ML22301A153

From kanterella
Jump to navigation Jump to search
Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011
ML22301A153
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 11/09/2022
From: Nick Taylor
NRC/RGN-IV/DORS/EB2
To: Sullivan J
Entergy Operations
Taylor N
References
EA-22-099 IR 2022011
Download: ML22301A153 (28)


See also: IR 05000313/2022011

Text

November 09, 2022

EA-22-099

Joseph Sullivan

Site Vice President

Entergy Operations, Inc.

N-TSB-58

1448 S.R. 333

Russellville, AR 72802-0967

SUBJECT: ARKANSAS NUCLEAR ONE - NOTICE OF VIOLATION; NRC INSPECTION

REPORT 05000313/2022011 AND 05000368/2022011

Dear Joseph Sullivan:

On October 25, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at Arkansas Nuclear One and discussed the results of this inspection with you and other

members of your staff. The results of this inspection are documented in the enclosed report,

Enclosure 2.

The enclosed report discusses a violation associated with a finding of very low safety

significance (Green). The NRC evaluated this violation in accordance with Section 2.3.2 of the

NRC Enforcement Policy, which can be found on the NRC website at http://www.nrc.gov/about-

nrc/regulatory/enforcement/enforce-pol.html. The violation met the criteria for treatment as a

non-cited violation; however, because the violation is associated with Entergys failure to

manage longstanding age-related degrading conditions in your buried service water supply

piping and given that subsequent follow-up inspection to ensure compliance with your renewed

operating license will be needed, the NRC determined the issuance of a Notice of Violation

(Enclosure 1) is appropriate in this case.

You are required to respond to this letter and should follow the instructions specified in the

Notice of Violation when preparing your response. If you have additional information that you

believe the NRC should consider, you may provide it in your response. The NRCs review of

your response will also determine whether further enforcement action is necessary to ensure

your compliance with regulatory requirements.

In addition, a violation of minor significance is documented in the enclosed report.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the

NRC Resident Inspector at Arkansas Nuclear One.

J. Sullivan

2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of

this letter, its enclosures, and your response will be made available electronically for public

inspection in the NRC Public Document Room or in the NRCs Agencywide Documents

Access and Management System (ADAMS), accessible from the NRC website at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, any response should not

include any personal privacy or proprietary information so that it can be made available to the

public without redaction.

Sincerely,

Nicholas H. Taylor

Engineering Branch 2

Division of Operating Reactor Safety

Docket Nos. 05000313, 05000368

License Nos. DPR-51, NPF-6

Enclosures:

1. Notice of Violation

2. Inspection Report 05000313/2022011

and 05000368/2022011 w/Attachment

cc w/ encl: Distribution via LISTSERV

Signed by Taylor, Nicholas

on 11/09/22

ML22301A153

SUNSI Review:

ADAMS:

Non-Publicly Available Non-Sensitive

Keyword:

By: GAP

Yes No

Publicly Available

Sensitive

OFFICE

SRI:EB2

SRI:EB2

SRI:EB2

RI:EB2

C:PBD

ES:ACES

NAME

GPick

CSmith

JDrake

JMejia

JDixon

ARoberts

SIGNATURE

/RA/ E

/RA/ E

/RA/ E

/RA/ E

/RA/ E

/RA/ E

DATE

10/28/22

10/31/22

10/29/22

10/31/22

10/31/22

10/28/22

OFFICE

TL:ACES

OE

OGC

DD:DORS

D:DORS

C:EB2

NAME

JGroom

DJones

SKirkwood

MHay

R.Lantz

N.Taylor

SIGNATURE

/RA/ E

/RA/ E

NLO

/RA/E

/RA/ E

/RA/ E

DATE

10/28/22

11/08/22

11/07/22

11/09/22

10/31/22

11/01/22

Enclosure

NOTICE OF VIOLATION

Entergy Operations, Inc.

Docket Nos. 50-313, 50-368

Arkansas Nuclear One, Units 1 and 2

License Nos. DPR-51, NPF-6

EA-22-099

During an NRC inspection conducted from June 13 through October 25, 2022, a violation of

NRC requirements was identified. In accordance with the NRC Enforcement Policy, the violation

is listed below:

10 CFR Part 50, Appendix B, Criterion III, requires, in part, that measures shall be

established for verifying or checking the adequacy of design, such as by the performance of

design reviews, using alternate or simplified calculational methods, or by the performance of

a suitable testing program.

Unit 1 UFSAR, section 16.2.19, Service Water Integrity states, in part, that thickness

mapping and visual inspections manage the aging effects of loss of material from the

service water components.

Unit 2 UFSAR, section 18.1.25, Service Water Integrity Program [SWIP] states, in part,

that the program relies on implementation of the recommendations of NRC Generic

Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment, to

ensure that the effects of aging on the service water system will be managed. The licensees

response to Generic Letter 89-13, dated January 26, 1990 (ML20006B723), Attachment 3

Program Document for SWIP Long-term Program Plans, section titled Non-Destructive

Examination, Step 2 states, in part, that mapping of piping thickness at selected locations

with computerized ultrasonic equipment is periodically performed and trended.

Contrary to the above, from April 12, 2001, for Unit 1 and from April 7, 2005, for Unit 2, to

September 29, 2022, the licensee failed to establish measures for verifying or checking the

adequacy of design by the performance of a suitable testing program for the service water

system. Specifically, when managing the effects of aging, the licensee had not performed

thickness measurements of its buried in-scope emergency cooling pond supply piping to

provide reasonable assurance that the service water system remained capable of

performing its design function.

This violation is associated with a Green Significance Determination Process finding.

Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc., is hereby required to

submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional

Administrator, U.S. Nuclear Regulatory Commission, Region IV, 1600 E. Lamar Blvd., Arlington,

TX 76011-4511, and a copy to the NRC resident inspector at Arkansas Nuclear One, and email

it to R4Enforcement@nrc.gov, within 30 days of the date of the letter transmitting this Notice of

Violation (Notice). This reply should be clearly marked as a Reply to a Notice of Violation;

EA-22-099 and should include for the violation: (1) the reason for the violation or, if contested,

the basis for disputing the violation or severity level, (2) the corrective steps that have been

taken and the results achieved, (3) the corrective steps that will be taken, and (4) the date when

full compliance will be achieved.

2

Your response may reference or include previous docketed correspondence if the

correspondence adequately addresses the required response. If an adequate reply is not

received within the time specified in this Notice, an order or a Demand for Information may be

issued as to why the license should not be modified, suspended, or revoked, or why such other

action as may be proper should not be taken. Where good cause is shown, consideration will

be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with the

basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs Agencywide Documents Access and Management

System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-

rm/adams.html, to the extent possible, it should not include any personal privacy or proprietary

information so that it can be made available to the public without redaction.

If personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request that such material is withheld from public disclosure, you must specifically identify the

portions of your response that you seek to have withheld and provide in detail the bases for your

claim (e.g., explain why the disclosure of information will create an unwarranted invasion of

personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for

withholding confidential commercial or financial information).

