ML23199A240

From kanterella
Jump to navigation Jump to search
Summary of the July 13, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2
ML23199A240
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 07/19/2023
From: Nestor Feliz-Adorno
NRC/RGN-III/DORS/ERPB
To:
Shared Package
ML23013A309 List:
References
Download: ML23199A240 (1)


Text

LICENSEE:

Indiana Michigan Power Company FACILITY:

Donald C. Cook Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE JULY 13, 2023, PUBLIC OUTREACH TO DISCUSS THE NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 On July 13, 2023, from 3:00 p.m. to 4:30 p.m. (EDT), an information meeting with a question and answer session was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2022 End-of-Cycle plant performance assessment of Donald C. Cook Nuclear Plant, Units 1 and 2, along with general information on the NRC. The open house was held at the Silver Beach Center in St. Joseph, Michigan. The NRC discussed plant performance with members of the public in attendance at this meeting, and state and local government officials listed in the attached enclosure.

The NRC discussed their assessment of the Donald C. Cook Nuclear Plant, as documented in the March 1, 2023, End-of-Cycle Assessment Letter (ADAMS Accession Number ML23059A345) during the public outreach. The NRC made various resources available to those in attendance, such as the assessment letter, inspection reports, fact sheets and brochures, and other public documents. Members of the public were given the opportunity to ask questions to the NRC staff.

Néstor J. Féliz Adorno, Chief, Engineering and Reactor Projects Branch Division of Operating Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 cc: Distribution via LISTSERV July 19, 2023 Signed by Feliz-Adorno, Nestor on 07/19/23

SUBJECT:

SUMMARY

OF THE JULY 13, 2023, PUBLIC OUTREACH TO DISCUSS THE NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 DISTRIBUTION:

Jeffrey Josey RidsNrrDorlLpl3 RidsNrrPMDCCook Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker Kimyata Morgan-Butler Jared Heck R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML23199A240 OFFICE RIII RIII NAME THartman:sw NFéliz Adorno DATE 07/18/2023 07/19/2023 OFFICIAL RECORD COPY

Enclosure PUBLIC MEETING ATTENDEES July 13, 2023 U.S. Nuclear Regulatory Commission N. Féliz Adorno, Chief, Engineering and Reactor Projects Branch, Division of Operating Reactor Safety (DORS), Region III (RIII)

P. Zurawski, Senior Resident Inspector J. Mancuso, Resident Inspector A. Guieb, Student Intern P. Chandrathil, Public Affairs Officer, RIII A. Barker, Regional Government Liaison Officer, RIII C. Hernandez, Resident Inspector Office Assistant Indiana Michigan Power Company B. Downey M. Scarpello State and Local Officials L. King, Indiana Department of Health and Safety R. Adams, Berrien County Sheriffs Department, Emergency Management and Homeland Security M. Troupe, Berrien County Sheriffs Department, Emergency Management and Homeland Security Members of the Public D. Bruck A. Graeber, International Brotherhood of Electrical Workers, Local 1392 M. Poluhanya J. Rutkowski