Responds to NRC Re Violations Noted in Insp Repts 50-313/85-15 & 50-368/85-16.Corrective Actions:Procedure 2203.09, Fire Protection Sys Annunciator Corrective Action, Rev 0 Revised
ML20133H503
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 08/23/1985
From: Enos J
ARKANSAS POWER & LIGHT CO.
To: Denise R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20133H498 List:
References
0CAN088509, CAN88509, NUDOCS 8510170410
Download: ML20133H503 (2)


Text

-

e >

ARKANSAS POWER & LIGHT COMPANY POST OFFICE BOX 551 LITTLE ROCK. ARKANSAS 72203 (501) 371-4000 August 23, 1985

, -@MDUQK I

JCAN088509 i Mr. Richard P. Denise, Director SEPl2505 4 Di/ision of Reactor Safety and Projects U -

~

O)l U. S. Nuclear Regulatory Commission J Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011

SUBJECT:

Arkansas Nuclear One - Units 1 & 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6 Response to Inspection Reports 50-313/85-15 and 50-368/85-16 Gentlemen:

The subject inspection report has been reviewed. A response to the Notice of Violation is attached.

Very tr,uly y urs,

/

ff WOW ed Enos y Manager, Licensing Attachment Mr. Richard C. DeYoung Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555 Mr. Norman M. Haller, Director Office of Management & Program Analysis U. S. Nuclear Regulatory Commission Washington, DC 20555 puoMRMTga l g_ str/#

l MEMBEA MICOLE SOUTH UTILITIES SYSTEM

-o -

e . .o NOTICE OF VIOLATION During an NRC inspection conducted on May 20-24, 1985, a violation of NRC requirements was identified. The violation involved failure to maintain procedures current. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions,"10 CFR Part 2, Appendix C (1985), the violation is listed below:

Failure to Maintain Procedures Arkansas Nuclear One, Unit 2, Technical Specifications paragraph 6.8.1 states: " Written procedures shall be established, implemented, and maintained covering the activities referenced below: . . . f. Fire protection program implementation . . . ."

Contrary to the above, Procedure 2203.09, " Fire Protection System Annunciator Corrective Action," Revision 0, dated June 26, 1981, Attachment A, 1-5-5, " Corridor by Emergency Control Room Chillers Zone Module," had not been revised to reflect deactivation of remote actuation by closing supply valve for deluge system automatic valve as a result of the granting of an exemption request to deactivate the automatic capability of this deluge valve.

This is a Severity Level V Violation. (Supplement I) (50-368/85-16)

Response

The procedure had not been revised due to an oversight at the time the valve position was changed. The procedure was revised May 23, 1985, to address the actions necessary to assure flow to the corridor by the emergency control room chillers, achieving full compliance. Previous fire protection program related exemptions will be reviewed and procedures will be revised as necessary. This review will be completed by November 30, 1985.

&