Dated this 9th day of November 2022

Enclosure 2

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000313 and 05000368

License Numbers:

DPR-51 and NPF-6

Report Numbers:

05000313/2022011 and 05000368/2022011

Enterprise Identifier:

I-2022-011-0039

Licensee:

Entergy Operations, Inc.

Facility:

Arkansas Nuclear One

Location:

Russellville, AR

Inspection Dates:

June 12 to June 17, 2022

Inspectors:

J. Mejia, Reactor Inspector

J. Drake, Senior Reactor Inspector

G. Pick, Senior Reactor Inspector

C. Smith, Senior Reactor Inspector

Accompanying

Personnel:

B. Allik, Materials Engineer, Corrosion and Steam Generator Branch,

Office of Nuclear Reactor Regulation

J. Gavula, Materials Engineer, Corrosion and Steam Generator Branch,

Office of Nuclear Reactor Regulation

Approved By:

Nicholas H. Taylor, Chief

Engineering Branch 2

Division of Operating Reactor Safety

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting a NRC inspection at Arkansas Nuclear One, in accordance with the

Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Perform Required Thickness Measurements as Required by Design to Manage the

Effects of Aging

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

VIO 05000313,05000368/2022011-01

Open

EA-22-099

[H.5] - Work

Management

71003

The team identified a green finding and associated Notice of Violation because the licensee

failed to manage the effects of aging on their buried unit 1 and unit 2 service water supply

piping as required by regulatory requirements. Specifically, the licensee failed to measure

pipe wall thickness to assess the condition of the supply piping that provides cooling during a

design basis accident.

Additional Tracking Items

Type

Issue Number

Title

Report Section

Status

URI

05000313/2021013-02

Condition of Emergency

Cooling Pond Buried Piping

71003

Closed

3

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

71003 - Post-Approval Site Inspection for License Renewal

Background

NRC inspectors completed a Phase IV inspection the week of April 11, 2022, as documented in

Inspection Report 05000313/2021013. This inspection occurred 8 years after unit 1 and 4 years

after unit 2 entered their periods of extended operation. The period of extended operation

included the additional 20 years beyond the original 40-year licensed term. The period of

extended operation for Arkansas Nuclear One, Unit 1 will end on May 20, 2034, and Unit 2 will

end on July 17, 2038. The inspection identified areas that required further review related to

managing aging effects for the buried service water piping return lines to the emergency cooling

pond and supply lines from the emergency cooling pond to the plant intake structure.

Unresolved Item (URI)05000313/2021013-02, Condition of Emergency Cooling Pond Buried

Piping described the concerns that affected both units. The emergency cooling pond provides

the backup ultimate heat sink supply in the event of a loss of Lake Dardanelle.

With the assistance of program experts in buried piping and service water programs from the

Office of Nuclear Reactor Regulation, the team evaluated the following items:

1.

The licensing requirements related to the buried piping, service water, and

microbiologically influenced corrosion programs

2.

Whether the licensee has properly implemented the interface requirements among the

buried piping, service water, and microbiologically influenced corrosion programs

3.

Whether the licensee has implemented their required external and internal inspections

and program requirements

4.

Action plans for inspecting the buried emergency cooling pond supply and return lines

5.

Plans for using carbon fiber reinforced polymer wrap, including interim actions to ensure

health of the lines until installation of the repair

Post-Approval Site Inspection for License Renewal (1 Sample)

Licensing Requirements (Item 1)

The team confirmed that the licensee described their buried piping aging

management programs in the unit 1 updated final safety analysis report (UFSAR),

section 16.1.1 and unit 2, UFSAR, section 18.1.4. The buried piping programs

focused on ensuring the integrity of the exterior coating on the buried piping and

4

maintaining the cathodic protection system. The licensee described their service

water integrity aging management programs in the unit 1 UFSAR, section 16.2.19

and unit 2 UFSAR, section 18.1.25. The service water integrity programs focused on

implementing commitments to Generic Letter 89-13, Service Water System

Problems Affecting Safety-Related Equipment, dated July 18, 1989. The activities

implemented by the service water integrity programs included flow balancing and

testing, heat exchanger inspections and testing, chemistry treatment, and pipe

condition monitoring.

The licensee established microbiologically influenced corrosion programs to monitor

the pipe interior conditions using periodic measurements of piping thickness. The

team noted that the licensee explicitly called out monitoring the coating on the interior

of the unit 1 return line to the emergency cooling pond. The team determined that the

licensee established procedure requirements to perform thickness monitoring using

their microbiologically influenced corrosion program to meet the Generic Letter 89-13,

Section III requirements, as prescribed by the unit 1 UFSAR, section 16.2.19 and

unit 2 UFSAR, section 18.1.25.

The implementing procedures for buried piping included the guidance in NEI 09-14,

Guideline for The Management of Underground Piping and Tank Integrity,

Revision 4. For unit 1 the team determined that the licensee had a requirement to

inspect the exterior coating of one in-scope buried pipe during the 20-year period of

extended operation, and for unit 2 the licensee had a requirement to plan and inspect

one in-scope buried pipe during the last 10 years of the period of extended operation

if no opportunistic inspection occurred during the first 10 years.

Program Implementation (Item 2 and Item 3)

Buried Piping and Underground Tanks

The buried piping program evaluated the effect of aging on the exterior of buried

piping by ensuring that the cathodic protection system remained available, and that

the licensee maintained external coatings in good condition. This program included

the fire water, diesel generator fuel oil, and service water systems. The buried service

water piping included for each unit: (1) the return piping from the plant to the

emergency cooling pond; (2) the supply piping from the emergency cooling pond to

the intake structure; (3) the supply loops from the intake structure to both units;

and (4) the return piping from each unit to the intake structure.

Procedure EN-DC-343, Underground Piping and Tanks Inspection and Monitoring

Program, described the requirements for managing the effects of aging of buried

piping including fitness-for-service examinations. Procedure CEP-UPT-0100,

Underground Piping and Tanks Inspection and Monitoring, provided details related

to the buried piping program at Entergy sites that included implementing NEI 09-14,

Revision 4. Procedure SEP-UIP-ANO-001, Underground Components Inspection

Plan Non-Rad and Rad Piping, described the site-specific ranking, inspection plans,

and historical evaluation activities for all buried piping within scope.

The asset management plan developed for procedure SEP-UIP-ANO-001 described

the history of inspections for in-scope buried piping. The licensee inspected the unit 1

return to the emergency cooling pond piping (HBD-13-18) prior to entering the period

5

of extended operation in August 2010. As part of this activity the licensee: (1) cleaned

and coated the interior of the piping, (2) evaluated the exterior condition of the pipe

including the coating, and (3) performed thickness measurements of the piping. Since

entering the period of extended operation, the licensee never inspected the exterior of

any of the return or supply lines to determine the condition of the external coating.

During review of procedure SEP-UIP-ANO-001, the team identified that the

classification tables misclassified some pipe segments. The team documented this

performance deficiency in the Results section.

The team identified that the licensee had mixed results with maintaining their cathodic

protection system. The licensee placed the site cathodic protection system on their

top ten equipment concerns list but removed it from the list once plans were

established to rehabilitate the system. The team documented the details in an

observation in the Results section.

