22

Work Orders

WO 538600, 297597, 52938738, 52945445, 52959599,

2962209, 52963105, 52969754,

71114.04

Miscellaneous

10CFR50.54(q)(3) Screening, Procedure/Document

Number: EPLAN, Revision: 047, Title: ANO Emergency Plan

11/09/2021

10CFR50.54(q)(3) Evaluation, Procedure/Document

Number: EPLAN, Revision: 047, Title: ANO Emergency Plan

11/11/2021

0CAN012202

Emergency Plan, Arkansas Nuclear One, Units 1 and 2;

NRC Docket Nos. 50-313, 50-368, and 72-13; Renewed

Facility Operating License Nos. DPR-51 and NPF-6

01/11/2022

71114.04

Procedures

EN-EP-305

Emergency Planning 10CFR50.54(q) Review Program

71114.06

Miscellaneous

Blue Team Drill Guide

EN-EP-609

Emergency Operations Facility (EOF) Operations

71151

Miscellaneous

ANO-1 and ANO-2 NRC Performance Indicator

Technique/Data Sheets - Initiating Events

Q2-2021

ANO-1 and ANO-2 NRC Performance Indicator

Technique/Data Sheets - Initiating Events

Q3-2021

ANO-1 and ANO-2 NRC Performance Indicator

Technique/Data Sheets - Initiating Events

Q4-2021

ANO-1 and ANO-2 NRC Performance Indicator

Technique/Data Sheets - Initiating Events

Q1-2021

71151

Procedures

EN-LI-114

Regulatory Performance Indicator Process

Corrective Action

Documents

CR-ANO-

1-1992-00070, 1-2000-00228, 1-2004-02409, 1-2009-00158,

2-2021-02116, C-2021-03092, C-2022-00538, 1-2022-0513

Miscellaneous

90-E-0038-04

Pressure Control Assessment During Loss of Offsite Power

04/29/1992

2-R-1006-01

Ambient Heat Loss Tests (Pre/Post 1R10)

10/28/1992

95-E-0001-02

ANO U1 Millstone Study - Connected Load, MCC Circuit

Voltage Drop and Load Center Accident Loading

NUREG-0578

NRR Lessons Learned Task Force Short-Term

Recommendations

07/1979

NUREG-0737

Clarification of TMI Action Plan Requirements

11/1980

SEP-PT-ANO-

001

Arkansas Nuclear One ASME Section XI Inservice

Inspection Pressure Testing (PT) Program Section

71152A

EN-NS-102

Fitness for Duty Program

26, 27

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EN-OM-123

Fatigue Management Program

OP-1307.009

Unit 1 Emergency Powered Pressurizer Heater Checkout

OP-2102.001

Plant Pre-Heatup an Pre-Critical Checklist

Work Orders

WO 2933247