ML13210A227

From kanterella
Revision as of 07:04, 13 April 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search

6/26/13, Summary of Pre-Application Meeting to Discuss Pending License Amendment Request to Modify the CNP Unit 1 Normal Operating Pressure and Temperature (TAC MF1973)
ML13210A227
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 08/02/2013
From: Wengert T J
Plant Licensing Branch III
To:
Wengert T J
Shared Package
ML13210A230 List:
References
TAC MF1973
Download: ML13210A227 (4)


Text

'" UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 2, 2013 LICENSEE: INDIANA MICHIGAN POWER COMPANY FACILITY: DONALD C. COOK NUCLEAR PLANT (CNP)

SUBJECT:

SUMMARY OF JUNE 26,2013, PRE-APPLICATION MEETING TO DISCUSS PENDING LICENSE AMENDMENT REQUEST TO MODIFY THE CNP UNIT 1 NORMAL OPERATING PRESSURE AND TEMPERATURE (TAC NO. MF1973) On June 26, 2013, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Indiana Michigan Power Company (I&M, the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss I&M's pending license amendment request (LAR) to modify the normal reactor coolant system operating conditions on CNP Unit 1 . . The proposed change would modify the plant's technical specifications to allow operation near the originally licensed normal operating pressure and temperature. A notice for this meeting was issued on June 12, 2013, and is available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML 13161A380. The licensee's meeting slides can be found in ADAMS at Accession No. ML 13176A133. During the meeting, the licensee described the operating history of the Unit 1 steam generators (SGs) and the tube wear observed at the SG fan bar supports, which it has attributed to resonance-related tube vibration due to low steam pressure. The licensee explained that, although the wear rate is low, it plans to correct this condition by restoring the reactor coolant system normal operating pressure and temperature to near the' previously licensed conditions. The licensee further described the impacts of this change on the current analyses of record and the technical specifications. The NRC staff queried the licensee and provided feedback throughout the presentation. The licensee stated that they plan to submit the LAR in October of 2013, and will request the NRC staff to complete its review in August 2014, to support the licensee's Unit 1 refueling outage schedule. Members of the public were not in attendance. Public Meeting Feedback forms were not received. A list of attendees is included as an enclosure.

-2 Please direct any inquiries to me at 301-415-4037, or thomas.wengert@nrc.gov. Sincerely, Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-315 List of cc w/encl: Distribution via LIST OF JUNE 26, 2013, PRE-APPLICATION MEETING INDIANA MICHIGAN POWER COMPANY DONALD C. COOK NUCLEAR NAME ORGANIZATION Q. Shane Lies I&M M. Scarpello I&M G.Hill I&M D. Hafer Sargent & Lundy M. Blumberg NRC/NRR/DRAlAADB J. Gall NRC/NRR/DSS/SRXB S. Mazumdar NRC/NRR/DE/EICB G. Kulesa NRC/NRR/DE/ESGB K. Karwoski NRC/NRR/DE A. Sallman NRC/N RR/DSS/SCVB C. Jackson NRC/NRR/DSS/SRXB T. Wengert NRC/NRR/DORL K. Bucholtz* NRC/NRR/DSS/STSB J. Giessner* NRC/Rill E. Sanchez* NRC/Rill J. Ellegood* NRC/RIII J. Vandenbroek* Scientech

  • PartiCipated via teleconference ACRONYMS AADB. : AcCident Dose Branch DE, Division of Engineering DORL Division of Operating Reactor Licensing DPR Division of Policy and Rulemaking DSS . Division of Safety Systems EICB Instrumentation and Controls ESGB Steam Generator Tube Integrity Branch NRC U.S. Nuclear Regulatory Commission NRR Office of Nuclear Reactor Regulafion . SCVB Containment and Ventilation Branch SRXB. Reactor Systems Branch STSB Technical SpeCifications Branch Enclosure

-2 Please direct any inquiries to me at 301-415-4037. or thomas.wengert@nrc.gov. Docket No. List of cc w/encl: Distribution via DISTRIBUTION: PUBLIC LPL3-1 RlF RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl3-1 Resource MBlumberg, NRRlDRA JGall, I\IRRlDSS SMazumdar, NRRlDE ADAMS Accession Nos.: Package ML 13210A230 Meeting Notice: ML 13161A380 Meeting Summary: ML 13210A227 M t' I es: ML 13176A133 eelng Srd Sincerely. IRAJ Karl D. Feintuch for Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsRgn3MailCenter Resource RidsNrrLASRohrer Resource VCampbell, EDO Region III RidsOgcMailCenter Resource RidsNrrPMDCCook Resource CJackson, NRRlSRXB GKulesa, NRRlDE JGiessner, Rill . KKarwoski, I\JRRlDE ESanchez, Rill, ASaliman, NRRlDSS KBucholtz, NRRlSTSB TWertz, NRR JEliegood, Rill OFFICE NAME !DATE NRR/LPL3-1/PM "!Wengert ITBeltz for 08/01/13 NRRlLPL3-lILA SRohrer 07/31/13 NRR/LPL3-1/BC RCarlson ITBeltz for 08/02/13 NRRlLPL3-1/PM "!Wengert IKFeintuch for 08/02/13 OFFICIAL RECORD