Service Water Integrity Program

The service water integrity program ensured that the service water systems met the

requirements of Generic Letter 89-13 and managed the effects of aging on the interior

of the piping. Procedure EN-DC-184, NRC Generic Letter 89-13 Service Water

Program, included requirements to implement (1) chemical treatment and monitoring,

(2) system flushing and flow testing, (3) internal inspections and maintenance of

service water piping and piping components, (4) condition monitoring and

assessment, which included thickness measurements, and (5) heat exchanger

capability verification. Procedure SEP-SW-ANO-001, NRC Generic Letter 89-13

Service Water Program, prescribed the site-specific actions and credited the

microbiologically influenced corrosion program for wall thickness monitoring as part of

the piping component inspection and maintenance.

Procedure EN-DC-340, Microbiologically Influenced Corrosion (MIC) Program,

provided the requirements for assessing and evaluating piping integrity caused by

microbiologically influenced and other types of corrosion. The licensee had two

additional documents that described the site-specific requirements for managing the

effects of aging caused by internal pipe corrosion (1) Procedure SEP-MIC-ANO-001,

Microbiologically Influenced Corrosion (MIC) Program, and (2) Engineering

Report A-EP-2005-001, Microbiologically Influenced Corrosion (MIC) Program. The

team reviewed licensee activities since 2003 related to evaluating the interior

condition of the buried service water piping that returns water from the plant to the

emergency cooling pond and that supplies water from the emergency cooling pond to

the intake structure. The team documented key events in the timeline in an

attachment to this report. The licensee initiated Condition Report CR-ANO-C-2003-

00923 to track resolution of outstanding service water integrity program notebook

actions using their corrective action program.

The licensee initiated several condition reports that documented a failure of the

buried pipe program, the microbiologically influenced corrosion program, or both

programs. These condition reports had outstanding corrective actions, as described

below:

6

Condition Report ANO-C-2019-01633 documented that the emergency

cooling pond supply piping had not been monitored for degradation by either

the buried pipe or the microbiologically influenced corrosion programs. A

corrective action remained open to track the inspection of a buried section of

the unit 1 supply pipe.

Condition Report ANO-C-2021-00987 documented fitness-for-service

evaluations had not been performed on buried safety-related service water

emergency cooling pond supply pipes (HBD-12-36 and 2HBC-88-42) as

required by procedure EN-DC-343. A corrective action remained open to take

thickness measurements and complete a fitness-for-service evaluation of the

supply pipes.

Condition Reports ANO-1-2021-02429 and 2-2021-01204 documented that

the licensee had not established an examination frequency to evaluate the

wear and wear rate to support determining the service life of the piping as

required by Procedure EN-DC-340, Section 5.5. A corrective action in each

condition report tracked the need to take thickness measurements to

determine a wear rate and evaluate the condition of the piping.

Because the licensee never performed thickness measurements for the supply lines

nor performed fitness-for-service examinations of their buried piping, the team

determined that the licensee failed to manage the effects of aging and ensure that the

supply piping could meet all its design requirements. The team documented this

performance deficiency in the Results section.

The team noted that the licensee performed ultrasonic testing of the entire unit 1

return line in August 2010 prior to coating the line. The team also noted that the

licensee completed a partial visual inspection of the interior of the Unit 1 supply pipe

from the emergency cooling pond in April 2021 to assess the pipe condition and

measure the piping ovality in preparation for the carbon fiber reinforced polymer

wrap. Similarly, in October 2021 the licensee attempted to visually inspect the interior

of the unit 2 supply pipe to determine the pipe condition in preparation for the carbon

fiber reinforced polymer wrap. The licensee only inspected the first 621-feet of the

approximately 2300-foot supply pipe. Both inspections provided limited insights into

the condition of the interior of the piping.

The team determined that the licensee inspected the interior coating of the unit 1

return line to the emergency cooling pond in 2016 as part of their aging management

activities. Condition Report ANO-1-2016-04449 documented some instances of lost

coating but concluded that the piping remained protected. The licensee coated this

piping to increase the design basis flow characteristics. Condition Report ANO-C-

2019-01633, CA10 described that work order 534148 existed to Re-inspect to

ensure coating has stopped ID [internal diameter] corrosion and pipe is structurally

sound (inspection method - internal PIG) on the SW ECP [service water emergency

cooling pond] Return Line (HBD-13-18). This work included 100 percent UT

[ultrasonic testing] scan from the internal (both ID and OD [outer diameter]

measurements) of the return line piping. The team determined that the licensee

cancelled this work in spring 2021 (1R29) and scheduled a visual inspection to review

the condition of the internal coating in fall 2022 (1R30). Work Order 563639 tracks the

7

automatic crawler visual examination to assess the condition of the coating in the fall

of 2022.

Corrective Actions

The team reviewed the operability evaluations that the licensee documented in

Condition Reports CR-ANO-1-2021-0249, CR-ANO-2-2021-1204, and CR-ANO-C-

2021-03142. The team determined that the conclusions that the piping remained

structurally intact provided reasonable assurance of operability and documented

specific observations related to the operability determinations in the Results section.

Short Term Actions (Item 4)

The team determined that the licensee scheduled work activities during the upcoming

unit 1 fall outage (1R30) and the unit 2 spring outage (2R29) on the service water

supply lines from the emergency cooling pond to the intake. The planned work

activities included:

Excavating and removing a section of piping during the unit 1 outage in

accordance work order 581554. The planned manual ultrasonic testing of

18-inch-wide sections on each end of the removed piping and an 18-inch-wide

section in the middle to perform a fitness-for-service evaluation as prescribed

by procedure EN-DC-343. The licensee plans to conduct an automatic

ultrasonic examination on the piping in support of the planned long-term

corrective actions. The licensee will evaluate these examination results to

evaluate actions required to use carbon fiber reinforced polymer wrap to

rehabilitate the piping.

Excavating and removing a section of piping during the unit 2 outage in

accordance with work order 572224. The licensee had not finalized details of

their plans at the time of this inspection. Like unit 1, the licensee planned to

conduct ultrasonic examination of the piping to support thickness monitoring, a

fitness-for-service examination, and assess the piping condition to support the

long-term corrective actions.

Long Term Actions (Item 5)

The NRC staff reviewed the licensees May 2021 scoping study IG-PM-SCO-03-TEM-

ScoDocV7.0, Scope Document - ANO-1 & ANO-2 Buried ECP Supply Pipe Projects

Revision 1. The licensees staff described that in May 2022, the site approved a

partial reroute solution that will involve (1) laying replacement piping in new trenches

that has termination points near both the emergency cooling pond and the intake

structure; (2) abandoning the existing piping in place, and (3) coating the existing

piping at the emergency cooling pond and at the intake structure with carbon fiber

polymer wrap up to the tie-in points to the replacement piping. The replacement

piping will be installed in accordance with Code Case N-752, Risk-Informed

Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3

SystemsSection XI, Division 1. The use of this code case was approved for ANO in

Letter Arkansas Nuclear One, Units 1 and 2 - Approval of Request for Alternative

from Certain Requirements of the American Society of Mechanical Engineers Boiler

and Pressure Vessel Code (EPID L-2020-LLR-0076) [ML21118B039].

