Confirms That Procedures Discussed in Generic Ltr 88-03 Re IE Bulletin 85-001, Steam Binding of Auxiliary Feedwater Pumps, in Place & Will Be Maintained
ML20154J100
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 05/17/1988
From: Howard D
ARKANSAS POWER & LIGHT CO.
To: Miraglia F
Office of Nuclear Reactor Regulation
References
0CAN058801, CAN58801, GL-88-03, GL-88-3, IEB-85-001, IEB-85-1, NUDOCS 8805260171
Download: ML20154J100 (2)


Text

J<~~ '

. f ARKANSAS POWER & LIGHT COMPANY POST OFFICE BOX 551 UTTLE ROCK, ARKANSAS 72203 [501) 377-4000 May 17, 1988 OCAN058801 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 ATTN: Frank J. Miraglia, Associate Director Office of Nuclear Reactor Regulation

SUBJECT:

Arkansas Nud aar One - Units 1 & 2 Docket Nos. 50-313 and 50-368 License Nos. OPR-51 and NPF-6 Response to Generic Letter 88-03

Dear Mr. Miraglia:

Generic Letter 88-03, dated February 17, 1988 (0CNA028819), transmitted the staff's resolution of Generic Safety Issue 93, "Steam Binding of Auxiliary Feedwater Pumps", and requested a letter of confirmation indicating that certain procedures are in place and will be maintained. Specifically, GL 88-03 stated that all addressees should:

1. Maintain procedures to monitor fluid conditions within the AFW system each shift during times when the system is required to be opeiable. This monitoring should ensure that fluid temperature at the AFW pump discharge is maintained at about ambient levels.
2. Maintain procedures for recognizing steam binding and for restoring the AFW system to operable status, should steam binding occur.

Generic Letter 88-03 resolved Generic Issue 93 by perpetuating the recommendations of IE Bulletin 85-01 regarding the above procedures.

Although AP&L was not an addressee for IE Bulletin 85-01, we already had addressed the issue of AFW pump steam binding and had procedures in place which satisfied the action items of the Bulletin. This has been reviewed and documented in inspection reports 85-07, dated June 10, 1985 (0CNA068503) and 86-13, dated May 19, 1986 (0CNA058617). This letter serves as the letter of confirmation requested by Generic Letter 88-03 that these procedures are in place and will be maintained.

Very truly yours,

(

D Howard  ;

Manager, Licensing f g6 DRH: RBT 8805260171 880517 ADOCK 0500 :3 gDR veveen uoote soutmmutics svstav

. e. .

t STATE OF ARKANSAS )

) SS COUNTY OF PULASKI )

l I, Dan R. Howard, being duly sworn, subscribe to and say that I am Manager, Licensing for Arkansas Power & Light Company; that I have full authority to execute this oath; that I have read the document numbered OCAN058801 and know the contents thereof; and that to the best of my knowledge, information and belief the statements in it are true.

SUBSCRIBED AND SWORN T0 before me, a Notary Public in and for the CountyandStateabovenamed,this/7/bdayof MQ f ,

1988.

c'rfuAAort d

Notary Public My Commission Expires:

h 0 fl Y ? / h k)

/