8

The licensee further described that planned supply line repair and replacement would

begin in 2025 be completed in 2026 for Unit 2 and 2027 for Unit 1. The licensee also

described plans to epoxy coat the unit 2 return piping in 2031.

INSPECTION RESULTS

Failure to Perform Required Thickness Measurements as Required by Design to Manage the

Effects of Aging

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

VIO 05000313,05000368/2022011-01

Open

EA-22-099

[H.5] - Work

Management

71003

The team identified a green finding and associated Notice of Violation because the licensee

failed to manage the effects of aging on the buried unit 1 and unit 2 service water supply

piping as required by regulatory requirements. Specifically, the licensee failed to measure

pipe wall thickness to assess the condition of the supply piping that provides cooling during a

design basis accident.

Description: The team reviewed licensee activities that managed the effects of aging related

to the buried service water piping that returned water from the plant to the emergency cooling

pond and the piping that supplied water from the emergency cooling pond to the service

water intake structure. Procedure EN-DC-340 detailed the requirements of the

microbiologically influenced corrosion program activities for in-scope piping and components

which included performing pipe wall thickness measurements for buried service water piping.

During review of the program implementation, the team identified that the licensee failed to

measure the supply piping wall thickness for either unit as required by their license basis, and

as such, the licensee failed to manage the effects of aging on the buried service water supply

lines from the emergency cooling pond.

The team reviewed the history related to corrosion of the service water return and supply

piping for the emergency cooling pond. From this review the team discerned that the licensee

maintained their design basis flows to the facility and to the emergency cooling pond. Further,

the licensee knew of the potential for piping leakage and the need to conduct repairs to retard

or stop the corrosion, as demonstrated by:

In 2003, the licensee placed the outstanding actions in the service water integrity

program notebook into their corrective action program. The actions included coating

the unit 1 and unit 2 return piping and ensuring that they met their design flow

requirements. The licensee ultimately chose to use pigging to clean the unit 2 piping

rather than coat the piping.

In 2013, the licensee had plans listed in their asset management plan to excavate and

inspect the unit 1 buried supply lines; however, the licensee cancelled these

inspections.

In 2016, the NRC identified that the licensee had not maintained specific

representative monitoring points in the microbiologically influenced corrosion program

9

and did not monitor pipe wall thickness frequently enough to prevent through-wall

leaks.

In 2020, the ANO-1 Emergency Cooling Pond (ECP) Supply Pipe Replacement

Project was deferred for 3 years (two outage cycles to 2023 and 2024) due to cost

variances.

In 2020, the licensee initiated actions to clean and ultrasonically inspect the unit 1

return line during the 1R29 outage; however, the licensee removed this activity from

the outage because of inadequate planning. The licensee changed the ultrasonic

inspection to a video crawler visual inspection in the fall 2022 (1R30) outage.

In 2021, the licensee again delayed their plans to repair/rehabilitate the unit 2

and unit 1 supply pipes from 2023 to 2026 and 2024 to 2027, respectively. The

licensee delayed implementation until they received approval to implement carbon

fiber reinforced polymer wrap and use of Code Case 752.

The team determined that, on April 12, 2001, after receipt of the license extension safety

evaluation report, the licensee described in section 16.2.19 of the unit 1 UFSAR that

thickness measurements of the service water piping would be performed as part of the

service water integrity program. On April 7, 2005, after receipt of the license extension safety

evaluation report, the licensee described in section 18.1.25 of the unit 2 UFSAR that they

would implement the requirements of Generic Letter 89-13. Generic Letter 89-13,

recommendation III, specified Ensure by establishing a routine inspection and maintenance

program for open-cycle service water system piping and components that corrosion, erosion,

protective coating failure, silting, and biofouling cannot degrade the performance of the

safety-related systems supplied by service water. Letter 0CAN019012, Response to

Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment,

Attachment 2, Ongoing Programs, Recommendation III.A, specified periodic thickness

mapping of service water piping using automated means of nondestructive examination.

Procedure SEP-MIC-ANO-001, Revision 3, Step 2.4, required, in part, that the

microbiologically influenced corrosion program owner shall take responsibility and ensure all

underground piping and tanks susceptible to microbiologically influenced corrosion are

included each outage. The team determined that the licensee changed Engineering

Report A-EP-2005-001 inspection instructions in a manner that eliminated any programmatic

guidance for taking thickness measurements for buried service water piping. Up through

Revision 4 of this report, the licensee included the number of monitoring points for numerous

in-scope line segments including the emergency cooling pond supply piping to the intake

structure. The team determined that Revision 5 inappropriately credited long-term planned

actions as the basis for no longer taking thickness measurements of the emergency cooling

pond supply piping. Specifically, the licensee revised Section 2.2.1.1 Buried Pipe, to specify,

These pipes are currently being addressed by long-range plan items that are in the planning

phase to replace and/or rehabilitate these pipes. Thus, no MIC Program activity is planned for

these pipes.

The team identified a performance deficiency because the licensee never performed

thickness measurements of the supply piping from their emergency cooling pond to the intake

structure to demonstrate that the piping would continue meet its design.

10

Corrective Actions: The licensee had several corrective action documents that tracked their

short term actions to determine the condition of the piping. The licensee completed a scoping

study that outlined replacing or rehabilitating segments of the buried piping.

Corrective Action References: C-2019-01633, C-2021-00987, 1-2021-02429, and 2-2021-

01204

Performance Assessment:

Performance Deficiency: The failure to perform thickness measurements as required by plant

procedures and as described in the license basis was a performance deficiency. Specifically,

the licensee failed to measure the thickness of the buried emergency cooling pond supply

piping for either unit.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Equipment Performance attribute of the Mitigating

Systems cornerstone and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the licensee has never taken required thickness

measurements of buried emergency cooling pond supply piping in either unit to support the

conclusion that the supply piping remained capable of performing its design function.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

team determined that the finding screened to green because the deficiency potentially

affected the ability of the ultimate heat sink supply piping to deliver the required water during

an accident; however, no failure or event had occurred.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of

planning, controlling, and executing work activities such that nuclear safety is the overriding

priority. The work process includes the identification and management of risk commensurate

to the work and the need for coordination with different groups or job activities. Specifically,

the team determined that the licensee did not take advantage of opportunities to inspect the

piping when presented.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, requires, in part, that measures

shall be established for verifying or checking the adequacy of design, such as by the

performance of design reviews, using alternate or simplified calculational methods, or by the

performance of a suitable testing program.

Unit 1 UFSAR, section 16.2.19, Service Water Integrity states, in part, that thickness

mapping and visual inspections manage the aging effects of loss of material from the service

water components.

Unit 2 UFSAR, section 18.1.25, Service Water Integrity Program [SWIP] states, in part, that

the program relies on implementation of the recommendations of NRC Generic Letter 89-13,

Service Water System Problems Affecting Safety-Related Equipment, to ensure that the

effects of aging on the service water system will be managed. The licensees response to

Generic Letter 89-13, dated January 26, 1990 (ML20006B723), Attachment 3 Program

Document for SWIP Long-term Program Plans, section titled Non-Destructive Examination

Step 2 states, in part, that mapping of piping thickness at selected locations with

11

computerized ultrasonic equipment is periodically performed and trended.

Contrary to the above, from April 12, 2001, for Unit 1 and from April 7, 2005, for Unit 2, to

September 29, 2022, the licensee failed to establish measures for verifying or checking the

adequacy of design by the performance of a suitable testing program for the service water

system. Specifically, when managing the effects of aging, the licensee never performed

thickness measurements of its buried in-scope emergency cooling pond supply piping to

provide reasonable assurance that the service water system remained capable of performing

its design function.

Enforcement Action: The violation met the criteria for treatment as a non-cited violation;

however, because the violation is associated with Entergys failure to manage longstanding

age-related degrading conditions in buried service water supply piping and given that

subsequent follow-up inspection is needed to ensure compliance with ANO's renewed

operating license, the NRC determined the issuance of a Notice of Violation is appropriate in

this case (Enforcement Manual Section 2.3.2).

The disposition of this finding and associated violation closes URI: 05000313/2021013-02.

Minor Violation

71003

Minor Violation: Procedure SEP-UIP-ANO, Underground Components Inspection Plan

Non-Rad and Rad Piping, Revision 7, Appendix C, Asset Management Plan, described

historical and current plans for managing buried piping such as coating the interior of the

emergency cooling pond return piping from the plant. During review of piping classifications

related to risk ranking the underground piping, the team identified that the licensee placed the

buried service water piping into a lower risk pipe grouping that affected the risk ranking of the

piping.

The team determined that the licensee failed to classify the safety-related service water

piping as described in procedure SEP-UIP-ANO, Underground Components Inspection Plan

Non-Rad and Rad Piping, Revision 6. The licensee identified the piping in their system as

nonradioactive nonsafety-related rather than nonradioactive safety-related, which affected the

ranking related to the relative risk of a piping failure.

Screening: The inspectors determined the performance deficiency was minor. The failure to

classify service water piping as nonradioactive safety-related was a performance deficiency

for failure properly implement the requirements in procedure SEP-UIP-ANO. Specifically, the

licensee misclassified the service water piping as nonradioactive nonsafety-related that

resulted in a lower risk ranking for selecting buried pipe segments to review. The team

determined that this performance deficiency was not more than minor because the licensee

treated the piping as safety-related despite the ranking and completed inspections of similar

material carbon steel pipes in the diesel fuel oil system.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, requires, in part, that activities

affecting quality shall be prescribed by documented procedures of a type appropriate to the

circumstances and shall be accomplished in accordance with these procedures.

Procedure SEP-UIP-ANO provides the guidance and requirements to manage the buried

piping based on risk ranking according, in part, to safety classification and the presence of

radioactive fluids. Contrary to the above, on January 31, 2022, the licensee failed to properly

classify the service water piping. Specifically, the licensee classified service water piping as

12

nonradioactive nonsafety-related, rather than nonradioactive safety-related. The licensee

documented this failure to properly classify the service water piping in condition report ANO-

1-2022-00171. This failure to comply with procedure SEP-UIP-ANO constitutes a minor

violation that is subject to enforcement action in accordance with the NRCs Enforcement

Policy.

Observation: Operability Evaluation Observations

71003

The team noted that procedure EN-OP-104, Operability Determination Process, described

that to determine if an ASME Class 2 or 3 system, structure, or component with a flaw is

OPERABLE then the degradation mechanism must be readily apparent. To be readily

apparent, the degradation mechanism is discernible from visual examination (as external

corrosion or wear) or there is substantial operating experience with the identified degradation

mechanism in the affected system, structure, or component. The team reviewed operability

evaluations related to condition reports ANO-1-2021-0249, ANO-2-2021-1204, and ANO-C-

2021-03142. All three operability evaluations assume that any degradation in the buried

portions of the supply and returns lines to the emergency cooling pond resulted from

microbiologically influenced corrosion, and based on extensive operating experience, had not

affected the structural integrity of the piping.

The licensee compared the minimum thickness values derived in CALC-19-E-0013-02,

Minimum Thickness Calculation for HBD-12-36", HBD-14-18", HBD-20-18", 2HBC-33-20,

2HBC-34-20, 2HBC-83 30, and 2HBC-88-42 Buried Pipe, Revision 0 with the pipe wall

thickness values derived in CALC-20-E-0001-30, Unit 2 Failure Effects Analysis for 2HBC-

83, Revision 0, and determined that the lowest measured thickness for the above ground

portion of 2HBC-83-30 did not challenge the largest calculated minimum wall thickness for

the buried portions of the system.

The team did not identify any specific issues with the conclusion related to structural integrity

but identified the following insights not addressed by the operability determinations:

1.

The licensee replaced significant amount of their treated, small-bore service water

piping (8 and under) because extensive internal corrosion caused low flow conditions

and pinhole leaks over the life of the plant. The team concluded that the buried,

untreated piping had a high likelihood of experiencing similar leakage. The team noted

that pinhole leaks in above ground piping would not alter the external surface

environment for the pipe; however, leakage through the buried coated pipe could trap

water against the pipe under the coating and create additional external corrosion.

Based on these differences, it was not clear to the team that the site has substantial

operating experience with the degradation mechanism in the associated buried piping

environment, such that the degradation mechanism can be considered readily

apparent as described in EN-OP-104.

2.

For the 30-inch unit 2 return line, the team did not identify where the licensee

addressed that the minimum wall thickness should be 0.200 inches for the specified

22-inch soil coverage depth to account for buckling shown in CALC-19-E-0013-02,

which provided the thinning limits. The calculation cautioned that the shallow-cover

regions were likely not subjected to surface loads but noted that the user of the

calculation must ultimately determine that the burial depth at the point of interest is

greater than 36 inches and that no surface loads are applicable. The operability

evaluations did not address this aspect of the calculation to determine the actual soil

13

coverage depth and to verify that the shallow portions of the pipe are not subject to

surface loads.

3.

CALC-19-E-0013-02 states that the ASME Code Case N-806, Analytical Evaluation

of Metal Loss in Class 2 and 3 Metallic Piping Buried in a Back-Filled Trench,

provided guidelines for the design of buried steel piping and served as the technical

basis and methodology for assessing the design of buried piping according to a

calculable required uniform minimum wall thickness. The team noted that the NRC

had not approved this code case for use as described in Regulatory Guide 1.193,

ASME Code Cases Not Approved for Use. Although the licensee determined that

they could have minimum wall thickness values of less than 0.1 inches in several of

their buried pipes, the team noted that these values did not meet the minimum

allowed thickness as specified in ASME Code Case N-806. Based on the questions,

the licensee reperformed their calculation and determined that the minimum wall

thickness in CALC-19-E-0013-02 will need to increase by 25 percent. The licensee

documented the change in the calculation in Condition Report ANO C-2022-02699.

Observation: Condition of Cathodic Protection System

71003

The team evaluated the condition of the cathodic protection system because a functioning

cathodic protection system effectively protects piping from external corrosion. Although not

required as part of the license extension, the NRC evaluated the protection afforded by

cathodic protection systems and the licensee credited the protection provided by their

cathodic protection system. Letter 1CNA090004, License Renewal Application RAIs,

dated September 12, 2000, response to Request for Additional Information 3.3.4.3.2-7.c(1),

described that the buried piping inspection program will be effective because coating,

wrapping, and cathodic protection have been demonstrated in this and many other industries

to be effective at mitigating corrosion by inhibiting environmental effects.

Procedure CEP-UPT-0100, Underground Piping and Tanks Inspection and Monitoring,

Revision 6, Section 5.6, specified preventive maintenance requirements for installed cathodic

protection systems. Based on the teams review of the 2020 and 2021 annual surveys, the

licensee had the system functioning at 50 percent of capability based on the -850 mV relative

to a copper/copper sulfate reference electrode, instant-off, acceptance criterion for their

buried piping. In addition, based on its review of the 2022 annual survey, the team noted the

following: (a) the effectiveness of the cathodic protection system had dropped to 42 percent;

and (b) many anodes at the site will reach the end of their service life within 5 years. The

team determined that the licensee recently removed the cathodic protection system from their

Top Ten Equipment Reliability concerns list after engineering established plans to restore the

system to optimal design conditions to protect the buried piping. The licensee started phase 2

of a three-phase plan to identify the upgrades and replacements needed to restore the

system. The licensee expects to complete phase 2 in 2022-2023. Phase 3 will implement any

system upgrades and replacements needed to ensure the system functioned as designed by

2024-2025. The licensee will replace depleted anodes and install new rectifiers as part of the

system upgrades. The licensee tracked these corrective actions in condition report ANO-C-

2019-01013.

14

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 25, 2022, the inspectors presented the NRC inspection results to Joseph

Sullivan, Site Vice President, and other members of the licensee staff.

15

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CALC-01-E-0012-

6

Evaluation of underground utilities from new wheel loads

during transport of Holtec DFS cask

0

CALC-13-D-2001-

12

Structural Evaluation of Haul Path at ANO

0

CALC-19-E-0013-

2

Minimum thickness calculation for buried pipes

0

Calculations

CALC-20-E-0001-

30

Unit 2 FEA for 2HBC-83

0

CR-ANO-1-

2011-00476, 2016-01133, 2016-01603, 2016-01793, 2016-

02087, 2016-04449, 2017-02152, 2019-00958, 2019-01507,

2019-01759, 2019-03104, 2019-03862, 2020-00427, 2020-

01675, 2020-01822, 2020-01855, 2021-00030, 2021-00492,

2021-01188, 2021-01263, 2021-01326, 2021-01841, 2021-

02129, 2021-02183, 2021-02429, 2021-02751, 2021-02815,

2021-02824, 2021-03018

CR-ANO-2-

2003-01339, 2003-01584, 2016-02365, 2016-02835, 2016-

02843, 2017-00968, 2017-03766, 2017-04493, 2019-00524,

2019-00741, 2019-00780, 2019-00964, 2019-00986, 2019-

01727, 2019-01812, 2019-02092, 2019-02313, 2019-02373,

2019-03029, 2020-00419, 2020-00509, 2020-01797, 2020-

02986, 2020-03628, 2020-03650, 2021-00739, 2021-01204,

2021-02199, 2021-02633, 2021-03502, 2021-03502, 2021-

03595

Corrective Action

Documents

CR-ANO-C-

2003-00923, 2004-00066, 2011-00476, 2011-00935, 2013-

02041, 2016-04023, 2019-00756, 2019-00756, 2019-01012,

2019-01015, 2019-01633, 2019-02458, 2019-03982, 2019-

04099, 2020-00373, 2020-01378, 2020-02404, 2020-03265,

2021-00987, 2021-02203, 2021-02633, 2021-02703, 2021-

02887, 2021-02893, 2021-03013, 2021-03110, 2021-03142,

2021-03176, 2021-03247, 2022-00137, 2022-00464, 2022-

00502, 2022-00804, 2022-00955

71003

Corrective Action

CR-ANO-1

2022-00171

16

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

CR-ANO-C-

2022-01673, 2022-01897

C-2064

Emergency Cooling Water Suction and Discharge Lines

9

Drawings

C-64

Emergency Cooling Water Suction and Discharge Lines 10"

Gas Line Relocation

7

Engineering

Changes

54483

Service Water Buried Piping Project Scoping Study

0

93-R-1011-01

Review of the Programs Credited in the License Renewal

Evaluations, Section 3.1 Buried Pipe Inspection

3

93-R-1011-01

Review of the Programs Credited in the License Renewal

Evaluations, Section 4.19 Service Water Integrity

3

A-EP-2005-001

ANO Microbiologically Influenced Corrosion (MIC) Program

0

A-EP-2005-001

ANO Microbiologically Influenced Corrosion (MIC) Program

4

A-EP-2005-001

ANO Microbiologically Influenced Corrosion (MIC) Program

5

CALC-ANO1-ME-

11-00002

Buried Pipe Inspection Program Review

0

CALC-ANO1-ME-

11-00004

Review of the Service Water Integrity Aging Management

Program for License Renewal Implementation

0

CALC-ANO2-ME-

15-00006

Review of the Buried Piping Inspection Program for License

Renewal Implementation

0

CALC-ANO2-ME-

15-00023

Review of the Service Water Integrity Program for License

Renewal Implementation

0

ER-ANO-2004-

0573-000

ANO Buried Piping Life Cycle Management Study for SW,

ACW, FW, CW and Fuel Oil Piping

7/2/2004

LA190752-R-001

Condition Assessment of Degraded Essential Service Water

Pipe Segment, Line HBD-20-18

0

LA200162-R-001

Fire Protection System Piping Condition Assessment and

MIC Sampling

0

LA211525-LR-

001

Independent Third Party Review (ITPR) of Engineering

Evaluation supporting Operability for Emergency Cooling

Pond (ECP) Service Water Piping - Arkansas Nuclear One

7/30/2021

R06045-0029-006

Arkansas Nuclear One Buried Piping Soil Sampling Report

5/30/2014

Miscellaneous

Visual Inspection Service for 36 Pipe at Arkansas Nuclear

5/18/2021

17

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

One Plant Unit 1

Visual Inspection Service for 42 Pipe at Arkansas Nuclear

One Plant Unit 2

11/8/2021

Case N-752

Risk-Informed Categorization and Treatment for

Repair/Replacement Activities in Class 2 and 3 Systems

Section XI, Division 1

7/23/2019

Case-N-806-1

Analytical Evaluation of Metal Loss in Class 2 and 3 Metallic

Piping Buried in a Back-Filled Trench Section XI, Division 1

12/15/2015

EN-20-RR-001

Arkansas Nuclear One, Units 1 and 2 - Approval of Request

for Alternate from Certain Requirements of the American

Society of Mechanical Engineers Boiler and Pressure Vessel

Code

1

IG-PM-SCO-03-

TEM-ScoDocV7.0

Scope Document - ANO-1 & ANO-2 Buried ECP Supply

Pipe Projects

5/2/2022

Letter

CAN019012

Response to Generic Letter 89-13, Service Water System

Problems Affecting Safety-Related Equipment

1/26/1990

LR-LAR-2008-

00048

Implement the Buried Piping and Tanks Inspection Program

as described in LRA Section B.1.1

2/27/2008

NEI 09-14

Guideline for the Management of Underground Piping and

Tank Integrity

4

R06045-0029-006

Buried Piping Soil Sampling Report

5/30/2014

Report 15422-

FOR-01-1

2022 Annual Survey Cathodic Protection Systems Entergy

Arkansas Nuclear One

5/2022

Report

1901127.01

2020 Annual Survey Report (Cathodic Protection)

9/3/2020

Report

2100141.021

2021 Annual Survey Report (Cathodic Protection)

9/4/2021

Report No.

1000089

Area Potential Electric Current Survey

2/16/2012

Risk

Assessments

ANO-1-2017-0661, Revision 0

ANO-1-2017-0661, Revision 1

ANO-1-2018-0253, Revision 0

ANO-1-2018-0253, Revision 1

ANO-1-2018-0253, Revision 2

18

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ANO-2-2017-0664, Revision 0

ANO-2-2017-0664, Revision 1

ANO-2-2017-0664, Revision 2

ANO-2-2020-0057, Revision 0

SPEC-6600-M-

400

Specification for External Surface Treatment of Underground

Metallic Pipe for the Arkansas Nuclear One Arkansas Power

and Light Company

4/1/1971

Specification

ANO-C-2301

Structural Backfill

4

Specification

SPEC-C-301

Technical Specification for Structural Backfill Pipe Trench

Excavation, and Pipe Trench Backfill

1

1-BOP-UT-21-

031

Oily Water Buried Pipe 6 Baseline Inspection

9/8/2021

1-BOP-UT-21-

032

Oily Water Buried Pipe: Buried 6 Pipe Outside of Oily Water

Separator

9/9/2021

2-BOP-UT-15-

050

Service Water Return Spool #8 (MC 2.C.3.1)

9/2/2015

2-BOP-UT-17-

006

  1. 1 Header supply to ECP (MIC 2.A.1.1)

2/1/2017

2-BOP-UT-17-01

O

ECP 30 in. Return Piping (MIC 2.C.3.2)

2/9/2017

2R27 ECP SW

Return_AUT 001

2R27 ECP SW Return (2HBC-83-30")

12/12/2019

BOP-UT-09-046

ECP 30 in. Return Piping (MIC 2.C.3.2)

8/11/2009

NDE Reports

Reports

NDE Reports

NDE Reports

NDE Reports

NDE Reports

NDE Reports

ISI-UT-08-024

Spool #1 (At tee to 2HBC-51-81")

2/27/2008

Operability

Evaluations

CR-ANO-1-2021-

02429

Per the requirements of EN-DC-340, Microbiologically

Influenced Corrosion (MIC) Monitoring Program, the

examination frequency has not been determined for the Unit

1 Emergency Cooling Pond Supply and Return

Lines.

ECH-EP-12-

00001

Guidelines for Management of Reasonable Assurance of

Integrity for Above and Underground SSCs Containing

Radioactive Material

0

EN-DC-147

Engineering Reports

8

19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EN-DC-184

NRC Generic Letter 89-13 Service Water Program

6

EN-DC-340

Microbiologically Influenced Corrosion (MIC) Monitoring

Program

5

EN-DC-343

Underground Piping and Tanks Inspection and Monitoring

Program

13

EN-EP-S-002-

MULTI

Underground Piping and Tanks General Visual Inspection

5

EN-OM-132

Nuclear Risk Management Process

3

EN-OP-104

Operability Determination Process

17

SEP-MIC-ANO-

001

Microbiologically Influenced Corrosion (MIC) Program

3

SEP-SW-ANO-

001

NRC Generic Letter 89-13 Service Water Program

1

HQNLO-2019-77

Self-Assessment on the Buried Pipe and Tank Program

9/30/2020

LO-ALO-2015-

0080

NRC Generic Letter 89-13 Service Water Program

Assessment

12/17/2015

LO-ALO-2015-

0095

Microbiologically Induced Corrosion (MIC) Monitoring

Program Assessment

9/18/2015

LO-ALO-2015-

0097

Underground Piping and Tank Inspection Program

12/18/2015

LO-ALO-2016-

0016

Underground Piping & Tanks Inspection and Monitoring

Program Snapshot Assessment

0

LO-ALO-2016-

0078

Confirmatory Action Letter Key Improvement Action 6:

Service Water System Operational Performance Inspection

12/2016

Self-Assessments

LO-ALO-2017-

0071

Pre-NRC Focused Self Assessment: Triennial Heat Sink

Assessment

0

Work Orders

WO- 478947, 507271, 507346, 549458, 556989, 559400, 559401,

563877, 567020, 567026, 572240,

Timeline of Important Buried Piping Corrective Action Documentation After Approval of Renewed License

Attachment

Date

Discussion

Reference

9/26/2003

Low service water flows in unit 2 to safety related loads resulted from corrosion on the

interior of the piping. Recovered some design margins and improved the flow conditions

by cleaning the emergency cooling pond return and supply piping through pigging. Long

term corrective actions proposed coating the interior of the piping and/or replacement.

Condition Report

ANO-2-2003-01339

10/27/2003

Conversion of outstanding service water integrity plan notebook actions to individual

actions in the corrective action program. Specific corrective actions included:

CA6 - tracked decision to clean the supply and return headers to the plant to meet flow

requirements; replacement of large bore piping to service water components in the plant;

determine the quantity and location to monitor piping thickness

CA10 - evaluate coating the unit 1 and 2 service water return piping to the emergency

cooling pond; identified that the coating on unit 1 had been successful and considered

coating the unit 2 return line. The licensee used pigging to clean the return line to restore

flows (refer to condition report 2-2003-01339).

Condition Report

ANO-C-2003-00923

1/16/2004

Service water integrity plan notebook specified mapping pipe wall thickness with

non-destructive examinations. The licensee identified the initial population from the

intake structure into the power block. The licensee had established these activities to

implement Generic Letter 89-13, recommendation III, and Unit 1 license renewal

commitments. The program did not have a defined a scope or implementation frequency

to manage the aging effects caused by corrosion/erosion occurring in the service water

system. Developed a program documented in engineering report A-EP-2005-001 that

discussed specific monitoring locations, piping systems and materials, ranking

methodology, and acceptance criteria.

Condition Report

ANO-C-2004-00066

3/12/2014

Procedure SEP-UIP-001, Underground Components Inspection Plan (Rad And Non-Rad

Lines), Revision 1 identified that the licensee had plans to inspect the unit 1 supply line in

accordance with work orders WO 292676 & 292678

Inspection Report 05000313/2014007

3/4/2015

A scoping study based on 2005 and 2012 Life Cycle Management Reports statistically

analyzed risks due to leaks in the buried service water and fire protection piping.

Identified a high likelihood of developing leaks caused by pitting and the lack of

consistent cathodic protection. Service water piping replacements had occurred inside

the power block for the past 30 years.

Because of feasibility uncertainty related to a cured-in-place piping repair option that had

been considered, the licensee discontinued this option, and evaluated other options.

The unit 2 service water return to the emergency cooling pond piping was scheduled to

be relined in spring 2017 (2R25).

Engineering

Change 54483

2

Date

Discussion

Reference

Recommended long term corrective actions for the unit 1 and unit 2 supply pipes

included evaluating site chemical controls to assist with passivation, developing an

inspection plan to validate structural integrity, evaluating industry experience with internal

coating/lining repairs, developing detailed construction estimates for pipe replacement or

refurbishment, and upgrading the cathodic protection system to ensure system reliability.

2/26/2016

During review of the microbiologically influenced corrosion program implementation, NRC

identified that the licensee had not maintained specific representative monitoring points

in the microbiologically influenced corrosion program and did not monitor pipe wall

thickness frequently enough to prevent through-wall leaks. Specifically, the licensee had

not established a maximum time limit for monitoring points

Condition Reports

ANO-C-2016-00435,

ANO-C-2016-00524,

ANO-C-2016-00546

Noncited Violation

05000313;

05000368/2016007

5/2/2019

Described that the emergency cooling pond supply piping that allows water to gravity

flow to the intake structure had not been monitored for degradation either by the buried

pipe or the microbiologically influenced corrosion programs. Identified gaps included:

(1) coordinating between the program owners; (2) identifying planned inspections;

and (3) selecting buried piping sections for evaluation based on risk ranking.

CA 7 (2/27/2020) initiated to track ultrasonically scanning the Unit 1 return piping inside

and outside diameters in 1R29. Inspection plans cancelled because of a lack of

preparedness and contingency planning.

CA 12 (5/5/2021) tracking completion of visual inspection of the unit 1 supply in 1R30 for

HBD-13

CA 13 (11/12/2021) documented video crawler inspection of the unit 2 supply line in

2R28. Inspected the first 681 feet of approximately 2300 feet

CA 14 (11/12/2021) documented ultrasonic inspection of accessible portions of the unit 2

return in 2R28

CA 16 (11/11/2021) incorporated Condition Report ANO-C-2021-02703 related to a

noncited violation for failure to test of buried piping to ensure it could perform its safety

function

Condition Report

ANO-C-2019-01633

7/9/2019

Buried piping program health report changed to red related to cathodic protection

deficiencies. Procedure EN-DC-143 required that the licensee identify causes for any

deficiencies and implement corrective actions

Condition Report

ANO-C-2019-02458

2/6/2020

Assessed the cathodic protection system as red and placed it on the top ten equipment

reliability concerns list. The plant developed actions to improve the system reliability with

an expected completion in 2025

Condition Report

ANO-C-2019-03982

3

Date

Discussion

Reference

5/7/2020

The cathodic protection system area potential earth current survey recommended actions

to optimize the level of protection provided across the system until permanent corrective

actions implemented.

Condition Report

ANO-C-2020-01378

4/8/2021

Fitness-for-service evaluations had not been performed on buried service water

emergency cooling pond supply pipes (HBD-12-36 and 2HBC-88-42) as required by

procedure EN-DC-343. The licensee program had until 2025 to complete this procedure

requirement.

Condition Report

ANO-C-2021-00987

4/19/2021

During setup of a robotic crawler at the unit 1 supply pipe entrance, licensee identified a

significant amount of microbiologically influenced corrosion tubercles on the inside

surfaces. The licensee advanced the crawler to the first 90-degree elbow (approximately

50 feet) to assess the conditions and inside diameter of the piping to support the planned

carbon fiber reinforced polymer wrap in the spring 2027 (1R33)

Condition Report

ANO-1-2021-01188

4/21/2021

Three sections of pipe between the emergency cooling pond supply piping entrance and

642 feet into the piping had ponding of water suggesting possible ground water in

leakage. Inspection personnel stopped the inspection because they had concerns about

the equipment getting stuck.

Condition Report

ANO-1-2021-01326

5/5/2021

Significant corrosion observed on wedges and associated studs and nuts on the gate

guide knuckles at the entrance to the unit 1 supply pipe (HBD-12-36) when initiating

crawler inspections.

Condition Report

ANO-1-2021-01841

7/15/2021

Documented no examination frequency established to evaluate the wear and wear rate

to determine the remaining service life of the piping. The licensee concluded that internal

environment for the piping in the auxiliary building immediately prior to going

underground had similar water quality, flow, and temperatures; therefore, the wear and

rate from the aboveground piping matches that of buried piping. Piping determined to be

operable and structurally sound by comparison.

Condition Reports

ANO-1-2021-02429

and

ANO-2-2021-01204

9/23/2021

The licensee delayed work order 563877 from the spring 2021 (1R29) until the fall 2022

(1R30). This activity would have removed and replaced a 20-foot section of piping to

provide insights into the condition of the supply piping and allowed performing a

fitness-for-service evaluation.

Condition Report

ANO-1-2021-02824

10/16/2021

Ultrasonic evaluation of location 2HBC-83-2 on the service water return to the

emergency cooling pond documented a degradation on the line greater than assumed in

in plant calculations that would maintain integrity for another 10 months. A failure effects

analysis demonstrated sufficient margin so that the piping would maintain integrity until

2031 at the expected wear rate.

Condition Report

ANO-2-2021-02633

4

Date

Discussion

Reference

12/8/2021

From review of video crawler results for the inside of the unit 2 supply piping, the

licensee identified ponding of water about 98 feet downstream of the first elbow. This

inspection assessed the interior pipe conditions to support using carbon fiber reinforced

polymer wrap to rehabilitate the piping in spring 2026 (2R32). The licensee delayed plans

to excavate and assess this section of the piping until the next unit 2 outage to ensure

more complete contingency planning and preparations for completion in spring 2023

(2R29).

Condition Report

ANO-C-2021-03142

12/22/2021

Independent review confirmed that performance of volumetric inspections and fitness-for-

service evaluations were needed to support the repair/replacement implementation dates

(2026 through 2031) for the service water supply pipes.

The review (1) identified the need to revisit interim actions once the repair projects were

deferred; (2) confirmed that prior corrective actions were not timely nor comprehensive to

address pipe wall thinning / pitting concerns; and (3) determined a lack of clear

ownership and accountability of microbiologically influenced corrosion monitoring by the

station.

An Organizational & Programmatic review identified organizational problems with

execution of needed repairs for a problem known to exist since 2005 related to enterprise

risk and conflicting work group priorities. Specifically, the condition analysis identified:

(1) site engineering had been concerned with the supply and return piping since 2005

and (2) microbiologically influenced corrosion program owners had changed at least nine

times since 2010, which led to missed opportunities and a lack of an advocate to collect

data.

Condition Report

ANO-C-2021-03247

May 2022

Entergy approved long term corrective action to replace center sections of the unit 1

and unit 2 supply piping and connect to pipe rehabilitated with carbon fiber reinforced

polymer wrap from the termination points to the emergency cooling pond outlet and to

the service water intake structure.

Scope Document -

ANO-1 & ANO-2

Buried ECP Supply

Pipe Projects